co#4-11046os positive train control project change order #4 october 17, 2013 related to agenda item...
TRANSCRIPT
CO#4-11046OS POSITIVE TRAIN CONTROL PROJECT
Change Order #4
October 17, 2013
Related to Agenda Item 11
2
Background• Purpose:
– Change in scope of the original PTC contract (11046 OS) removing the peer to peer radio communications network and adding the engineering, procurement, installation, test and commission of the network utilizing the fiber optic infrastructure previously installed.
• Background: – The PTC contract originally awarded to Herzog did not
originally utilize the fiber optic network.– Eliminating the peer to peer radio communications and
using the fiber network provides for future expandability and a more robust system.
3
PTC Contract 11046-OS• Addition = $2,905,150.03
– Includes the engineering, procurement, installation, testing, and commissioning of the fiber network.
• Deduction = $1,815,583.00 – Deletes existing scope associated with the Wayside
Segment that is no longer being implemented including field installation, including labor and equipment, wayside communications component material, spare material, test equipment and special tool allowance, and training.
• Net = $1,089,567.03
4
Recommendation• Staff recommends that the Board authorize the
Executive Director to issue a contract change order to Herzog Technologies, Inc. to deduct scope to remove the peer to peer radio communications network in the amount of $1,815,583.00 and to add scope in the amount not-to-exceed $2,905,150.03 for the communications network utilizing the fiber optic infrastructure, with the net difference being $1,089,567. These changes will allow the PTC project to comply with the performance specifications required for the PTC project.