cityharb

Upload: firdaus-fadzil

Post on 07-Apr-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/6/2019 cityharb

    1/17

    View Publication

    You have asked to view a publication

    When you have finished viewing, click on in the toolbar to return to this screen.

    Now choose one of the following options:

    return topublicationslist

    viewpublicationchosen

    http://publicat.pdf/http://publicat.pdf/http://publicat.pdf/http://publicat.pdf/
  • 8/6/2019 cityharb

    2/17

    P R O J E C T

    P R O F I L E

    P R O J E C T

    P R O F I L E

  • 8/6/2019 cityharb

    3/17

    All advice or information from the Br itish Cement Association is intended for those who will evaluate the significance and limitation of its contents and take responsibilityfor its use and application. No liability (including that for negligence) for any loss resulting from such advice or information is accepted. Readers should note that all BCA

    publications are subject to revision from time to time and should therefore ensure that they are in possession of the latest version.

    97.324

    First published 1992

    ISBN 0 7210 1444 5

    Price Group C

    British Cement Association 1992

    Published by the British Cement Association on behalf of

    the industry sponsors of the Reinforced Concrete Council.

    British Cement Association

    Telford Avenue, Crowthorne, Berkshire RG11 6YS

    Telephone (0344) 762676

    Fax (0344) 761214

  • 8/6/2019 cityharb

    4/17

  • 8/6/2019 cityharb

    5/17

    P R O J E C T P R O F I L E

    2

    Merchant House and Woodchester House are

    two office buildings that form a significant part of

    the City Harbour development in the heart of

    Londons Docklands.The site adjoins the east side of Millwall Docks

    and is at the centre of an expanding communications

    network - only minutes from City Airport and

    immediately adjacent to Crossharbour Station on the

    Docklands Light Railway.

    The scheme for the five-acre development

    includes three major office buildings (totalling some

    240 000 ft2), individual office units, a luxury hotel, a

    multi-storey car park and other ancillary buildings.

    The architecture and planning take full advantage of

    the sites extensive dockside frontage, creating a

    modern working environment with attractive views.

    Merchant House and Woodchester House overlook

    the water and border a tree-lined piazza called

    Watermans Square.

    The development of City Harbour was divided

    into five phases, the first of which consisted of

    Merchant House and the smaller Woodchester

    House. For these two buildings, the development

    team chose precast concrete frames. Neither

    structural steel nor in-situ concrete frames could

    meet the exacting lead-in time and erection

    programme requirements; neither could theyprovide the economy and quality of precast concrete.

    THE PROJECT

    The City Harbour development is on the former Olsen 3 site

    of Milwall Docks

  • 8/6/2019 cityharb

    6/173

    Description

    Merchant House and Woodchester House offer

    high-quality office accommodation in a central

    London location, but with much lower occupancy

    costs than those in the City. Their design offers the

    flexibility for changing the layout to accommodate a

    wide range of future uses.

    Each building may be used as a self-contained

    office headquarters, with its own entrance, servicing

    and car parking, or may be sub-divided into separate

    tenancies. The two buildings incorporate varied

    floor plans, with balconies and terraces that form a

    distinctive stepped profile and provide unobstructed

    views across the water.

    The buildings have the following principalfeatures:

    Eight levels of office accommodation in MerchantHouse and six in Woodchester House.

    Ground floor reception lobbies with high-speedautomatic passenger lifts to all floors.

    Flexibility for open-plan or cellular office layouton a 1.5m grid.

    Raised access floors for electrical and communi-cations installations.

    Fully accessible suspended ceilings allowingpartition-head fixings on a 1.5 m module.

    Knock-out panels in floors for additional verticalservices distribution.

    Fixed sealed double glazing with tinted solar-control glass.

    Full air conditioning. Terraces, conservatories and balconies. Dedicated parking with additional visitor spaces in

    Watermans Square.

    BUILDING SPECIFICATION

    P R O J E C T P R O F I L E

    The distinctive dockside elevations

    Office adjoining one of the terraces

    Conservatory office

    Terraces on Woodchester House

  • 8/6/2019 cityharb

    7/17

    P R O J E C T P R O F I L E

    4

    Space provisions

    The net floor area of Merchant House is 55 000 ft2,

    with typically 7000 ft2 per floor from ground to fifth

    floor levels, and 6000 ft2 and 5000 ft2 respectively at

    sixth and seventh floor levels. Woodchester House

    has a net floor area of 37 000 ft2, typically 7000 ft2 perfloor; but reducing at the third, fourth and fifth floor

    levels. Because of the high water table, the buildings

    have no basements.

