Chapter 5:Chapter 5:Project Scope ManagementProject Scope Management
Information TechnologyInformation Technology
Project Management,Project Management,Fifth EditionFifth Edition
-
8/7/2019 Chapter05 Project Scope Management
2/35
Information Technology Project Management, Fifth Edition, Copyright 20072
Learning ObjectivesUnderstand the elements that make good project
scope management importantExplain the scope planning process and describe
the contents of a scope management plan
Describe the process for developing a project scopestatement using the project charter andpreliminary scope statement
Discuss the scope definition process and work
involved in constructing a work breakdownstructure using the analogy, top-down, bottom-up, and mind-mapping approaches
-
8/7/2019 Chapter05 Project Scope Management
3/35
Information Technology Project Management, Fifth Edition, Copyright 20073
Learning Objectives (continued)
Explain the importance of scope verification andhow it relates to scope definition and control
Understand the importance of scope control andapproaches for preventing scope-related
problems on information technology projectsDescribe how software can assist in project
scope management
-
8/7/2019 Chapter05 Project Scope Management
4/35
Information Technology Project Management, Fifth Edition, Copyright 20074
What is Project Scope Management?
Scope refers to allthe work involved in creatingthe products of the project and the processesused to create them
A deliverable is a product produced as part of a
project, such as hardware or software, planningdocuments, or meeting minutes
Project scope management includes theprocesses involved in defining and controlling
what is or is not included in a project
-
8/7/2019 Chapter05 Project Scope Management
5/35
Information Technology Project Management, Fifth Edition, Copyright 20075
Project Scope ManagementProcessesScope planning:deciding how the scope will be defined,
verified, and controlled
Scope definition: reviewing the project charter andpreliminary scope statement and adding moreinformation as requirements are developed andchange requests are approved
Creating the WBS: subdividing the major projectdeliverables into smaller, more manageable
componentsScope verification: formalizing acceptance of the project
scope
Scope control: controlling changes to project scope
-
8/7/2019 Chapter05 Project Scope Management
6/35
Information Technology Project Management, Fifth Edition, Copyright 20076
Figure 5-1: Project ScopeManagement Summary
-
8/7/2019 Chapter05 Project Scope Management
7/35
Information Technology Project Management, Fifth Edition, Copyright 20077
Scope Planning and the ScopeManagement PlanThe scope management plan is a document that
includes descriptions of how the team willprepare the project scope statement, create the
WBS, verify completion of the projectdeliverables, and control requests for changesto the project scope
Key inputs include the project charter, preliminary
scope statement, and project management plan
-
8/7/2019 Chapter05 Project Scope Management
8/35
Information Technology Project Management, Fifth Edition, Copyright 20078
What Went Right?
Many financial service companies use customerrelationship management (CRM) systems to improvetheir understanding of and responsiveness to customers
A senior management team at the Canadian moneymanagement company Dynamic Mutual Funds (DMF)launched an enterprise-wide, national program to buildand manage its customer relationships
They needed a faster and more organized, highlyparticipative approach, so they proposed a new seven-
step concept called project scope designDMF won an eCustomer World Golden Award for world-
class innovation
-
8/7/2019 Chapter05 Project Scope Management
9/35
Information Technology Project Management, Fifth Edition, Copyright 20079
Table 5-1: Sample Scope ManagementPlan
-
8/7/2019 Chapter05 Project Scope Management
10/35
Information Technology Project Management, Fifth Edition, Copyright 200710
Table 5-2: Sample Project Charter
-
8/7/2019 Chapter05 Project Scope Management
11/35
Information Technology Project Management, Fifth Edition, Copyright 200711
Scope Definition and theProject Scope Statement
The preliminary scope statement, project charter,organizational process assets, and approvedchange requests provide a basis for creating the
project scope statementAs time progresses, the scope of a project should
become more clear and specific
-
8/7/2019 Chapter05 Project Scope Management
12/35
Information Technology Project Management, Fifth Edition, Copyright 200712
Table 5-3: Further DefiningProject Scope
-
8/7/2019 Chapter05 Project Scope Management
13/35
Information Technology Project Management, Fifth Edition, Copyright 200713
Media Snapshot
Many people enjoy watching television shows like Changing Roomsor Trading Spaces, where participants have two days and $1,000 toupdate a room in their neighbors house. Since the time and cost are set,its the scope that has the most flexibility. Designers on these shows oftenhave to change initial scope goals due to budget or time constraints.
