co2 capture ready power plants - iea greenhouse gas r&d ... · co 2 capture ready power plants...
TRANSCRIPT
www.ieagreen.org.uk
COCO22 Capture Ready Power PlantsCapture Ready Power Plants
John Davison
IEA Greenhouse Gas R&D Programme (IEA GHG)([email protected])
CCT2009 Conference, Dresden, Germany, 18th-21st May 2009
www.ieagreen.org.uk
Outline of PresentationOutline of Presentation• Definition of capture ready• Implications for power plants technologies • Economics of capture ready pre-investments• Capture ready policies
www.ieagreen.org.uk
Capture Ready Definition Capture Ready Definition • A CO2 capture-ready power plant is a plant which can
include CO2 capture when the necessary regulatory or economic drivers are in place.
• The aim of building plants that are capture-ready is to reduce the risk of ‘carbon lock-in’ or ‘stranded assets’.
Source: CO2 capture ready plants, IEA GHG report 2007/4, May 2007
www.ieagreen.org.uk
Carbon LockCarbon Lock--in and Stranded Assetsin and Stranded Assets
Time
$/t C
O2
Retrofit CCS, if possible.If not, continue to operate the plant and emit CO2- Carbon Lock-in
Shut down plant without CCS - Stranded Asset
Cost of CCS
Power plant marginal revenue
Carbon price
Present
www.ieagreen.org.uk
Why not Include Full CCS Now? Why not Include Full CCS Now? • Integrated CCS at power plants needs to be
demonstrated• CCS costs are high for demonstration plants• Carbon prices are low• CO2 emission reduction is not a priority in some
countries
www.ieagreen.org.uk
Capture Ready Requirements Capture Ready Requirements • ‘Essential’ requirements
• Carry out a design study on retrofit of CO2 capture• Include sufficient space and access for the additional
facilities that would be required• Identify reasonable route(s) to storage of CO2
• The developer should identify other known factors in their control that would prevent installation and operation of CO2 capture
• Optional pre-investments• To reduce the downtime and cost of capture retrofit• To optimise the plant performance after retrofit
www.ieagreen.org.uk
Space and Access Space and Access • Space for new equipment etc
• CO2 scrubber, oxygen plant, CO2 compressor etc • It may be possible to install some equipment off-site
• Electrical distribution, cooling water, water treating etc• Extra space needed during construction
• Space for access within the existing plant• Pipe work and tie-ins with existing equipment
• Health and safety barrier zones• Additional generating capacity, if required
• CO2 capture usually reduces net power output • By about 20% for current post-combustion and oxy-combustion
• May need to build new capacity to maintain the site power output
www.ieagreen.org.uk
COCO22 Capture Ready PlantCapture Ready Plant
Proposed ‘capture ready’ power plant at Tilbury Courtesy of RWE Npower
‘Capture Ready’
area
www.ieagreen.org.uk
COCO22 Capture Ready PlantCapture Ready Plant
Tilbury plant with capture (some details omitted) Courtesy of RWE Npower
Capture plant
www.ieagreen.org.uk
Routes to CORoutes to CO22 StorageStorage• Identify suitable storage sites or regions• Identify transport routes to the storage site
• Rights of way for pipelines• Safety issues• Proximity to other potential CO2 sources
• Major economies of scale for CO2 transport
www.ieagreen.org.uk
Optional Capture Ready PreOptional Capture Ready Pre--InvestmentsInvestments• Provision for expansion of the control system, electricity
distribution, and cooling capacity and oversizing pipe racks etc• These investments may have low costs and high returns
• Maximizing thermal efficiency• Capture affects the trade-off between efficiency and
capital cost • Select a process that is well suited to capture
• e.g. IGCC instead of pulverised coal• A major investment - may not be worthwhile
www.ieagreen.org.uk
PrePre--Investments Investments -- PostPost--Combustion CaptureCombustion Capture
Fuel Boiler Solvent scrubbing
FGD
Air
Power
CO2 to storage
N2, O2, H2O to atmosphere
Steam turbine
Steam
CO2compression
LP Steam
High efficiency SOx removal to meet the needs of a CO2 scrubber
Ability to upgrade the efficiency
Ability to extract low pressure steam for CO2 solvent regeneration