    The internal clear height, from finished floor

    level to underside of ceiling, is 2.6 m for all office

    areas. A 700 mm deep ceiling void and 150 mm deep

    floor void are provided for installing services.

    Structure

    The superstructures consist of precast reinforced

    concrete columns, shear walls, beams and stairs, andprecast prestressed hollow-core floor units. The

    precast frames are based on 6.0 x 6.0 and 6.0 x 7.5 m

    grids, and are supported on piled foundations.

    The floors were designed to carry an imposed

    load of 5.0 kN/m2 (including 1.0 kN/m2 allowance

    for partitions) plus 0.4 kN/m2 for services.

    Cladding

    The aluminium cladding system is based on

    top-quality products and workmanship, and the

    elevations feature dark grey glazing units usedfull-height or within colour-coated panels.

    Services

    The buildings have full variable air volume (VAV) air

    conditioning, with individually controlled terminal

    boxes in each structural bay, at all levels, to provide

    an efficient and highly flexible system.

    Precast concrete frames were specified for both buildings

    Details of the curtain wall cladding

    Typical office floor section

    showing precast concrete frame

  • 8/6/2019 cityharb

    8/17

    P R O J E C T P R O F I L E

    5

    Facilities for power, telecommunications and data

    wiring are provided within the 150 mm raised floor.

    The ceilings have integral light fittings and the lighting

    zones can be rearranged to suit future requirements.

    Each floor is served by ten-person automatic lifts,

    and additional lifts, also serving as firemens lifts,adjoin the goods entrances.

    The east

    elevations

    The dockside setting of the two buildings

    Architecture

    The site encompasses a landscaped setting on the

    former Olsen 3 site, to the east of Millwall Docks on

    the Isle of Dogs. The City Harbour masterplan

    integrates three separate self-contained headquarters-

    style office buildings, seven smaller terraced frontdoor office units, a major hotel, a multi-storey car

    park, a health centre, restaurant, and wine bar.

    Merchant House and Woodchester House occupy

    the east and north sides of Watermans Square - a

    paved and tree-planted piazza. The elevations take

    full advantage of the sites extensive dockside

    frontage to make a strong visual impact.

    The exteriors are clad with a high-quality

    colour-coated aluminium curtain wall system, the

    solid panels having outer panels that act as a

    secondary rain screen to the fully weatherproofed

    inner system.

    In addition to its attractive appearance, the

    curtain wall system allows for future refurbishment

    or alterations without disturbing the integrity of the

    inner system. At ground level the outer cosmetic

    panels are a slate-stone-composite material that

    provides a more robust and vandal-resistant surface.

    Tinted solar-control double glazing complements

    and mirrors the surrounding waterside. Plant con-

    tainers on terraces and balconies provide visual relief.

    DESIGN

    Watermans Square

  • 8/6/2019 cityharb

    9/17

    P R O J E C T P R O F I L E

    6

    The internal lighting, fittings and finishes in the

    offices are all of the highest standard. The interior

    design fully anticipated that occupiers would require

    flexible internal layouts, and the scheme benefited from

    a full space-planning exercise at its conceptual stage.

    Structure

    A number of different frame designs were considered

    and reviewed to determine which would best suit

    the project requirements. Least cost and minimum

    time were paramount. Flexibility, quality and ease of

    erection were also crucial.

    Only precast concrete could meet all these

    criteria. It was found to be cheaper and quicker to

    erect than either steelwork or in-situ concrete

    frames, and it beat steelwork on lead-in time.

    The use of precast, prestressed concrete floorunits obviated the need for transverse internal floor

    beams and kept the floor plate thickness to a

    minimum. This in turn generated the maximum

    depth of ceiling void. The flat soffits of the floor

    units, and the clear longitudinal runs, made it easier

    to install services. They also allow for future

    alterations to services and office layouts.

    The floor units in Merchant House were 150 mm

    and 200 mm thick, and 200 mm thick units were

    used in Woodchester House. Small service

    penetrations were formed in situ through the voids

    of the hollow-core floor units. Major penetrationswere preformed within the floor layout, and

    knock-out panels are provided to allow for possible

    future modification of the services.

