commercial construction project plan

Upload: mustafa-sayeed

Post on 08-Jul-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/19/2019 Commercial Construction Project Plan

    1/60

    ID Task

    Mode

    Task Name Duration Start Finish

    0Commercial

    Construction

    344 days Thu

    16 03 17

    Tue

    17 07 11

    1General Conditions17 days Thu 16 03 17Fri 16 04 08

    2 Receive notice

    to proceed and

    sign contract

    3 days Thu

    16-03-17

    Mon

    16-03-21

    3 Submit bond

    and insurance

    documents

    2 days Tue

    16-03-22

    Wed

    16-03-23

    4 Prepare and

    submit project

    schedule

    2 days Thu

    16-03-24

    Fri 16-03-25

    5 Prepare and

    submit schedule

    of values

    2 days Mon

    16-03-28

    Tue

    16-03-29

    6 Obtain buildingpermits

    4 days Tue16-03-22

    Fri 16-03-25

    7 Submit

    preliminary shop

    drawings

    2 wks Mon

    16-03-28

    Fri 16-04-08

    8 Submit monthly

    requests for

    payment

    1 day Tue

    16-03-22

    Tue

    16-03-22

    9Long Lead

    Procurement

    70 days Wed

    16 03 23

    Tue

    16 06 28

    G.C. General Management

    G.C. Project Management,G.C. General Management[

    G.C. Project Management[25%],G.C. Scheduler

    G.C. General Management[10%],G.C. Project Manag

    G.C. Project Management[50%],G.C. Procurement[50

    G.C. Project Management[50%],G.C. Procurement

    W S T M F T S W S T M F

      '16 Jan 17 '16 Mar 13 '16 May 08 '16 Jul 03 '16 Aug 28 '1

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 1

    Project: Commercial Constructio

    Date: Thu 16-03-17

  • 8/19/2019 Commercial Construction Project Plan

    2/60

    ID Task

    Mode

    Task Name Duration Start Finish

    10 Submit shop

    drawings and

    order long lead

    items - steel

    2 wks Wed

    16-03-23

    Tue

    16-04-05

    11 Submit shop

    drawings and

    order long lead

    items - roofing

    2 wks Mon

    16-04-11

    Fri 16-04-22

    12 Submit shop

    drawings and

    order long lead

    items - elevator

    2 wks Mon

    16-04-11

    Fri 16-04-22

    13 Submit shop

    drawings and

    order long lead

    items - plumbing

    2 wks Mon

    16-04-11

    Fri 16-04-22

    14 Submit shop

    drawings and

    order long lead

    items - electric

    2 wks Mon

    16-04-11

    Fri 16-04-22

    15 Submit shop

    drawings and

    order long lead

    items - HVAC

    2 wks Mon

    16-04-11

    Fri 16-04-22

    Steel Erection Contractor Management

    Roofing Contractor Management

    Elevator Contractor Management

    Plumbing Contractor Management

    Electric Contractor Management

    HVAC Contractor Management

    W S T M F T S W S T M F

      '16 Jan 17 '16 Mar 13 '16 May 08 '16 Jul 03 '16 A

    ug 28 '1

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 2

    Project: Commercial Constructio

    Date: Thu 16-03-17

  • 8/19/2019 Commercial Construction Project Plan

    3/60

    ID Task

    Mode

    Task Name Duration Start Finish

    16 Detail, fabricate

    and deliver steel

    12 wks Wed

    16-04-06

    Tue

    16-06-28

    17Mobilize on Site 10 days Tue 16 03 22Mon 16 04 04

    18 Install

    temporary

    power

    2 days Tue

    16-03-22

    Wed

    16-03-23

    19 Install

    temporary

    water service

    2 days Tue

    16-03-22

    Wed

    16-03-23

    20 Set up site office 3 days Thu 16-03-24Mon 16-03-2

    21 Set line and

    grade

    benchmarks

    3 days Tue

    16-03-29

    Thu

    16-03-31

    22 Prepare site - lay

    down yard and

    temporaryfencing

    2 days Fri 16-04-01 Mon

    16-04-04

    23Site Grading and

    Utilities

    35 days Tue

    16 04 05

    Mon

    16 05 23

    24 Clear and grub

    site

    3 days Tue

    16-04-05

    Thu

    16-04-07

    25 Stone site access

    and temporary

    parking area

    2 days Fri 16-04-08 Mon

    16-04-11

    26 Rough grade site

    (cut and fill)

    1 wk Tue

    16-04-12

    Mon

    16-04-18

    Steel Erection Contractor Man

    Electric Contractor

    Plumbing Contractor

    G.C. Superintendent,G.C. Labor Crew[10%]

    G.C. Survey Crew

    Site Grading Contractor,G.C. Labor Crew[10%]

    Site Grading Contractor

    Site Grading Contractor

    Site Grading Contractor

    W S T M F T S W S T M F

      '16 Jan 17 '16 Mar 13 '16 May 08 '16 Jul 03 '16 A

    ug 28 '1

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 3

    Project: Commercial Constructio

    Date: Thu 16-03-17

  • 8/19/2019 Commercial Construction Project Plan

    4/60

    ID Task

    Mode

    Task Name Duration Start Finish

    27 Install storm

    drainage

    2 wks Tue

    16-04-19

    Mon

    16-05-02

    28 Install exterior

    fire line and

    building fire

    riser

    2 wks Tue

    16-04-19

    Mon

    16-05-02

    29 Perform final

    site grading

    2 wks Tue

    16-05-03

    Mon

    16-05-16

    30 Erect building

    batter boards

    and layout

    building

    1 wk Tue

    16-05-17

    Mon

    16-05-23

    31Foundations 33 days Tue 16 05 24Thu 16 07 07

    32 Excavate

    foundations

    2 wks Tue

    16-05-24

    Mon

    16-06-06

    33 Excavateelevator pit

    2 days Tue16-05-24

    Wed16-05-25

    34 Form column

    piers and spread

    foundations

    4 days Tue

    16-06-07

    Fri 16-06-10

    35 Rough-in electric

    and plumbing in

    elevator

    4 days Thu

    16-05-26

    Tue

    16-05-31

    36 Form elevator

    pit walls

    4 days Wed

    16-06-01

    Mon

    16-06-06

    Site Grading Contractor

    Plumbing Contractor

    Site Grading Contractor

    G.C. Survey Crew

    Site Grading Contractor[50%]

