chapter04_switching overvoltage analysis.pdf

Upload: eleazar-sierra-espinoza

Post on 03-Jun-2018

241 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/12/2019 Chapter04_Switching Overvoltage Analysis.pdf

    1/38

    Chapter 4

    Switching Overvoltage Analysis

    4.1 Introduction

    In the extra high voltage (EHV) transmission line, switching overvoltages are

    used to determine the insulation design rather than lightning overvoltages. The

    insulation level required to withstand the switching surge overvoltages can had a

    significant influence on the cost of the transmission systems. Therefore, an accurate

    estimation of the switching overvoltages under various conditions of the operation is

    important factor for the design of transmission systems. Switching overvoltages result

    from the operation of switching devices, either during normal conditions or as a result

    of fault clearings. These transients have durations from ten to thousands of

    microseconds. This thesis investigates the switching overvoltages occurring during

    the switching of line circuit breaker on each side of the 500 kV transmission line

    between Nam Theun 2 and Thailand network at Roi Et 2 substation as shown in

    Figure 4.1. The analyses to assess the switching overvoltages in cases are as

    following: [4], [5], [16]

    - Line energization

    - Line re-energization due to single phase to ground and three phases to

    ground faults.

    Two cases above bring to get the highest overvoltage. In case of line re-

    energization, more than 85-90% comes from line to ground faults and the other comes

    from three phases to ground faults. However, case of three phases to ground faults hasmore damage than single line to ground fault.

    4.2 Line Energization Analysis

    4.2.1 Cases of the study

    The 500 kV transmission line between Nam Theu 2 and Roi Et 2 had

    double circuits. The study of line energization is divided into three cases as following:

  • 8/12/2019 Chapter04_Switching Overvoltage Analysis.pdf

    2/38

    58

    1) Line energization from Nam Theun 2 to Roi Et 2 circuit 1 with open

    circuit at the receiving end at RE 2 substation and energizing with load

    conditions.

    2) Line energization from Nam Theu 2 to Roi Et 2 circuit 2 with open

    circuit at the receiving end at RE 2 substation.

    3) Line energization from Nam Theun 2 to Roi Et 2 circuit 1 and circuit 2

    energizing with load.

    Switching overvoltages during line energization of the 500 kV transmission line

    between Nam Theun 2 and Thailand network at Rio Et 2 substation is analyzed with a

    presence of 444 kV surge arresters at both sides and 355 Mvar shunt reactors at Nam

    Theun 2 Power Plant and 255 Mvar at Roi Et 2 substation at both sides terminal. It

    was assumed that protection devices switched turning on/off during line energization.

    The 200 operations statistical switching are considered for finding that the maximum

    overvoltage occurring the transmission lines.

    4.2.2 Methodology

    All cases of the study, the circuit breaker at bus the sending end is

    operating energizing to lines. The line energization overvoltages study during no load,

    half load and full load are considered. In case of line energization, it brings to get the

    maximum overvoltages and more damage, for example, open circuit breaker at the

    receiving end during the energization from the sending end will get the overvoltages

    at the receiving end. As well known, switching overvoltage occurred on power

    systems due to many factors which have an effect on the value and waveform. The

    maximum overvoltage is found out by the statistical method. This method is random

    many parameters such as circuit breaker closing time, time scatter between phases,line parameters. It should be note that the closing time plays an important role on the

    value of energization overvoltage. First step to study switching energization, we have

    to find out the worst closing and the statistical closing time.

    4.2.3 Line Energizing from NTN 2- RE2 Circuit 1

    Line energization overvoltage study of circuit 1, energizing from the

    sending end named NTN 2 to the receiving end named RE 2 as illustrated in Figure

    4.1.

  • 8/12/2019 Chapter04_Switching Overvoltage Analysis.pdf

    3/38

    59

    Figure 4.1 Single line diagram of 500 kV transmission line NTN 2 RE 2 substation

    circuit 1 energizing.

    Before closing the circuit breaker of Nam Theun 2, the generator of power plant

    has to be in steady state condition. All line circuit breakers at both sides of these two

    circuits are opened and one set of line circuit breaker on the circuit 1 of the double

    circuit lines a Nam Theun 2 is operated.

    Since one circle of waveform has 20 ms, result in many closing times can apply

    for circuit breaker. To find the worst closing time ( mean closing time ), we have

    change the closing phase angle and find out the particular closing phase angle which

    can cause the highest value. Table: 4.1 shown the results for different closing time

    ( when the three phases closing at same time ). The highest overvoltage is 1.704 p.u

    occurred at the receiving end when the closing time is 15ms.

    Table: 4.1. The effect of different closing time on the energization overvoltage

    closing 3 poles of circuit breaker at the same time from NTN 2

    RE 2 with protection devices terminal.

    Maximum overvoltage at Roi Et 2 substation ( 1 p.u = 429 kV )

  • 8/12/2019 Chapter04_Switching Overvoltage Analysis.pdf

    4/38

  • 8/12/2019 Chapter04_Switching Overvoltage Analysis.pdf

    5/38

    61

    ( p.u ) ( p.u ) ( p.u ) ( p.u ) ( p.u )

    1 1.688 41 1.695 81 1.693 121 1.700 161 1.702

    2 1.702 42 1.704 82 1.665 122 1.676 162 1.6943 1.706 43 1.697 83 1.704 123 1.681 163 1.692

    4 1.704 44 1.690 84 1.701 124 1.676 164 1.699

    5 1.699 45 1.701 85 1.703 125 1.665 165 1.702

    6 1.703 46 1.704 86 1.702 126 1.702 166 1.680

    7 1.704 47 1.697 87 1.680 127 1.703 167 1.682

    8 1.699 48 1.703 88 1.694 128 1.682 168 1.704

    9 1.686 49 1.686 89 1.704 129 1.688 169 1.701

    10 1.701 50 1.691 90 1.671 130 1.680 170 1.700

    11 1.702 51 1.703 91 1.704 131 1.698 171 1.678

    12 1.676 52 1.706 92 1.706 132 1.702 172 1.694

    13 1.695 53 1.688 93 1.672 133 1.685 173 1.703

    14 1.703 54 1.704 94 1.674 134 1.662 174 1.690

    15 1.664 55 1.703 95 1.704 135 1.703 175 1.703

    16 1.697 56 1.697 96 1.678 136 1.694 176 1.702

    17 1.691 57 1.686 97 1.706 137 1.704 177 1.702

    18 1.703 58 1.691 98 1.688 138 1.704 178 1.662

    19 1.667 59 1.703 99 1.706 139 1.690 179 1.701

    20 1.702 60 1.686 100 1.702 140 1.704 180 1.697

    21 1.704 61 1.695 101 1.703 141 1.667 181 1.703

    22 1.704 62 1.704 102 1.686 142 1.689 182 1.691

    23 1.704 63 1.697 103 1.705 143 1.678 183 1.70424 1.703 64 1.690 104 1.676 144 1.704 184 1.671

