commercial department. pupil report
TRANSCRIPT
-
7/31/2019 Commercial Department. Pupil Report
1/5
NATIONALPOWER AUTHORITY PUPILAGE REPORT
1
COMMERCIAL DEPARTMENT
Inspectorate
TOTAL STAFF STRENGTH---------------7
ORGANOGRAM
SUPERVISORS-------------------------------3
ZONES DISTRICTS
EAST 70,71,72,82,83
WEST 80,81,84
CENTRAL 73,74,75,76,77,78,79
SPECIFIC FUNCTIONS:
Receive application forms and query letters from customers through the Commercial Managerand from the Customer Service Section
Inspections on tariff clarifications (TC)New connections-NC
Separate meters-SM
Change of Tenancies-CT
Additional Wiring Meter Required-AWMR
Rewiring Meter Required-RWMR
Temporary Supplies-TS
Non-payment of Withdrawn Meter CasesStolen Meter Cases
Preparation of Job instructions for meter replacement
Calculations on installed load and Assessments for energy recoveries
Installation of check meters to address some customer queries and advices
Inspections of Meter Account Queries
Inspections on Meter Performances
Faulty Meter Cases- MSS
Investigations on illegal supplies and meters
Burnt Meter Cases
MDI Disconnections an Reconnections
Inspections on General Electrical Installations
Determination of Faulty meter for Faulty Meter Cases
Install a check meter
o Domestic consumerat least 30 dayso MDIsat least 24 hrs.
Establish variables and proceed with the calculations.
-
7/31/2019 Commercial Department. Pupil Report
2/5
NATIONALPOWER AUTHORITY PUPILAGE REPORT
2
X % error
Or Where WSM=
ISM= CIF=Check index final
IEE Regulation
Error limit=
Example:
IfCIF = 1164,WSF= 29981 and ISF= 28820, then
Comment:sinceis within the limit, the meter is considered to be ingood working order.Calculations on installed load and Assessments for energy recoveries
Energy recovery can be achieved by taking inventory of all utilities in the consumers premises as
follows:
Utility Qty Minimum rating (watt) Product
Bulbs 5 40 200
TV 1 80 80
DVD 1 25 25
Fan 1 70 70
-
7/31/2019 Commercial Department. Pupil Report
3/5
NATIONALPOWER AUTHORITY PUPILAGE REPORT
3
Freezer 1 150 150
Installed Load= 525W
( )
GENERAL CHALLENGES:
Low staff strength
Inadequate office space
Provision of ladder carrying vehicle with communication facility
Provision of electrical instruments and tools
Provision of more office equipment and furniture
More training on investigation Techniques and report writing skills
Provision of motor bikes for each respective zone
LARGE POWER UNIT SECTION
MDI & MDAs
TOTAL STAFF STRENGTH---------------Three
ZONES: EAST, WEST, CENTRAL AND MAKENI
SPECIFIC FUNCTIONS:Billing, Bill Distribution and treatment of Customer Queries
GENERAL FUNCTIONS:
Prepare reading tickets for MDI and MDAs
Send read entry to Data Processing for entry
Meter editing (three stages)
Preview (three stages)
-
7/31/2019 Commercial Department. Pupil Report
4/5
NATIONALPOWER AUTHORITY PUPILAGE REPORT
4
Bill production and distribution
Customer queries for the following ledgers:
1. Staff account2. Welders3.
Churches and mosques4. Schools and hospitals
GENERAL CHALLENGES:
Inadequate staff
Transport
METER READING
ORGANOGRAM
1. HEAD OF SECTION2. SUPERVISORS-33. SENIOR METER READERS-44. PERMANENT METER READERS-25. CONTRACT METER READERS-17
TOTAL STAFF STRENGHT-27
SPECIFIC FUNCTIONS:
Supervisors preparation of statistical reports with regards the no. of meters read, met disconnected,
suspected faulty and addressing customer complaints.
GENERAL FUNCTIONS:
Meter reading
-
7/31/2019 Commercial Department. Pupil Report
5/5
NATIONALPOWER AUTHORITY PUPILAGE REPORT
5
Bills distribution and reporting for the attention of management
GENERAL CHALLENGES:
Inadequate staff strength
Inadequate logistics: Motor bikes, Vans, door lock cardsInconsistent data base records
Random installation of prepaid meters
STATUS REPORT
PITFALLS:
No proper supervision of meter readers by the supervisors
o Schedule books are not checked regularly to know completed and pending taskso No proper check to ensure that team members report every day at the office
Too many door lock conditions:
o Most meters are installed inside the houses and thus create lots of difficulties ingaining access the meters.
o This will eventually lead to a drag in revenue collection.