Cincinnati Dayton Rd
Widening
Project Overview
• Widening of Cincinnati Dayton Rd to four lanes - providing a center turn lane and an additional northbound lane
• Realignment of Station Rd
• Widening of bridge on Cincinnati Dayton Rd; Replacement of bridge on Station Rd
• New sidewalk and decorative lighting along corridor
• New closed storm system
• New mid-block crosswalks
• Includes rectangular rapid flashing beacons
• Rectangular rapid
flashing beacon: • Corridor lighting:
Mid-block crosswalks
Cincinnati Dayton Rd Bridge
Mid-block crosswalks
Cincinnati Dayton Rd
Boys & Girls Club
Cincinnati Dayton Rd
Interstate 75 >>> Post Office
Standing at the Intersection of Station Rd and
Cincinnati Dayton Rd – Looking north
Existing Proposed
Standing south of the Cincinnati Dayton Rd bridge
– Looking south
Existing Proposed
Tentative Project Schedule
• Right-of-Way Acquisition Complete – End of 2017
• Utility Relocations – Ongoing
• Contract Sell Date – Spring, 2018
• Construction Start Date – Spring, 2018
• Construction Completion Date – Summer, 2019
General Construction Notes
• Operating hours: • 7:00AM – 9:00PM Monday through Saturday
• 1:00PM – 9:00PM Sunday
• Lane restrictions allowed Monday-Friday during non-peak
hours • Peak hours: (7:00AM – 8:30AM & 4:30PM – 6:30PM)
• Lane restrictions will be allowed on weekends
• Pile driving for the Cincinnati Dayton Rd bridge will be
restricted to the weekday hours of 8:00AM – 4:00PM
Construction Sequence
• 2018:
• Phase 1
• Phase 2
• Phase 3
• 2019:
• Phase 4
• Phase 5
• Phase 6
Phase 1 Construction - 2018
• Phase 1 construction begins in Spring, 2018
• Construct temporary pavement on west side of Cincinnati Dayton Rd between Seminary St and I-75
• Permanently widen east side of Cincinnati Dayton Rd bridge
• Permanently widen east side of Cincinnati Dayton Rd between the Cin Day bridge and I-75 up to the intermediate pavement
Phase 1 Construction - 2018
Phase 1 Construction - 2018
West Chester
Presbyterian Church
Phase 1 Construction - 2018
Lesourd
svill
e
West C
heste
r R
d
Phase 1 Construction - 2018 Seminary St
You are Here
Phase 1 Construction - 2018 Boys & Girls Club
Cresthaven Ave
• Phase 2 construction will close Station Rd from May 14th, 2018 through July 23rd, 2018 (10 weeks).
• Realign Station Rd with the intersection of Cincinnati Dayton Rd and Lesourdsville West Chester Rd.
• Complete construction up to the intermediate pavement and open Station Rd on July 23rd, 2018.
• This schedule was implemented to avoid detours during the St. John’s festival (August 3-5, 2018).
Phase 2 Construction – 2018 (Realignment of Station Rd)
Station Road Official Detour
Station Rd Closed
Official Detour (Trucks)
• Phase 3 construction begins after the completion of Phase 1 (Phase 2 is independent of other phases)
• Shift traffic to completed east side of Cincinnati Dayton Rd
• Permanently widen west side of Cincinnati Dayton Rd between the Cin Day bridge and I-75 up to the intermediate pavement
• All roadway widening north of the Cincinnati Dayton Rd bridge will be complete up to the intermediate pavement by Winter, 2018
Phase 3 Construction - 2018
Phase 3 Construction - 2018
West Chester
Presbyterian Church
Phase 3 Construction - 2018
Lesourd
svill
e
West
Cheste
r R
d
Phase 3 Construction - 2018 Seminary St
You are Here
Phase 3 Construction - 2018 Boys & Girls Club Cresthaven Ave
• Phase 4 construction begins in Spring, 2019
• Permanently widen the west side of the bridge on Cincinnati Dayton Rd
• Permanently widen the west side of Cincinnati Dayton Rd up to the intermediate pavement between West Chester Rd and the Cin Day bridge
Phase 4 Construction – 2019 (South of Cin Day Bridge)
Phase 4 Construction - 2019
Locust S
t
Phase 4 Construction - 2019
St. John Entrance
• Phase 5 construction will begin after the completion of phase 4
• Permanently widen the east side of Cincinnati Dayton Rd up to the intermediate pavement between West Chester Rd and the Cincinnati Dayton Rd bridge
• This is the final phase of widening construction. Will be completed by Summer, 2019.
Phase 5 Construction – 2019 (South of Cin Day Bridge)
Phase 5 Construction - 2019
Locust S
t
Phase 5 Construction - 2019
St. John Entrance
• Phase 6 construction will begin once all widening
phases are complete
• Pave the final asphalt surface course through the
entire project
• Apply all final pavement markings
• Final completion date: Summer, 2019
Phase 6 (Final) Construction - 2019
West C
heste
r R
d
Cincinnati Dayton Rd
Boys & Girls Club
Cincinnati Dayton Rd
Post Office