    The precast reinforced concrete internal spine

    beams were restricted to 500 mm deep overall to suit

    the distribution of services. The precast spandrel

    beams are generally 900 mm deep, with a downstand

    providing a fire break in the ceiling void below, so no

    time-consuming blockwork was needed. Upstands

    for roof balcony and terrace details are provided by

    1350 mm deep spandrel beams.The versatility of precast concrete easily enabled

    the stepped profile, irregnlar-shaped terraces, and

    curved balconies to be produced. A late change in the

    location of the lifts was also easily accommodated.

    The components are durable and quality assured,

    and have immediate structural loading capacity. They

    also have in-built fire resistance, both in service and

    during construction.

    The in-situ concrete slab at ground level is

    supported by precast concrete beams resting on the

    pile caps.

    Lateral stability is provided by a minimum number

    of precast concrete shear walls located around the stair

    The simplicity of the precast concrete frames

    Floor units span onto l ongitudinal beams

  • 8/6/2019 cityharb

    10/17

    wells and lift cores. Thus the structure behaves as a

    braced frame, which permitted economy of

    column design. As the building was over five storeys

    high, full provision against progressive collapse was

    provided by simple horizontal and vertical ties.

    The design of the precast columns took fulladvantage of high-strength concrete and the quality

    control available under factory conditions. The use

    of grade 50 concrete resulted in 450 mm square

    internal columns at the ground floor of Merchant

    House. The column sections were cast up to

    11.4 m long to support three storeys, with cast-in

    rectangular hollow section billets to carry the shear

    forces from the beams.

    The precast concrete stair units, with cantilevered

    half-landings, are supported by precast mid-storey

    beams and floor landings.

    Generally the connections were made, and the

    ties installed, by stitching-in with in-situ concrete.

    Channel and other fixings, as required for the

    following trades, were cast into the precast units to

    speed construction on site.

    The detailed design, manufacture and erection

    of the precast frames were carried out by the

    manufacturer. This single-point responsibility was seen

    as another benefit of precast concrete construction.

    Services

    The services were designed for an office occupancy

    level of 10 m2 per person with a fresh air supply of

    12 litres per person per second and an interual tem-

    perature of 21C 2C with 30 to 70% r.h.

    The warm air supply of the air conditioning serves

    the perimeter wall panels and is controlled from the

    rooftop plant room. Each panel is individually isolated

    and the system is zoned, with thermostatically

    controlled circuits.

    The principal feature of the heating system is that

    the cold radiation and downdraught effects of the

    glazing are offset by the strategically placed heating

    panels in the flush under-sill panels. This arrangementensures that the heaters do not encroach upon usable

    floor or wall space.

    The gas boilers and all other major plant are

    contained within plant rooms and screened

    compounds at roof level.

    The lighting level was set at 500 lux average and

    was achieved using continuous twin tube low-glare

    recessed luminaires which incorporated return air

    slots. On-floor power requirements were assessed at

    25 w/m2 with outlets provided in the raised floor.

    Other services included hot and cold water, lifts,sanitation, drainage, fire alarms, and facilities for

    telecommunications and data wiring.

    P R O J E C T P R O F I L E

    7

    Precast walls for the lift shafts

    and stairs act as shear walls

    The pland room -

    Woodchester House

    Precast column units are up to 11.4 m long

    Flush under-sill heating

    panels in office areas

  • 8/6/2019 cityharb

    11/17

    P R O J E C T P R O F I L E

    8

    General

    A straightforward approach to construction was

    adopted, and met the principal requirements of cost

    and speed.

    The buildings are founded on a combination of

    driven and bored piles. The precast frame proceeded

    quickly, with a floor being completed every two

    weeks, on average.

    No fire protection, either in the form of sprays or

    boards, was required. No scaffolding was needed for

    the cladding, and access on foot was gained via the

    precast stairs. No drying-out period was necessary

    which, together with minimal propping requirements,

    gave following trades rapid and clear access.

    Substructures

    Generally, the driven piles have a nominal diameter of

    400 mm and a safe working load of 110 tonnes, but

    vibration during construction close to the existing dock

    wall and sewers was identified as a potential problem.

    Therefore, bored continuous-flight-augured piles

    (CFA), with a nominal diameter of 600 mm and a

    safe working load of 90 tonnes, were used within a

    distance of 24 m from the existing dock wall and

    within 10 m of the main sewers. Ground vibrations

    were monitored for both forms of piling.

    Where necessary, the pile caps were restrained

    laterally by the precast concrete ground beams.

    Holding-down bolts for the first section of the precast

    concrete columns were cast direcdy into the pile caps.

