City of Fargo Meadow Creek Area Flood Risk Management – Project 5944 Public Information Meeting June 21, 2010

Upload: derica

Post on 11-Jan-2016

31 views

Category:

Documents


0 download

DESCRIPTION

City of Fargo Meadow Creek Area Flood Risk Management – Project 5944 Public Information Meeting June 21, 2010. Agenda Recent Flood Fight Strategy (2009/2010) 2010/11 Proposed City Flood Risk Management Projects Assessment of Flood Risk Overview of Project Project Schedule / Financing. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: City of Fargo Meadow Creek Area Flood Risk Management – Project 5944 Public Information Meeting

City of Fargo

Meadow Creek Area FloodRisk Management – Project

5944

Public Information Meeting

June 21, 2010

Page 2: City of Fargo Meadow Creek Area Flood Risk Management – Project 5944 Public Information Meeting

Agenda Recent Flood Fight Strategy (2009/2010) 2010/11 Proposed City Flood Risk

Management Projects Assessment of Flood Risk Overview of Project Project Schedule / Financing

Meadow Creek Flood Risk Management

Page 3: City of Fargo Meadow Creek Area Flood Risk Management – Project 5944 Public Information Meeting

Agenda Recent Flood Fight Strategy (2009/2010) 2010/11 Proposed City Flood Risk

Management Projects Assessment of Flood Risk Overview of Project Project Schedule / Financing

Meadow Creek Flood Risk Management

Page 4: City of Fargo Meadow Creek Area Flood Risk Management – Project 5944 Public Information Meeting

2009 Spring Flood – Meadow Creek Drive

Page 5: City of Fargo Meadow Creek Area Flood Risk Management – Project 5944 Public Information Meeting

2009 Spring Flood – Meadow Creek Area

Page 6: City of Fargo Meadow Creek Area Flood Risk Management – Project 5944 Public Information Meeting

2009 Flood Information Probabilistic Stage Predictions as of 3/11/2009 Actual Crest 3/28/2009

Approx.50% Chance

of 36.0-ftand

10% Chance of 38.5-ft

6

Approx.50% Chance of

38-ft10% Chance of

40-ftActual Crest

40.8- ft

Page 7: City of Fargo Meadow Creek Area Flood Risk Management – Project 5944 Public Information Meeting

2010 Flood Information Probabilistic Stage Predictions as of 3/9/2010 Actual Crest – 3/21/2010

Approx.50% Chance

of 36.0-ftand

10% Chance of 38.5-ft

7

Approx.50% Chance of

38.0-ftand

10% Chance of 42.7-ft

Actual Crest36.99-ft

Page 8: City of Fargo Meadow Creek Area Flood Risk Management – Project 5944 Public Information Meeting

Current Flood Fight Strategy

Predicted Crest - RS

Top with Freeboard -

RS

Estimated Sandbags Required

35 37 036 38 10037 39 7,60038 40 32,80039 41 79,30040 42 138,30041 43 221,10042 44 314,90043 45 435,100

Page 9: City of Fargo Meadow Creek Area Flood Risk Management – Project 5944 Public Information Meeting

2009 Flood Fight - Meadow Creek Drive

Page 10: City of Fargo Meadow Creek Area Flood Risk Management – Project 5944 Public Information Meeting

Sandbagging Effort

Page 11: City of Fargo Meadow Creek Area Flood Risk Management – Project 5944 Public Information Meeting

Agenda Recent Flood Fight Strategy (2009/2010) 2010/11 Proposed City Flood Risk

Management Projects Assessment of Flood Risk Overview of Project Project Schedule / Financing

Meadow Creek Flood Risk Management

Page 12: City of Fargo Meadow Creek Area Flood Risk Management – Project 5944 Public Information Meeting

Potential Flood Risk Reduction Projects.• Total Est.

