cm p planning

Upload: ahmed

Post on 03-Apr-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 CM P Planning

    1/19

    Project Planning

    13/01/2002 Emad Elbeltagi

    Project Planning

    Planning in General : SWOT analysis

    S: Strengths

    W: Weaknesses

    O: Opportunities

    T: ThreatsObjectives should be: SMART

    S: Specific

    M: Measurable

    A: Achievable

    R: Realistic

    T: Timely

  • 7/28/2019 CM P Planning

    2/19

    13/01/2002 Emad Elbeltagi

    Project Planning

    Characteristics of a good plan

    Based on clearly definite and practical objectives Simple

    Flexible

    Easy to control

    Provide proper standards

    Exploit existing resources, etc.

    13/01/2002 Emad Elbeltagi

    Project Planning

    Planning Inputs and Outputs

    Contract information

    Drawings

    SpecificationsAvailable resources

    Bills of quantities

    Site reports

    Organizational data

    Construction methods

    Activities

    Relationships among activities

    Method statement

    Responsibility

    Reporting levels

    Project network diagram

    Activities duration

    Activities cost

    INPUTS OUTPUTS

    PLANNING

  • 7/28/2019 CM P Planning

    3/19

    13/01/2002 Emad Elbeltagi

    Project Planning

    Planning Major steps

    Determination of Project Activities (WHAT)

    Establishment of Logic; Relationships and overlap (How)

    Presentation (Table, Network, Chart, )

    Estimate Activities Duration and Cost (When)

    13/01/2002 Emad Elbeltagi

    Project Planning

    Work Breakdown Structure (WBS)

    The WBS is a hierarchical structure which is designed to

    logically sub-divide all the work-elements of the project into

    smaller elements.

    House

    Civil Plumping Electrical

    Foundations Walls/

    Roof

    Pipin

    g

    H/C

    Water

    Wiring Finishing

  • 7/28/2019 CM P Planning

    4/19

    13/01/2002 Emad Elbeltagi

    Project Planning

    Work Breakdown Structure (Why)

    Prepare project plan

    Identifying Activities

    Scheduling

    Identifying cost & schedule at various levels of

    details

    Time & cost control

    Identifying individual or departmental responsibilities

    13/01/2002 Emad Elbeltagi

    Project Planning

    WBS & Organizational Breakdown Structure (OBS)

    Project

    Area 1 Area 3

    Beams Columns Slabs

    Formwork Reinforcement Concreting

    OBS

    (Responsibility

    & reporting)

    Area 2

    Project

    manager

    WBS (Work elements)

    Subcontr

    actor A

    General

    contractor

    Subcontr

    actor B

    Civil

    superinte

    ndent

    Mechanic

    al

    superinte

    ndent

    Electricalsuperinte

    ndent

    Formwork

    foreman

    Rebar

    foreman

    Concrete

    foreman

    Control account

  • 7/28/2019 CM P Planning

    5/19

    13/01/2002 Emad Elbeltagi

    Project Planning

    WBS Coding

    Each work package or activity in a WBS is given a

    unique code that is used in project planning and

    control Identifying Activities

    13/01/2002 Emad Elbeltagi

    Project Planning

    Project Activities

    Project is divided into segments of work called activities

    Activity: Time-consuming single work element

    Guidelines for project breakdown: by: area of

    responsibility, structural element, category of work, etc.

    Level of details depends on: planning stage, size of the

    project, complexity of the work, etc.

  • 7/28/2019 CM P Planning

    6/19

    13/01/2002 Emad Elbeltagi

    Project Planning

    Project Activities

    Types of construction activities:

    Production: taken directly from drawings and/or

    specifications

    Management (Approvals, site establishment, etc).

    Procurement (equipment delivery, material

    procurement)

    13/01/2002 Emad Elbeltagi

    Project Planning

    Project Activities

    Example (Double Span Bridge):