    Site Grading Contractor

    G.C. Rough Carpenter Crew

    Plumbing Contractor,Electric Contra

    G.C. Rough Carpenter Crew

    W S T M F T S W S T M F

      '16 Jan 17 '16 Mar 13 '16 May 08 '16 Jul 03 '16 Aug 28 '1

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 4

    Project: Commercial Constructio

    Date: Thu 16-03-17

  • 8/19/2019 Commercial Construction Project Plan

    5/60

    ID Task

    Mode

    Task Name Duration Start Finish

    37 Set reinforcing

    and anchor bolts

    4 days Mon

    16-06-13

    Thu

    16-06-16

    38 Pour column

    piers and

    foundations

    5 days Fri 16-06-17 Thu

    16-06-23

    39 Pour concrete

    elevator walls

    1 day Tue

    16-06-07

    Tue

    16-06-07

    40 Cure elevator

    wall concrete

    7 days Wed

    16-06-08

    Thu

    16-06-16

    41 Cure piers and

    foundations

    7 days Fri 16-06-24 Mon

    16-07-04

    42 Strip wall forms 1 day Fri 16-06-17 Fri 16-06-17

    43 Strip column

    piers and

    foundation

    forms

    3 days Tue

    16-07-05

    Thu

    16-07-07

    44 Install

    pneumatic tube

    in elevator pit

    3 days Mon

    16-06-20

    Wed

    16-06-22

    45 Prepare and

    pour concrete

    floor in elevator

    pit

    1 day Thu

    16-06-23

    Thu

    16-06-23

    46Steel Erection 45 days Fri 16 07 08 Thu 16 09 08

    G.C. Rough Carpenter Crew

    G.C. Concrete Crew

    G.C. Concrete Crew

    G.C. Labor Crew[10%]

    G.C. Labor Crew[10%]

    G.C. Labor Crew[10%]

    G.C. Labor Crew

    Elevator Contractor

    G.C. Concrete Crew

    W S T M F T S W S T M F

      '16 Jan 17 '16 Mar 13 '16 May 08 '16 Jul 03 '16 Aug 28 '1

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 5

    Project: Commercial Constructio

    Date: Thu 16-03-17

  • 8/19/2019 Commercial Construction Project Plan

    6/60

    ID Task

    Mode

    Task Name Duration Start Finish

    47 Erect steel

    columns, beams

    and joist - 1st

    and 2nd floors

    2 wks Fri 16-07-08 Thu

    16-07-21

    48 Erect steel

    columns, beams

    and joist - 3rdfloor and roof 

    2 wks Fri 16-07-22 Thu

    16-08-04

    49 Install

    miscellaneous

    iron and bracing

    - 1st and 2nd

    floors

    2 wks Fri 16-07-22 Thu

    16-08-04

    50 Install

    miscellaneous

    iron and bracing

    - 3rd floor and

    roof 

    2 wks Fri 16-08-05 Thu

    16-08-18

    51 Install stairs and

    miscellaneous

    iron railing

    2 wks Fri 16-08-19 Thu

    16-09-01

    52 Touch-up paint

    on steel

    1 wk Fri 16-09-02 Thu

    16-09-08

    53Form and Pour

    Concrete Floors

    and Roof

    85 days Fri 16 07 22 Thu

    16 11 17

    Steel Erection Contracto

    Steel Erection Contra

    Steel Erection Contra

    Steel Erection Co

    Steel Erection

    Steel Erectio

    W S T M F T S W S T M F

      '16 Jan 17 '16 Mar 13 '16 May 08 '16 Jul 03 '16 Aug 28 '1

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 6

    Project: Commercial Constructio

    Date: Thu 16-03-17

  • 8/19/2019 Commercial Construction Project Plan

    7/60

    ID Task

    Mode

    Task Name Duration Start Finish

    54 Form 2nd floor

    including all

    floor openings

    5 days Fri 16-09-09 Thu

    16-09-15

    55 Install rebar and

    in-floor utilities

    (including

    mechanical,electrical,

    plumbing)

    5 days Fri 16-07-22 Thu

    16-07-28

    56 Pour 2nd floor

    slab

    4 days Fri 16-09-16 Wed

    16-09-21

    57 Cure 2nd floor

    slab

    7 days Thu

    16-09-22

    Fri 16-09-30

    58 Strip forms from

    2nd floor slab

    2 days Mon

    16-10-03

    Tue

    16-10-04

    59 Form 3rd floor

    including all

    floor openings

    5 days Mon

    16-10-03

    Fri 16-10-07

    60 Install rebar and

    in-floor utilities

    (including

    mechanical,

    electrical,

    plumbing)

    5 days Mon

    16-10-03

    Fri 16-10-07

    61 Pour 3rd floor

    slab

    4 days Mon

    16-10-10

    Thu

    16-10-13

    G.C. Roug

    G.C. Labor Crew[33%],

    G.C. Con

    G.C. La

    G.C. L

    G.C.

