christchurch cathedral · 2012. 7. 14. · christchurch cathedral maximum retention option stage 6...

6
CHRISTCHURCH CATHEDRAL MAXIMUM RETENTION OPTION STAGE 1 De-construct west porch & west nave wall Form level access platform into west side of the cathedral De-construct west porch & west nave wall Relocate existing west bracing frame to southern side If required Relocate existing west bracing frame to southern side If required Existing concrete shearwall strengthening

Upload: others

Post on 29-Aug-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CHRISTCHURCH CATHEDRAL · 2012. 7. 14. · CHRISTCHURCH CATHEDRAL MAXIMUM RETENTION OPTION STAGE 6 Install fifth row of aisle temporary frames Propel Primary Shield Frame through

CHRISTCHURCH CATHEDRALMAXIMUM RETENTION OPTION

STAGE 1De-construct west porch& west nave wall

Form level access platform into west side of the cathedral

De-constructwest porch

& west navewall

Relocate existing west bracing frame to southern sideIf required

Relocate existingwest bracing frameto southern sideIf required

Existing concrete shearwallstrengthening

Page 2: CHRISTCHURCH CATHEDRAL · 2012. 7. 14. · CHRISTCHURCH CATHEDRAL MAXIMUM RETENTION OPTION STAGE 6 Install fifth row of aisle temporary frames Propel Primary Shield Frame through

CHRISTCHURCH CATHEDRALMAXIMUM RETENTION OPTION

STAGE 2Propel Primary Shield

Frame throughwest wall opening

Propel PrimaryShield Frame

throughwest wall opening

Install west end column frames

Page 3: CHRISTCHURCH CATHEDRAL · 2012. 7. 14. · CHRISTCHURCH CATHEDRAL MAXIMUM RETENTION OPTION STAGE 6 Install fifth row of aisle temporary frames Propel Primary Shield Frame through

CHRISTCHURCH CATHEDRALMAXIMUM RETENTION OPTION

STAGE 3

Install second row of aisle temporary frames

Support aisle roof rafters.

Install second row of aisletemporary frames

Brace aisle walls

West end column frames

Support nave rafters

Page 4: CHRISTCHURCH CATHEDRAL · 2012. 7. 14. · CHRISTCHURCH CATHEDRAL MAXIMUM RETENTION OPTION STAGE 6 Install fifth row of aisle temporary frames Propel Primary Shield Frame through

CHRISTCHURCH CATHEDRALMAXIMUM RETENTION OPTION

STAGE 4

Install first & third rows of aisle temporaryframes

Support roof rafters.

Install first row of aisletemporary frames

Brace aisle walls

Install third row of aisletemporary frames

Propel PrimaryShield Frame

throughto next grid

Install nave column framesat first row of column

Page 5: CHRISTCHURCH CATHEDRAL · 2012. 7. 14. · CHRISTCHURCH CATHEDRAL MAXIMUM RETENTION OPTION STAGE 6 Install fifth row of aisle temporary frames Propel Primary Shield Frame through

CHRISTCHURCH CATHEDRALMAXIMUM RETENTION OPTION

STAGE 5

Brace aisle walls

Install forth row of aisletemporary frames

Propel PrimaryShield Frame

throughto next grid

Install nave column framesat second row of columns

Support aisle roof rafters.

Brace aisle walls

Support nave roof rafters.

Brace clerestory walls

Brace navecolumns

Page 6: CHRISTCHURCH CATHEDRAL · 2012. 7. 14. · CHRISTCHURCH CATHEDRAL MAXIMUM RETENTION OPTION STAGE 6 Install fifth row of aisle temporary frames Propel Primary Shield Frame through

CHRISTCHURCH CATHEDRALMAXIMUM RETENTION OPTION

STAGE 6

Install fifth row of aisletemporary frames

Propel PrimaryShield Frame

throughto next grid

Install nave column framesat third row of columns

Support aisle roof rafters.

Support nave roof rafters.

Brace clerestory walls

Brace navecolumns

Brace aisle walls