![Page 1: CHBWV Project Update Citizen Task Force Meeting · The Tank Waste Corporate Board meeting was held at West Valley on June 16-17. The Tank Waste Corporate Board is a chartered group](https://reader034.vdocuments.site/reader034/viewer/2022042417/5f33400b660d00433c184d72/html5/thumbnails/1.jpg)
www.energy.gov/EM 1
CHBWV Project UpdateCitizen Task Force Meeting
Dan Coyne, President and General Manager
CH2M HILL BWXT West Valley, LLC
June 24, 2015
![Page 2: CHBWV Project Update Citizen Task Force Meeting · The Tank Waste Corporate Board meeting was held at West Valley on June 16-17. The Tank Waste Corporate Board is a chartered group](https://reader034.vdocuments.site/reader034/viewer/2022042417/5f33400b660d00433c184d72/html5/thumbnails/2.jpg)
www.energy.gov/EM 2
Safety
As of 6/18/2015, CHBWV employees and subcontractors have worked 1,454,145 work hours
(955 days) without a lost-time work accident or illness. TRC – 0, DART – 0
![Page 3: CHBWV Project Update Citizen Task Force Meeting · The Tank Waste Corporate Board meeting was held at West Valley on June 16-17. The Tank Waste Corporate Board is a chartered group](https://reader034.vdocuments.site/reader034/viewer/2022042417/5f33400b660d00433c184d72/html5/thumbnails/3.jpg)
www.energy.gov/EM 3
The Tank Waste Corporate Board meeting was held at West Valley on June 16-17. The Tank Waste Corporate Board is a chartered group of senior DOE, contractor, and laboratory managers and staff who coordinate implementation of the National Tank Waste Program. Attendees included Monica Regalbuto, nominee to be Assistant Secretary for Environmental Management U. S. Department of Energy and Kenneth Picha, currently the Deputy Assistant Secretary for Tank Waste and Nuclear Materials Management in the Office of Environmental Management (EM).
Tank Waste Corporate Board
Heatherly Dukes/CHBWV, Monica Regalbuto/EM,
Bryan Bower/DOE, and Kenneth Picha/EM-20
Heatherly Dukes/CHBWV and
Monica Regalbuto/EM Checking Out
Vertical Cask Transporter (VCT)
Temporarily Staged at HLW Storage Pad
![Page 4: CHBWV Project Update Citizen Task Force Meeting · The Tank Waste Corporate Board meeting was held at West Valley on June 16-17. The Tank Waste Corporate Board is a chartered group](https://reader034.vdocuments.site/reader034/viewer/2022042417/5f33400b660d00433c184d72/html5/thumbnails/4.jpg)
www.energy.gov/EM 4
HLW Project - Process
![Page 5: CHBWV Project Update Citizen Task Force Meeting · The Tank Waste Corporate Board meeting was held at West Valley on June 16-17. The Tank Waste Corporate Board is a chartered group](https://reader034.vdocuments.site/reader034/viewer/2022042417/5f33400b660d00433c184d72/html5/thumbnails/5.jpg)
www.energy.gov/EM 5
HLW Equipment Readiness
VCT Testing and Haul Road Verification was Conducted using an Empty Cask
Witnessed Rail Cart Load Testing
Air Pallet Testing
![Page 6: CHBWV Project Update Citizen Task Force Meeting · The Tank Waste Corporate Board meeting was held at West Valley on June 16-17. The Tank Waste Corporate Board is a chartered group](https://reader034.vdocuments.site/reader034/viewer/2022042417/5f33400b660d00433c184d72/html5/thumbnails/6.jpg)
www.energy.gov/EM 6
HLW Load-In Facility (LIF) Preparations
Balance of LIF Runway Floor Plating was Installed (Left) and Grouting Beneath the Plates (Right) was Completed
Completed Cask Transfer Pad
LIF Modifications
![Page 7: CHBWV Project Update Citizen Task Force Meeting · The Tank Waste Corporate Board meeting was held at West Valley on June 16-17. The Tank Waste Corporate Board is a chartered group](https://reader034.vdocuments.site/reader034/viewer/2022042417/5f33400b660d00433c184d72/html5/thumbnails/7.jpg)
www.energy.gov/EM 7
Installed EDR Soaking Pit Cover
Core Boring
Floor Grouting
HLW EDR and Tunnel Preparations
![Page 8: CHBWV Project Update Citizen Task Force Meeting · The Tank Waste Corporate Board meeting was held at West Valley on June 16-17. The Tank Waste Corporate Board is a chartered group](https://reader034.vdocuments.site/reader034/viewer/2022042417/5f33400b660d00433c184d72/html5/thumbnails/8.jpg)
www.energy.gov/EM 8
Haul Road Paving and Steel Plating
HLW Haul Road Pathways
Completed 1,600 Feet of Paving on
Haul Road and Road Leveling for Site Entry
![Page 9: CHBWV Project Update Citizen Task Force Meeting · The Tank Waste Corporate Board meeting was held at West Valley on June 16-17. The Tank Waste Corporate Board is a chartered group](https://reader034.vdocuments.site/reader034/viewer/2022042417/5f33400b660d00433c184d72/html5/thumbnails/9.jpg)
www.energy.gov/EM 9
Waste Operations Accomplishments
• Concentrator Feed Make-up Tank (CFMT), Melter Feed Hold
Tank (MFHT), Melter Shipping Preparations
• Impact Limiter Request for Proposal (RFP) ready to award
• Shipped Cement Filter Boxes (Last of Legacy MLLW)
![Page 10: CHBWV Project Update Citizen Task Force Meeting · The Tank Waste Corporate Board meeting was held at West Valley on June 16-17. The Tank Waste Corporate Board is a chartered group](https://reader034.vdocuments.site/reader034/viewer/2022042417/5f33400b660d00433c184d72/html5/thumbnails/10.jpg)
www.energy.gov/EM 10
Liquid Waste Cell Pipe Removal
XC-1 Floor Debris Removal
Off-Gas Cell Pipe Removal
MSM Shop – Before and After Cleanup
Head-End Ventilation Replacement
Ventilation Units Duct Supports Installation
Milestone 3 Accomplishments
![Page 11: CHBWV Project Update Citizen Task Force Meeting · The Tank Waste Corporate Board meeting was held at West Valley on June 16-17. The Tank Waste Corporate Board is a chartered group](https://reader034.vdocuments.site/reader034/viewer/2022042417/5f33400b660d00433c184d72/html5/thumbnails/11.jpg)
www.energy.gov/EM 11
Preparations for MPPB Demolition
Work Activity Description % Complete
Characterization Complete 48%
Hazardous Material Removed 27%
Piping and Strip-Out Complete 28%
Mechanical Isolation Complete 21%
Asbestos Removed/Demolition Ready 46%
Penetration Stabilized or Repaired 12%
Decontamination Complete 10%
Electrical Isolation Complete 15%
![Page 12: CHBWV Project Update Citizen Task Force Meeting · The Tank Waste Corporate Board meeting was held at West Valley on June 16-17. The Tank Waste Corporate Board is a chartered group](https://reader034.vdocuments.site/reader034/viewer/2022042417/5f33400b660d00433c184d72/html5/thumbnails/12.jpg)
www.energy.gov/EM 12
Questions?