    G.C.

    G.C

    W S T M F T S W S T M F

      '16 Jan 17 '16 Mar 13 '16 May 08 '16 Jul 03 '16 Aug 28 '1

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 7

    Project: Commercial Constructio

    Date: Thu 16-03-17

  • 8/19/2019 Commercial Construction Project Plan

    8/60

    ID Task

    Mode

    Task Name Duration Start Finish

    62 Cure 3rd floor

    slab

    7 days Fri 16-10-14 Mon

    16-10-24

    63 Strip forms from

    3rd floor slab

    2 days Tue

    16-10-25

    Wed

    16-10-26

    64 Form roof slab

    including all

    floor openings

    5 days Tue

    16-10-25

    Mon

    16-10-31

    65 Install rebar and

    in-floor utilities

    (including

    mechanical,

    electrical,

    plumbing)

    5 days Tue

    16-10-25

    Mon

    16-10-31

    66 Pour roof slab 4 days Tue 16-11-01Fri 16-11-04

    67 Cure roof slab 7 days Mon 16-11-0 Tue 16-11-15

    68 Strip forms fromroof slab

    2 days Wed16-11-16

    Thu16-11-17

    69 Form 1st floor 4 days Wed 16-10-0 Mon 16-10-1

    70 Install electrical

    underground

    1 wk Wed

    16-10-05

    Tue

    16-10-11

    71 Install plumbing

    underground

    1 wk Wed

    16-10-05

    Tue

    16-10-11

    72 Install rebar and

    in-floor utilities

    4 days Wed

    16-10-05

    Mon

    16-10-10

    73 Pour 1st floor

    slab

    4 days Wed

    16-10-12

    Mon

    16-10-17

     

    G.C.

    Elec

    Plu

    G.C.

    G.

    W S T M F T S W S T M F

      '16 Jan 17 '16 Mar 13 '16 May 08 '16 Jul 03 '16 Aug 28 '1

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 8

    Project: Commercial Constructio

    Date: Thu 16-03-17

  • 8/19/2019 Commercial Construction Project Plan

    9/60

    ID Task

    Mode

    Task Name Duration Start Finish

    74 Cure 1st floor

    slab

    7 days Tue

    16-10-18

    Wed

    16-10-26

    75 Strip forms from

    1st floor slab

    2 days Thu

    16-10-27

    Fri 16-10-28

    76Carpentry Work 15 days Fri 16 11 18 Thu 16 12 08

    77 Install exterior

    sheathing and

    metal studs

    3 wks Fri 16-11-18 Thu

    16-12-08

    78Masonry Work 110 days Fri 16 08 19 Thu 17 01 19

    79 Rough-in

    plumbing at

    toilets and

    masonry walls

    4 wks Mon

    16-10-31

    Fri 16-11-25

    80 Lay masonry at

    core,

    mechanical, andtoilets

    4 wks Fri 16-08-19 Thu

    16-09-15

    81 Install exterior

    masonry work

    5 wks Fri 16-12-09 Thu

    17-01-12

    82 Install roof

    drains

    2 days Fri 17-01-13 Mon

    17-01-16

    83 Install tile in

    toilet rooms

    2 wks Mon

    16-11-28

    Fri 16-12-09

    84 Clean masonry 1 wk Fri 17-01-13 Thu 17-01-19

    85 Clean toilet

    room tile

    1 wk Mon

    16-12-12

    Fri 16-12-16

     

