Page 1: CMS Offline and Computing Project : Status & Plans CMS Offline and Computing Project : Status & Plans Lucia Silvestris INFN-Bari Napoli, 14/02/07

CMS Offline and Computing Project : Status & PlansCMS Offline and Computing Project : Status & Plans

Lucia Silvestris INFN-Bari

Napoli, 14/02/07

Page 2: CMS Offline and Computing Project : Status & Plans CMS Offline and Computing Project : Status & Plans Lucia Silvestris INFN-Bari Napoli, 14/02/07

14/2/200714/2/2007 Planning and MilestonesPlanning and Milestones L. SilvestrisL. Silvestris 2

OutlineOutline

Scope and organizational structure of the projectStatus : some highlights from 2006Plans for 2007:

– Goals and Milestones– Offline Release Plan & Production

Key tasks and manpower needs

Page 3: CMS Offline and Computing Project : Status & Plans CMS Offline and Computing Project : Status & Plans Lucia Silvestris INFN-Bari Napoli, 14/02/07

14/2/200714/2/2007 Planning and MilestonesPlanning and Milestones L. SilvestrisL. Silvestris 3

CMS Organization ChartCMS Organization ChartComputing, Offline, Detector Performance Groups (DPG)Computing, Offline, Detector Performance Groups (DPG)

Computing Coordination

M. KasemmanP. McBride

ReconstructionT. Boccali

S. Rahatlou

SimulationF. CossuttiD. Elvira

Analysis ToolsC. JonesL. Lista

FrameworkL Sexton-Kennedy,

NN

Software Development Tools

D.Lange, A.PFeiffer

L1 SoftwareJ. BrookeW. Sun

Data & Workflow ManagementP. Elmer, NN

Offline Coordination

J. HarveyL. Silvestris

HLT andDQM frameworkE. Meschi, NN

Common Coordination &

Integration Tasks

I.Fish, NN

Fast SimulationF. Beaudette

P. Janot

Commissioning & Run CoordinationT. Camporesi,D.

Acosta

Calibration/Alignment

O. BuchmullerL. Malgeri

ECAL DPG

HCAL DPG

MUON DPG

TRACKER DPG

Facilities / Infrastructure

OperationsD. Bonacorsi,

NN

Data Operations

C. Pauss, NN

Computing Commissioni

ngS.Belforte,

F.Würthwein

User SupportKati Lassila-Perini, NN

Page 4: CMS Offline and Computing Project : Status & Plans CMS Offline and Computing Project : Status & Plans Lucia Silvestris INFN-Bari Napoli, 14/02/07

14/2/200714/2/2007 Planning and MilestonesPlanning and Milestones L. SilvestrisL. Silvestris 4

Much of the new organization is built on continuity– Changes are motivated by preparations for operations– Effective operations of data taking requires close coordination

with Offline and Computing

Scope of Computing The Computing Project is responsible for managing the

computing infrastructure and for all operational aspects of CMS data processing activities.

Scope of the CMS Computing ProjectScope of the CMS Computing Project

Page 5: CMS Offline and Computing Project : Status & Plans CMS Offline and Computing Project : Status & Plans Lucia Silvestris INFN-Bari Napoli, 14/02/07

14/2/200714/2/2007 Planning and MilestonesPlanning and Milestones L. SilvestrisL. Silvestris 5

Scope of CMS Offline ProjectScope of CMS Offline Project

Coordinates release of all CMS Offline SoftwareCore Software Programme: specialist software skills

– Develops framework that implements common software services needed in all data processing applications

– Delivers data and workload management tools, interfaces and monitoring services for the production system

– Supports the development, optimisation, testing, release and distribution of CMS offline software

Integration tasks: physics and software skills– provide oversight and integration framework for delivering

detector subsystem software and high-level physics objects– Reconstruction, Simulation, Fast Simulation, Calibration &

Alignment, Analysis Tools , L1 emulation s/w

Offline discharges responsibility for integration, validation and delivery of releases using the Software Release Plan

Page 6: CMS Offline and Computing Project : Status & Plans CMS Offline and Computing Project : Status & Plans Lucia Silvestris INFN-Bari Napoli, 14/02/07

14/2/200714/2/2007 Planning and MilestonesPlanning and Milestones L. SilvestrisL. Silvestris 6