    Precast

    beams

    Deck

    slab

    Road base left Road base right

    Hand rail

  • 7/28/2019 CM P Planning

    7/19

    -Clear site200

    -Bridge railing190

    -Road surface180

    -Right road base170

    -Left road base160

    -Construct deck slab155

    -Fill right embankment150

    -Fill left embankment140

    -Erect right P.C. Beams120

    -Erect left P.C. Beams110

    -Construct central pier100

    -Construct right abutment90

    -Construct left abutment80

    -Foundation central pier70

    -Foundation right abutment60

    -Foundation left abutment50

    -Excavate central pier40

    -Excavate right abutment30

    -Excavate left abutment20

    -Procure P.C. Beams16

    -Procure RFT14

    -Set-up site10

    DescriptionCode

    13/01/2002 Emad Elbeltagi

    Project Planning

    Activities Relationships

    The order in which project activities are to be performed

    Which activity(ies) must be completed before an activity

    can start

    Which activity(ies) can not start until activity completion

    Which activity(ies) have no logical relations

    Logic constraints: Physical, and Resources

  • 7/28/2019 CM P Planning

    8/19

    13/01/2002 Emad Elbeltagi

    Project Planning

    Predecessors

    Controls the start or finish of another activity

    Successors

    Depends on the start or finish of another activity

    Predecessor

    to Act. B

    Successor to

    Act. B

    180, 190Clear site200

    155Bridge railing190

    155, 160, 170Road surface180

    150Right road base170

    140Left road base160

    110, 120Construct deck slab155

    90Fill right embankment150

    80Fill left embankment140

    16, 90, 100Erect right P.C. Beams120

    16, 80, 100Erect left P.C. Beams110

    70Construct central pier100

    60Construct right abutment90

    50Construct left abutment80

    14, 40Foundation central pier70

    14, 30Foundation right abutment60

    14, 20Foundation left abutment50

    10Excavate central pier40

    10Excavate right abutment30

    10Excavate left abutment20

    ---Procure P.C. Beams16

    ---Procure RFT14

    ---Set-up site10

    PredecessorsDescriptionCode

  • 7/28/2019 CM P Planning

    9/19

    13/01/2002 Emad Elbeltagi

    Project Planning

    Type of Activities Relationships

    Four Types:

    Finish to Start (FS) Finish to Finish (FF)

    Start to Start (SS) Start to Finish (SF)

    FS FF

    SS SF

    13/01/2002 Emad Elbeltagi

    Project Planning

    Type of Activities Relationships

    Finish-Start

    When A finishes, then B can start

    Default Relationship

    A

    First Activity

    B

    Second Activity

  • 7/28/2019 CM P Planning

    10/19

    13/01/2002 Emad Elbeltagi

    Project Planning

    Type of Activities Relationships

    Start-Start

    When A starts, then B can start

    A

    First Activity

    B

    Second Activity

    13/01/2002 Emad Elbeltagi

    Project Planning

    Type of Activities Relationships

    Finish-Finish

    When A finishes, then B can finish

    AFirst Activity

    B

    Second Activity

  • 7/28/2019 CM P Planning

    11/19

    13/01/2002 Emad Elbeltagi

    Project Planning

    Type of Activities Relationships

    Start-Finish

    When A starts, then B can finish

    A

    First Activity

    B

    Second Activity

    13/01/2002 Emad Elbeltagi

    Project Planning

    Overlaps

    how much a particular activity must be completed

    before a succeeding activity may start

    Used for activities not using the same type of resources

    With a value less than the duration of the preceding activity

    +ve overlap (-ve lag) -ve overlap (+ve lag)

  • 7/28/2019 CM P Planning

    12/19

    13/01/2002 Emad Elbeltagi

    Project Planning

    Overlaps

    Example

    Consider the construction of the following sequential activities of

    a bridge consists of 19 bays

    Pile manufacturing with duration 2.5 wks/pier

    Pile driving with duration 1.5 wks/pier

    Pile cap with duration 2.0 wks/pier

    Pier shaft with duration 2.5 wks/pier

    Determine the appropriate overlap between activities

    13/01/2002 Emad Elbeltagi

    Project Planning

    Relationships Considering Resource Constraints

    -

    A1B1

    A1

    B1, A2

    C1, B2

    A2

    B2, A3

    C2, B3

    -

    A1B1

    -

    A2

    B2

    -

    A3

    B3

    Excavate unit 1

    Concreting unit 1Brickwork unit 1

    Excavate unit 2

    Concreting unit 2

    Brickwork unit 2

    Excavate unit 3

    Concreting unit 3

    Brickwork unit 3

    A1

    B1C1

    A2

    B2

    C2

    A3

    B3

    C3

    Predecessors

    (constrained

    resources)

    Predecessors

    (unconstrained

    resources)

    descriptionActivity

  • 7/28/2019 CM P Planning

    13/19

    13/01/2002 Emad Elbeltagi

    Project Planning

    Project networks: AOA

    Two Types:

    Activity-On-Arrow; AOA (Arrow Networks).Activity-On-Node; AON (Precedence Networks):

