CMSC 345
Project Planning
Customer’s Perspective Do you understand my problem? Can you develop and deliver a
system that will solve my problem? How long will it take? How much will it cost?
Project Deliverables Documents Demonstration of function Demonstration of subsystems Demonstration of accuracy Demonstration of extra-functional
properties: reliability, security, performance, etc.
Milestone = end of activity producing deliverable
Project Schedule Derived from deliverables Phases or stages of project Break into discrete activities that produce
deliverables Estimate time each activity will take Estimate number (and skills) of developers
needed to complete each activity Estimate other resources required for each
activity Timeline for activity begin/end and
corresponding delivery
PROJECT
PHASE 1 ACTIVITY 1.1ACTIVITY 1.2ACTIVITY 1.3:
PHASE 2
PHASE n
STEP 1STEP 2:
STEP 1STEP 2:
STEP 1STEP 2:
ACTIVITY 2.1ACTIVITY 2.2ACTIVITY 3.3:
Work Breakdown Structure Depicts project as set of discrete
pieces of work Customer can be informed which
activities are in progress and which milestones have been achieved
Does not show interdependencies and possible parallelism of work units
Build communications software
System planning (1.0) Coding (3.0)Testing(4.0)Delivery (5.0)
Top-level design (2.1)
Prototyping (2.2)
User interface (2.3)
Detailed design (2.4)
System design (2.0)
Review specification(1.1)
Review budget (1.2)
Review schedule(1.3)
Develop plan (1.4)
Activity Definition Precursor: events that must occur
before activity can begin Duration: length of time to complete
activity (estimated) Due date: date when activity must be
completed (e.g., contractual deadline) Endpoint: milestone and/or
deliverable
Activity Graph Depicts dependencies among activities Nodes are project milestones Directed edges are activities involved in
producing those milestones Shows what can be done simultaneously
(assuming sufficient personnel) Depend on understanding of parallel
nature of tasks. If work cannot be done in parallel, the (mostly straight) graph is not useful
Milestones in Building a House1.1 Survey complete1.2 Permits issued1.3 Excavation complete1.4 Materials on hand2.1 Foundations laid2.2 Outside walls complete2.3 Exterior plumbing
complete2.4 Exterior electrical work
complete2.5 Exterior siding
complete
2.6 Exterior painting done2.7 Exterior doors and
fixtures mounted2.8 Roof complete3.1 Interior plumbing done3.2 Interior electrical work
complete3.3 Wallboard in place3.4 Interior painting done3.5 Floor covering laid3.6 Interior doors and
fixtures mounted
1.11.2
1.3
1.4
2.1
2.22.3
2.4
2.5
2.7
2.62.8
3.2
3.3
3.1
3.5
3.6
3.4
START
FINISH
SurveyingRequest permits
Excavation
Buy materials
Lay foundation
Build outside wall
Install interior plumbing Install interior electrical
Install wallboardPaint interior
Installinterior doorsand fixtures
Install flooringInstall roofing
Install exterior plumbing
Install exteriorelectricalInstall exteriorsiding
Paint exterior
Install exteriordoors and fixtures
1.11.2
1.3
1.4
2.1
2.22.3
2.4
2.5
2.7
2.62.8
3.2
3.3
3.1
3.5
3.6
3.4
START
FINISH
315
10
10
15
20
1215
911
7
189
10
10
6
8
5
0
00
0
Project Personnel Differences Ability to perform the work Interest in the work Experience with similar applications Experience with similar tools or languages Experience with similar techniques Experience with similar development
environment Training Ability to communicate with others Ability to share responsibility with others Management skills
Two people 1 line of communication
Three people
Four people
Five people
3 lines of communication
6 lines of communication
10 lines of communication
:n people n(n-1)/2 lines of
communication
Meetings – Ugh! Purpose of meeting unclear Attendees unprepared Essential people absent or late Conversation veers away from purpose Some meeting participants argue,
dominate, or do not participate Decisions made not enacted
afterwards
Productive Meetings Clarify who should attend, when start
and end, and what accomplish Written agenda distributed in advance Moderator to keep discussion on track
and resolve conflicts Recorder records each action item and
ensures it is done Minimize number of meetings and
number of participants
Work Style Components The way your thoughts are
communicated and ideas gathered Extrovert – tell others your thoughts Introvert – ask for suggestions
The degree to which emotions affect decisions
Intuitive – base decisions on feelings Rational – examine facts; consider options
INTUITIVE
RATIONAL
INTR
OV
ER
TEX
TR
OV
ER
T
INTUITIVEINTROVERT:Asks othersAcknowledges feelings
INTUITIVEEXTROVERT:Tells othersAcknowledges feelings
RATIONALINTROVERT:Asks othersDecides logically
RATIONALEXTROVERT:Tells othersDecides logically
Work Styles Rational extrovert: judges
colleagues by results produced, efficiency is priority, good at making sound decisions quickly
Rational introvert: judges peers by busyness, accurate and thorough, gathers all information on subject
Work Styles (2) Intuitive extrovert: follows feelings
(professional judgment), assertive, creative, enjoys interaction
Intuitive introvert: sensitive, good listener, wants to make the right decision, examines relational dependencies and emotions
Implications of Work Styles Determine communication styles Understanding work styles can help
you be flexible in dealing with others Choice of workers for a task
Intuitive may prefer design & development (requiring new ideas)
Rational may prefer maintenance(analysis and attention to detail)
Project Organization Project organization based on
Backgrounds and work styles of members
Number of members Management styles of customers and
developers Flexibility of team members
Chief Programmer Team Chief: totally responsible for design and
development, supervises all others, does all design, assigns programming to others
Understudy: substitutes for chief when necessary
Librarian: maintains documentation, compiles and links code, performs preliminary testing as code submitted
Hierarchy minimizes communication
Chief programmer
Assistant chief programmer
Test teamAdministrationLibrarianSeniorprogrammers
Juniorprogrammers
Egoless Approach Everyone held equally responsible Criticism of process or product, but
not people involved Democratic - members vote on
decisions
Risks Unwanted event with negative consequences Risk impact: loss (of time, quality, money,
control, understanding, etc.) associated with event
Risk probability: likelihood that event will occur Risk control: ability to change outcome (minimize
or avoid impact) Risk exposure: impact * probability, must be
tracked over time Major risk sources:
Generic – common to all software projects Project-specific – threats for this project
Risk Reduction Strategies for risk reduction
Avoid the risk Transfer the risk Assume the risk
Boehm’s Top 10 Risks1. Personnel shortfalls – top talent, morale, team
building2. Unrealistic schedules and budgets – design to
schedule, incremental development, requirements scrubbing
3. Developing the wrong software functions – organizational analysis, prototyping, early user’s manuals
4. Developing the wrong user interface – prototyping, scenarios (use cases)
5. Gold plating – cost-benefit analysis, design to cost
Boehm’s Risks (cont’d)6. Continuing stream of requirements changes –
high change threshold, incremental development
7. Shortfalls in externally performed tasks – preaward audits, competitive design
8. Shortfalls in externally furnished components – inspections, compatibility analysis
9. Real-time performance shortfalls – simulation, instrumentation, tuning, modeling
10. Straining computer science capabilities – technical analysis, prototyping