Status: Highlights from 2006Status: Highlights from 2006

New framework – ~ 0.5 M lines of CMSSW code developed since April 2005

MTCC– Supported readout, calibration, local reconstruction and visualisation of

data– components of Event Filter integrated with DAQ/Run Control system – > 30M events; maximum rate of 200 Hz; transfer rate to CASTOR 20 MB/s– parasitic stream to serve event display and Data Quality Monitoring

consumers

CSA06– Simulation chain extensively validated in terms of robustness and

performance (SVSuite); ~60M events generated– All main reconstruction components included

• local, global, physics objects– Calibration/Alignment - tested ability to pull in constants from Offline DB – fully functional prototype of production system

• WM: Tier 0, MC production system (ProdAgent), CMS Remote Analysis Builder (CRAB), which is used for submission of analysis jobs to the grid DM: successful integration of DBS, DLS, PhEDEx, FronTier, Dashboard

Feb 2007: major milestone for validation of CMSSW wrt ORCA

Page 7: CMS Offline and Computing Project : Status & Plans CMS Offline and Computing Project : Status & Plans Lucia Silvestris INFN-Bari Napoli, 14/02/07

14/2/200714/2/2007 Planning and MilestonesPlanning and Milestones L. SilvestrisL. Silvestris 8

Plans for 2007: MilestonesPlans for 2007: Milestones

End Feb: CMSSW validation complete– Physics-TDR Volume I recovered

End May: MTCC3 & Commissioning tests– First Global Run foreseen; repeated on a monthly basis

Mid June: HLT exercise complete– Full trigger table, algorithms, CPU

Beg July: CSA07 Computing Offline and Analysis Exercise– 5-05 (June): Software complete - HLT, reconstruction,

simulation, calibration & alignment, visualisation and analysis

October 15: First physics papers prepared– Full analysis breakdown; details of how and what for each

physics paper

October 15: Offline and Computing ready for Pilot Runhttp://cms.cern.ch/iCMS/jsp/page.jsp?mode=cms&action=url&urlkey=CMS_OFFLINE

Page 8: CMS Offline and Computing Project : Status & Plans CMS Offline and Computing Project : Status & Plans Lucia Silvestris INFN-Bari Napoli, 14/02/07

14/2/200714/2/2007 Planning and MilestonesPlanning and Milestones L. SilvestrisL. Silvestris 11

Offline Release Plan & ProductionOffline Release Plan & Production

End Jan: 1_2_2 – Complete Physics validation of CMSSW– Production of samples for HLT Studies (Geant4.7.1)

Mid Feb: 1_2_3– Production of samples for Physics Studies (Geant4.7.1)

End Feb : 1_3_0– all components needed for HLT exercise; no changes in geometry– Re-Reco processing with 1_3_x in March

End March : 1_4_0 – Changes to geometry allowed; new/improved local reconstruction

algorithms– Improved DQM and HLT software; support for partial releases.– Integration and commissioning tests with 1_4_x in May-June– Production of SIMU + Digi events for CSA07 start end of April.

Mid May : 1_5_0: – new/improved global reconstruction algorithms and calibration

alignment algorithms– 1_5_x: Production of RECO and AOD for CSA07 can start mid June– 1_5_x: New cycle of integration and commissioning tests in July-August

Page 9: CMS Offline and Computing Project : Status & Plans CMS Offline and Computing Project : Status & Plans Lucia Silvestris INFN-Bari Napoli, 14/02/07

14/2/200714/2/2007 Planning and MilestonesPlanning and Milestones L. SilvestrisL. Silvestris 12

Offline Release Plan & Production Offline Release Plan & Production

Mid June : 1_6_0 – complete calibration & alignment, visualization, analysis

components for CSA07.– 1_6_x: Production of AlCaReco and Physics streams; T1-T2 involved – 1_6_x: New cycle of integration and commissioning tests in July-August

Mid July : 1_7_0 – new cycle with improvements/fixes– 1_7_x: New cycle of integration and commissioning tests August -

November

Beg Sept : 1_8_0 – new cycle with improvements/fixes– Lesson learnt from CSA07 and from integration and commissioning

tests– 1_8_x: New cycle of integration and commissioning tests August-

November

Mid Oct: 1_9_0– 1_9_x: Pilot Run

Page 10: CMS Offline and Computing Project : Status & Plans CMS Offline and Computing Project : Status & Plans Lucia Silvestris INFN-Bari Napoli, 14/02/07

14/2/200714/2/2007 Planning and MilestonesPlanning and Milestones L. SilvestrisL. Silvestris 13

Towards CSA07Towards CSA07

Need to demonstrate performance and capacity of CMS Data and Analysis Model at >50% of 2008 capacity and performance.