    25 1.678 65 1.701 105 1.686 145 1.705 185 1.702

    26 1.688 66 1.704 106 1.706 146 1.672 186 1.702

    27 1.704 67 1.697 107 1.704 147 1.693 187 1.683

    28 1.702 68 1.703 108 1.693 148 1.704 188 1.705

    29 1.696 69 1.686 109 1.697 149 1.704 189 1.704

    30 1.678 70 1.691 110 1.699 150 1.674 190 1.674

    31 1.687 71 1.703 111 1.703 151 1.704 191 1.665

    32 1.694 72 1.706 112 1.683 152 1.702 192 1.702

    33 1.680 73 1.688 113 1.706 153 1.681 193 1.676

    34 1.701 74 1.704 114 1.704 154 1.684 194 1.694

    35 1.704 75 1.703 115 1.693 155 1.703 195 1.669

    36 1.704 76 1.697 116 1.684 156 1.686 196 1.678

    37 1.676 77 1.686 117 1.671 157 1.702 197 1.704

    38 1.705 78 1.691 118 1.680 158 1.702 198 1.697

    39 1.691 79 1.703 119 1.691 159 1.703 199 1.703

    40 1.704 80 1.686 120 1.700 160 1.700 200 1.702

  • 8/12/2019 Chapter04_Switching Overvoltage Analysis.pdf

    6/38

    62

    From table: 4.2, the 200 operations switching line energization circuit 1 with

    protection devices of 500 kV transmission lines Nam Theun 2 to Roi Et 2 substation.

    The line energization overvoltage in circuit breakers occurs at the closing time of

    14.28 ms. The maximum overvoltage at the receiving end is reach 1.706 p.u. The

    minimum overvoltage at the receiving end is 1.662 p.u. The mean of overvoltage at

    the receiving end is 1.692 p.u and the standard deviation is 5.056 %. The voltage

    waveform is illustrated in Figure 4.2.

    Figure 4.2 SOV during line energizing circuit 1 with protection devices.

  • 8/12/2019 Chapter04_Switching Overvoltage Analysis.pdf

    7/38

    63

    Table: 4.3 The 200 statistical calculations for energization overvoltage from

    NTN 2 RE 2 circuit 1 without shunt reactor at NTN 2.

    No.Voltage

    ( p.u )No.

    Voltage

    ( p.u )No.

    Voltage

    ( p.u )No.

    Voltage

    ( p.u )No.

    Voltage

    ( p.u )

    1 1.701 41 1.708 81 1.706 121 1.715 161 1.721

    2 1.721 42 1.722 82 1.684 122 1.697 162 1.714

    3 1.721 43 1.710 83 1.722 123 1.703 163 1.705

    4 1.722 44 1.711 84 1.720 124 1.689 164 1.712

    5 1.718 45 1.714 85 1.721 125 1.684 165 1.721

    6 1.721 46 1.722 86 1.718 126 1.721 166 1.701

    7 1.722 47 1.710 87 1.693 127 1.720 167 1.695

    8 1.712 48 1.720 88 1.707 128 1.695 168 1.722

    9 1.699 49 1.699 89 1.719 129 1.701 169 1.71410 1.720 50 1.712 90 1.684 130 1.693 170 1.715

    11 1.721 51 1.716 91 1.722 131 1.711 171 1.691

    12 1.689 52 1.723 92 1.722 132 1.721 172 1.707

    13 1.716 53 1.709 93 1.684 133 1.706 173 1.722

    14 1.721 54 1.719 94 1.687 134 1.681 174 1.711

    15 1.677 55 1.719 95 1.721 135 1.721 175 1.721

    16 1.712 56 1.710 96 1.691 136 1.707 176 1.721

    17 1.712 57 1.699 97 1.723 137 1.722 177 1.721

    18 1.720 58 1.712 98 1.701 138 1.720 178 1.675

    19 1.680 59 1.719 99 1.722 139 1.702 179 1.71720 1.715 60 1.699 100 1.721 140 1.722 180 1.712

    21 1.722 61 1.714 101 1.719 141 1.680 181 1.721

    22 1.722 62 1.691 102 1.699 142 1.702 182 1.704

    23 1.721 63 1.690 103 1.720 143 1.691 183 1.722

    24 1.716 64 1.687 104 1.689 144 1.722 184 1.684

    25 1.691 65 1.708 105 1.699 145 1.722 185 1.721

    26 1.709 66 1.678 106 1.721 146 1.684 186 1.721

    27 1.718 67 1.721 107 1.723 147 1.706 187 1.705

    28 1.721 68 1.722 108 1.706 148 1.723 188 1.720

    29 1.710 69 1.721 109 1.712 149 1.722 189 1.722

    30 1.691 70 1.716 110 1.713 150 1.687 190 1.687

    31 1.708 71 1.718 111 1.716 151 1.718 191 1.684

    32 1.707 72 1.710 112 1.705 152 1.721 192 1.718

    33 1.693 73 1.695 113 1.722 153 1.703 193 1.697

    34 1.714 74 1.721 114 1.721 154 1.697 194 1.707

    35 1.721 75 1.721 115 1.706 155 1.722 195 1.682

    36 1.722 76 1.722 116 1.697 156 1.699 196 1.691

    37 1.697 77 1.690 117 1.692 157 1.721 197 1.722

    38 1.723 78 1.722 118 1.693 158 1.721 198 1.710

    39 1.704 79 1.718 119 1.712 159 1.720 199 1.716

    40 1.722 80 1.707 120 1.716 160 1.716 200 1.721

  • 8/12/2019 Chapter04_Switching Overvoltage Analysis.pdf

    8/38

    64

    From table: 4.3, the 200 operations switching line energization circuit 1 without

    shunt reactors at Nam Theun 2 of 500 kV transmission lines Nam Theun 2 to Roi Et 2

    substation. The energization overvoltage in circuit breakers closing time is 14.31 ms.

    The maximum overvoltage at the receiving end is reach 1.723 p.u. The minimum

    overvoltage at the receiving end is 1.675 p.u. The mean of overvoltage at the

    receiving end is 1.709 p.u and the standard deviation is 5.582 %. The voltage

    waveform is illustrated in Figure 4.3.

    Figure 4.3 SOV during line energizing circuit 1 without shunt reactor at NTN 2.

  • 8/12/2019 Chapter04_Switching Overvoltage Analysis.pdf

    9/38

    65

    Table: 4.4 The 200 statistical calculations for energization overvoltage from

    NTN 2 RE 2 circuit 1 without shunt reactor at RE 2.

    No.Voltage

    ( p.u )No.

    Voltage

    ( p.u )No.

    Voltage

    ( p.u )No.

    Voltage

    ( p.u )No.

