PRODUCT COST CONTROLLING END USER TRAINING DOCUMENTS COST CENTER ACCOUNTING CK40N - Functionality Costing run is basically a single transaction code which covers both CK11N (Create cost estimate) and CK24 (Mark and release cost estimate). Further it has the benefit that you can do a mass costing (more than one material) at the same time and more than one plant at the same time. Thus you should always use costing run even to cost a single material code, because when you mark and release it marks and release even for all the lower level material codes which have BOM and recipe. Scenario We want to do a mass costing run for all the finished and semi finished products that are valued at standard price. Requirements Bill of Materials must be maintained. Activity prices must exist as planned prices on the cost centers. Routings and activity types must be maintained. Menu Path Accounting Controlling Product Cost Controlling Product Cost Planning Material Costing CK40N - Edit Costing Run Transaction Code CK40N 1. Double click on CK40N - Edit Costing Run. Page 1 of 40

Upload: peter-sand

Post on 07-Mar-2015

2.406 views

Category:

Documents


8 download

TRANSCRIPT

Page 1: CK40N Edit Costing Run Instruction

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

CK40N -

Functionality

Costing run is basically a single transaction code which covers both CK11N (Create cost estimate) and CK24 (Mark and release cost estimate).Further it has the benefit that you can do a mass costing (more than one material) at the same time and more than one plant at the same time.Thus you should always use costing run even to cost a single material code, because when you mark and release it marks and release even for all the lower level material codes which have BOM and recipe.

Scenario

We want to do a mass costing run for all the finished and semi finished products that are valued at standard price.

Requirements

Bill of Materials must be maintained. Activity prices must exist as planned prices on the cost centers. Routings and activity types must be maintained.

Menu Path Accounting Controlling Product Cost Controlling Product Cost Planning Material Costing CK40N - Edit Costing Run

Transaction Code CK40N

1. Double click on CK40N - Edit Costing Run.

Page 1 of 37

Page 2: CK40N Edit Costing Run Instruction

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

Edit Costing Run

2. Click the Create button.

Page 2 of 37

Page 3: CK40N Edit Costing Run Instruction

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

Create Costing Run

3. Update the following fields:

Field Name Description Values

Costing run Costing run name 9100_06

Costing run Costing run description Costing run for Company 9100

Costing run date Costing run date of creation 03.03.2006

Costing variant Costing variant Z9P1

Costing version Costing version (always use this value)

01

Controlling area Controlling Area. 9100

Company Code legal entity for which costing is carried out.

9100

4. Click the Enter button.

Page 3 of 37

Page 4: CK40N Edit Costing Run Instruction

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

Create Costing Run

Note: Check posting period specified in the field 'Posting period'. Stock will be revaluated for this period.

5. Update the following fields:

Field Name Description Values

Costing date from Description of the Costing date from.

03.03.2006

Qty structure date Description of the Qty structure date.

03.03.2006

Valuation date Description of the Valuation date.

03.03.2006

6. Click the Enter button.

7. Click the Save button.

Page 4 of 37

Page 5: CK40N Edit Costing Run Instruction

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

Edit Costing Run

8. Click the Selection Parameter button.

Page 5 of 37

Page 6: CK40N Edit Costing Run Instruction

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

Costing Run: Selection - Change Parameters

9. Update the following fields:

Field Name Description Values

Material Type Code identifying the material type Eg Semi-finished & Finished goods.

HALB click & update FERT

Plant Code identifying the operational unit of the company where the material is manufactured and stored