Although most homeowners are very happy with work done on the
show, some are obviously disappointed. Unlike most projects where theproject team works closely with the customer, homeowners have little sayin what gets done and cannot inspect the work along the way Whathappens when the homeowners dont like the work thats been done? TheFAQ section of tlc.com says, Everyone on our show is told upfront thattheres a chance they wont like the final design of the room. Eachapplicant signs a release acknowledging that the show is not responsiblefor redecorating a room that isnt to the owners taste.
Too bad you cant get sponsors for most projects to sign a similarrelease form. It would make project scope management much easier!
-
8/7/2019 Chapter05 Project Scope Management
14/35
Information Technology Project Management, Fifth Edition, Copyright 200714
Creating the Work BreakdownStructure (WBS)A WBS is a deliverable-oriented grouping of the
work involved in a project that defines the totalscope of the project
WBS is a foundation document that provides thebasis for planning and managing projectschedules, costs, resources, and changes
Decomposition is subdividing project
deliverables into smaller piecesA work package is a task at the lowest level of
the WBS
-
8/7/2019 Chapter05 Project Scope Management
15/35
Information Technology Project Management, Fifth Edition, Copyright 200715
Figure 5-2: Sample Intranet WBS
Organized by Product
-
8/7/2019 Chapter05 Project Scope Management
16/35
Information Technology Project Management, Fifth Edition, Copyright 200716
Figure 5-3: Sample Intranet WBSOrganized by Phase
-
8/7/2019 Chapter05 Project Scope Management
17/35
Information Technology Project Management, Fifth Edition, Copyright 200717
Table 5-4: Intranet WBS in TabularForm
1.0 Concept1.1 Evaluate current systems1.2 Define Requirements
1.2.1 Define user requirements1.2.2 Define content requirements
1.2.3 Define system requirements1.2.4 Define server owner requirements1.3 Define specific functionality1.4 Define risks and risk management approach1.5 Develop project plan1.6 Brief Web development team
2.0 Web Site Design3.0 Web Site Development4.0 Roll Out5.0 Support
-
8/7/2019 Chapter05 Project Scope Management
18/35
Information Technology Project Management, Fifth Edition, Copyright 200718
Figure 5-4: Intranet WBS and GanttChart in Microsoft Project
-
8/7/2019 Chapter05 Project Scope Management
19/35
Information Technology Project Management, Fifth Edition, Copyright 200719
Figure 5-5: Intranet Gantt ChartOrganized by Project Management
Process Groups
-
8/7/2019 Chapter05 Project Scope Management
20/35
Information Technology Project Management, Fifth Edition, Copyright 200720
Table 5-5: Executing Tasks forJWD Consultings WBS
-
8/7/2019 Chapter05 Project Scope Management
21/35
Information Technology Project Management, Fifth Edition, Copyright 200721
Approaches to Developing WBSs
Using guidelines: some organizations, like theDOD, provide guidelines for preparing WBSsThe analogy approach: review WBSs of similar
projects and tailor to your project
The top-down approach: start with the largestitems of the project and break them downThe bottom-up approach: start with the specific
tasks and roll them up
Mind-mapping approach: mind mapping is atechnique that uses branches radiating out froma core idea to structure thoughts and ideas
-
8/7/2019 Chapter05 Project Scope Management
22/35
Information Technology Project Management, Fifth Edition, Copyright 200722
Figure 5-6: Sample Mind-MappingApproach for Creating a WBS
-
8/7/2019 Chapter05 Project Scope Management
23/35
Information Technology Project Management, Fifth Edition, Copyright 200723
Figure 5-7: Resulting WBS inChart Form
-
8/7/2019 Chapter05 Project Scope Management
24/35
Information Technology Project Management, Fifth Edition, Copyright 200724
The WBS Dictionary and ScopeBaselineMany WBS tasks are vague and must be
explained more so people know what to do andcan estimate how long it will take and what it
will cost to do the workA WBS dictionary is a document that describes
detailed information about each WBS itemThe approved project scope statement and its
WBS and WBS dictionary form the scopebaseline, which is used to measureperformance in meeting project scope goals
-
8/7/2019 Chapter05 Project Scope Management
25/35
Information Technology Project Management, Fifth Edition, Copyright 200725
Advice for Creating a WBS and WBSDictionary*A unit of work should appear at only one place in
the WBSThe work content of a WBS item is the sum of the
WBS items below it
A WBS item is the responsibility of only oneindividual, even though many people may beworking on it
The WBS must be consistent with the way inwhich work is actually going to be performed; itshould serve the project team first, and otherpurposes only if practical
*Cleland, David I. Project Management: Strategic Design and Implementation,1994
-
8/7/2019 Chapter05 Project Scope Management
26/35
Information Technology Project Management, Fifth Edition, Copyright 200726
Advice for Creating a WBS andWBS Dictionary (continued)*Project team members should be involved in
developing the WBS to ensure consistency andbuy-in
Each WBS item must be documented in a WBS
dictionary to ensure accurate understanding ofthe scope of work included and not included inthat item
The WBS must be a flexible tool to accommodate
inevitable changes while properly maintainingcontrol of the work content in the projectaccording to the scope statement
*Cleland, David I. Project Management: Strategic Design and Implementation,1994
-
8/7/2019 Chapter05 Project Scope Management
27/35
Information Technology Project Management, Fifth Edition, Copyright 200727
What Went Wrong?