    Voltage

    ( p.u )

    1 1.708 41 1.718 81 1.713 121 1.724 161 1.729

    2 1.729 42 1.730 82 1.691 122 1.704 162 1.722

    3 1.730 43 1.717 83 1.730 123 1.710 163 1.715

    4 1.730 44 1.718 84 1.728 124 1.696 164 1.720

    5 1.726 45 1.722 85 1.730 125 1.691 165 1.729

    6 1.730 46 1.731 86 1.727 126 1.729 166 1.709

    7 1.730 47 1.717 87 1.700 127 1.728 167 1.702

    8 1.720 48 1.728 88 1.716 128 1.702 168 1.731

    9 1.707 49 1.706 89 1.728 129 1.708 169 1.72210 1.728 50 1.720 90 1.691 130 1.700 170 1.724

    11 1.729 51 1.725 91 1.731 131 1.718 171 1.698

    12 1.696 52 1.731 92 1.731 132 1.729 172 1.716

    13 1.723 53 1.717 93 1.692 133 1.714 173 1.730

    14 1.730 54 1.728 94 1.694 134 1.688 174 1.718

    15 1.685 55 1.728 95 1.730 135 1.730 175 1.730

    16 1.721 56 1.717 96 1.698 136 1.716 176 1.729

    17 1.720 57 1.707 97 1.731 137 1.731 177 1.729

    18 1.728 58 1.720 98 1.709 138 1.729 178 1.682

    19 1.687 59 1.728 99 1.731 139 1.710 179 1.72620 1.724 60 1.706 100 1.729 140 1.731 180 1.721

    21 1.731 61 1.722 101 1.728 141 1.687 181 1.730

    22 1.730 62 1.698 102 1.706 142 1.711 182 1.711

    23 1.730 63 1.696 103 1.729 143 1.698 183 1.730

    24 1.726 64 1.694 104 1.696 144 1.731 184 1.691

    25 1.698 65 1.718 105 1.707 145 1.731 185 1.729

    26 1.717 66 1.685 106 1.730 146 1.692 186 1.729

    27 1.727 67 1.730 107 1.731 147 1.713 187 1.712

    28 1.729 68 1.731 108 1.713 148 1.731 188 1.729

    29 1.720 69 1.729 109 1.721 149 1.730 189 1.730

    30 1.698 70 1.725 110 1.722 150 1.694 190 1.694

    31 1.715 71 1.726 111 1.726 151 1.727 191 1.691

    32 1.714 72 1.720 112 1.712 152 1.729 192 1.727

    33 1.700 73 1.702 113 1.731 153 1.710 193 1.704

    34 1.722 74 1.729 114 1.730 154 1.704 194 1.714

    35 1.730 75 1.729 115 1.713 155 1.730 195 1.689

    36 1.731 76 1.730 116 1.704 156 1.706 196 1.698

    37 1.704 77 1.696 117 1.699 157 1.729 197 1.730

    38 1.731 78 1.730 118 1.700 158 1.729 198 1.717

    39 1.711 79 1.727 119 1.720 159 1.728 199 1.725

    40 1.730 80 1.716 120 1.725 160 1.725 200 1.729

  • 8/12/2019 Chapter04_Switching Overvoltage Analysis.pdf

    10/38

    66

    From table: 4.4, the 200 operations switching line energization circuit 1 without

    shunt reactors at Roi Et 2 of 500 kV transmission lines Nam Theun 2 to Roi Et 2

    substation. The energization overvoltage in circuit breakers closing time is 14.31 ms.

    The maximum overvoltage at the receiving end is reach 1.731 p.u. The minimum

    overvoltage at the receiving end is 1.682 p.u. The mean of overvoltage at the

    receiving end is 1.717 p.u and the standard deviation is 5.835 %. The voltage

    waveform is illustrated in Figure 4.4.

    Figure 4.4 SOV during line energizing circuit 1 without shunt reactor at RE 2.

  • 8/12/2019 Chapter04_Switching Overvoltage Analysis.pdf

    11/38

    67

    Table: 4.5 The 200 statistical calculations for energization overvoltage from

    NTN 2 RE 2 circuit 1 without arrester at NTN 2.

    No.Voltage

    ( p.u )No.

    Voltage

    ( p.u )No.

    Voltage

    ( p.u )No.

    Voltage

    ( p.u )No.

    Voltage

    ( p.u )

    1 1.693 41 1.705 81 1.698 121 1.710 161 1.713

    2 1.713 42 1.716 82 1.673 122 1.685 162 1.705

    3 1.715 43 1.703 83 1.715 123 1.691 163 1.702

    4 1.714 44 1.700 84 1.711 124 1.681 164 1.706

    5 1.709 45 1.709 85 1.714 125 1.673 165 1.713

    6 1.714 46 1.715 86 1.713 126 1.713 166 1.689

    7 1.715 47 1.703 87 1.686 127 1.714 167 1.688

    8 1.706 48 1.714 88 1.703 128 1.690 168 1.715

    9 1.695 49 1.691 89 1.714 129 1.693 169 1.70910 1.711 50 1.702 90 1.677 130 1.686 170 1.710

    11 1.713 51 1.711 91 1.715 131 1.705 171 1.686

    12 1.681 52 1.716 92 1.716 132 1.713 172 1.703

    13 1.706 53 1.699 93 1.679 133 1.695 173 1.714

    14 1.714 54 1.714 94 1.679 134 1.670 174 1.700

    15 1.671 55 1.713 95 1.715 135 1.714 175 1.714

    16 1.708 56 1.703 96 1.684 136 1.703 176 1.713

    17 1.702 57 1.695 97 1.716 137 1.715 177 1.713

    18 1.714 58 1.702 98 1.696 138 1.715 178 1.668

    19 1.674 59 1.713 99 1.716 139 1.695 179 1.71220 1.710 60 1.691 100 1.713 140 1.715 180 1.708

    21 1.715 61 1.709 101 1.713 141 1.674 181 1.714

    22 1.715 62 1.684 102 1.691 142 1.698 182 1.697

    23 1.715 63 1.678 103 1.715 143 1.684 183 1.714

    24 1.712 64 1.681 104 1.684 144 1.715 184 1.677

    25 1.684 65 1.705 105 1.695 145 1.716 185 1.713

    26 1.699 66 1.667 106 1.715 146 1.679 186 1.713

    27 1.713 67 1.714 107 1.716 147 1.698 187 1.693

    28 1.713 68 1.716 108 1.698 148 1.716 188 1.715

    29 1.706 69 1.713 109 1.708 149 1.716 189 1.715

    30 1.684 70 1.711 110 1.709 150 1.681 190 1.681

    31 1.697 71 1.709 111 1.712 151 1.713 191 1.673

    32 1.700 72 1.706 112 1.693 152 1.713 192 1.713

    33 1.688 73 1.690 113 1.716 153 1.691 193 1.685

    34 1.709 74 1.713 114 1.715 154 1.692 194 1.700

    35 1.715 75 1.713 115 1.698 155 1.714 195 1.676

    36 1.715 76 1.715 116 1.690 156 1.691 196 1.684

    37 1.685 77 1.678 117 1.681 157 1.713 197 1.715

    38 1.716 78 1.715 118 1.688 158 1.713 198 1.703

    39 1.697 79 1.713 119 1.702 159 1.714 199 1.711

    40 1.714 80 1.698 120 1.711 160 1.711 200 1.713

  • 8/12/2019 Chapter04_Switching Overvoltage Analysis.pdf

    12/38

    68

    From table: 4.5, the 200 operations switching line energization circuit 1 without

    arresters at Nam Theun 2 of 500 kV transmission lines Nam Theun 2 to Roi Et 2

    substation. The line energization overvoltage closing time is 14.28 ms. The maximum

    overvoltage at receiving end is reach 1.716 p.u. The minimum overvoltage at

    receiving end is 1.667 p.u. The mean of overvoltage at receiving end is 1.702 p.u and

    the standard deviation is 5.787 %. The voltage waveform is illustrated in Figure 4.5.

