characterization of radioactive contamination inside …

9
CHARACTERIZATIONOF RADIOACTIVE CONTAMINATION INSIDE PIPES WITH THE PIPE EXPLORER"" SYSTEM AUTHORS: William Lowry CONTRACTORS: Science and Engineering Associates, Inc. 1570 Pacheco, Suite D-1 Santa Fe, NM 87505 CONTRACT NUMBER: DE-AC21-93MC30172 CONFERENCE TITLE: Opportunity '95 - Environmental Technology Through Small Business CONFERENCE LOCATION: Morgantown, West Virginia CONFERENCE DATES: November 16 - 17, 1994 CONFERENCE SPONSOR: U.S. Department of Energy - Morgantown Energy Technology Center

Upload: others

Post on 28-May-2022

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CHARACTERIZATION OF RADIOACTIVE CONTAMINATION INSIDE …

CHARACTERIZATION OF RADIOACTIVE CONTAMINATION INSIDE PIPES WITH THE PIPE EXPLORER"" SYSTEM

AUTHORS:

William Lowry

CONTRACTORS:

Science and Engineering Associates, Inc. 1570 Pacheco, Suite D-1 Santa Fe, NM 87505

CONTRACT NUMBER:

DE-AC21-93MC30172

CONFERENCE TITLE:

Opportunity '95 - Environmental Technology Through Small Business

CONFERENCE LOCATION:

Morgantown, West Virginia

CONFERENCE DATES:

November 16 - 17, 1994

CONFERENCE SPONSOR:

U.S. Department of Energy - Morgantown Energy Technology Center

Page 2: CHARACTERIZATION OF RADIOACTIVE CONTAMINATION INSIDE …

DISCLAIMER

This report was prepared as an account of work sponsored by an agency of the United States Government. Neither the United States Government nor any agency thereof, nor any of their employees, makes any warranty, express or implied, or assumes any legal liability or responsibility for the accuracy, completeness, or usefulness of any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately owned rights. Reference herein to any specific commercial product, process, or service by trade name, trademark, manufacturer, or otherwise does not necessarily constitute or imply its endorsement, recommendation, or favoring by the United States Government or any agency thereof. The views and opinions of authors expressed herein do not necessarily state or reflect those of the United States Government or any agency thereof.

This report has been reproduced directly from the best available copy.

Available to DOE and DOE contractors from the Office of Scientific and Technical Information, 175 Oak Ridge Turnpike, Oak Ridge, TN 37831; prices available at (615) 576-8401.

Available to the public from the National Technical Information Service, U.S. Department of Commerce, 5285 Port Royal Road, Springfield, VA 22161; phone orders accepted at (703) 487-4650.

Page 3: CHARACTERIZATION OF RADIOACTIVE CONTAMINATION INSIDE …

DISCLAIMER

Portions of this document may be illegible in electronic image products. images are produced from the best available original document.

I

Page 4: CHARACTERIZATION OF RADIOACTIVE CONTAMINATION INSIDE …

4.1 Characterization of Radioactive Contamination Inside Pipes With the Pipe Explorer" System

CONTRACT INFORMATION

Contract Number

Contractor

Principal Investigator

METC Project Manager

Period of Performance

Schedule and Milestones

DE-AC2 1 -93MC30 172

Science and Engineering Associates, Inc. 1570 Pacheco, Suite D-1 Santa Fe, NM 87505 (505) 983-6698

William E. Lowry

C. Edward Christy

9/23/93 - 1 1/28/94

FY94 Program Schedule

O N D J F M A M J J N S Test Plan Fabrication Testing Analysis

OBJECTIVES

The objective for the development of the Pipe ExplorerTM radiological characterization system is to achieve a cost effective, low risk means of characterizing gamma radioactivity on the inside surface of pipes. The goal for the contract effort is to show that:

The internal surface of pipe can be character- ized to differentiate between clean and con- taminated piping, according to DOE contami- nation standards.

The internal surface of pipe can be character- ized in a manner that protects expensive radia- tion detectors from contamination.

The characterization process protects person- nel from coming in contact with contaminated material.

-173-

The system can be used without difficulty in a range of environments, in both removed and in-place piping.

