UNIVERSITY OF THE EAST

RECTO, MANILA

COLLEGE OF ENGINEERING

CIVIL ENGINEERING DEPARTMENT

“PROPOSED TWO – STOREY RESIDENTIAL

BUILDING WITH ROOF DECK”

CONSTRUCTION METHOD AND PROJECT MANAGEMENT

NCE 514 – CE1

SUBMITTED BY:

AQUINO, ROSEMAY T.

20110109574

SUBMITTED TO:

ENGR. MARYCON A. SERRANO

24 MARCH 2015

Page 2: CMPM PROJECT.pdf

ACKNOWLEDGMENT

It would not have been possible to write this project without the help and support of the kind

people of whom it is possible to give particular mention here.

Above all, I would like to thank God for the guidance He has providing me throughout this work,

for the wisdom He is giving me, and for giving knowledge as well.

I would like to thank Engr. Jefferson A. Lachica, Owner of JLachica Construction and Consultancy,

who guided me and had given me the knowledge I needed to finish this work.

I would also like to express sincere appreciation to young and beautiful Professor, Engr. Marycon

A. Serrano, who has supported the students throughout this work with patience and knowledge. The

students know that it wouldn’t have been possible to finish this requirement without the Professor’s great

supervision.

Finally, I thank my parents for the support throughout all studies at University of the East – Manila

and for providing a home in which to complete the project.

Page 3: CMPM PROJECT.pdf

TABLE OF CONTENTS

I. Project Description .................................................................................................................................... 1

II. Construction Drawings .................................................................................................................... 2 – 16

III. Bill of Quantities ......................................................................................................................... 17 – 107

IV. Schedules ................................................................................................................................... 108 – 112

4.1 Gantt Chart ............................................................................................................................. 108

4.2 Manpower Schedule .............................................................................................................. 109

4.3 Equipment Schedule ............................................................................................................... 110

4.4 Precedence Network ............................................................................................................. 111

4.5 S – Curve ................................................................................................................................. 112

V. Work Methodogy Statement ................................................................................................ 113 – 127

VI. Appendix .................................................................................................................................. 128 – 136

6.1 Resume ......................................................................................................................... 128 – 131

6.2 Computation for Labor ............................................................................................. 132 – 136

6.3 Rates Used .................................................................................................................. 132 – 136

Page 4: CMPM PROJECT.pdf

PROJECT DESCRIPTION

Name: Proposed Two – Storey Residential Building with Roof Deck

Lot Area: 240 square meters

Floor Area: 400.948875 square meters

Location: Guiguinto, Bulacan

Engineer: Engr. Jefferson A. Lachica

Owner: Carolina Rosales and Rowena Rosales

Page 5: CMPM PROJECT.pdf

GANTT CHART

Page 6: CMPM PROJECT.pdf

MANPOWER SCHEDULE

MANPOWER SCHEDULE

MANPOWER WEEKS

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

Foreman 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Carpenter 2 2 3 3 6 6 6 6 6 6 4 4 4 4

Mason 2 2 4 4 4 4 4 6 6 6 6 4 4

Electrician 3 2 3 3 1 1 1 2 2

Plumber 2 2 2 3 3 3 2 2

Welder 3 3 3 3 4 4 2

Painter 6 6 6 6

Steelman 2 2 3 3 5 6 6 6 6 6 3

Helper / Laborer 5 7 7 10 10 10 10 10 8

Others:

Surveyor 1

Survey Aid 1

TOTAL: 3 5 7 14 18 23 27 32 34 37 38 29 25 20 21 11

Page 7: CMPM PROJECT.pdf

EQUIPMENT SCHEDULE

EQUIPMENT SCHEDULE

EQUIPMENTS WEEKS

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

Mini - Excavator 1 1 1 1

Plate Compactor 1 1

Concrete Mixer 1 1 1 1 1 1 1 1 1

Concrete Vibrator 1 1 1 1 1 1 1 1 1

Welding Machine 2 2 2

Rebar Cutter 2 2 2 2 2 2 2 2 2 2

Rebar Bender 2 2 2 2 2 2 2 2 2 2

Grinder 2 2 2 2 2 2

Compressor 2 2 2 2

TOTAL: 5 5 6 6 6 6 10 8 10 8 4 4 6 4 2

Page 8: CMPM PROJECT.pdf

PRECEDENCE NETWORK

Page 9: CMPM PROJECT.pdf

S – CURVE

Page 10: CMPM PROJECT.pdf

ROSEMAY T. AQUINO 4 Davao Street Bago Bantay, Quezon City

Contact Numbers: 0905-9332013 239-2712/982-8163

E-mail Address: [email protected]

OBJECTIVE To increase my knowledge, skills and experience in the applications of Civil Engineering in the

industry and gain an insight on how the industry works as a preparation of my future career.