    Figure 4.5 SOV during line energizing circuit 1 without Arrester at NTN 2.

  • 8/12/2019 Chapter04_Switching Overvoltage Analysis.pdf

    13/38

  • 8/12/2019 Chapter04_Switching Overvoltage Analysis.pdf

    14/38

    70

    From table: 4.6, the 200 operations switching line energization circuit 1 without

    arresters at Rio Et 2 of 500 kV transmission lines Nam Theun 2 to Roi Et 2 substation,

    for energization overvoltage closing time is 17.47ms. The maximum overvoltage atreceiving end is 2.023 p.u. The minimum overvoltage at receiving end is 1.855 p.u.

    The mean of overvoltage at receiving end is 1.980 p.u and the standard deviation is

    18.524 %. The voltage waveform is illustrated in Figure 4.6.

    Figure 4.6 SOV during line energizing circuit 1 without Arrester at RE 2.

  • 8/12/2019 Chapter04_Switching Overvoltage Analysis.pdf

    15/38

    71

    Table 4.7 The 200 statistical calculations for energization overvoltage from

    NTN 2 RE 2 circuit 1 without shunt reactor at both sides.

    No.Voltage

    ( p.u )No.

    Voltage

    ( p.u )No.

    Voltage

    ( p.u )No.

    Voltage

    ( p.u )No.

    Voltage

    ( p.u )

    1 1.723 41 1.736 81 1.728 121 1.742 161 1.749

    2 1.749 42 1.749 82 1.708 122 1.723 162 1.746

    3 1.748 43 1.733 83 1.750 123 1.732 163 1.731

    4 1.750 44 1.743 84 1.749 124 1.711 164 1.736

    5 1.748 45 1.740 85 1.749 125 1.708 165 1.749

    6 1.749 46 1.750 86 1.745 126 1.749 166 1.729

    7 1.750 47 1.733 87 1.716 127 1.747 167 1.718

    8 1.736 48 1.747 88 1.734 128 1.718 168 1.750

    9 1.721 49 1.722 89 1.746 129 1.723 169 1.74010 1.749 50 1.744 90 1.707 130 1.716 170 1.742

    11 1.749 51 1.743 91 1.750 131 1.734 171 1.714

    12 1.711 52 1.750 92 1.749 132 1.749 172 1.734

    13 1.746 53 1.741 93 1.707 133 1.737 173 1.749

    14 1.749 54 1.746 94 1.709 134 1.705 174 1.743

    15 1.701 55 1.746 95 1.748 135 1.749 175 1.749

    16 1.740 56 1.733 96 1.714 136 1.734 176 1.749

    17 1.744 57 1.721 97 1.750 137 1.750 177 1.749

    18 1.747 58 1.744 98 1.724 138 1.747 178 1.698

    19 1.703 59 1.746 99 1.749 139 1.725 179 1.74420 1.742 60 1.722 100 1.749 140 1.750 180 1.740

    21 1.750 61 1.740 101 1.746 141 1.703 181 1.749

    22 1.750 62 1.714 102 1.722 142 1.726 182 1.727

    23 1.748 63 1.714 103 1.747 143 1.714 183 1.750

    24 1.744 64 1.709 104 1.711 144 1.750 184 1.707

    25 1.714 65 1.736 105 1.721 145 1.749 185 1.749

    26 1.741 66 1.701 106 1.748 146 1.707 186 1.749

    27 1.745 67 1.749 107 1.750 147 1.728 187 1.734

    28 1.750 68 1.749 108 1.728 148 1.750 188 1.747

    29 1.738 69 1.749 109 1.740 149 1.749 189 1.750

    30 1.714 70 1.743 110 1.741 150 1.709 190 1.709

    31 1.739 71 1.748 111 1.744 151 1.745 191 1.708

    32 1.730 72 1.738 112 1.734 152 1.749 192 1.745

    33 1.716 73 1.718 113 1.749 153 1.732 193 1.723

    34 1.740 74 1.749 114 1.748 154 1.720 194 1.730

    35 1.748 75 1.749 115 1.728 155 1.749 195 1.705

    36 1.750 76 1.750 116 1.720 156 1.722 196 1.714

    37 1.723 77 1.714 117 1.717 157 1.749 197 1.750

    38 1.750 78 1.748 118 1.716 158 1.749 198 1.733

    39 1.727 79 1.745 119 1.744 159 1.747 199 1.743

    40 1.750 80 1.734 120 1.743 160 1.743 200 1.749

  • 8/12/2019 Chapter04_Switching Overvoltage Analysis.pdf

    16/38

    72

    From table: 4.7, the 200 operations switching line energization circuit 1 without

    shunt reactors at both sides of 500 kV transmission lines Nam Theun 2 to Roi Et 2

    substation, for energization overvoltage closing time is 14.31ms. The maximum

    overvoltage at receiving end is reach 1.750 p.u. The minimum overvoltage at

    receiving end is 1.698 p.u. The mean of overvoltage at receiving end is 1.736 p.u and

    the standard deviation is 6.430 %. The voltage waveform is illustrated in Figure 4.7.

    Figure 4.7 SOV during line energizing circuit 1 without Shunt reactor at both sides.

  • 8/12/2019 Chapter04_Switching Overvoltage Analysis.pdf

    17/38

    73

    Table: 4.8 The 200 statistical calculations for energization overvoltage from

    NTN 2 RE 2 circuit 1 without arrester at both sides.

    No.Voltage

    ( p.u )No.

    Voltage

    ( p.u )No.

    Voltage

    ( p.u )No.

    Voltage

    ( p.u )No.

    Voltage

    ( p.u )

    1 2.121 41 2.183 81 2.139 121 2.188 161 2.068

    2 2.068 42 2.157 82 2.094 122 2.058 162 2.016

    3 2.151 43 2.154 83 2.099 123 2.044 163 2.176

    4 2.096 44 2.025 84 2.055 124 2.103 164 2.161

    5 2.044 45 2.165 85 2.078 125 2.094 165 2.068

    6 2.078 46 2.109 86 2.183 126 2.068 166 2.047

    7 2.114 47 2.154 87 2.106 127 2.177 167 2.106

    8 2.161 48 2.177 88 2.180 128 2.146 168 2.119

    9 2.158 49 2.115 89 2.163 129 2.121 169 2.16510 2.055 50 2.019 90 2.102 130 2.106 170 2.188

    11 2.068 51 2.166 91 2.119 131 2.158 171 2.133

    12 2.103 52 2.134 92 2.146 132 2.068 172 2.180

    13 2.023 53 2.030 93 2.125 133 2.037 173 2.089

    14 2.078 54 2.163 94 2.104 134 2.099 174 2.025

    15 2.114 55 2.181 95 2.169 135 2.078 175 2.078

    16 2.187 56 2.154 96 2.105 136 2.180 176 2.068

    17 2.019 57 2.158 97 2.127 137 2.109 177 2.068

    18 2.177 58 2.019 98 2.164 138 2.174 178 2.109

    19 2.117 59 2.181 99 2.146 139 2.128 179 2.18520 2.166 60 2.115 100 2.068 140 2.109 180 2.187