www.ieagreen.org.uk
PrePre--Investments Investments -- OxyOxy--Combustion Combustion
Fuel Boiler Purification & compression
FGD and cooling
Air separation
Air
Power
Oxygen
CO2
VentRecycled flue gas
Steam turbine
SteamDesign to cope with conditions after
retrofit (if FGD is still required)
Minimise air in-leakage
Design ducts and fans to enable them to be re-used
Design to use low grade heat for feed-water heating
www.ieagreen.org.uk
PrePre--Investments Investments -- IGCC IGCC
Coal Gasification Acid gas removal
Shift conversion
Air separation
Combined cycle
Air
Fuel gas (mainly H2)
NitrogenPower
Oxygen
CO2CO2compression
Sulphur
Air
H2S
Air
Sulphur recovery
Choose a GT that can burn hydrogen
Oversize the gasifiers, to fully load the gas turbines after retrofit
Pre-install shift converters
Oversize the ASU
Design for addition of CO2 separation
www.ieagreen.org.uk
Reasons for not PreReasons for not Pre--InvestingInvesting
• Uncertainties• Economic discounting
www.ieagreen.org.uk
UncertaintiesUncertainties• If or when will capture retrofit be required?
• Future values of CO2 emission permits• Regulatory requirements
• How will capture technologies develop in future?• Incremental improvements• Possibility of substantially better technologies• Will the capture ready investment be for an obsolete
technology?
www.ieagreen.org.uk
Economic DiscountingEconomic Discounting
• Economic resources are worth less in the future than at present
• It may be several years before capture retrofit is required
Major pre-investment is unlikely to be worthwhile if it will be a long time before capture is retrofitted
0
20
40
60
80
100
0 5 10 15 20 25
Year
Net
Pre
sent
Val
ue
5%10%15%
Discount rate
www.ieagreen.org.uk
Implementation of Capture ReadyImplementation of Capture Ready• Utilities will probably choose to make their new plants
capture ready anyway if there is an expectation of high future CO2 prices or regulatory limits• Capture ready is low cost• A non-capture ready plant would be high risk investment
• Include in licensing requirement for new plants
www.ieagreen.org.uk
EU CCS DirectiveEU CCS Directive• Will have to be implemented by Member States by spring 2011• For plants > 300 MWe licensed after then, the operator will have to
have assessed whether the following conditions are met:• Suitable storage sites are available• Transport facilities are technically and economically feasible• It is technically and economically feasible to retrofit for CO2 capture
• If these conditions are met, space for capture and compression should be set aside at the site
• Capture readiness is not necessarily required
www.ieagreen.org.uk
UK UK • UK Government consultation on ‘Towards Capture and Storage’,
including capture readiness • Results published April 2009• Government’s intention not to consent any future applications for new
combustion plants at or over 300MWe unless they are capture ready• Space to be provided on site, or in some cases nearby• Take account of health and safety implications • Operator to report back every 2 years on their capture ready status
• 29th April government announcement on CCS• No new coal plants without CCS demonstration from day one• Up to 4 CCS demonstration plants• Full scale retrofit of CCS within 5 years of the technology being
independently judged as technically and commercially proven
www.ieagreen.org.uk
GermanyGermany• TÜV Nord Standard TN-CC 006• Voluntary assessment of power plant capture readiness• Similar to the requirements in the IEA GHG definition with
some minor additions and clarifications
www.ieagreen.org.uk
ConclusionsConclusions• Capture Ready can reduce the risk of Stranded Assets and
Carbon Lock-in• Essential Capture Ready requirements are:
• Carry out a study of capture retrofit options• Leave space and access for capture retrofit • Identify reasonable route(s) to storage of CO2
• Some optional pre-investment may be worthwhile• Major pre-investment is unlikely to be worthwhile unless capture is
going to be retrofitted soon after start-up of the power plant• Capture Ready should help to facilitate CCS• Capture Ready is not a substitute for capture