BACKGROUND INFORMATION

The SEA pipe inspection system performs a radiological survey of the internal surface of a pipe by transporting a gamma detector through the pipe using an inverting membrane deployment method. The system is versatile in that it can negotiate bends and limited obstructions, can travel both horizontally and vertically, and can inspect pipes of smaller diameter than is capable with current pipe crawler technology.

The unique feature of this inspection system is the use of a pneumatically inflated impermeable membrane which transports the detector into the pipe as it inverts (Figure 1). The membrane's internal air pressure tows the detector and tether I

Page 5: CHARACTERIZATION OF RADIOACTIVE CONTAMINATION INSIDE …

around canister outlet

Pipe to be inspected Deployment

Canister Membrane rolled up on reel

Membrane inverts U under air pressure I I

J)

(* /Tether/signal cable I I -

\ Detector being towed into pipe

Fully deployed survey system W '

Figure 1. Inverting Membrane Pipe Inspection System Operating Sequence

through the pipe. This mechanism isolates the detector and its cabling from the contaminated surface, yet allows measurement of radioactive emissions which can readily penetrate the thin plastic membrane materia1 (such as gamma and high energy beta emissions).

the pipe, continuously recording count rates to map areas of high surface activity. After the sur- vey is completed, the detector can be located at hot spots during the retrieval for detailed spectro- scopic measurements.

The detector travels slowly down the length of

The DOE has established radioactive contam- inant threshold levels above which material must be considered contaminated (Table 1). The activ- ity levels range from 20 to 10,000 disintegrations per minute (dpm) per 100 cm* (depending on the source of the radiation and if it is either fixed or removable). Given the limitations of scintillation detectors and likely background radiation levels, gamma detection limits as low as 20 dpd100 cm2 will not be likely achievable with portable detec-

tors. The threshold value of 1000 dpd100 cm* is considered viable depending on the extent of background radiation and the gamma production efficiency of the radioisotope.

PROJECT DESCRIPTION

To develop and demonstrate the Pipe Explorerm system, a two-phased approach was employed. In Phase I, an initial survey of DOE facilities was conducted to determine the physical and radiological characteristics of piping systems. The inverting membrane deployment system was designed and extensively tested in the laboratory. A range of membrane materials was tested to evaluate their ruggedness and deployment charac- teristics. Two different sizes of gamma scintilla- tion detectors were procured and tested with cali- brated sources. Radiation transport modeling evaluated the measurement system's sensitivity to detector position relative to the contaminated sur- face, the distribution of the contamination, back- ground gamma levels, and gamma source energy levels. In the culmination of Phase I, a field demonstration was conducted at the Idaho National Engineering Laboratory's Idaho Chemical Processing Plant. The project is cur- rently in transition from Phase I to Phase 11, where more extensive demonstrations will occur at several sites.

RESULTS

A. Deployment System

The emphasis of the inverting membrane deployment system design was to allow for the capability to remotely operate the deployment and retrieval of membranes in piping systems with minimal operator intervention. The deployment system components are depicted in Figure 2. The control system allows the operator to select either deployment or retrieval at a specific rate. The system then controls the process within preset operational parameters until fully retrieved or deployed. Operational parameters monitored continuously include tether tension and membrane pressure. The control system was tested exten- sively during the lab scale tests as well as at the Phase I demonstration and proved to work as desired.

- 174-

Page 6: CHARACTERIZATION OF RADIOACTIVE CONTAMINATION INSIDE …

Table 1. Summary of Maximum Allowable Surface Radiological Contami- nation (Reproduced from “DOE Radiological Control Manual,” DOE/EH-O256T, June 1992)

Nuclide Removable fdDm/loo cm2)

U-natural, U-235, U-238 and associated decay products Transuranics, Ra-226, Ra-228, Th-230, Th- 228, Pa-231, Ac-227,I-125,I-129 Th-natural, Th-232, Sr-90, Ra-223, Ra-224,

Beta-gamma emitters (nuclides with decay modes other than alpha emission or sponta- neous fission) except Sr-90 and others noted above. Includes mixed fission

U-232,1-126,1-131,1-133

1,OOO alpha

20

200

1,000 beta- gamma

- products containing Sr-90.

contaminated by HT, HTO and metal tritide aerosols

Tritium organic compounds, surfaces 10,000

rota1 (Fixed + Removable) fdDm/100 cm2)

5,000 alpha

500

1,000 _I

5,000 beta-gamma

10,000

I I Deployment I ; Data I

I I I I

I I I I I

Pressurized I

Compressed Air supply

Figure 2. Integrated Pipe Inspection System, Showing Pressure Canister and Instrumentation System

-175-

.