    21 2.119 61 2.165 101 2.181 141 2.117 181 2.078

    22 2.099 62 2.105 102 2.115 142 2.169 182 2.133

    23 2.169 63 2.081 103 2.160 143 2.105 183 2.106

    24 2.166 64 2.129 104 2.132 144 2.109 184 2.102

    25 2.105 65 2.183 105 2.158 145 2.150 185 2.068

    26 2.030 66 2.104 106 2.151 146 2.125 186 2.068

    27 2.165 67 2.078 107 2.129 147 2.139 187 2.041

    28 2.066 68 2.146 108 2.139 148 2.129 188 2.160

    29 2.186 69 2.068 109 2.187 149 2.157 189 2.099

    30 2.105 70 2.187 110 2.186 150 2.129 190 2.129

    31 2.033 71 2.044 111 2.166 151 2.165 191 2.094

    32 2.145 72 2.186 112 2.041 152 2.068 192 2.183

    33 2.138 73 2.146 113 2.146 153 2.044 193 2.058

    34 2.165 74 2.068 114 2.169 154 2.150 194 2.145

    35 2.169 75 2.068 115 2.139 155 2.089 195 2.121

    36 2.109 76 2.114 116 2.110 156 2.115 196 2.105

    37 2.058 77 2.081 117 2.074 157 2.068 197 2.099

    38 2.137 78 2.164 118 2.138 158 2.068 198 2.154

    39 2.133 79 2.165 119 2.019 159 2.177 199 2.166

    40 2.106 80 2.180 120 2.187 160 2.187 200 2.068

  • 8/12/2019 Chapter04_Switching Overvoltage Analysis.pdf

    18/38

    74

    From table: 4.8, the 200 operations switching line energization circuit 1 without

    arresters at both sides of 500 kV transmission lines Nam Theun 2 to Roi Et 2

    substation, for energization overvoltage closing time is 17.05 ms. The maximum

    overvoltage at receiving end is reach 2.188 p.u. The minimum overvoltage at

    receiving end is 2.016 p.u. The mean of overvoltage at receiving end is 2.119 p.u and

    the standard deviation is 20.225 %. The voltage waveform is illustrated in Figure 4.8.

    Figure 4.8 SOV during line energizing circuit 1 without arrester at both sides.

  • 8/12/2019 Chapter04_Switching Overvoltage Analysis.pdf

    19/38

    75

    Table: 4.9 The 200 statistical calculations for energization overvoltage from NTN 2

    RE 2 circuit 1 without any protection at both sides.

    No.Voltage

    ( p.u )No.

    Voltage

    ( p.u )No.

    Voltage

    ( p.u )No.

    Voltage

    ( p.u )No.

    Voltage

    ( p.u )

    1 2.362 41 2.365 81 2.369 121 2.364 161 2.320

    2 2.320 42 2.352 82 2.262 122 2.236 162 2.265

    3 2.359 43 2.373 83 2.334 123 2.224 163 2.363

    4 2.335 44 2.237 84 2.310 124 2.334 164 2.373

    5 2.297 45 2.370 85 2.326 125 2.262 165 2.320

    6 2.326 46 2.339 86 2.357 126 2.320 166 2.229

    7 2.349 47 2.373 87 2.345 127 2.352 167 2.350

    8 2.373 48 2.352 88 2.365 128 2.345 168 2.342

    9 2.353 49 2.358 89 2.359 129 2.362 169 2.37010 2.310 50 2.247 90 2.321 130 2.345 170 2.364

    11 2.320 51 2.366 91 2.342 131 2.373 171 2.335

    12 2.334 52 2.355 92 2.358 132 2.320 172 2.365

    13 2.273 53 2.227 93 2.317 133 2.220 173 2.330

    14 2.326 54 2.359 94 2.327 134 2.271 174 2.237

    15 2.296 55 2.355 95 2.353 135 2.326 175 2.326

    16 2.366 56 2.373 96 2.339 136 2.365 176 2.320

    17 2.247 57 2.353 97 2.352 137 2.339 177 2.320

    18 2.352 58 2.247 98 2.356 138 2.353 178 2.288

    19 2.303 59 2.355 99 2.358 139 2.365 179 2.36020 2.368 60 2.358 100 2.320 140 2.339 180 2.366

    21 2.342 61 2.370 101 2.355 141 2.303 181 2.326

    22 2.334 62 2.339 102 2.358 142 2.359 182 2.368

    23 2.353 63 2.247 103 2.359 143 2.339 183 2.339

    24 2.363 64 2.324 104 2.330 144 2.339 184 2.321

    25 2.339 65 2.365 105 2.353 145 2.351 185 2.320

    26 2.227 66 2.280 106 2.359 146 2.317 186 2.320

    27 2.360 67 2.326 107 2.345 147 2.369 187 2.222

    28 2.322 68 2.358 108 2.369 148 2.345 188 2.359

    29 2.366 69 2.320 109 2.366 149 2.352 189 2.334

    30 2.339 70 2.362 110 2.365 150 2.324 190 2.324

    31 2.218 71 2.297 111 2.363 151 2.360 191 2.262

    32 2.371 72 2.366 112 2.222 152 2.320 192 2.357

    33 2.341 73 2.345 113 2.358 153 2.224 193 2.236

    34 2.370 74 2.320 114 2.353 154 2.349 194 2.371

    35 2.353 75 2.320 115 2.369 155 2.330 195 2.311

    36 2.339 76 2.349 116 2.354 156 2.358 196 2.339

    37 2.236 77 2.247 117 2.244 157 2.320 197 2.334

    38 2.347 78 2.353 118 2.341 158 2.320 198 2.373

    39 2.368 79 2.360 119 2.247 159 2.352 199 2.366

    40 2.339 80 2.365 120 2.362 160 2.362 200 2.320

  • 8/12/2019 Chapter04_Switching Overvoltage Analysis.pdf

    20/38

    76

    From table: 4.9, the 200 operations switching line energization circuit 1 without

    arresters at both sides of 500 kV transmission lines Nam Theun 2 to Roi Et 2

    substation, for energization overvoltage closing time is 13.85 ms. The maximum

    overvoltage at receiving end is reach 2.373 p.u. The minimum overvoltage at

    receiving end is 2.218 p.u. The mean of overvoltage at receiving end is 2.331 p.u and

    the standard deviation is 17.45 %. The voltage waveform is illustrated in Figure 4.9.

    Figure 4.9 SOV during line energizing circuit 1 without protection devices at both

    sides.

    Switching overvoltages during line energization in circuit 1 with different load

    condition such as: no load or light load, half load and full load are considered. The

    study was set line circuit breakers at sending end circuit 1 operated and breakers at

    receiving end connected with load conditions as illustrated in Figure 4.1. The 200

    switching operated in circuit 1 with turning on and off protection devices at both

    sides. The switching overvoltages during line energization with different loads

    conditions, no load or light load system made the maximum transient overvoltages, is

    illustrated in table 4.10 and voltage waveform is illustrated in Figure 4.10 Fiure

    4.12.