– Aim to include DAQ and HLT– Aim for simultaneous functionality– Include functionality we didn’t include in the CSA06 scope

Schedule: summer 2007

Page 11: CMS Offline and Computing Project : Status & Plans CMS Offline and Computing Project : Status & Plans Lucia Silvestris INFN-Bari Napoli, 14/02/07

14/2/200714/2/2007 Planning and MilestonesPlanning and Milestones L. SilvestrisL. Silvestris 15

CSA07 Goals: Increase ScaleCSA07 Goals: Increase Scale

CMS demonstrated 25% performance in 2006. We have two more factors of 2 to ramp up before data taking in 2008The data transfer between Tier-0 and Tier-1 reached about 50% of scale

– Very successful test, but some signs of system stress were visibleJob submission rate reached 25%. Another factor of 2 will be

possible with the current system

– The next factor of two is less clear

We plan another formal challenge in 2007 A >50% challenge in the summer of 2007

– Extend the system to include the HLT farm– Add elements like simulation production– Increase user load– Run concurrent with other experiments stressing the system

Page 12: CMS Offline and Computing Project : Status & Plans CMS Offline and Computing Project : Status & Plans Lucia Silvestris INFN-Bari Napoli, 14/02/07

14/2/200714/2/2007 Planning and MilestonesPlanning and Milestones L. SilvestrisL. Silvestris 19

Key tasks and Manpower needsKey tasks and Manpower needs

in Offline & Computingin Offline & Computing

Page 13: CMS Offline and Computing Project : Status & Plans CMS Offline and Computing Project : Status & Plans Lucia Silvestris INFN-Bari Napoli, 14/02/07

14/2/200714/2/2007 Planning and MilestonesPlanning and Milestones L. SilvestrisL. Silvestris 20

DatabasesDatabases

Variety of DB Subsystems– Construction DB– Equipment Mgt DB– Geometry DB– Configuration DB– Conditions DB– Bookkeeping DB (DBS/DLS)

Figure shows OMDS /ORCON / ORCOF deployment model– All critical CMS data should

reside in this set of databases

Create a Core Database Team to plan

evolution of DB systems together with subsystems

HLTORCON

OnlineOMDS

OfflineORCOF

PVSS Monitoring, Configuration

Monitoring, Configuration

Conditions

Conditions

Online

Offline

Conditions=calibration,alignment, slow controls data

Tier 0

OfflineApps

HCAL

‘tables’

‘objects’

‘objects’

Page 14: CMS Offline and Computing Project : Status & Plans CMS Offline and Computing Project : Status & Plans Lucia Silvestris INFN-Bari Napoli, 14/02/07

14/2/200714/2/2007 Planning and MilestonesPlanning and Milestones L. SilvestrisL. Silvestris 21

Core Database TeamCore Database Team

Main responsibilities are to :– increase commonalities between subsystems– implement and maintain common services and policies– manage common schedules and milestones

Need new effort to setup a core team comprising:– A DB coordinator : physicist profile (physics data, analysis)– Core DB software specialists : C++ and SQL developer profile– Operations team : DBA profile

• co-operate with IT+ other LHC experiments to establish a 24/7 service

Page 15: CMS Offline and Computing Project : Status & Plans CMS Offline and Computing Project : Status & Plans Lucia Silvestris INFN-Bari Napoli, 14/02/07

14/2/200714/2/2007 Planning and MilestonesPlanning and Milestones L. SilvestrisL. Silvestris 22

Calibration and AlignmentCalibration and Alignment

Delivers executable for prompt calibration and alignment task and for the export of constants to the HLTProvides forum for discussing global strategies and policies for driving new calibration updates

– Works closely with the Detector Performance GroupsIt provides mechanisms for accessing databases and migrating data between them in collaboration with Online ProjectSpecific tasks requiring new effort:

- develop the general alignment strategy utilizing the global alignment approaches (e.g. Millepede II)