ELIGIBILITY

7th HONORABLE MENTION 1st YEAR and 2nd YEAR – 2nd SEMESTER

Quezon City Academy University of the East – Manila Batch 2010 – 2011 Academic Half – Scholar

S.Y. 2011 – 2012

EDUCATIONAL ATTAINMENT

Tertiary Education: University of the East - Manila

Bachelor of Science in Civil Engineering

S.Y. 2011 – Present

Secondary Education: Quezon City Academy 1144 Epifanio delos Santos Avenue, Quezon City S.Y. 2007 - 2011

Primary Education: Bago Bantay Elementary School

Bago Bantay, Quezon City S.Y. 2001 - 2007

WORK EXPERIENCE

CASHIER @ MOA Arena’s VIP RESTAURANT BBMarciano Catering Services 52 Road 2, Pag-asa, Quezon City

Tel. (02) 929-8291 April 2014 – May 2014

ASSISTANT BANQUET MANAGER BBMarciano Catering Services

52 Road 2, Pag-asa, Quezon City Tel. (02) 929-8291 December 17, 2011 – April 2013

Page 11: CMPM PROJECT.pdf

PERSONAL INFORMATION

Birthday : December 10, 1994

Age : 20 years old Gender : Female Height : 4’ 11”

Civil Status : Single Religion : Methodist / Born Again Christian Skills : Knowledgeable in Microsoft office

(i.e. Excel, Word, PowerPoint, Publisher, etc.) : Skilled in some Design / Engineering software

(i.e. AutoCAD, Google Sketchup, Solid Edge) : Have good negotiating skills.

: Has the ability to attend good customer relation and has good communication skills

TRAININGS/SEMINARS ATTENDED ENGINEERING SEMINAR 2015

Safe and Sound: An Engineering Checklist on Redefining Safety February 07, 2015

University of the Philippines – Los Baños JPICE STUDENT’S SEMINAR

Building Supremacy February 02, 2015 University of the East – Manila

THE ROTARACT SERVICE AND LEADERSHIP JOURNEY

Rotaract Club of San Francisco Del Monte – Malaya Achievers January 15, 2015 Bluepoint Building Kamuning, Quezon City

INFRASTRUCTURE SOLUTIONS FOR SUSTAINING THE ENVIRONMENT AND PROFESSIONS

November 26, 2014 University of the East – Manila

ENGINEERS ON SCENE A Civil Engineering Specialization Congress November 21, 2013

University of the East – Manila

NATIONAL CIVIL ENGINEERING SYMPOSIUM 2013 September 06, 2013

University of the Philippines – Diliman

AFFILIATIONS ACES PICE

Treasurer (S.Y. 2015 – 2016) University of the East – Manila 2219 CM Recto Avenue Sampaloc, Manila

YOUTH PROFESSIONAL CIRCLE

Word of Hope Christian Family Church EDSA, Quezon City May 13, 2014 – Present

CHOIR, MUSIC MINISTRY

Word of Hope Christian Family Church EDSA, Quezon City March 2011 – August 2013

Page 12: CMPM PROJECT.pdf

CHARACTER REFERENCES

ENGR. MARK ANTHONY L. ESCOBER

Instructor, College of Engineering University of the East – Manila 09178046486

ENGR. MARYCON A. SERRANO Instructor, College of Engineering

University of the East – Manila 09175527595

ENGR. REGINALD G. MORA Instructor, College of Engineering

University of the East – Manila 09275560762

I hereby certify that the above information is true and correct to the best of my

knowledge and belief.