Cost $35 Million

Page 13: City of Fargo Meadow Creek Area Flood Risk Management – Project 5944 Public Information Meeting

Agenda Recent Flood Fight Strategy (2009/2010) 2010/11 Proposed City Flood Risk

Management Projects Assessment of Flood Risk Overview of Project Project Schedule / Financing

Meadow Creek Flood Risk Management

Page 14: City of Fargo Meadow Creek Area Flood Risk Management – Project 5944 Public Information Meeting

Assessment of Flood Risk

River Stage 37.0ft

Insert MapSandbag Estimate – 7,600

Page 15: City of Fargo Meadow Creek Area Flood Risk Management – Project 5944 Public Information Meeting

Assessment of Flood Risk

River Stage 38.0ft

Insert MapSandbag Estimate –

32,800

Page 16: City of Fargo Meadow Creek Area Flood Risk Management – Project 5944 Public Information Meeting

Assessment of Flood Risk

River Stage 39.0ft

Insert MapSandbag Estimate –

79,300

Page 17: City of Fargo Meadow Creek Area Flood Risk Management – Project 5944 Public Information Meeting

Assessment of Flood Risk

River Stage 40.0ft

Insert MapSandbag Estimate –

138,300

Page 18: City of Fargo Meadow Creek Area Flood Risk Management – Project 5944 Public Information Meeting

Assessment of Flood Risk

River Stage 41.0ft

Insert MapSandbag Estimate –

221,100

Page 19: City of Fargo Meadow Creek Area Flood Risk Management – Project 5944 Public Information Meeting

Assessment of Flood Risk

River Stage 42.0ft

Insert MapSandbag Estimate –

314,900

Page 20: City of Fargo Meadow Creek Area Flood Risk Management – Project 5944 Public Information Meeting

Assessment of Flood Risk

River Stage 42.5ft

Insert MapFEMA 100-yr Flood Stage 39.5

USACE Recent Evaluation – 1% Flood in Fargo is 42.4?

Sandbag Estimate – 375,000

Page 21: City of Fargo Meadow Creek Area Flood Risk Management – Project 5944 Public Information Meeting

Agenda Recent Flood Fight Strategy (2009/2010) Assessment of Flood Risk Overview of Project Project Schedule / Financing

Meadow Creek Flood Risk Management

Page 22: City of Fargo Meadow Creek Area Flood Risk Management – Project 5944 Public Information Meeting

Bike Path (East and

West)

Permanent Storm Water

Pond

Channel Relocation

Low Flow Storm Sewer Extension

Low Flow Storm Sewer Extension and Channel Re-

grade

Completion of Timberline

Levee

Earthen Flood Control Levees to

RS 43+1ft

Page 23: City of Fargo Meadow Creek Area Flood Risk Management – Project 5944 Public Information Meeting
Page 24: City of Fargo Meadow Creek Area Flood Risk Management – Project 5944 Public Information Meeting
Page 25: City of Fargo Meadow Creek Area Flood Risk Management – Project 5944 Public Information Meeting

VISUALIZATION

Modified Long 720.wmv

Page 26: City of Fargo Meadow Creek Area Flood Risk Management – Project 5944 Public Information Meeting

Agenda Recent Flood Fight Strategy (2009/2010) Assessment of Flood Risk Overview of Project Project Schedule / Financing

Meadow Creek Flood Risk Management

Page 27: City of Fargo Meadow Creek Area Flood Risk Management – Project 5944 Public Information Meeting

Preliminary Construction Cost Estimate:– Approximately $2.0M

Preliminary Funding Plan – City of Fargo Flood Control Sales Tax– ND State Water Commission (50%)– Potential Special Assessments

Project Schedule / Financing

Page 28: City of Fargo Meadow Creek Area Flood Risk Management – Project 5944 Public Information Meeting

Conceptual Planning Preliminary Geotechnical Review Preliminary Design City/Park District Meetings Public Informational Meeting(tonight)

Detailed Geotechnical Analysis Hydraulic Analysis / Impacts Final Plans / Specifications / Cost Estimates Permitting Construction Bidding Anticipated Construction Begins (Fall 2010)

Project Schedule / Financing

Page 29: City of Fargo Meadow Creek Area Flood Risk Management – Project 5944 Public Information Meeting

Comment Form

Page 30: City of Fargo Meadow Creek Area Flood Risk Management – Project 5944 Public Information Meeting

Questions / Discussion

www.cityoffargo.com\Engineering

Meadow Creek Area Flood Risk Management – Project 5944