• How to align >100K parameters with global alignment– implement global alignment approaches into the work and data flow of

prompt alignment/calibration at Tier 0– work and dataflow management for alignment at Tier 1/ Tier 2 centers– establish offline monitoring of online calibration constants

• requires development of new interface in CMSSW

Page 16: CMS Offline and Computing Project : Status & Plans CMS Offline and Computing Project : Status & Plans Lucia Silvestris INFN-Bari Napoli, 14/02/07

14/2/200714/2/2007 Planning and MilestonesPlanning and Milestones L. SilvestrisL. Silvestris 23

HLTHLT and DQM and DQM

Provides infrastructure for executing HLT algorithms in the Filter FarmNew effort needed for commissioning of detector code in Event Filter

– organize and lead online sessions with subdetectors to validate code – prepare and document validation procedures – write documentation for shifters– need to understand many aspects of reconstruction code plus

implication of online operation (access to resources/robustness issues)– become one of the "experts on call" for the filter farm

New effort needed for developing Conditions DB access infrastructure– Collaborate to tests of various options for access to calibration data

from Filter Farm (direct oracle access, frontier/squid,..) – This task needs to converge rapidly on a viable scheme to be used in

the Filter Farm in 2008. Once the solution is identified, the person would become responsible for the deployment/maintenance of the required infrastructure in Cessy. Depending on the solution chosen, this may be in collaboration with external teams

Ideally should be resident at CERN for these tasks

Page 17: CMS Offline and Computing Project : Status & Plans CMS Offline and Computing Project : Status & Plans Lucia Silvestris INFN-Bari Napoli, 14/02/07

14/2/200714/2/2007 Planning and MilestonesPlanning and Milestones L. SilvestrisL. Silvestris 24

HLT and HLT and DQMDQM

DQM provides the monitoring environment for safe operation of the HLT software and Filter Farm

– DQM components are also used in offline monitoring

DQM system essential for the commissioning and operation of CMS– Work with sub-detectors to modularise and make more uniform DQM code– Work on commissioning aspects of DQM in online environment – Manage technical aspects of DQM shift

organization/documentation/training– Liaise with Commissioning and Run Coordination

• DQM half-day workshop in next CMS Week

DQM development work also required– Implementation of history plots and development / adaptation of data

management tools for DQM data– Implementation of a "DQM catalog" database

Effort urgently needed to work on the DQM GUI– Component of IGUANA (event display) - debug tool for offline simulation and

reconstruction, data analysis, test beams, and detector monitoring

Page 18: CMS Offline and Computing Project : Status & Plans CMS Offline and Computing Project : Status & Plans Lucia Silvestris INFN-Bari Napoli, 14/02/07

14/2/200714/2/2007 Planning and MilestonesPlanning and Milestones L. SilvestrisL. Silvestris 25

ReconstructionReconstruction

Delivers executables for event selection in HLT and prompt reconstruction in the Tier0 (and re-R in Tier 1)

Oversees development and manages integration of all reconstruction code and RECO data formats

– local, global, high-level physics objects

Tasks requiring effort– certifying releases used for physics, organizing/testing/

integrating– following the nightly builds; check what went ok/not ok every

day, and help developers to fix problems– make performance optimisation studies - cpu, memory

footprint; act as a contact person to the Performance Task Force

Page 19: CMS Offline and Computing Project : Status & Plans CMS Offline and Computing Project : Status & Plans Lucia Silvestris INFN-Bari Napoli, 14/02/07

14/2/200714/2/2007 Planning and MilestonesPlanning and Milestones L. SilvestrisL. Silvestris 26

FrameworkFramework

Provides the necessary services for building CMS data processing applications (reconstruction, analysis)

– Module scheduling, event setup, provenance tracking, EDM…

Effort is concentrated at FNAL - people based in Europe (preferably CERN) are needed to work closely with HLT

and Tier 0 projects, especially during commissioningDevelopment effort is needed for several tasks

– Geometry infrastructure; improvements to the DDD ( XML-based detector description language) and regression testing and validation of the CMS geometry at every release

– Infrastructure code for the Calibration and Alignment databases

– Development and maintenance of the event setup and parameter set services

Page 20: CMS Offline and Computing Project : Status & Plans CMS Offline and Computing Project : Status & Plans Lucia Silvestris INFN-Bari Napoli, 14/02/07

14/2/200714/2/2007 Planning and MilestonesPlanning and Milestones L. SilvestrisL. Silvestris 27

SimulationSimulation

Delivers full CMS simulation program– framework that interfaces to geometry, event generators,

and Geant4 – Performs tuning and validation, profiling and optimisation

studies – Oversees production workflow of MC data samples

Most urgent tasks requiring effort– improvement/maintenance of Magnetic Field interface to

Geant4, implementation of new field maps, development of validation code

– work on local magnetic field management is needed to speed up full simulation. Needs significant Geant4 expertise.