    Masonry C

    W S T M F T S W S T M F

      '16 Jan 17 '16 Mar 13 '16 May 08 '16 Jul 03 '16 Aug 28 '1

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 9

    Project: Commercial Constructio

    Date: Thu 16-03-17

  • 8/19/2019 Commercial Construction Project Plan

    10/60

  • 8/19/2019 Commercial Construction Project Plan

    11/60

    ID Task

    Mode

    Task Name Duration Start Finish

    97Building Finishes 80 days Fri 17 02 17 Thu 17 06 08

    98 Install millwork

    and wood trim

    3 wks Fri 17-03-24 Thu

    17-04-13

    99 Paint walls and

    woodwork

    4 wks Fri 17-04-14 Thu

    17-05-11

    100 Install conduit at

    ceiling plenum

    space

    3 wks Fri 17-02-17 Thu

    17-03-09

    101 Install duct in

    ceiling plenum

    space

    3 wks Fri 17-03-24 Thu

    17-04-13

    102 Install ceiling

    grid

    2 wks Fri 17-04-14 Thu

    17-04-27

    103 Install ceiling tile 2 wks Fri 17-04-28 Thu

    17-05-11

    104Hang wallpaper 2 wks Fri 17-04-28 Thu 17-05-11

    105 Install building

    carpet

    4 wks Fri 17-05-12 Thu

    17-06-08

    106 Install hardware

    and accessories

    3 wks Fri 17-05-12 Thu

    17-06-01

    107 Complete

    interior and

    exterior sod and

    plantings

    2 wks Fri 17-05-12 Thu

    17-05-25

    W S T M F T S W S T M F

      '16 Jan 17 '16 Mar 13 '16 May 08 '16 Jul 03 '16 Aug 28 '1

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 11

    Project: Commercial Constructio

    Date: Thu 16-03-17

  • 8/19/2019 Commercial Construction Project Plan

    12/60

    ID Task

    Mode

    Task Name Duration Start Finish

    108 Pave, curb, and

    stripe parking

    lot

    2 wks Fri 17-05-26 Thu

    17-06-08

    109Elevators 40 days Fri 16 09 16 Thu 16 11 10

    110 Set elevator

    equipment in

    shafts

    4 wks Fri 16-09-16 Thu

    16-10-13

    111 Set equipment

    in mechanical

    room

    2 wks Fri 16-10-14 Thu

    16-10-27

    112 Test and align

    doors and

    equipment

    2 wks Fri 16-10-28 Thu

    16-11-10

    113Plumbing 90 days Fri 17 01 20 Thu 17 05 25

    114 Rough-in

    plumbing in

    drywall walls

    4 wks Fri 17-02-17 Thu

    17-03-16

    115 Tie-in fire line

    riser and set

    valves

    2 wks Fri 17-01-20 Thu

    17-02-02

    116 Set plumbing

    fixtures and trim

    3 wks Fri 17-03-17 Thu

    17-04-06

    117 Flush, test, and

    clean piping and

    fixtures

    2 wks Fri 17-05-12 Thu

    17-05-25

    118Electrical 139 days Mon 16 10 31Thu 17 05 11

    Ele

    W S T M F T S W S T M F

      '16 Jan 17 '16 Mar 13 '16 May 08 '16 Jul 03 '16 Aug 28 '1

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 12

    Project: Commercial Constructio

    Date: Thu 16-03-17

  • 8/19/2019 Commercial Construction Project Plan

    13/60

    ID Task

    Mode

    Task Name Duration Start Finish

    119 Rough-in

    electrical in

    masonry walls

    4 wks Mon

    16-10-31

    Fri 16-11-25

    120 Rough-in

    electrical in

    drywall walls

    4 wks Fri 17-02-17 Thu

    17-03-16

    121 Pull wire inconduit and set

    area

    transformers

    3 wks Fri 17-03-10 Thu17-03-30

    122 Install and

    terminate

    electrical

    devices

    3 wks Fri 17-03-31 Thu

    17-04-20

    123 Make electrical

    terminations for

    HVAC

    equipment

    2 days Fri 17-03-31 Mon

    17-04-03

    124 Install light

    fixtures - test

    and clean

    2 wks Fri 17-04-28 Thu

    17-05-11

    125Heating and

    Ventilating AC

    180 days Fri 16 09 16 Thu

    17 05 25

    126 Set equipment

    in mechanical

    room

    2 wks Fri 16-09-16 Thu

    16-09-29

    HVAC

    W S T M F T S W S T M F

      '16 Jan 17 '16 Mar 13 '16 May 08 '16 Jul 03 '16 Aug 28 '1

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 13

    Project: Commercial Constructio

    Date: Thu 16-03-17

  • 8/19/2019 Commercial Construction Project Plan

    14/60

    ID Task

    Mode

    Task Name Duration Start Finish

    127 Rough-in

    mechanical in

    masonry walls

    4 wks Mon

    16-10-31

    Fri 16-11-25

    128 Rough-in

    mechanical in

    drywall walls

    2 wks Fri 17-02-17 Thu

    17-03-02

    129 Install duct inbuilding chase

    3 wks Fri 17-02-17 Thu17-03-09

    130 Set HVAC trim

    and test and

    balance system

    4 wks Fri 17-04-28 Thu

    17-05-25

    131Final Clean up and

    Occupancy

    60 days Fri 17 03 24 Thu

    17 06 15

    132 Install hard tile

    flooring in

    common areas

    1 wk Fri 17-03-24 Thu

    17-03-30

    133 Clean hard tile

    floors

    4 days Fri 17-03-31 Wed

    17-04-05

    134 Remove debris

    from building

    and do final

    clean-up

    4 days Fri 17-06-09 Wed

    17-06-14

    135 Substantial

    completion date

    1 day Thu

    17-06-15

    Thu

    17-06-15

    136Complete Final

    Inspections

    6 days Thu

    17 06 15

    Thu

    17 06 22

    W S T M F T S W S T M F

      '16 Jan 17 '16 Mar 13 '16 May 08 '16 Jul 03 '16 Aug 28 '1

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 14

    Project: Commercial Constructio

    Date: Thu 16-03-17

  • 8/19/2019 Commercial Construction Project Plan

    15/60

    ID Task

    Mode

    Task Name Duration Start Finish

    137 Complete

    elevator

    inspection and

    certification

    3 days Thu

    17-06-15

    Mon

    17-06-19

    138 Perform

    architect's

    inspection

    1 day Tue

    17-06-20

    Tue

    17-06-20

    139 Perform local

    building agency

    inspection

    1 day Wed

    17-06-21

    Wed

    17-06-21

    140 Perform Fire

    Marshal's

    inspection

    1 day Thu

    17-06-22

    Thu

    17-06-22

    141 Complete punch

    list items from all

    inspections

    2 wks Fri 17-06-23 Thu

    17-07-06

    142 Obtain certificate

    of occupancy

    2 days Fri 17-07-07 Mon

    17-07-10

    143 Issue final

    completion

    documents

    including

    warranties

    1 day Fri 17-07-07 Fri 17-07-07

    144 Issue final request

    for payment

    1 day Tue

    17-07-11

    Tue

    17-07-11

    W S T M F T S W S T M F

      '16 Jan 17 '16 Mar 13 '16 May 08 '16 Jul 03 '16 Aug 28 '1

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 15

    Project: Commercial Constructio

    Date: Thu 16-03-17

  • 8/19/2019 Commercial Construction Project Plan

    16/60

    ent[25%]

      anagement

    nt[50%]

    ment[50%]

    F T S W S T M F T S W S T M F T S W S T M F T S W

      '16 Oct 23 '16 Dec 18 '17 Feb 12 '17 Apr 09 '17 Jun 04 '17 Jul 30 '17 Sep 24 '17 Nov 19 '18 Jan 14 '18 Mar 11 '18 May 06