Page 7: CHARACTERIZATION OF RADIOACTIVE CONTAMINATION INSIDE …

Testing of the deployment system included 1.5- to 6-inch-diameter pipes at a maximum length of 200 feet. Several deployment system limitations exist with regard to piping system geometry and pipe size. The primary limitation is the number of elbows encountered in a pipe run. The elbows used in the lab scale tests and for the Phase I demonstration were drain line 1/4 bend 90 degree elbows for water service. It had been determined early in lab scale tests that for small diameter pipe, 4 inches or less, the deployment system could not manage the short radius straight or vent 90 degree elbows commonly used for high pressure gas service. For 2-inch pipe (ZOO-foot length), the maximum number of elbows readily negotiated with the actual tether and detector assembly is two. For 3- and 4-inch pipe the maximum number of elbows is 4. These limita- tions are dependent on the location of the elbows with respect to the pipe entrance and the total pipe length. If shorter pipes are to be inspected, more elbows can be negotiated. Lighter weight tethers also allow more elbows to be negotiated. For example, up to six elbows were negotiated in a 2-inch, 200-foot-long pipe with a lightweight rope as the tether. Qualitative information was obtained with regard to pipe obstructions and inline valves. Initial lab scale tests performed on 2- and 4-inch pipes proved the ability of the deployment system and detector to negotiate 25 percent cross-sectional area obstructions with little or no difficulty.

The membranes selected for deployment are typically oversized by 20 to 50 percent of the pipe diameter. This enables the membrane to negotiate corners more easily. The best general purpose membrane used for deployment has proved to be a 0.004-inch thick, 100 percent low density polyethylene (LDPE). The LDPE provides a rela- tively high burst pressure to pipe diameter ratio when compared to other polyethylene blends. LDPE is also elastic and tear resistant which is desirable when encountering sharp edges or obstructions which could destroy a membrane. Costs for this material range from $0.03 to $0.05 per lineal foot. Typically, a 200-foot membrane costs less than $10 and consumes less than half a cubic foot in volume. Consequently, it is less expensive, and produces less secondary waste, to consider the membranes disposable after each use.

this also eliminates cross contamination mea- surement issues.

B. Radiological Measurements

The Phase I demonstration at the INE,L/ICPP and laboratory tests of the Pipe ExplorerlM demonstrated the utility of the system to deploy gamma scintillation detectors into a variety of piping configurations. These were successfully deployed with the system and were shown to have the sensitivity required to make very low level measurements inside of pipes. For example, a laboratory test was conducted where a C0-60 source with an NIST traceable calibrated activity of 1000 dpd100 cm2 was placed inside of a 3-inch schedule 40 steel pipe. A 2- by 2-inch NaI detector was used to survey the pipe and the re- sults are shown in Figure 3. The data shows that low activity radioactive sources are distinguish- able from the background radiation.

1500

1400

2 1300 0 ,m 1200

1100

1000

cn L

-

loo0 dpW100 Cnr2 Cb60 ......................................

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

.................................. > 0.5 1 1.5 2 2.5

Distance (m)

Figure 3. Results of a Survey of a 1000 dpd100 cm2 Co-60 Source Inside of a 3 -inch I.D. Schedule 40 Steel Pipe

The INEL drain line mockup configuration (with calibrated sources mounted on the outer sur- face of the pipes) is depicted in Figure 4, and the radiological survey results are plotted in Figure 5. The system clearly located the sources with the detector moving at 0.5 ft/min.

- 176-

Page 8: CHARACTERIZATION OF RADIOACTIVE CONTAMINATION INSIDE …

60 U

50 0 $ 40 g 30 L.