    Superstructures

    Delivery of the frame components was carefully

    scheduled so that they could be lifted directly from

    the delivery vehicles and placed into position using a

    rail-mounted tower crane. This had the capacity to

    lift the heaviest component, which weighed 6.2

    tonnes, and was supplemented by mobile cranes asrequired. Erection of the frame was unaffected by

    weather, and the required storage area was minimal.

    The columns were usually erected in three-storey

    lifts and temporarily propped. They have bolted steel

    base plates and the splice joints were formed with

    loose continuity reinforcing bars inserted in

    preformed ducts in the ends of the units. When the

    units had been lined and levelled, the voids were

    filled by pressure grouting.

    The main precast concrete beams were securely

    seated on projecting RHS steel billets cast into the

    columns, and the tops of the beams were fixed in

    position by an angle cleat. Generally the beams sitThe first lift of columns

    for Merchant House

    Column base detail

    CFA piling in progressCONSTRUCTION

  • 8/6/2019 cityharb

    12/17

    P R O J E C T P R O F I L E

    9

    between columns with a nominal 10 mm gap left at

    each end to allow for production and erection

    tolerances. The gap was pointed with cement mortar

    to enable the remaining void around the billet and

    seating cleat to be enveloped in poured grout.

    Curved edge-beams were temporarily propped untilthe floor was completed.

    The prestressed concrete floor units span from

    edge spandrel beams to internal spine beams. They are

    seated on wide nibs which are an integral part of the

    precast beams. These nibs not only provide ample

    bearing for the floor units, but also allow space at the

    ends of the units for the longitudinal ties. These consist

    of unstressed 12.7 mm prestressing strands anchored

    by right angle returns at each end of the building.

    Transverse ties were formed by loose

    reinforcement placed and concreted into open

    hollow cores, and hooked over reinforcement leftprojecting from the top of the precast beams. The

    floor units were delivered with the concrete above

    every third core already removed at each end. Similar

    details were used at the sides of the floor.

    The joints between prestressed concrete floor

    units, and the stitching between floor units and

    beams, were completed using a grade 40 concrete

    with 75 mm slump and 10 mm aggregate. This

    ensured the diaphragm action of the floor against

    lateral loads. No formwork was necessary as the

    precast units completely surrounded the voids. The

    plant room floor units have a 100 mm thick30 N/mm2 structural concrete topping to carry an

    additional imposed load.

    The precast concrete shear walls were inter-

    connected by vertical lacing bars threaded through

    the projecting link reinforcement allowing the joint

    to be finished with 40 N/mm2 in-situ concrete.

    The stair units were lifted into position on to

    simple halvingjoints at floor level, and on to

    dowelled bearings at mid-storey height. Flights were

    precast to finished floor levels, but landings were

    screeded. The cantilever semicircular half landings

    were tied with steel channels that also provide lateralsupport for blockwork.

    The efficient and disciplined approach to design

    resulted in the precast concrete subcontractor being

    able to use cross-sections with a high repetition

    factor, thus minimizing costs. The resulting

    construction is accurate and well within the specified

    tolerances. The choice of precast concrete provided

    rapid and easy construction to give a robust structure

    with economy of design.

    The frames contain 1100 precast concrete column,

    beam, wall and staifflight components, plus 9400 m2

    of precast floor units. The entire structural frame of

    Merchant House was erected in 16 weeks at a rate of

    Floor/beam/perimeter column

    connection detail

    Precast stair unit being lifted into position

  • 8/6/2019 cityharb

    13/17

    P R O J E C T P R O F I L E

    10

    approximately 95 precast units per week. The surface

    finish throughout was ex-factory type A in accordance

    with BS 8110. During production, strict quality control

    procedures were maintained under a BSI-registered

    Quality Assurance Scheme. The units were also

    inspected by the design team before despatch to site.

    Following trades

    The inherently dry construction and total absence of

    formwork allowed safe, clear and rapid access for

    following trades using the precast stairs. Fixings for the

    cladding, temporary handrails, and the conservatory

    and plant room steelwork were cast into the factory-

    produced units to speed following trades. For

    example, the aluminium curtain walling on

    Woodchester House was fixed only two floors

    behind the precast concrete frame.The curtain walling is an aluminium stick

    system and the two-or three-storey high mullions

    were fixed before infliling with transomes, and the

    solid and glazed panels.

    Meanwhile internal concrete block walls were

    being constructed just ahead of first-fix services and

    joinery. The absence of transverse beams or drops

    encouraged the prefabrication and fast installation of

    M & E services. Small service holes were formed in

    situ through the easily locatable voids in the hollow-

    core units. Supports for the services and suspended

    ceiling grids were fixed directly into the concretesoffits using drilled and self-tapping devices.