A project scope that is too broad and grandiosecan cause severe problemsScope creep and an overemphasis on technology for
technologys sake resulted in the bankruptcy of a
large pharmaceutical firm, Texas-based FoxMeyerDrugIn 2001, McDonalds fast-food chain initiated a
project to create an intranet that would connect itsheadquarters with all of its restaurants to provide
detailed operational information in real time; afterspending $170 million on consultants and initialimplementation planning, McDonalds realized thatthe project was too much to handle and terminatedit
-
8/7/2019 Chapter05 Project Scope Management
28/35
Information Technology Project Management, Fifth Edition, Copyright 200728
Scope Verification
It is very difficult to create a good scope statementand WBS for a project
It is even more difficult to verify project scope andminimize scope changes
Scope verification involves formal acceptance ofthe completed project scope by the stakeholders
Acceptance is often achieved by a customerinspection and then sign-off on key deliverables
-
8/7/2019 Chapter05 Project Scope Management
29/35
Information Technology Project Management, Fifth Edition, Copyright 200729
Scope Control
Scope control involves controlling changes tothe project scope
Goals of scope control are to:Influence the factors that cause scope changes
Assure changes are processed according toprocedures developed as part of integrated changecontrol
Manage changes when they occur
Variance is the difference between planned andactual performance
-
8/7/2019 Chapter05 Project Scope Management
30/35
Information Technology Project Management, Fifth Edition, Copyright 200730
Best Practices for Avoiding ScopeProblems
1. Keep the scope realistic: Dont make projects so large thatthey cant be completed; break large projects down into aseries of smaller ones
2. Involve users in project scope management: Assign keyusers to the project team and give them ownership of
requirements definition and scope verification3. Use off-the-shelf hardware and software whenever
possible: Many IT people enjoy using the latest and greatesttechnology, but business needs, not technology trends,
must take priority4. Follow good project management processes: As described
in this chapter and others, there are well-defined processesfor managing project scope and others aspects of projects
-
8/7/2019 Chapter05 Project Scope Management
31/35
Information Technology Project Management, Fifth Edition, Copyright 200731
Suggestions for Improving User Input
Develop a good project selection process andinsist that sponsors are from the userorganization
Have users on the project team in important roles
Have regular meetings with defined agendas,and have users sign off on key deliverablespresented at meetings
Deliver something to users and sponsors on a
regular basisDont promise to deliver when you know you cantCo-locate users with developers
-
8/7/2019 Chapter05 Project Scope Management
32/35
Information Technology Project Management, Fifth Edition, Copyright 200732
Suggestions for ReducingIncomplete and ChangingRequirementsDevelop and follow a requirements management
process
Use techniques such as prototyping, use casemodeling, and JAD to get more user involvement
Put requirements in writing and keep them currentCreate a requirements management database for
documenting and controlling requirements
-
8/7/2019 Chapter05 Project Scope Management
33/35
Information Technology Project Management, Fifth Edition, Copyright 200733
Suggestions for ReducingIncomplete and ChangingRequirements (continued)Provide adequate testing and conduct testing
throughout the project life cycleReview changes from a systems perspectiveEmphasize completion dates to help focus on
whats most important
Allocate resources specifically for handlingchange requests/enhancements like NWA didwith ResNet
-
8/7/2019 Chapter05 Project Scope Management
34/35
Information Technology Project Management, Fifth Edition, Copyright 200734
Using Software to Assist in ProjectScope ManagementWord-processing software helps create several
scope-related documentsSpreadsheets help to perform financial
calculations and weighed scoring models, anddevelop charts and graphs
Communication software like e-mail and the Webhelp clarify and communicate scope information
Project management software helps in creating aWBS, the basis for tasks on a Gantt chart
Specialized software is available to assist inproject scope management
-
8/7/2019 Chapter05 Project Scope Management
35/35
Information Technology Project Management Fifth Edition Copyright 200735
Chapter Summary
Project scope management includes theprocesses required to ensure that the projectaddresses all the work required, and only thework required, to complete the project
successfullyMain processes include:
Scope planningScope definition
Creating the WBSScope verificationScope control