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 16

    Project: Commercial Constructio

    Date: Thu 16-03-17

  • 8/19/2019 Commercial Construction Project Plan

    17/60

    F T S W S T M F T S W S T M F T S W S T M F T S W

      '16 Oct 23 '16 Dec 18 '17 Feb 12 '17 Apr 09 '17 Jun 04 '17 Jul 30 '17 Sep 24 '17 Nov 19 '18 Jan 14 '18 Mar 11 '18 May 06

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 17

    Project: Commercial Constructio

    Date: Thu 16-03-17

  • 8/19/2019 Commercial Construction Project Plan

    18/60

    r Management[50%],Steel Erection Contractor[50%]

    ]

    F T S W S T M F T S W S T M F T S W S T M F T S W

      '16 Oct 23 '16 Dec 18 '17 Feb 12 '17 Apr 09 '17 Jun 04 '17 Jul 30 '17 Sep 24 '17 Nov 19 '18 Jan 14 '18 Mar 11 '18 May 06

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 18

    Project: Commercial Constructio

    Date: Thu 16-03-17

  • 8/19/2019 Commercial Construction Project Plan

    19/60

      ontractor

    F T S W S T M F T S W S T M F T S W S T M F T S W

      '16 Oct 23 '16 Dec 18 '17 Feb 12 '17 Apr 09 '17 Jun 04 '17 Jul 30 '17 Sep 24 '17 Nov 19 '18 Jan 14 '18 Mar 11 '18 May 06

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 19

    Project: Commercial Constructio

    Date: Thu 16-03-17

  • 8/19/2019 Commercial Construction Project Plan

    20/60

     F T S W S T M F T S W S T M F T S W S T M F T S W

      '16 Oct 23 '16 Dec 18 '17 Feb 12 '17 Apr 09 '17 Jun 04 '17 Jul 30 '17 Sep 24 '17 Nov 19 '18 Jan 14 '18 Mar 11 '18 May 06

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 20

    Project: Commercial Constructio

    Date: Thu 16-03-17

  • 8/19/2019 Commercial Construction Project Plan

    21/60

      tractor

      ontractor

      ontractor[75%]

    n Contractor[75%]

      ction Contractor[50%]

      rection Contractor[20%]

    F T S W S T M F T S W S T M F T S W S T M F T S W

      '16 Oct 23 '16 Dec 18 '17 Feb 12 '17 Apr 09 '17 Jun 04 '17 Jul 30 '17 Sep 24 '17 Nov 19 '18 Jan 14 '18 Mar 11 '18 May 06

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 21

    Project: Commercial Constructio

    Date: Thu 16-03-17

  • 8/19/2019 Commercial Construction Project Plan

    22/60

     Rough Carpenter Crew,G.C. Labor Crew[20%]

    33%],Plumbing Contractor[33%],Electric Contractor[33%]

    . Concrete Crew

    .C. Labor Crew[10%]

    G.C. Labor Crew

    G.C. Rough Carpenter Crew[50%],G.C. Labor Crew[20%]

    G.C. Labor Crew[33%],Plumbing Contractor[33%],Electric Contractor[33%]

    G.C. Concrete Crew

    F T S W S T M F T S W S T M F T S W S T M F T S W

      '16 Oct 23 '16 Dec 18 '17 Feb 12 '17 Apr 09 '17 Jun 04 '17 Jul 30 '17 Sep 24 '17 Nov 19 '18 Jan 14 '18 Mar 11 '18 May 06

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 22

    Project: Commercial Constructio

    Date: Thu 16-03-17

    b l

  • 8/19/2019 Commercial Construction Project Plan

    23/60

    G.C. Labor Crew[10%]

    G.C. Labor Crew

    G.C. Rough Carpenter Crew,G.C. Labor Crew[20%]

    G.C. Labor Crew[33%],Plumbing Contractor[33%],Electric Contractor[33%]

    G.C. Concrete Crew

    G.C. Labor Crew[10%]

    G.C. Labor Crew

    G.C. Rough Carpenter Crew

    Electric Contractor

    Plumbing Contractor

    G.C. Labor Crew[33%],Plumbing Contractor[33%],Electric Contractor[33%]

    G.C. Concrete Crew

    F T S W S T M F T S W S T M F T S W S T M F T S W

      '16 Oct 23 '16 Dec 18 '17 Feb 12 '17 Apr 09 '17 Jun 04 '17 Jul 30 '17 Sep 24 '17 Nov 19 '18 Jan 14 '18 Mar 11 '18 May 06

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 23

    Project: Commercial Constructio

    Date: Thu 16-03-17

    '16 O t 23 '16 D 18 '17 F b 12 '17 A 09 '17 J 04 '17 J l 30 '17 S 24 '17 N 19 '18 J 14 '18 M 11 '18 M 06

  • 8/19/2019 Commercial Construction Project Plan

    24/60

    G.C. Labor Crew[10%]

    G.C. Labor Crew

    Drywall Contractor

    Plumbing Contractor

    nry Contractor

    Masonry Contractor

    Roofing Contractor

    Tile Contractor

    Masonry Contractor[50%]

    Tile Contractor[50%]

    F T S W S T M F T S W S T M F T S W S T M F T S W

      '16 Oct 23 '16 Dec 18 '17 Feb 12 '17 Apr 09 '17 Jun 04 '17 Jul 30 '17 Sep 24 '17 Nov 19 '18 Jan 14 '18 Mar 11 '18 May 06