2 20

5 10 0

0

3' 58'

Clear 3" PVC ' Point source (typ.)

1 Ocm x 1 Ocm source -

0

1 Ocm x 1 Ocm source -

0

4 61'

Figure 4. INEWICPP Drain Line Mockup

D (IMI an'2) ..... .,. ........... 0 20 40 60 80 100 120

Depth into Pipe (ft)

Figure 5. INELLICPP Drain Line Mockup Survey Results (Calibrated Sources)

FUTURE WORK

The laboratory tests and the Phase I field test demonstrated the capability of a Pipe ExplorerTM characterization system to emplace in a range of pipe diameters and pipe configurations. The limitations of the systems operation identified in both the laboratory tests and the field demon- stration are primarily related to the maximum number of elbows negotiable by the detector transport system and a maximum total length of the emplacement systems capability. Several

design enhancements will facilitate ease of use and diagnostics capability of the system during its normal use. Minor changes associated with slack indications of the tether, control switches and indicators will enhance the operability of the system in field use. One instrumentation change recommended for implementation prior to the next field demonstration applies to the way that the counts from the radiation detector are monitored and recorded by the data acquisi- tion system. As currently configured, the multi- channeled analyzer card accepts the count pulses from the scintillation detector over a defined window, called the region of interest (ROI). While this methodology is good from the standpoint of allowing us to collect multiple ROIs and also do spectral determinations con- tinuously, it is a time consuming process and results in limited spatial resolutions of the activ- ity as a function of depth in the pipe. What is planned for implementation prior to the next field demonstration is to use a ratemeter, which provides counts as a function of time over a relatively narrow time period such as 10 to 30 seconds. This would allow us to send the output from the rate meter directly into the analoddigital conversion card running under LabView software to more readily give us a plot of counts versus depth in the pipe in real time. This will be implemented by using a conven- tional nuclear measurement bin type design

-177-

Page 9: CHARACTERIZATION OF RADIOACTIVE CONTAMINATION INSIDE …

which allows us to install multiple rate meters and multiple power conditioning equipment in one modular package. This has the added bene- fit of allowing simultaneous use of different sensors, as well as applying pulse shaping amplifiers that enhance the versatility of the electrical measurement system. For example, the small diameter detector CsI(Na) has limited resolution in its present configuration. This device can be expected to resolve energy differ- ences on the order of 30 percent. With adjust- ments in signal conditioning, such as using a pulse shaping amplifier, the energy resolution of this detector can be improved to a level of about 15 percent instead of the current 30 percent. The bin type approach is a modular one that allows addition of signal conditioners for vari- ous specific applications. We are considering implementing a beta detector in the Phase I1 demonstration that requires a different type of ratemeter than would currently be applied to our CsI(Na) or NaI(T1) detectors. The bin system would allow us to purchase a ratemeter custom designed for the beta detector along with ratemeters designed for use with scintillation counters.

Modifications to the system which would enhance its deployment capabilities (in terms of total length of pipe and total numbers of elbows) focus on lightening the weight of the tether assembly, which would result in reduced drag and allowed further emplacement. We are cur- rently using conductors that are larger than they need to be for the coaxial and DC connections. Reductions in tether weight result in an almost proportional impact on the maximum deploy- able length of pipe. For example, if we were able to reduce the weight of tether by 50 percent, we can in effectively double our emplacement length or increase, although not proportionally, the number of elbows negotiable by the detector emplacement system. We also plan to assemble custom tether packages. For example, one tether could be a single coaxial cable that could be used with some of the scintillation counters that require only a single coaxial cable and carry their power on the inner conductor of the coax. Having a range of tether types available allows reconfiguration of the system for deployment of several different instruments in the field.

Field activities proposed for Phase 11 are intended to provide additional experience at dif- ferent sites and under different radiological con- ditions to qualify the Pipe Explorer"' system. Further demonstrations at the Idaho Chemical Processing Plant at INEL as well as field demonstrations in at least one other DOE site are planned.

REFERENCES

1. "Radiological Control Manual," U.S. Department of Energy , DOE/EH-,0256T, June 1992.