– GFLASH infrastructure, implementation and tuning of EM and HAD showers to full simulation.

– develop simulation tools/features requested by users, interact and support users

Page 21: CMS Offline and Computing Project : Status & Plans CMS Offline and Computing Project : Status & Plans Lucia Silvestris INFN-Bari Napoli, 14/02/07

14/2/200714/2/2007 Planning and MilestonesPlanning and Milestones L. SilvestrisL. Silvestris 28

Software Development ToolsSoftware Development Tools

Prepares and maintains the software environment for development,release, distribution and deploymentA major task requiring effort relates to development of the Software Validation Suite (SVSuite) for certifying new releases of CMSSW applications

– involves communication with all groups involved: now mainly simulation, reconstruction,...in the future other groups doing trigger, calib/align, fast simulation, MC/data comparison packages

– Integration/testing of all packages into the MC Production environment– Communication with computing about production of RelVal samples and

with the rest of the software groups on configuration file availability– Coordination of the software validation process at the time of a release.– Integration of DQM tools into SVSuite: histogram transfer to server, web

publishing, implementation of macros as DQM client programs

Page 22: CMS Offline and Computing Project : Status & Plans CMS Offline and Computing Project : Status & Plans Lucia Silvestris INFN-Bari Napoli, 14/02/07

14/2/200714/2/2007 Planning and MilestonesPlanning and Milestones L. SilvestrisL. Silvestris 29

Data and Workflow Mgt ToolsData and Workflow Mgt Tools

Development of tools used in production system– Data management tools: DBS and DLS, PhEDEx, Frontier– Workload management tools: CRAB, ProdAgent system,Tier 0 – Monitoring tools, CMS Dashboard– Web interfaces to enhance end-user usability

Tasks requiring effort– a developer to work on the Tier 0 workflow system, and its

integration with the HLT and Data Management system– a developer to join the team working on the production system,

including various features and improvements: https://twiki.cern.ch/twiki/bin/view/CMS/ProdAgentDevPlanCurrent

– A developer to work on web interfaces to the WM/DM tools

Page 23: CMS Offline and Computing Project : Status & Plans CMS Offline and Computing Project : Status & Plans Lucia Silvestris INFN-Bari Napoli, 14/02/07

14/2/200714/2/2007 Planning and MilestonesPlanning and Milestones L. SilvestrisL. Silvestris 30

Fast SimulationFast Simulation

Provides a framework for fast simulation and reconstruction– interaction of particles in the tracker are simulated and shower

parametrizations are used in the calorimeters– standard reconstruction algorithms used for track reconstruction, b-

tagging, clustering, jets etc.

Tasks requiring effort– simulation of the L1 calorimeter trigger; the standard L1 emulator cannot

be used, since it relies on the digis which are not available in the FastSimulation; a parametrization of the L1 response on trigger tower basis has to be developed

– simulation of the hits in the muon detector; the path and the energy deposit of the muons in the calorimeters have to be computed

– precise tuning of the fast simulation using real (testbeam) data– detailed comparison of the Fast Simulation output w.r.t. the Full

Simulation output in a wide range of energy

Page 24: CMS Offline and Computing Project : Status & Plans CMS Offline and Computing Project : Status & Plans Lucia Silvestris INFN-Bari Napoli, 14/02/07

14/2/200714/2/2007 Planning and MilestonesPlanning and Milestones L. SilvestrisL. Silvestris 31

Analysis ToolsAnalysis Tools

Provide a software suite integrated with the framework that facilitates data and physics analysis

Organise and manage release of libraries developed in physics analysis projects

Provide frameworks that support batch and interactive analysis– FWLite, Iguana, Python, PROOF, ROOT

Effort needed for all parts of the work programme including– porting the FWLite based code to Microsoft's VC++ and work on an