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 24

    Project: Commercial Constructio

    Date: Thu 16-03-17

  • 8/19/2019 Commercial Construction Project Plan

    25/60

    '16 Oct 23 '16 Dec 18 '17 Feb 12 '17 Apr 09 '17 Jun 04 '17 Jul 30 '17 Sep 24 '17 Nov 19 '18 Jan 14 '18 Mar 11 '18 May 06

  • 8/19/2019 Commercial Construction Project Plan

    26/60

    G.C. Finish Carpenter Crew

    Painting Contractor

    Electric Contractor

    HVAC Contractor

    Drywall Contractor

    Drywall Contractor

    Painting Contractor

    Carpet Contractor

    G.C. Finish Carpenter Crew

    Landscape Contractor

    F T S W S T M F T S W S T M F T S W S T M F T S W

      16 Oct 23 16 Dec 18 17 Feb 12 17 Apr 09 17 Jun 04 17 Jul 30 17 Sep 24 17 Nov 19 18 Jan 14 18 Mar 11 18 May 06

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 26

    Project: Commercial Constructio

    Date: Thu 16-03-17

      '16 Oct 23 '16 Dec 18 '17 Feb 12 '17 Apr 09 '17 Jun 04 '17 Jul 30 '17 Sep 24 '17 Nov 19 '18 Jan 14 '18 Mar 11 '18 May 06

  • 8/19/2019 Commercial Construction Project Plan

    27/60

    Paving Contractor

    Elevator Contractor

    Elevator Contractor

    Elevator Contractor

    Plumbing Contractor

    Plumbing Contractor

    Plumbing Contractor

    Plumbing Contractor

    F T S W S T M F T S W S T M F T S W S T M F T S W

    6 Oct 3 6 ec 8 eb p 09 Ju 0 Ju 30 Sep o 9 8 Ja 8 a 8 ay 06

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 27

    Project: Commercial Constructio

    Date: Thu 16-03-17

      '16 Oct 23 '16 Dec 18 '17 Feb 12 '17 Apr 09 '17 Jun 04 '17 Jul 30 '17 Sep 24 '17 Nov 19 '18 Jan 14 '18 Mar 11 '18 May 06

  • 8/19/2019 Commercial Construction Project Plan

    28/60

    Electric Contractor

    Electric Contractor

    Electric Contractor

    Electric Contractor

    Electric Contractor

    Electric Contractor

    VAC Contractor

    F T S W S T M F T S W S T M F T S W S T M F T S W

    p p y

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 28

    Project: Commercial Constructio

    Date: Thu 16-03-17

      '16 Oct 23 '16 Dec 18 '17 Feb 12 '17 Apr 09 '17 Jun 04 '17 Jul 30 '17 Sep 24 '17 Nov 19 '18 Jan 14 '18 Mar 11 '18 May 06

  • 8/19/2019 Commercial Construction Project Plan

    29/60

    HVAC Contractor

    HVAC Contractor

    HVAC Contractor

    HVAC Contractor

    Tile Contractor

    Tile Contractor[50%]

    G.C. Labor Crew

    G.C. Superintendent

    F T S W S T M F T S W S T M F T S W S T M F T S W

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 29

    Project: Commercial Constructio

    Date: Thu 16-03-17

      '16 Oct 23 '16 Dec 18 '17 Feb 12 '17 Apr 09 '17 Jun 04 '17 Jul 30 '17 Sep 24 '17 Nov 19 '18 Jan 14 '18 Mar 11 '18 May 06

  • 8/19/2019 Commercial Construction Project Plan

    30/60

    Elevator Contractor

    G.C. Superintendent[50%],G.C. Project Management[50%]

    G.C. Project Management[50%],G.C. Superintendent[50%]

    G.C. Superintendent[50%],G.C. Project Management[50%]

    G.C. Superintendent[11%],G.C. Labor Crew[11%],Plumbing Contractor[11%],Electric Co

    G.C. Project Management

    G.C. Project Management

    G.C. Project Management[33%],G.C. Accounting[33%],G.C. General Management[33%]

    F T S W S T M F T S W S T M F T S W S T M F T S W

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 30

    Project: Commercial Constructio

    Date: Thu 16-03-17

    S T M F T S W S T M F T S W S T M F T S W S T M F

    '18 Jul 01 '18 Aug 26 '18 Oct 21 '18 Dec 16 '19 Feb 10 '19 Apr 07 '19 Jun 02 '19 Jul 28 '19 Sep 22 '19 Nov 17 '20 Jan 12 '20

  • 8/19/2019 Commercial Construction Project Plan

    31/60

    S T M F T S W S T M F T S W S T M F T S W S T M F

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 31

    Project: Commercial Constructio

    Date: Thu 16-03-17

  • 8/19/2019 Commercial Construction Project Plan

    32/60

    S T M F T S W S T M F T S W S T M F T S W S T M F

    '18 Jul 01 '18 Aug 26 '18 Oct 21 '18 Dec 16 '19 Feb 10 '19 Apr 07 '19 Jun 02 '19 Jul 28 '19 Sep 22 '19 Nov 17 '20 Jan 12 '20

  • 8/19/2019 Commercial Construction Project Plan

    33/60

    S T M F T S W S T M F T S W S T M F T S W S T M F

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 33

    Project: Commercial Constructio

    Date: Thu 16-03-17

    S T M F T S W S T M F T S W S T M F T S W S T M F

    '18 Jul 01 '18 Aug 26 '18 Oct 21 '18 Dec 16 '19 Feb 10 '19 Apr 07 '19 Jun 02 '19 Jul 28 '19 Sep 22 '19 Nov 17 '20 Jan 12 '20

