1

CITY OF PHOENIX

WATER SERVICES DEPARTMENT

CITYWIDE STREET LANDSCAPE

MAINTENANCE

PROJECT NO. 4108JOC140

Job Order Contract

April 8, 2016

Pre-Submittal Meeting

2

Donna L. Wiltshire, Contracts Specialist Street Transportation Department

Rubben Lolly, Civil Engineer IIITeam Lead, Project ManagerStreet Transportation Department

Joanne McLaughlin, Equal Opportunity Programs Assistant Equal Opportunity Department

Welcome and Introductions

3

Sign-in please…copies of sign in sheet will be

available on website:

https://www.phoenix.gov/streets/procurement/

current-opportunities

Please hold questions until the Q&A period.

This is the ONLY opportunity to discuss this

project with City staff.

Meeting Overview

4

Project Description

Project Scope of Work

SBE Participation

Submittal Requirements

Selection Schedule

Questions?

Agenda

5

The City of Phoenix is seeking up to three (3) qualified Job Order Contractors to do business with the City of Phoenix on an “on-call” basis. This Job Order Contract (JOC) is for the maintenance and as-needed restoration, of established right-of-way landscaping.

The JOC Period of Performance is for 36-months with an option to renew for an additional 24-months.

Citywide Landscape JOC Capacity Options

Project Description

Citywide Landscape JOC Capacity Options

5 Year Total

36 Month

Capacity

+ 24 Month

Capacity

All Three Contractors (Total) 6,250,000 3,750,000 2,500,000

Per Contractor 2,083,333 1,250,000 833,333

6

Project Scope of Work (SOW)

At a minimum, the JOC Contractor will be expected to

successfully perform the following construction services,

including but not limited to: Repair and/or restoration of landscape irrigation systems including backflow prevention

system testing, repair/replacement.

Herbicide applications in compliance with the State of Arizona Office of Pest Management

primarily to inhibit and/or eradicate existing weed growth.

Planting, pruning and removal of landscape shrubs, ground cover plants, vines and trees.

Utilize Certified Arborist for tree pruning.

Equipment and operations utilized for maintenance work to be performed in strict

compliance with Arizona Department of Environmental Quality and Maricopa County Air

Quality regulations.

Repair and/or install various types of fencing and traffic control bollards.

Perform various methods of graffiti removal including but not limited to painting and sand

blasting.

Repair and/or replace concrete pedestrian pathways and miscellaneous concrete flat work.

Coordinate traffic control based on City of Phoenix requirements.

7

QUESTIONS?

The City of Phoenix strives to advance the economic growth

of local businesses through its Small Business Enterprise

(SBE) Program.

The City requires the participation of SBE firms

throughout all phases of contracts.

Subject to City of Phoenix Code, Chapter 18, Article Vl,

pertaining to the participation of Small Business

Enterprise (SBE) firms.

During the term of this JOC, the JOC Contractor is

expected to meet an annual SBE utilization goal of seven

(7) % which will be reviewed on a semi-annual basis.

SBE goals must be met or a waiver requested in order to

perform a job order under the JOC.

Small Business Enterprise Program

No SBE documents due submittal time

A directory of all eligible certified SBE firms is available online

at: https://phoenix.diversitycompliance.com

“Good Faith Efforts”

If Contractor is unable to meet the goal, a fully documented

waiver request must be submitted.

To be counted for credit towards SBE utilization, the certified

firm must perform a commercially useful function in their

certified scope of work.

SBE firms must be certified at the time of each job order

agreement.

SBE documents due to Equal Opportunity Department (EOD)

for each Job Order Agreement (JOA)

Contractor’s Statement of Proposed SBE Utilization

Letter of Intent to Perform as an SBE

Subcontractor/Supplier

For additional information contact:

Joanne McLaughlin

Equal Opportunity Programs Assistant

[email protected]

602-534-1279

11

QUESTIONS?

12

General Information – 15 points

Design Experience of the Prime Firm – 25 points

Experience of Key Personnel Assigned – 20 points

Approach to Performing Required Svcs – 30 points

Overall evaluation – 10 points

Statement of Qualifications (SOQ)

Evaluation Criteria

13

Cover Letter (company name, address and contact

information)

Evaluation Criteria (including project

organizational chart)

Additional Content (resumes or other information)

Bonding Statement (separate sealed envelope)

MAXIMUM pages permitted is 12 pages:

+ Evaluation Criteria (including organizational chart)

+ Additional Content (resumes or other information)

= 12 MAXIMUM pages permitted

Statement of Qualifications Criteria (Continued)

14

Each page side with criteria information will be

counted.

Pages that have photos, charts, and graphs will be

counted toward maximum number of pages.

Front and back cover, Cover Letter, Table of

Contents and tab dividers will NOT be counted

toward the maximum page limit, UNLESS they

include information that may be considered by the

selection panel.

Statement of Qualifications Criteria (Continued)

15

Submit six (6) copies of the SOQ.

SOQ due:

12:00pm Noon – Arizona local time

Monday, April 25, 2016Phoenix City Hall

200 W. Washington

6th Floor, Submittal Box

Statement of Qualifications Criteria (Continued)

AMENDMENT

NOTE: An Amendment to the RFQ will be

issued to

Correct Page 1, Section I: Project Description

– This JOC will be for a 36-month duration or $3,750,000

per JOC ($1,250,000 per Contractor)

Correct Page 6, Section VI: Selection Process and

Schedule

– The following tentative schedule has been prepared for

this JOC:

– SOQs due April 25, 2016 at 12 noon

16

17

Grounds for Disqualification:

Receipt of submittal after specified cut-off

date and time.

Too few copies of the submittal.

Deposit of submittal in the wrong location.

Violating the “Contact with City Employees”

policy which is contained in the RFQ.

Statement of Qualifications Criteria (Continued)

18

SOQs due at 12:00 P.M. April 25, 2016

RFPs to Finalist May 8, 2016

Finalist Recommentation June 2016

Job Order Workshop TBD

Selection Schedule

19

Please contact:

Donna L. Wiltshire, Contracts Specialist

(602) 261-8894

[email protected]

QUESTIONS AFTER TODAY