Windows 'friendly' installation– creating a 'provenance viewer' for EDM ROOT files which runs nicely

in ROOT

Page 25: CMS Offline and Computing Project : Status & Plans CMS Offline and Computing Project : Status & Plans Lucia Silvestris INFN-Bari Napoli, 14/02/07

14/2/200714/2/2007 Planning and MilestonesPlanning and Milestones L. SilvestrisL. Silvestris 32

Level 1 SoftwareLevel 1 Software

The L1 Trigger offline software includes packages that provide

bit-level emulation of the trigger electronics, along with tools

for interpreting, monitoring and analysing L1 data.A further task would be to figure out exactly how the HLT Supervisor will communicate with CMSSW modules(e.g. through EventSetup). Another project would be to develop prototype offline DB schema for emulator configuration constants.

Page 26: CMS Offline and Computing Project : Status & Plans CMS Offline and Computing Project : Status & Plans Lucia Silvestris INFN-Bari Napoli, 14/02/07

14/2/200714/2/2007 Planning and MilestonesPlanning and Milestones L. SilvestrisL. Silvestris 33

Integration Integration

N.N. forIntegration I.Fisk, N.N.Organize the program of work for integrating the software infrastructure (production tools, applications) and data

handling systems (facilities, data operations) in preparation for data

taking

Senior Physicists/Computer Scientist with computing expertise,operations experience and organizational talentsPresence at CERN: 50%, (I.Fisk is 25% at CERN)coordination of remote activities from remote (this was done by M.Ernst)

Page 27: CMS Offline and Computing Project : Status & Plans CMS Offline and Computing Project : Status & Plans Lucia Silvestris INFN-Bari Napoli, 14/02/07

14/2/200714/2/2007 Planning and MilestonesPlanning and Milestones L. SilvestrisL. Silvestris 34

Data OperationsData Operations

N.N. forData Operations C.Paus, N.N.Responsible for data processing and executing productionworkflows.Overall responsibility to ensure that detector corrections, calibration and alignment constants are readily applied at prompt processing and distributed.

Senior Physicists with computing expertise and operationsexperience and organizational talentsPresence at CERN: 50%, (C.Paus is >75% at CERN)coordination of remote activities from remote is feasable

Page 28: CMS Offline and Computing Project : Status & Plans CMS Offline and Computing Project : Status & Plans Lucia Silvestris INFN-Bari Napoli, 14/02/07

14/2/200714/2/2007 Planning and MilestonesPlanning and Milestones L. SilvestrisL. Silvestris 35

Facility/InfrastructureFacility/Infrastructure

N.N. forFacility / Infrastructure Operations D.Bonacorsí, N.N.Responsible to provide and maintain a working distributed

computing fabric. - consistent working environment for the Data operation and the users- Coordination of facilities operation, resource management- liaison to external projects and organisations involved in this

process.

Physicist/Computer Scientist with strong systems and grid systems expertise

- Presence at CERN required 100% (D.Bonacorsi is 50% at CERN)

Page 29: CMS Offline and Computing Project : Status & Plans CMS Offline and Computing Project : Status & Plans Lucia Silvestris INFN-Bari Napoli, 14/02/07

14/2/200714/2/2007 Planning and MilestonesPlanning and Milestones L. SilvestrisL. Silvestris 36

User SupportUser Support

N.N. forProvide user support for analysis K.Lassila-Perini, N.N.Helpdesk, triaging of problemsProvide guidance to user for trouble shooting analysis jobsOrganize and provide documentationOrganize tutorialsDefine what is need for users to monitor and track jobs and data in the

systemUser accounts and VO management

Coordination based at CERN– team based at CERN– involvement of SW developers– involvement of Physicist teaching how to perform analysis– user support front-end person at each T1/T2

Physicist or Computer Scientist with good data analysis experience, writing skills to assist users

- Presence at CERN: up to 50% (K.Lassila-perini is 100% at CERN)

Page 30: CMS Offline and Computing Project : Status & Plans CMS Offline and Computing Project : Status & Plans Lucia Silvestris INFN-Bari Napoli, 14/02/07

Back-upBack-up

Page 31: CMS Offline and Computing Project : Status & Plans CMS Offline and Computing Project : Status & Plans Lucia Silvestris INFN-Bari Napoli, 14/02/07

14/2/200714/2/2007 Planning and MilestonesPlanning and Milestones L. SilvestrisL. Silvestris 38