  • 8/19/2019 Commercial Construction Project Plan

    34/60

    S T M F T S W S T M F T S W S T M F T S W S T M F

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 34

    Project: Commercial Constructio

    Date: Thu 16-03-17

    S T M F T S W S T M F T S W S T M F T S W S T M F

    '18 Jul 01 '18 Aug 26 '18 Oct 21 '18 Dec 16 '19 Feb 10 '19 Apr 07 '19 Jun 02 '19 Jul 28 '19 Sep 22 '19 Nov 17 '20 Jan 12 '20

  • 8/19/2019 Commercial Construction Project Plan

    35/60

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 35

    Project: Commercial Constructio

    Date: Thu 16-03-17

    S T M F T S W S T M F T S W S T M F T S W S T M F

    '18 Jul 01 '18 Aug 26 '18 Oct 21 '18 Dec 16 '19 Feb 10 '19 Apr 07 '19 Jun 02 '19 Jul 28 '19 Sep 22 '19 Nov 17 '20 Jan 12 '20

  • 8/19/2019 Commercial Construction Project Plan

    36/60

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 36

    Project: Commercial Constructio

    Date: Thu 16-03-17

    S T M F T S W S T M F T S W S T M F T S W S T M F

    '18 Jul 01 '18 Aug 26 '18 Oct 21 '18 Dec 16 '19 Feb 10 '19 Apr 07 '19 Jun 02 '19 Jul 28 '19 Sep 22 '19 Nov 17 '20 Jan 12 '20

  • 8/19/2019 Commercial Construction Project Plan

    37/60

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 37

    Project: Commercial Constructio

    Date: Thu 16-03-17

    S T M F T S W S T M F T S W S T M F T S W S T M F

    '18 Jul 01 '18 Aug 26 '18 Oct 21 '18 Dec 16 '19 Feb 10 '19 Apr 07 '19 Jun 02 '19 Jul 28 '19 Sep 22 '19 Nov 17 '20 Jan 12 '20

  • 8/19/2019 Commercial Construction Project Plan

    38/60

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 38

    Project: Commercial Constructio

    Date: Thu 16-03-17

    S T M F T S W S T M F T S W S T M F T S W S T M F

    '18 Jul 01 '18 Aug 26 '18 Oct 21 '18 Dec 16 '19 Feb 10 '19 Apr 07 '19 Jun 02 '19 Jul 28 '19 Sep 22 '19 Nov 17 '20 Jan 12 '20

  • 8/19/2019 Commercial Construction Project Plan

    39/60

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 39

    Project: Commercial Constructio

    Date: Thu 16-03-17

    S T M F T S W S T M F T S W S T M F T S W S T M F

    '18 Jul 01 '18 Aug 26 '18 Oct 21 '18 Dec 16 '19 Feb 10 '19 Apr 07 '19 Jun 02 '19 Jul 28 '19 Sep 22 '19 Nov 17 '20 Jan 12 '20

  • 8/19/2019 Commercial Construction Project Plan

    40/60

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 40

    Project: Commercial Constructio

    Date: Thu 16-03-17

    S T M F T S W S T M F T S W S T M F T S W S T M F

    '18 Jul 01 '18 Aug 26 '18 Oct 21 '18 Dec 16 '19 Feb 10 '19 Apr 07 '19 Jun 02 '19 Jul 28 '19 Sep 22 '19 Nov 17 '20 Jan 12 '20

  • 8/19/2019 Commercial Construction Project Plan

    41/60

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 41

    Project: Commercial Constructio

    Date: Thu 16-03-17

    S T M F T S W S T M F T S W S T M F T S W S T M F

    '18 Jul 01 '18 Aug 26 '18 Oct 21 '18 Dec 16 '19 Feb 10 '19 Apr 07 '19 Jun 02 '19 Jul 28 '19 Sep 22 '19 Nov 17 '20 Jan 12 '20

  • 8/19/2019 Commercial Construction Project Plan

    42/60

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 42

    Project: Commercial Constructio

    Date: Thu 16-03-17

    S T M F T S W S T M F T S W S T M F T S W S T M F

    '18 Jul 01 '18 Aug 26 '18 Oct 21 '18 Dec 16 '19 Feb 10 '19 Apr 07 '19 Jun 02 '19 Jul 28 '19 Sep 22 '19 Nov 17 '20 Jan 12 '20

  • 8/19/2019 Commercial Construction Project Plan

    43/60

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 43

    Project: Commercial Constructio

    Date: Thu 16-03-17

    S T M F T S W S T M F T S W S T M F T S W S T M F

    '18 Jul 01 '18 Aug 26 '18 Oct 21 '18 Dec 16 '19 Feb 10 '19 Apr 07 '19 Jun 02 '19 Jul 28 '19 Sep 22 '19 Nov 17 '20 Jan 12 '20

  • 8/19/2019 Commercial Construction Project Plan

    44/60

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 44

    Project: Commercial Constructio

    Date: Thu 16-03-17

    S T M F T S W S T M F T S W S T M F T S W S T M F

    '18 Jul 01 '18 Aug 26 '18 Oct 21 '18 Dec 16 '19 Feb 10 '19 Apr 07 '19 Jun 02 '19 Jul 28 '19 Sep 22 '19 Nov 17 '20 Jan 12 '20

  • 8/19/2019 Commercial Construction Project Plan

    45/60

      ontractor[11%],HVAC Contractor[11%],Drywall Contractor[11%],Carpet Contractor[11%],Paving Contractor[11%],Painting Contractor[11%]

    ]