    AOA

    Activity represented as arrows with start and finish nodes called

    Events

    i jActivity A

    j > i

    13/01/2002 Emad Elbeltagi

    Project Planning

    Project networks: AOA

    5A

    10 15B

    B depends on A

    5A

    10 15C

    5

    B

    C depends on A and B

    5A

    10 15C

    15B B depends on A

    C depends on A

    15D

    15C C depends on A and B

    D depends on A and B

    5

    B 10

    5 A

  • 7/28/2019 CM P Planning

    14/19

    13/01/2002 Emad Elbeltagi

    Project Planning

    Project networks: AOA

    Dummy activity

    Activity with zero duration and no resources to adjust the network

    Incorrect representation

    20C

    5A

    15

    10

    B

    C depends on A and B; D depends on B only

    25

    D

    Correct representation

    5A

    20 25C

    1510B

    30D

    Dummy

    15A

    5

    B

    5 15A

    10

    BDummy

    13/01/2002 Emad Elbeltagi

    Project Planning

    Project networks: AON

    AOA

    Activity represented as nodes

    10

    A

    Activity number

    Activity name

  • 7/28/2019 CM P Planning

    15/19

    13/01/2002 Emad Elbeltagi

    Project Planning

    Project networks: AON

    B depends on A10

    A

    20

    B

    C depends on A and B

    D depends on C

    30

    C

    10

    A

    20

    B

    40

    D

    B depends on A

    C depends on B

    D depends on B

    10

    A

    20

    B

    40D

    30

    C

    13/01/2002 Emad Elbeltagi

    Project Planning

    Project networks: Example

    --

    A, B

    C

    C

    D

    D, E

    AB

    C

    D

    E

    F

    G

    PredecessorsActivity

  • 7/28/2019 CM P Planning

    16/19

    13/01/2002 Emad Elbeltagi

    Project Planning

    Project networks: Example (AOA)

    13/01/2002 Emad Elbeltagi

    Project Planning

    Project networks: Example (AON)

    SS(C)+1 = 4

    SS(D)+1 = 4

    Highest of [SS(D), SS(E)] = 5

    Highest of [SS(F), SS(G)] = 5

    C

    D

    D, E

    F, G

    E

    F

    G

    Finish

    Calculate the Sequence step

    Start - SS(Start) = 1

    A - SS(Start) +1 = 2

    B - SS(Start) +1 = 2

    C A, B Highest of [SS(B), SS(A)] = 3

    D C SS(C) +1 = 4

    Activity Predecessor Sequence step (SS)

  • 7/28/2019 CM P Planning

    17/19

    13/01/2002 Emad Elbeltagi

    Project Planning

    Project networks: Example (AON)

    Sequence step 1 2 3 4 5 6

    13/01/2002 Emad Elbeltagi

    Project Planning

    Activity Duration & Direct Cost

    Planning time unit (hours, days, weeks, months)

    Establish method statement (method of construction)

    Specify number of resources, and hence output

    Duration = Quantity of work / No. of Res. x Res. Output

  • 7/28/2019 CM P Planning

    18/19

    13/01/2002 Emad Elbeltagi

    Project Planning

    Activity Duration & Direct Cost

    Productivity data

    Man-hours/ unit

    Mhrs/unit

    Daily production

    Units/day

    How long it takes form one

    labor to finish one unit

    Applies to any crew formation

    How many units can be done

    in one time unit

    Applies to a given crew

    Productivity can be estimated:

    From published data ( )

    Previous records of a company

    13/01/2002 Emad Elbeltagi

    Project Planning

    Activity Duration & Direct CostExample

    What is the duration to install 6000 square feet of walls shuttering if:

    Crew of 2 carpenters is used, output of 200 square feet/day

    Productivity is measured as 0.008 man-hour/square feet. Number

    of carpenters =3, and number of working hours/day = 8 hours

    a. Duration = 6000 / 200 = 3 days

    b. Total man-hours needed = 6000 x 0.008 = 48 man-hours (if one manused)

    Duration = 48 / 8 = 6 days (if one man used)

    Duration using 3 men = 6 / 3 = 2 days

  • 7/28/2019 CM P Planning

    19/19

    13/01/2002 Emad Elbeltagi

    Project Planning

    Activity Duration & Direct Cost

    Example (balanced mix of resources)

    A wall involves 660 m3 concrete, 50 tone of steel, and 790 m2 of formwork.

    - A 6 man concrete crew can place 16 m3 of concrete/day.

    - A steel-fixer and assistant can fix 0.5 ton of reinforcement/day.

    - A carpenter and assistant can fix and remove 16 m2 of shuttering/day

    - using one steel-fixer: duration = 50 / 0.5 = 100 days

    - using one carpenter: duration = 790 / 16 = 49.4 days

    - using one concreting crew: duration = 660 / 16 = 41.25 days.

    2 steel-fixer crews, one carpenter crew, and cone concreting crew.

    duration = 50 / 0.5 x 2 = 50 days

    13/01/2002 Emad Elbeltagi

    Project Planning

    Activity Duration & Direct Cost

    Activity direct cost:

    Duration, resources, and cost are interrelated elements

    Direct cost comprises: labor, material, equipment, and/or

    subcontractors

    Unit cost = total cost / quantity