Relationship to Run CoordinationRelationship to Run Coordination

Commissioning will involve large scale tests of data- and work-flow in steps up to full scale operation in 2008Run coordination is making a plan for the commissioning and operation of the CMS detectorEffective operations of data-taking requires close coordination with Offline and ComputingWeekly to daily interaction with contacts, in particular

– DQM - monitoring, error diagnostics– HLT - operation of online filter software– Calibration and alignment, derivation of constants and population

of database– Reconstruction - identify and solve problems, ensure quality of

data

Integration tasks are critical component of commissioning and run activities (releases, databases)

Page 32: CMS Offline and Computing Project : Status & Plans CMS Offline and Computing Project : Status & Plans Lucia Silvestris INFN-Bari Napoli, 14/02/07

MeetingsMeetings

Page 33: CMS Offline and Computing Project : Status & Plans CMS Offline and Computing Project : Status & Plans Lucia Silvestris INFN-Bari Napoli, 14/02/07

14/2/200714/2/2007 Planning and MilestonesPlanning and Milestones L. SilvestrisL. Silvestris 40

Weekly Offline Meeting Schedule Weekly Offline Meeting Schedule

Start Time Monday Tuesday Wednesday Thursday Friday08:3009:0009:3010:0010:3011:0011:3012:0012:3013:0013:3014:0014:3015:0015:3016:0016:3017:0017:3018:0018:3019:00

COMPUTING

L1 Coordination

Task Forces/ Production

Tools/ Framework &

SW Devel Tools

Commissioning

Calibration & Alignment/ HLT&DQM

Reconstruction/ Analysis

Tools

Simulation/ Level1 SW/

Fast Simulation

J oint Comp/ Off L2

Online Selection

Plenary/Physics

Detectors Offline

Joint Commissioning

Offline

Page 34: CMS Offline and Computing Project : Status & Plans CMS Offline and Computing Project : Status & Plans Lucia Silvestris INFN-Bari Napoli, 14/02/07

14/2/200714/2/2007 Planning and MilestonesPlanning and Milestones L. SilvestrisL. Silvestris 41

Physics DaysPhysics Days

Start Time Monday Tuesday Wednesday Thursday Friday08:3009:0009:3010:0010:3011:0011:3012:0012:3013:0013:3014:0014:3015:0015:3016:0016:3017:00

17:3018:0018:30

Common Offline-

Computing meeting

J oint Offline-Physics meeting

Reports from DPGs,

alignment & calibration,

commissioning news

Physics Coordination

Meeting

Analysis Groups

presentations

Plenary Physics Meeting (group

highlights, analysis

approvals)

POG and analysis meetings

Page 35: CMS Offline and Computing Project : Status & Plans CMS Offline and Computing Project : Status & Plans Lucia Silvestris INFN-Bari Napoli, 14/02/07

14/2/200714/2/2007 Planning and MilestonesPlanning and Milestones L. SilvestrisL. Silvestris 42

Joint Offline/Physics Meetings during Physics DaysJoint Offline/Physics Meetings during Physics Days

6 Feb 6-8 Feb27 Mar 27-29 Mar24 Apr Physics Trigger Week22 May 22-24 May11-15 Jun Annual Review10 Jul 10-12 Jul31 Jul 31-2 Aug28 Aug 28-20 Aug23 Oct Physics Trigger Week13 Nov 13-15 Nov

Offline and Computing Weeks16 Apr Offline & Computing Week15 Oct Offline & Computing Week

Page 36: CMS Offline and Computing Project : Status & Plans CMS Offline and Computing Project : Status & Plans Lucia Silvestris INFN-Bari Napoli, 14/02/07

14/2/200714/2/2007 Planning and MilestonesPlanning and Milestones L. SilvestrisL. Silvestris 43

CMS weeksCMS weeks

Monday Tuesday Wednesday Thursday Friday8:30 Sub-Detectors Plenary Plenary Physics9:00 Sub-Detectors Parallel Technical Coordn Computing Plenary II9:30 Parallel and Software10:0010:3011:00 OPENING 11:30 SESSION12:0012:30

CB

14:00 Plenary Physics14:30 Commissioning Plenary I15:0015:30 PM16:00 Reports16:3017:0017:3018:00 FB Special MB18:3019:00

