chevron environmental management company - … · chevron environmental management company. ......

20
© Chevron 2010 Casper Wind Project Chevron Environmental Management Company Thomas Rinehart, Regulatory Affairs Specialist, EMC Kurt Tuggle, Senior Project Engineer, Trihydro Corp.

Upload: trandung

Post on 26-Jul-2018

243 views

Category:

Documents


0 download

TRANSCRIPT

© Chevron 2010

Casper Wind Project

Chevron Environmental Management Company

Thomas Rinehart, Regulatory Affairs Specialist, EMCKurt Tuggle, Senior Project Engineer, Trihydro Corp.

© Chevron 2010

Overview of Presentation

2

Chevron’s Renewable Strategy

Site History and Regulatory Setting

Business, Regulatory and Technical Drivers

Technical Challenges

Community Engagement

Permitting

Key Challenges and Lessons Learned

Key Success and Benefits

Question & Answer

© Chevron 2010

Demands on Energy Industry

Produce more energy

Develop cleaner fuels and technologies

Make energy supply more secure

Lower greenhouse-gas emissions

Diversify supply –integrate sustainable resources

Improve energy efficiency

3

© Chevron 2010

Chevron’s Renewable StrategyCapturing profitable positions where Chevron technologies and organizational capabilities can be leveraged

4

© Chevron 2010

Chevron’s Current Renewable Focus

5Geothermal Biofuels Solar Wind

© Chevron 2010

New Life for an Idle Site

Wind Power Project in Casper, Wyoming

Former refinery site6

© Chevron 2010

Refinery History and Regulatory Setting

RCRA Clean-up Process

7

1400 acre former petroleum refinery Refinery operated from 1923 – 1982 Produced motor fuels and asphalt Decommissioned 1995-2000 RCRA Facility (two AOCs, interim

status) Entered into Wyoming’s Voluntary

program in 2003 Currently in corrective measures

study phase Positive EIs achieved for soils and

groundwater (2001- 2002)

© Chevron 2010

Business, Regulatory and Technical Drivers

Beneficial reuse of property8

Business Chevron maintains property ownership and control

Revenue generation on liability property

Regulatory Risk-based soil remediation contingent on reuse

under Wyoming VRP

Technical Beneficial reuse consistent with environmental

conditions and institutional controls

It’s windy in Wyoming

© Chevron 2010

Wind Industry

Challenges Not in my backyard Intermittent resource Transmission / distribution

constraints Capital expenditures Environmental / ecological

Strengths Predictable ROCE Level earnings profile CDM credits obtainable

and used by many countries

Incentives and RPS

9

© Chevron 2010

Technical Challenges and Successes

10

Engineering Straightforward design Wind resource good Transmission interconnect

nearby

Challenges Limiting wetland impacts Avian birds Project economics

Technical Successes Incident/injury free

construction/operation Protection of habitat

© Chevron 2010

Pouring Base Section

11

© Chevron 2010

Blade Delivery

12

© Chevron 2010

Setting Mid-Tower Section

13

© Chevron 2010

Rotor Assembly

14

© Chevron 2010

Installing the Rotor Assembly

15

© Chevron 2010

Community Engagement

16

What We Did

Public meetings

Over a dozen public meetings conducted at local school and senior center from 2006 - Present

Invitations sent via mail and published in local newspaper

County Commissioner and Planning & Zoning engagement

Informational webpage online during permitting, construction and now operation

How it Worked

Largely positive/supportive

Vocal minority opposed to wind development near their property (NIMBY)

© Chevron 2010

Permitting

17

Permits

County conditional use permit required Wind development regulations

Chevron was “trail-blazer”

Impacts to public and infrastructure

Roads (traffic and damage)

Noise, dust and light

Impacts to environment

County building permit

No State permit required based on CAPEX

FAA permits and light requirements

Notifications

USFWS

USACE (<0.5 acre impacts)

SHPO

Wyoming DEQ

© Chevron 2010

Key Challenges and Lessons Learned

18

Lessons Learned Communicate early and

often Ensure stakeholders have

access to information Clear/consistent message

to construction contractor works (safety and habitat protection)

Challenges Permitting first commercial wind

project in Natrona County Public engagement Executing project injury and

incident free Controlling impacts to habitat

during construction

© Chevron 2010

Beneficial re-use of former refinery Liability property developed to generate

revenue Renewable energy generation Incident and injury free operations Habitat protection

Key Successes and Benefits

19

© Chevron 2010

Q&A

20