  • 8/12/2019 Chapter04_Switching Overvoltage Analysis.pdf

    21/38

    77

    Table: 4.10 The 200 statistical calculations for energization overvoltage from

    NTN 2 RE 2 circuit 1 during energizing with differrent loads

    conditions and turning on/off protection devices terminal.

    Max. Overvoltage ( p.u )

    No.

    Shunt

    Reactor

    NTN 2

    Shunt

    Reactor

    RE 2

    Arrester

    NTN 2

    Arrester

    RE 2No load

    Half

    load

    Full

    load

    1 yes yes yes yes 1.706 1.397 1.146

    2 no yes yes yes 1.723 1.423 1.186

    3 yes no yes yes 1.731 1.436 1.191

    4 yes yes no yes 1.716 1.401 1.160

    5 yes yes yes no 2.023 1.408 1.1796 no no yes yes 1.750 1.491 1.235

    7 yes yes no no 2.188 1.419 1.196

    8 no no no no 2.373 1.645 1.301

    Figure 4.10 SOV during line energization with no load condition.

    Figure 4.11 SOV during line energization with half load condition.

  • 8/12/2019 Chapter04_Switching Overvoltage Analysis.pdf

    22/38

  • 8/12/2019 Chapter04_Switching Overvoltage Analysis.pdf

    23/38

    79

    Figure 4.13 Single line diagram of 500 kV transmission line NTN 2 RE 2 substation

    circuit 2 energizing.

    Table: 4.11 The 200 statistical calculations for energization overvoltage from

    NTN 2 RE 2 circuit 2 turning on/off protection devices terminal.

    No.Shunt Reactor

    NTN 2

    Shunt Reactor

    RE 2

    Arrester

    NTN 2

    Arrester

    RE 2

    Overvoltage

    receiving

    end ( p.u )

    1 yes yes yes yes 1.707

    2 no yes yes yes 1.724

    3 yes no yes yes 1.7334 yes yes no yes 1.719

    5 yes yes yes no 2.024

    6 no no yes yes 1.750

    7 yes yes no no 2.189

    8 no no no no 2.376

    4.2.5 Line Energizing from NTN 2- RE2 Circuit 1 during Circuit 2

    Energization with Load

    In this case, circuit 2 is closed and connected with load while circuit 1 isopen at the receiving end and energized from Nam Theun 2 as illustrated in Figure

    4.14. Base on the statistical analysis, the program is run 200 times per case to find out

    the maximum overvoltage. Table 4.12 shows the various cases (shunt reactor and

    arrester of both sides are closed or opened) for running the program and the maximum

    overvoltages.

  • 8/12/2019 Chapter04_Switching Overvoltage Analysis.pdf

    24/38

    80

    Figure 4.14 Single line diagram of 500 kV transmission line NTN 2 - RE 2 substation

    circuit 1 energizing during circuit 2 energizing with load.

    Table: 4.12 The 200 statistical calculations for energization overvoltage from

    NTN 2 RE 2 circuit 1 during circuit 2 energizing with light load

    turning on/off protection devices terminal.

    No.Shunt Reactor

    NTN 2

    Shunt Reactor

    RE 2

    Arrester

    NTN 2

    Arrester

    RE 2

    Overvoltage

    receiving

    end ( p.u )

    1 yes yes yes yes 1.6972 no yes yes yes 1.708

    3 yes no yes yes 1.717

    4 yes yes no yes 1.706

    5 yes yes yes no 1.947

    6 no no yes yes 1.730

    7 yes yes no no 1.988

    8 no no no no 2.175

    4.3 Line Re-energization Analysis

    4.3.1 Case of the Study

    The 500 kV transmission line between Nam Theun 2 and Roi Et 2 has

    double circuits. The study of line re-energization during single line to ground fault

    and three phases to ground fault, the step of fault is divided into six, the distance each

    step approximately 50 km from sending end as following:

    - Line re-energization during single line to ground fault and three phases to

    ground fault in circuit 1, energizing from Nam Theun 2 sending end to Roi

    Et 2 receiving end.

  • 8/12/2019 Chapter04_Switching Overvoltage Analysis.pdf

    25/38

    81

    - Line re-energization during single line to ground fault and three phases to

    ground fault in circuit 1 at energizing with different load conditions.

    - Line re-energization during single line to ground fault and three phases to

    ground fault in circuit 1 at circuit 2 energizing with different load conditions.

    - Line re-energization during single line to ground fault and three phases to

    ground fault in circuit 2 at energizing with different load conditions.

    4.3.2 Methodology

    The cases of line re-energization during single line to ground fault and

    three phases to ground fault with different load (no load, half load and full load) are

    considered. The distance between Nam Theun 2 to Roi Et 2 is divided into 6 parts (50

    km per part) to find out the maximum overvoltage occurred in the transmission line.

    4.3.3 Line Re-energizing during Single Line to Ground Fault Circuit 1

    The case of single line to ground fault with re-energization operation is

    examined, the studied according to the variation of fault position from sending

    end to receiving end in step different location fault approximately 50 km as

    illustrated in Figure 4.15. The simultaneous fault clearing case of single line to

    ground fault in circuit 1 and changing phase fault from A, B and C, is selected in

    determine the maximum overvoltage. During single line to ground fault is applied

    at time t = 1 ms. Cleared time at t = 5 ms and re-energized at time t = 10 ms at

    different load condition.

    Figure 4.15 Single line diagram NTN 2- RE 2 line re-energizing during fault.

  • 8/12/2019 Chapter04_Switching Overvoltage Analysis.pdf

    26/38

    82

    The maximum overvoltage from line reclosing during single line to ground fault

    during phase A to ground clearing fault is 1.748 p.u as illustrated Figure 4.16, phase B

    to ground clearing fault is 1.749 p.u as illustrated in Figure 4.17, Phase C to ground

    clearing fault is 1.750 p.u as illustrate in Figure 4.18 in the no load condition. The

    highest maximum overvoltage during single line to ground fault is set switched on/off

    protection devices. The maximum overvoltage without arrester at both sides is 2.782

    p.u, higher than without shunt reactor as illustrated in Figure 4.19 and Figure 4.20.

    Overvoltage without any protection devices during single line to ground fault is reach

    3.265 p.u as illustrated in Figure 4.21.

    Figure 4.16 Re-energization overvoltage during phase A to ground fault.

    Figure 4.17 Reclosing overvoltage during phase B to ground fault.

  • 8/12/2019 Chapter04_Switching Overvoltage Analysis.pdf

    27/38

    83

    Figure 4.18 Reclosing overvoltage during Phase C to ground fault.

    Figure 4.19 Reclosing overvoltages during phase C to ground fault without shunt

    reactors at both sides.

    Figure 4.20 Reclosing overvoltage during phase C to ground without arresters at both

    sides.