Page 37: CMS Offline and Computing Project : Status & Plans CMS Offline and Computing Project : Status & Plans Lucia Silvestris INFN-Bari Napoli, 14/02/07

14/2/200714/2/2007 Planning and MilestonesPlanning and Milestones L. SilvestrisL. Silvestris 44

CMS Week Meetings 26 Feb -2 MarCMS Week Meetings 26 Feb -2 Mar

Plenary Offline and Computing Meeting on Thursday afternoon instead of Thursday morning

Parallel session can be done during Tuesday full day, Wednesday and Thursday morning

CMS Tutorial on Tuesday morning

Page 38: CMS Offline and Computing Project : Status & Plans CMS Offline and Computing Project : Status & Plans Lucia Silvestris INFN-Bari Napoli, 14/02/07

SchedulesSchedules

Page 39: CMS Offline and Computing Project : Status & Plans CMS Offline and Computing Project : Status & Plans Lucia Silvestris INFN-Bari Napoli, 14/02/07

14/2/200714/2/2007 Planning and MilestonesPlanning and Milestones L. SilvestrisL. Silvestris 46

Offline/Production ScheduleOffline/Production Schedule

Releases/Milestones Production Activities

End Jan : 1_2_1: Production version for HLT StudiesEnd Jan : 1_2_2: Version to be used for Physics Validation of CMSSW

1_2_1: HLT Production and Physics analysis Production Feb-March. Mainly Generation and Simulation step.

Mid Feb : Complete Physics Validation of CMSSW

End Feb : 1_3_0: all components needed for HLT exercise; no changes in geometry; Geant4.7.1End Feb : 1_3_0_Geant4.81 all components needed for HLT exercise; no changes in geometry; Geant4.7.1

1_3_x: re-reprocessing for HLT in March 1_3_x: Production of Physics Samples (30M/mth) Reco Step in March1_3_x_geant4.81 Validation samples

End March : 1_4_0 : Changes to geometry allowed. new/improved local reconstruction algorithmsImproved DQM and HLT SW. This release should resolve dependencies problems in a way that we can release Online releases without Geant4 components.

1_4_x: HLT test in April 1_4_x: Integration and Commissioning tests in May 1_4_x: Production of SIMU end of April

Page 40: CMS Offline and Computing Project : Status & Plans CMS Offline and Computing Project : Status & Plans Lucia Silvestris INFN-Bari Napoli, 14/02/07

14/2/200714/2/2007 Planning and MilestonesPlanning and Milestones L. SilvestrisL. Silvestris 47

Offline/Production ScheduleOffline/Production Schedule

Releases/Milestones Production Activities

Mid May : 1_5_0: new/improved global reconstruction algorithms and calibration alignment algorithms

1_5_x: Production of RECO and AOD can start mid June T0 Production for CSA07

1_5_x: New cycle of integration and commissioning tests in July-August

Mid June : 1_6_0 – complete calibration & alignment, visualization and analysis components needed CSA07.

1_6_x: Production of AlCaReco and Physics streams. T1-T2 involved 1_6_x: New cycle of integration and commissioning tests in July-August

mid July : 1_7_0 - new cycle withimprovements/fixes

This version will need also an Online ReleaseFurther updated on Geometry and Data format

1_7_x: New cycle of integration and commissioning tests August- November

Page 41: CMS Offline and Computing Project : Status & Plans CMS Offline and Computing Project : Status & Plans Lucia Silvestris INFN-Bari Napoli, 14/02/07

14/2/200714/2/2007 Planning and MilestonesPlanning and Milestones L. SilvestrisL. Silvestris 48

Offline/Production ScheduleOffline/Production Schedule

Releases/Milestones Production Activities

Beg Sept : 1_8_0 - new cycle withimprovements/fixesLesson learnt from CSA07 and integration and commissioning tests

1_8_x: New cycle of integration and commissioning tests August- November and Pilot Run.

Mid Oct: 1_9_0 1_9_x: Pilot Run

Page 42: CMS Offline and Computing Project : Status & Plans CMS Offline and Computing Project : Status & Plans Lucia Silvestris INFN-Bari Napoli, 14/02/07

14/2/200714/2/2007 Planning and MilestonesPlanning and Milestones L. SilvestrisL. Silvestris 49

Updated Milestones for LHCCUpdated Milestones for LHCC