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 45

    Project: Commercial Constructio

    Date: Thu 16-03-17

    T S W S T M F T S W S T M F T S W S T M F T S W S

     Mar 08 '20 May 03 '20 Jun 28 '20 Aug 23 '20 Oct 18 '20 Dec 13 '21 Feb 07 '21 Apr 04 '21 May 30 '21 Jul 25 '21 Sep 19 '21 N

  • 8/19/2019 Commercial Construction Project Plan

    46/60

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 46

    Project: Commercial Constructio

    Date: Thu 16-03-17

    T S W S T M F T S W S T M F T S W S T M F T S W S

     Mar 08 '20 May 03 '20 Jun 28 '20 Aug 23 '20 Oct 18 '20 Dec 13 '21 Feb 07 '21 Apr 04 '21 May 30 '21 Jul 25 '21 Sep 19 '21 N

  • 8/19/2019 Commercial Construction Project Plan

    47/60

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 47

    Project: Commercial Constructio

    Date: Thu 16-03-17

    T S W S T M F T S W S T M F T S W S T M F T S W S

     Mar 08 '20 May 03 '20 Jun 28 '20 Aug 23 '20 Oct 18 '20 Dec 13 '21 Feb 07 '21 Apr 04 '21 May 30 '21 Jul 25 '21 Sep 19 '21 N

  • 8/19/2019 Commercial Construction Project Plan

    48/60

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 48

    Project: Commercial Constructio

    Date: Thu 16-03-17

    T S W S T M F T S W S T M F T S W S T M F T S W S

     Mar 08 '20 May 03 '20 Jun 28 '20 Aug 23 '20 Oct 18 '20 Dec 13 '21 Feb 07 '21 Apr 04 '21 May 30 '21 Jul 25 '21 Sep 19 '21 N

  • 8/19/2019 Commercial Construction Project Plan

    49/60

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 49

    Project: Commercial Constructio

    Date: Thu 16-03-17

    T S W S T M F T S W S T M F T S W S T M F T S W S

     Mar 08 '20 May 03 '20 Jun 28 '20 Aug 23 '20 Oct 18 '20 Dec 13 '21 Feb 07 '21 Apr 04 '21 May 30 '21 Jul 25 '21 Sep 19 '21 N

  • 8/19/2019 Commercial Construction Project Plan

    50/60

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 50

    Project: Commercial Constructio

    Date: Thu 16-03-17

    T S W S T M F T S W S T M F T S W S T M F T S W S

     Mar 08 '20 May 03 '20 Jun 28 '20 Aug 23 '20 Oct 18 '20 Dec 13 '21 Feb 07 '21 Apr 04 '21 May 30 '21 Jul 25 '21 Sep 19 '21 N

  • 8/19/2019 Commercial Construction Project Plan

    51/60

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 51

    Project: Commercial Constructio

    Date: Thu 16-03-17

    T S W S T M F T S W S T M F T S W S T M F T S W S

     Mar 08 '20 May 03 '20 Jun 28 '20 Aug 23 '20 Oct 18 '20 Dec 13 '21 Feb 07 '21 Apr 04 '21 May 30 '21 Jul 25 '21 Sep 19 '21 N

  • 8/19/2019 Commercial Construction Project Plan

    52/60

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 52

    Project: Commercial Constructio

    Date: Thu 16-03-17

  • 8/19/2019 Commercial Construction Project Plan

    53/60

    T S W S T M F T S W S T M F T S W S T M F T S W S

     Mar 08 '20 May 03 '20 Jun 28 '20 Aug 23 '20 Oct 18 '20 Dec 13 '21 Feb 07 '21 Apr 04 '21 May 30 '21 Jul 25 '21 Sep 19 '21 N

  • 8/19/2019 Commercial Construction Project Plan

    54/60

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 54

    Project: Commercial Constructio

    Date: Thu 16-03-17

    T S W S T M F T S W S T M F T S W S T M F T S W S

     Mar 08 '20 May 03 '20 Jun 28 '20 Aug 23 '20 Oct 18 '20 Dec 13 '21 Feb 07 '21 Apr 04 '21 May 30 '21 Jul 25 '21 Sep 19 '21 N

  • 8/19/2019 Commercial Construction Project Plan

    55/60

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 55

    Project: Commercial Constructio

    Date: Thu 16-03-17

  • 8/19/2019 Commercial Construction Project Plan

    56/60

    T S W S T M F T S W S T M F T S W S T M F T S W S

     Mar 08 '20 May 03 '20 Jun 28 '20 Aug 23 '20 Oct 18 '20 Dec 13 '21 Feb 07 '21 Apr 04 '21 May 30 '21 Jul 25 '21 Sep 19 '21 N

  • 8/19/2019 Commercial Construction Project Plan

    57/60

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 57

    Project: Commercial Constructio

    Date: Thu 16-03-17

    T S W S T M F T S W S T M F T S W S T M F T S W S

     Mar 08 '20 May 03 '20 Jun 28 '20 Aug 23 '20 Oct 18 '20 Dec 13 '21 Feb 07 '21 Apr 04 '21 May 30 '21 Jul 25 '21 Sep 19 '21 N

  • 8/19/2019 Commercial Construction Project Plan

    58/60

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 58

    Project: Commercial Constructio

    Date: Thu 16-03-17

    T S W S T M F T S W S T M F T S W S T M F T S W S

     Mar 08 '20 May 03 '20 Jun 28 '20 Aug 23 '20 Oct 18 '20 Dec 13 '21 Feb 07 '21 Apr 04 '21 May 30 '21 Jul 25 '21 Sep 19 '21 N

  • 8/19/2019 Commercial Construction Project Plan

    59/60

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 59

    Project: Commercial Constructio

    Date: Thu 16-03-17

  • 8/19/2019 Commercial Construction Project Plan

    60/60