____________________ ROSEMAY T. AQUINO

Page 13: CMPM PROJECT.pdf

COMPUTATION FOR LABOR and RATES USED

ACTIVITY QUANTITY UNIT UNIT/MH NO. OF WORKERS NO. OF DAYS

I. MOBILIZATION AND DEMOBILIZATION 1.00 lot 1 20 112

II. SURVEY WORKS 1.00 lot 40 2 7

III. SITE CLEARING 1.00 lot 1 2 3

IV. EARTHWORKS

Excavation 213.22 cu.m. 0.255 10 17

Gravel Bedding 5.48 cu.m. 9.46 2 4

Lean Concrete 1.19 cu.m. 9.46 2 3

Soil Poisoning 261.90 sq.m. - 4 3

Backfill 275.38 cu.m. 1.22 5 3

Earthfill 120.00 cu.m. 1.22 4 3

Compaction 118.61 cu.m. 7 3 7

V. CIVIL STRUCTURAL WORKS

Form Works

79

Footing 29.68 sq.m. 1 5 13

Columns 208.98 sq.m. 0.85 4 24

Footing Tie Beam 61.88 sq.m. 1 7 5

Wall Footing 26.60 sq.m. 1 5 3

Slab on Grade 110.32 sq.m. 1.2 10 2

Suspended Slab 115.96 sq.m. 1.2 9 7

Stairs 14.05 sq.m. 1.2 5 7

Beams and Girders 75.67 sq.m. 0.65 7 11

Roof Beams 73.14 sq.m. 0.65 8 4

Septic Tank 2.40 sq.m. 1.2 5 3

Page 14: CMPM PROJECT.pdf

COMPUTATION FOR LABOR and RATES USED

ACTIVITY QUANTITY UNIT UNIT/MH NO. OF WORKERS NO. OF DAYS

Form Works

Footing 47.35 kgs. 10 3 14

Columns 3,314.06 kgs. 10 4 24

Footing Tie Beam 789.12 kgs. 10 3 15

Wall Footing 229.35 kgs. 10 3 3

Slab on Grade 965.50 kgs. 10 5 3

Suspended Slab 965.50 kgs. 10 5 10

Stairs 186.00 kgs. 10 4 6

Wall 6,614.21 kgs. 10 10 25

Beams and Girders 1,494.49 kgs. 10 9 5

Roof Beams 1,413.84 kgs. 10 8 4

Septic Tank 44.3907042 kgs. 10 4 3

Concrete Works 33

Footing 27.42 cu.m. 0.665 5 3

Columns 10.51 cu.m. 1.1 4 8

Footing Tie Beam 6.19 cu.m. 0.765 5 4

Wall Footing 3.33 cu.m. 0.765 5 2

Slab on Grade 11.0324375 cu.m. 1.262 4 2

Suspended Slab 11.8081875 cu.m. 0.986 2 4

Stairs 0.83 cu.m. 0.2 2 4

Beams and Girders 5.27 cu.m. 1.262 3 2

Roof Beams 4.70 cu.m. 1.262 3 2

Septic Tank 3.84 cu.m. 0.2 3 2

Structural Steel Works 5,308.88 kgs. 20 5 10

Page 15: CMPM PROJECT.pdf

COMPUTATION FOR LABOR and RATES USED

ACTIVITY QUANTITY UNIT UNIT/MH NO. OF WORKERS NO. OF DAYS

VI. ARCHITECTURAL WORKS

Masonry Works

CHB Laying 1,167.29 sq.m. 6.4 12 25

Plastering 1,167.29 sq.m. 7.5 14 21

Floor Topping 141.51 sq.m. 1.33 4 21

Ceiling Works 424.52 sq.m. 2.4 3 21

Tile Works

Supply and Installation of 200 x 200 Lavatory Counter Tiles 13.00 sq.m. 3.2 3 7

Supply and Installation of 300 x 300 Toilet Wall Tiles 123.23 sq.m. 3.2 5 14

Supply and Installation of 600 x 600 Floor Tiles 141.51 sq.m. 2.67 6 25

Supply and installation of 150 x 900 Vinyle Planks 71.66 sq.m. 4 4 7

Painting Works

Wall Painting (Semi Gloss Latex in Roller Finish) 1,743.05 sq.m. 7 3 28

Ceiling Painting (Flat Latex in Roller Finish) 424.52 sq.m. 8 2 21

Painting of Doors (Enamel Paint in Roller Finish) 36.96 sq.m. 7 2 7

Doors and Windows 43.00 sets 4 4 7

Carpentry Works 1 lot - 3 14

Metal Works 1 lot - 5 21

VII. ELECTRICAL WORKS

Roughing - ins 1 lot - 5 27

Wires and Cables 1 lot - 4 21

Fixtures and Devices 1 lot - 3 7

Testing and Commissioning 1 lot - 3 7

Page 16: CMPM PROJECT.pdf

COMPUTATION FOR LABOR and RATES USED

ACTIVITY QUANTITY UNIT UNIT/MH NO. OF WORKERS NO. OF DAYS

VIII. PLUMBING AND SANITARY WORKS

Roughing - ins 1 lot - 8 34

Fixtures and Devices 1 lot - 6 7

Testing and Commissioning 1 lot - 3 14

IX. THERMAL AND MOISTURE PROTECTION 218.75 sq.m. 9 7

X. SITE DEVELOPMENT WORKS

Fence and Posts 1 lot - 8 28

Lights 1 lot - 4 7

Gates 2 sets - 4 21

Page 17: CMPM PROJECT.pdf

SCHEDULES

Page 18: CMPM PROJECT.pdf

APPENDIX