  • 8/12/2019 Chapter04_Switching Overvoltage Analysis.pdf

    28/38

    84

    Figure 4.21 Reclosing overvoltage during Phase C to ground fault without any

    protection devices.

    Figure 4.22 to Figure 4. 24 presents that in case of single line during Phase A, B

    and C, The approximately 50 km of faults in circuit 1. The magnitude voltage level is

    similar in each phase and step of fault. The maximum overvoltage in phase C is 1.750

    p.u. at no load condition, distance of fault is set 100 km from sending end NTN 2

    Power Plant.

    Reclosing during Ph. A to ground fault

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    1.2

    1.4

    1.6

    1.8

    2.0

    50 km 100 km 150 km 200 km 250 km 300 km

    Fault location from sending end [km]

    Maximumo

    vervoltage[p.u

    ]

    No load

    Half load

    Full load

    Figure 4.22 Reclosing during phase A to ground of location fault.

  • 8/12/2019 Chapter04_Switching Overvoltage Analysis.pdf

    29/38

    85

    Reclosing during Ph. B to ground fault

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    1.2

    1.4

    1.6

    1.8

    2.0

    50 km 100 km 150 km 200 km 250 km 300 km

    Fault location from sending end [km]

    Maximumovervoltage[p.u

    ]

    No load

    Half load

    Full load

    Figure 4.23 Reclosing during phase B to ground of location fault.

    Reclosing during Ph. C to ground fault

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    1.2

    1.4

    1.6

    1.8

    2.0

    50 km 100 km 150 km 200 km 250 km 300 km

    Fault location from sending end [km]

    Maximum

    overvoltage[p.u

    ]

    No load

    Half load

    Full load

    Figure 4.24 Reclosing during phase C to ground of location fault.

  • 8/12/2019 Chapter04_Switching Overvoltage Analysis.pdf

    30/38

    86

    4.3.4 Line Re-energizing during Three Phases to Ground Fault Circuit 1

    Switching overvoltages during three phases to ground faults are re-

    energization at different load condition. It is finding that the highest overvoltage when

    energizing from Nam Theun 2 Power Plant Roi Et 2 substation in circuit 1. The

    three phases to ground fault is studied according to the variation of fault position from

    sending end to receiving end in step approximately 50 km as illustrated in Figure

    4.15. The simultaneous fault clearing case of three phases to ground fault is applied at

    time 1 ms. Cleared time 5 ms and re-energized 1 ms at the different load condition.

    The maximum overvoltage re-energized after three phases to ground fault at receiving

    end is 1.784 p.u as illustrated in Figure 4.25, three phases to ground fault with

    protection devices put in service. Reclosing overvoltage is 3.379 p.u during three

    phases to ground without arresters at the both sides. The maximum overvoltage is

    4.069 p.u without any protection. After arresters put in services, the voltage is reduces

    to 1.786 p.u. The voltage waveform is illustrated in Figure 26 to Figure 28. The

    simulation results from re-energized during three phases to ground fault, with

    different load condition as illustrated in Figure 4.29.

    Figure 4.25 Reclosing overvoltage during three phases to ground fault with protection

    devices.

  • 8/12/2019 Chapter04_Switching Overvoltage Analysis.pdf

    31/38

    87

    Figure 4.26 Reclosing overvoltages during three phases to ground fault without shunt

    reactors at both sides.

    Figure 4.27 Reclosing during three phases to ground fault without arresters at both

    sides.

    Figure 4.28 Reclosing during three phases to ground fault without protection devices.

  • 8/12/2019 Chapter04_Switching Overvoltage Analysis.pdf

    32/38

    88

    Reclosing during three phases to groud fault

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    1.2

    1.4

    1.6

    1.8

    2.0

    50 km 100 km 150 km 200 km 250 km 300 km

    Fault location from sending end [km]

    Maxim

    umovervoltage[p.u

    ]

    No load

    Half load

    Full load

    Figure 4.29 Reclosing overvoltages during three phases to ground of location fault.

    The summarized simulation from cases line re-energization during single to

    ground fault and three phases to ground fault in circuit 1, circuit 2 and fault in circuit

    1 due to circuit 2 energizing with load condition as shown in table 4.13 to table 4.15.

    It is realized that, in case of having double circuits of 500 kV transmission line

    between Nam Theun 2 and Roi Et 2 substation. Reclosing overvoltages during single

    line to ground fault and three phases to ground fault level is similar at circuit 1 and

    circuit 2. Reclosing overvoltage during three phases to ground fault is always higher

    than single line to ground fault. In case of no load condition, the maximum

    overvoltage is higher than those of half load and full load.The highest overvoltage

    during three phases to ground fault is 1.784 p.u in circuit 1 and single line to ground

    fault is 1.750 p.u in circuit 1 at no load condition.

  • 8/12/2019 Chapter04_Switching Overvoltage Analysis.pdf

    33/38

    89

    Table: 4.13 Maximum overvoltages during single phase to ground fault and

    three phases to ground fault circuit 1 energizing with different load

    condition.

    Load condition Fault type

    Fault location

    from sending

    end (NTN2)

    Max. SOV at

    receiving end

    RE 2[ p.u ]

    Max. SOV at

    sending end

    NTN 2 [ p.u ]

    50 km 1.748 1.566

    100 km 1.750 1.551

    150 km 1.749 1.540

    200 km 1.747 1.547

    250 km 1.748 1.488

    Single

    phase

    300 km 1.747 1.50350 km 1.777 1.642

    100 km 1.784 1.656

    150 km 1.781 1.649

    200 km 1.779 1.657

    250 km 1.764 1.572

    No load

    Three phase

    300 km 1.755 1.569

    50 km 1.318 1.160

    100 km 1.316 1.154

    150 km 1.314 1.145

    200 km 1.316 1.137

    250 km 1.312 1.138

    Single

    phase

    300 km 1.315 1.150

    50 km 1.414 1.156

    100 km 1.313 1.175

    150 km 1.307 1.314

    200 km 1.311 1.422

    250 km 1.309 1.429

    Half load

    Three phase

    300 km 1.285 1.376

    50 km 1.017 1.024100 km 1.018 1.026

    150 km 1.017 1.034

    200 km 1.019 1.038

    250 km 1.018 1.034

    Single

    phase

    300 km 1.019 1.031

    50 km 1.026 1.045

    100 km 1.027 1.098

    150 km 1.026 1.217

    200 km 1.027 1.302

    250 km 1.025 1.290

    Full load

    Three phase

    300 km 1.028 1.264

  • 8/12/2019 Chapter04_Switching Overvoltage Analysis.pdf

    34/38

    90

    Table: 4.14 Maximum overvoltages during single phase to ground fault and

    three phases to ground fault circuit 1, circuit 2 energizing.