9100

10. Click the Background processing to deselect.

11. Click the Save button.

12. Click the Back button.

Page 6 of 37

Page 7: CK40N Edit Costing Run Instruction

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

Edit Costing Run

13. Click the Selection Execute button.

Page 7 of 37

Page 8: CK40N Edit Costing Run Instruction

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

Edit Costing Run

14. Click the Costing results Collapse button

15. Click the Materials Overview button and scroll down

Page 8 of 37

Page 9: CK40N Edit Costing Run Instruction

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

16. Click the Struct. explosion Parameter button.

Page 9 of 37

Page 10: CK40N Edit Costing Run Instruction

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

Costing Run: BOM Explosion - Change Parameters

17. Click the Background processing to deselect.

18. Click the Save button.

19. Click the Back button.

Page 10 of 37

Page 11: CK40N Edit Costing Run Instruction

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

Edit Costing Run

20. Click the Struct. explosion Execute button.

21. Click the Materials Overview button.

Page 11 of 37

Page 12: CK40N Edit Costing Run Instruction

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

22. Click the Costing Parameter button.

Page 12 of 37

Page 13: CK40N Edit Costing Run Instruction

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

Costing Run: Cost Estimate - Change Parameters

23. Click the Background processing to deselect.

24. Click the All selections button.

25. Click the Save button.

26. Click the Back button.

Page 13 of 37

Page 14: CK40N Edit Costing Run Instruction

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

Edit Costing Run

27. Click the Costing Execute button.

28. Click if the Costing Log button appears

Page 14 of 37

Page 15: CK40N Edit Costing Run Instruction

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

29. Click the Back button.

Page 15 of 37

Page 16: CK40N Edit Costing Run Instruction

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

Edit Costing Run

30. Click the Materials Overview button.

31. Click the Analysis Parameter button.

Page 16 of 37

Page 17: CK40N Edit Costing Run Instruction

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

Choose reference for selection parameter

32. Select the SAP&11 - Results of Costing Run in list box.

Page 17 of 37

Page 18: CK40N Edit Costing Run Instruction

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

Costing Run: Analysis - Change Parameters

33. Click the All selections button.

34. Click the Save button.

35. Click the Back button.

Page 18 of 37

Page 19: CK40N Edit Costing Run Instruction

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

Edit Costing Run

36. Click the Analysis Execute button.

Page 19 of 37

Page 20: CK40N Edit Costing Run Instruction

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

Analyze/Compare Material Cost Estimates

Note: To display detailed report with cost estimate of particular material click on

the Detail report: cost estimate button.

37. Click the Back button.

Exit list

38. Click the Yes button.

Page 20 of 37

Page 21: CK40N Edit Costing Run Instruction

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

Edit Costing Run

39. Click the Marking Padlock button to allow marking.

Page 21 of 37

Page 22: CK40N Edit Costing Run Instruction

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

Price Update: Organizational Measure

40. Select the 9100 Legal valuation line and click the Issue marking allowance button.

Note: To allow marking for Group valuation and Profit center valuation you should follow the step described above.

Page 22 of 37

Page 23: CK40N Edit Costing Run Instruction

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

Permitted std. cost est. variant

41. Click the Costing variant Drop-down list button to select an entry.

Permitted std. cost est. variant

42. Click the Save button.

43. Click the Back button.

Page 23 of 37

Page 24: CK40N Edit Costing Run Instruction

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

Edit Costing Run

44. Click the Marking Parameter button.

Page 24 of 37

Page 25: CK40N Edit Costing Run Instruction

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

Price Update: Mark Standard Price

45. Click the Test run button to deselect.

46. Click the Background processing to deselect.

47. Click the Save button.

48. Click the Back button.

Page 25 of 37

Page 26: CK40N Edit Costing Run Instruction

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

Edit Costing Run

49. Click the Marking Execute button.

Page 26 of 37

Page 27: CK40N Edit Costing Run Instruction

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

Price Update: Mark Standard Price

50. Click the Back button.

Page 27 of 37

Page 28: CK40N Edit Costing Run Instruction

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

Edit Costing Run

51. Click the Marking Log button.

Page 28 of 37

Page 29: CK40N Edit Costing Run Instruction

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

Costing Run: Marking - Log

52. Click the Back button.

Page 29 of 37

Page 30: CK40N Edit Costing Run Instruction

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

Edit Costing Run

53. Click the Release Parameter button.

Page 30 of 37

Page 31: CK40N Edit Costing Run Instruction

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

Price Update: Release Standard Price

54. Click the Test run button to deselect.

55. Click the Background processing to deselect.

.

56. Click the Save button.

57. Click the Back button.

Page 31 of 37

Page 32: CK40N Edit Costing Run Instruction

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

Edit Costing Run

58. Click the Release Execute button.

Page 32 of 37

Page 33: CK40N Edit Costing Run Instruction

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

Price Update: Release Standard Price

59. Click the Back button.

Page 33 of 37

Page 34: CK40N Edit Costing Run Instruction

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

Edit Costing Run

60. Click the Materials Overview button.

Page 34 of 37

Page 35: CK40N Edit Costing Run Instruction

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

Edit Costing Run

61. Click the Analysis button.

Page 35 of 37

Page 36: CK40N Edit Costing Run Instruction

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

Edit Costing Run

Note: To display detailed reports for costed materials, i.e. itemization, cost

components, etc. select the particular material and click the Goto button.

62. Click the Back button.

63. Click the Back button to go back to SAP Easy Access screen.

Page 36 of 37

Page 37: CK40N Edit Costing Run Instruction

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

Page 37 of 37