CKOV1 at the MICE Experiment. TOF2. EMCAL. TOF0. TOF1. CKOV1. CKOV1 to perform mu/pi id w TOF0/TOF1. Progress since CM16 CKOV1 Fabrication and Installation. L. Cremaldi, CM17 CERN, Feb 24, 2007. 2 Threshold Aerogel Counters. Aerogel Counter. L. Cremaldi, CM17 CERN, Feb 24, 2007. - PowerPoint PPT PresentationTRANSCRIPT
1
CKOV1 at the MICE Experiment
•CKOV1 to perform mu/pi id w TOF0/TOF1.•Progress since CM16•CKOV1 Fabrication and Installation
TOF0 CKOV1 TOF1 EMCALTOF2
L. Cremaldi, CM17 CERN, Feb 24, 2007
2
2 Threshold Aerogel Counters2 Threshold Aerogel Counters
Aerogel Counter
L. Cremaldi, CM17 CERN, Feb 24, 2007
3
A
B
C
ISIS Beam Line ISIS Beam Line
4
Magnetic Shielding- 2D Model
9.4%
4.6% 3.4%
3.3%
58%
48% 41%
17%
Btube = 10%BZ + 60% BBZg , B <5g
BZ
B
L. Cremaldi, CM17 CERN, Feb 24, 2007
5
- H20 fraction is negligible.- Tested with low energy betas.- Background may be dominated by-rays, etc.
L. Cremaldi, CM17 CERN, Feb 24, 2007
6
QuickTime™ and aTIFF (Uncompressed) decompressor
are needed to see this picture.
Rate Tests
L. Cremaldi, CM17 CERN, Feb 24, 2007
7
Rate Tests
L. Cremaldi, CM17 CERN, Feb 24, 2007
8
Number of Photo Electrons vs Frequency
0
10
20
30
40
50
60
70
0 1000 2000 3000 4000 5000 6000 7000
Frequency (kHz)
# of PE
8in 5PE8in 10PE8in 15PE8in 20PE8in 25PE5in 5PE8inTB
Transistor base prototype
Resistive base
RCA 8854 Transistor base
L. Cremaldi, CM17 CERN, Feb 24, 2007
9
Transistor Base Transistor Base
L. Cremaldi, CM17 CERN, Feb 24, 2007
10
CKOV1 Electronics
•CAEN V1724 8 Channel 14 bit 100 MS/s FlashADC 250-500 ps t resolution•CAEN V1290 TDC 25 ps t resolution
20 ns.div
L. Cremaldi, CM17 CERN, Feb 24, 2007
11
-Machining- UM-Nickel Plating-Ready in Spring '07 for light tests
Light Box AssemblyLight Box Assembly
L. Cremaldi, CM17 CERN, Feb 24, 2007
12
-Needed June/July ‘07.-Aerogel order in Mar’07-4mo lead time?-Assembly in Mississippi-Ship to RAL in Jul ’07
Radiator Box AssemblyRadiator Box Assembly
L. Cremaldi, CM17 CERN, Feb 24, 2007
13L. Cremaldi, CM17 CERN, Feb 24, 2007
- CKOV1 Platform Design-GG -Decision should be made if RAL or US responsiblity.
14
-Magnetic shields and PMT assemblies from Treste.-Mu-metal shield needs modification and re-annealing.-10 PMTs checked at Trieste before shipping to RAL. (UM)
PMT + Shield AssemblyPMT + Shield Assembly
L. Cremaldi, CM17 CERN, Feb 24, 2007
15
Mirror Flashing Concept Mirror Flashing Concept
•Mirror aluminized in 2 sections.
•Large Vacuum vessel.
16
Mirror Fabrication
•CERN Facility - Andre Braem - meeting next week•FNAL Facility - Eileen Hahn - Lab7
Large Vacuum Chamber- Off Line.Small Chamber- On Line.
90cm id
38cm id
L. Cremaldi, CM17 CERN, Feb 24, 2007
44cm id
60cm od
17
quartz fiber PMT
DAQGate
LED Pulser
LED Pulser•Non-linear Response•Sensitive to LED Vapp•Adequate for Monitoring•Calibration of 1-Photon
•LEDs mounted near PMTs•Pulser fanned out at CKOV1•Two BNC control lines.
VME/NIMPULSER
L. Cremaldi, CM17 CERN, Feb 24, 2007
18
Alignment & Self Calibration - 1,2 PE most probable in PMT 1-4.- Small correlation with muon x,y.- Data 1,2 pe signals self calibrating- Some Alignment of CKOV1 by balancing PMT light yield.
L. Cremaldi, CM17 CERN, Feb 24, 2007
19
CKOV1 Services - 12 45m signal cables RG-58 type. 8 CKOV1 signals 2-Pulser 2 spare Should terminate at a patch panel in the Control Room.
- 10 SHV type high voltage cables. - HV supply not specified yet, may start with something simple Lecroy 4032??
-4 Low voltage Monitor cables for humidity sensor, gas flow, etc
-Dry air supply for mirror box or silica gel packs.
- NIM Crate for Pulser and checkout.
ckov1
Contr
Room
45m
20
CKOV1 ScheduleCKOV1 Schedule
Mar Apr May Jun Jul Aug Sep Oct ‘07
Light Box
Aerogel Order
Mirror
Assemble
PMT Check + Housing to RAL
PMT Bases(FNAL)
Radiator Box
Mirror Assembly
Nickle Plate
CKOV1 Stand (RAL)
Mu-metal Shield Mod(??)
L. Cremaldi, CM17 CERN, Feb 24, 2007
Radiator Box
21
Hardware/Software Experience
•TOF + CKV systems installed by hardware experts. H2 Testbeam CERN
• User analysis by software experts FNAL.
•Specialization, wave of the future!
L. Cremaldi, CM17 CERN, Feb 24, 2007
22