    Suspended ceilings and raised floors were installed

    before final decoration. Wet trades were confined

    mainly to the stairs, lobbies and toilets.

    Flat roofs and terraces are of inverted roof con-

    struction laid to falls, and were made weathertight

    before first fixing began. The waterproof membrane

    is covered with 100 mm insulation board protected

    by concrete paving slabs.

    Merchant House was completed ahead of

    programme in 22 months and Woodchester Housewas completed in 20 months.

    THE PRECAST CONCRETE SOLUTION

    The frames for both buildings were quality assured

    Curtain walling

    during erection

    Paving on the

    completed terraces

    Merchant House and Woodchester House clearly

    demonstrate the advantages of using precast concrete

    construction to meet clients requirements for the

    following:

    Speed and economy - the precast concrete framewas the least-cost solution with the lowest storeyheight, and had a shorter lead-in time than a steelwork

  • 8/6/2019 cityharb

    14/17

    P R O J E C T P R O F I L E

    11

    frame. It gave rapid erection with less contractor

    preliminaries and quicker returns on investments. It

    also gave rapid, clear and safe access for following

    trades. High repetition factors and the use of high-

    strength concrete produced further cost benefits.

    Simplicity - the disciplined approach to design ledto repetitive elements of design, detailing,manufacture and construction. Construction was

    uncomplicated, with simple connections, no form-

    work, no weather problems, cast-in fixings for

    following trades, and minimal storage and propping

    requirements. Flat soffits and preformed holes made

    services quick and easy to install.

    Quality - the robust and rigid frames were builtfrom quality-assured factory-produced components,

    to give accurate and durable structures. The quality

    of construction was further assured by one-point

    responsibility for the detailed structural design,

    manufacture and erection.

    Flexibility - the precast concrete frames accom-modated balconies, terraces, curves and irregular

    shapes, and also permitted a late design change. The

    precast floors allow for flexible future office

    planning. The flat soffits and large ceiling voids

    permit alterations to services, ceilings and office

    layouts. Knock-out panels are provided for possible

    future large service penetrations. Smaller holes can

    be made through the easily locatable hollow cores in

    the floor units.

    Precast concrete was the only structural frame

    material that could meet the cost, speed, quality and

    versatility requirements for Merchant House and

    Woodchester House. The result is two prestigious

    buildings which are a credit to all those involved in

    their design and construction.

    January 1988: frame of Merchant House

    well advanced, cladding in progress

    at Woodchester House

    May 1987: piling commenced

    April 1988:

    cladding to

    Woodchester House

    nearing completion,

    internal walls and

    cladding in progress

    on Merchant House

    Woodchester House was handed over in January 1989 and Merchant House in April 1989

  • 8/6/2019 cityharb

    15/17

    P R O J E C T P R O F I L E

    12

    Developer Brunel Centre Limited

    Architect, structural Building Design Partnership

    engineer and quantity

    surveyorServices engineer Ralph T. King Associates

    Main contractor John Laing (London)

    Frame contractor Crendon Structures

    Flooring supplier Bison Floors

    THE PROJECT TEAMA P P E N D I X

    CONSTRUCTIONCOSTS /m2 gross

    WoodchesterHouse

    Enabling works 15

    Piling 15

    Substructure 25

    Frame 100

    M & E 295

    Cladding/roofing 335

    Finishes 215

    External works 35

    Preliminaries 125

    Sundries 30Total 1190

    Merchant WoodchesterHouse House

    Gross floor area 6540m2 4500m2

    Net lettable area 5100m2 3500m2

    Number of storeys 8 6

    AREAS

    THE PROGRAMME

  • 8/6/2019 cityharb

    16/17

    P R O J E C T P R O F I L E

    13

    Woodchester MerchantHouse House

    Start May 1987 May 1987

    Finish January 1989 April 1989

    Duration 20 months 22 months

    CONSTRUCTION TIME

    TYPICAL FLOOR PLANS

    WoodchesterHouse

    Floor one

    MerchantHouse

    Floor one

    MerchantHouse

    Floor seven

    WoodchesterHouse

    Floor five

  • 8/6/2019 cityharb

    17/17

    PROJECT PROFILE: MERCHANT HOUSE AND WOODCHESTER HOUSE

    C.H.Goodchild and P.Seilen

    BRITISH CEMENT ASSOCIATION PUBLICATION 97.324