    Load

    conditionFault type

    Fault location

    from sending

    end (NTN2)

    Max. SOV at

    receiving end

    RE 2[ p.u ]

    Max. SOV at

    sending end

    NTN 2 [ p.u ]

    50 km 1.650 1.426

    100 km 1.662 1.346

    150 km 1.549 1.346

    200 km 1.561 1.416

    250 km 1.598 1.460

    Single phase

    300 km 1.682 1.568

    50 km 1.686 1.514100 km 1.688 1.519

    150 km 1.686 1.509

    200 km 1.680 1.497

    250 km 1.683 1.498

    Light load

    Three phase

    300 km 1.682 1.496

    50 km 1.603 1.269

    100 km 1.600 1.268

    150 km 1.652 1.258

    200 km 1.560 1.260

    250 km 1.595 1.260

    Single phase

    300 km 1.556 1.246

    50 km 1.602 1.270

    100 km 1.605 1.271

    150 km 1.551 1.259

    200 km 1.549 1.259

    250 km 1.534 1.255

    Half load

    Three phase

    300 km 1.549 1.251

    50 km 1.414 1.178

    100 km 1.345 1.177

    150 km 1.446 1.195

    200 km 1.444 1.196

    250 km 1.339 1.173

    Single phase

    300 km 1.325 1.172

    50 km 1.491 1.212

    100 km 1.482 1.210

    150 km 1.455 1.204

    200 km 1.452 1.204

    250 km 1.447 1.202

    Full load

    Three phase

    300 km 1.440 1.199

  • 8/12/2019 Chapter04_Switching Overvoltage Analysis.pdf

    35/38

    91

    Table: 4.15 Maximum overvoltages during single phase to ground fault and

    three phases to ground fault circuit 2 energizing.

    Load

    conditionFault type

    Fault location

    from sending

    end (NTN2)

    Max. SOV at

    receiving end

    RE 2[ p.u ]

    Max. SOV at

    sending end

    NTN 2 [ p.u ]

    50 km 1.750 1.554

    100 km 1.748 1.545

    150 km 1.747 1.560

    200 km 1.749 1.555

    250 km 1.748 1.550

    Single phase

    300 km 1.747 1.547

    50 km 1.776 1.640100 km 1.782 1.655

    150 km 1.780 1.645

    200 km 1.779 1.656

    250 km 1.758 1.571

    No load

    Three phase

    300 km 1.756 1.570

    50 km 1.312 1.150

    100 km 1.317 1.156

    150 km 1.312 1.153

    200 km 1.317 1.156

    250 km 1.312 1.148

    Single phase

    300 km 1.414 1.150

    50 km 1.313 1.152

    100 km 1.312 1.178

    150 km 1.309 1.314

    200 km 1.310 1.421

    250 km 1.308 1.429

    Half load

    Three phase

    300 km 1.287 1.375

    50 km 1.041 1.040

    100 km 1.016 1.026

    150 km 1.017 1.043

    200 km 1.015 1.024

    250 km 1.017 1.029

    Single phase

    300 km 1.016 1.036

    50 km 1.026 1.053

    100 km 1.023 1.098

    150 km 1.026 1.216

    200 km 1.025 1.301

    250 km 1.027 1.290

    Full load

    Three phase

    300 km 1.029 1.267

  • 8/12/2019 Chapter04_Switching Overvoltage Analysis.pdf

    36/38

    92

    4.4 Conclusion of Switching Overvoltages Analysis

    Switching overvoltages during line energization and re-energization duringsingle line to ground fault and three phases to ground faults on the 500 kV

    transmission line between Nam Theun 2 substation and Roi Et 2 substation were

    analyzed for the cases by PSCAD/EMTDC program, the conclusion can be draw as

    following:

    1). Line energization overvoltage

    The maximum overvoltage during line energization circuit 1, the 200

    operations statistical switching is 1.706 p.u at receiving end. The maximum

    overvoltage during line energization circuit 2 is 1.707 p. The maximum overvoltage

    during line enerzation circuit 1 with circuit 2 energizing during light load or no load is

    1.697 p.u. Line energization are considered from Nam Theun 2 to Roi Et 2 substation

    with protection devices. When the transmission line without any protection at both

    sides, the maximum overvoltage are too high, the overvoltage is reach to 2.376 p.u in

    circuit 2 at no load condition.

    2). Line energization overvoltage due to different load condition

    The maximum overvoltage during line energization circuit 1 is quite low,

    when the load condition is considered. The 200 operations statistical switching is

    tested; three conditions of loading are studied: no load, half load and full load. The

    maximum overvoltage during no load is 1.706 p.u. The maximum overvoltage line

    energization during half load is 1.397 p.u. Which is energized during full load

    conditions is 1.146 p.u. The results shown the behavior of the system under switching

    conditions and the switching overvoltage investigations are usually made with no load

    represented on the system. The switching operations on unloaded system will produce

    the most severe transient overvoltages.

    3). Line energization in circuit 1 and circuit 2 energizing with load during turn

    on/off protection devices

    Line energization during turn on/off protection devices circuit 1 and circuit

    2 energized with load conditions. The 200 operations statistical switching is tested

    with load. The maximum overvoltage during line energization without any protection

    at both sides is 2.175 p.u. When the transmission line put in protection devices in

  • 8/12/2019 Chapter04_Switching Overvoltage Analysis.pdf

    37/38

    93

    services, the overvoltage could be also reduced to 1.697 p.u at no load condition. The

    overvoltage is lower than line energization in circuit 1 and circuit 2.

    4). Line re-energization overvoltage during single line to ground faults

    The maximum overvoltage due to line re-energization overvoltage during

    single line to ground fault is set in the step of fault approximately 50 km from sending

    end. The maximum overvoltage is 1.748 p.u during phase A to ground fault. The

    overvoltage in phase B to ground fault is 1.749 p.u and phase C to ground fault the

    maximum overvotlae is reach to 1.750 p.u energizes with protection devices. When

    energized without arresters the maximum overvoltage during phase C to ground fault

    is 2.782 p.u and without any protection devices in services the voltage is reach 3.265

    p.u.

    5). Line re-energization overvoltage during three phase to ground faults

    The maximum overvoltage line re-energization overvoltage during three

    phases to ground fault was set in the step of faults approximately 50 km from sending

    end. The maximum overvoltage is 1.784 p.u at location fault from sending 100 km

    ( Nam Theun 2 Power Plant ). The maximum overvoltage during three phases to

    ground fault without arresters at the both sides is 3.379 p.u and without any protection

    devices the overvoltage is reach 4.069 p.u at the receiving end Roi Et 2.

    Extensive electromagnetic transient study has been performed for a guide line

    for operation and expansion the 500 kV transmission line in Lao PDR. In light of

    these study results following main conclusions could be drawn:

    - The simulation results line energization with 200 operations statistical

    switching from table: 4.9 table: 4.11 in each case, can be concluded that the

    maximum overvoltage occurred the transmission lines is 1.196 p.u energized with fullload condition and 2.188 p.u energized without arresters at both sides, no load

    condition. When the line put in protection devices in service, the maximum

    overvoltage is 1.706 p.u at no load condition and 1.146 p.u at full load condition. It is

    found that switching overvoltage on the no load system make produce the most severe

    transient overvoltage.

    - The simulation results line re-energization during single phase to ground fault

    and three phases to ground fault. Three conditions of loading were considered such as:

    No load, half load and full load and step of fault approximately 50 km form sending

  • 8/12/2019 Chapter04_Switching Overvoltage Analysis.pdf

    38/38