chapter 8 evaluating and terminating the project
TRANSCRIPT
Friday, April 21, 2023 BA 424 Project Management in Practice
Project Management in Practice
Evaluating and Terminating the Project
Friday, April 21, 2023 BA 424 Project Management in Practice
Project Management in Practice
Evaluating and Terminating the Project
Evaluation Project Auditing Project Termination
Friday, April 21, 2023 BA 424 Project Management in Practice
Project Evaluation
Appraises the progress and performance of the project relative to (a) the goals and objectives set for it during
the selection process and (b) the initial or revised plan
Projects should be evaluated at key points in the project life cycle
Purpose is to improve process of carrying out future projects via execution feedback
8-3
Friday, April 21, 2023 BA 424 Project Management in Practice
Evaluation Criteria Original criteria for selecting and funding project Success to-date Customer impact/satisfaction Business/direct success
• such as the level of commercial success for external projects and reduced throughput time for internal projects
Future potential Contribution to organization’s goals Contribution to team member objectives
8-4
Friday, April 21, 2023 BA 424 Project Management in Practice
Measurement of a Project’s Performance
Measuring performance against planned budgets and schedules • relatively straightforward
Measurement of actual expenditure and earned values • more complicated
8-5
Friday, April 21, 2023 BA 424 Project Management in Practice
The Audit Process
Formal audit very special type of evaluation The project audit is not a financial audit The timing of the audit depends on the purpose An audit can be conducted at three levels:
• General – limited by time and cost
• Detailed – often initiated if the general audit uncovers something
• Technical- performed by a person with special technical skills
Generally the earlier the audit is conducted in the project life cycle the better it is
8-6
Friday, April 21, 2023 BA 424 Project Management in Practice
Steps in Completing a Project Audit
Familiarize audit team with the requirements of the project
Conduct audit on site Write up audit report Distribute report
8-7
Friday, April 21, 2023 BA 424 Project Management in Practice
Keys to Ensuring an Effective Audit
Audit team must • have free access to anyone with knowledge of the
project• make sure the project team is aware of the audit• avoid judgmental comments• understand the politics of project team• confirm all information ( wherever possible) • understand that project team members rarely trust
auditors
8-8
Friday, April 21, 2023 BA 424 Project Management in Practice
The Audit Report
Introduction• description of project and its goals
Current status• comparison of work completed and planned
Future project status• conclusions regarding project progress• recommendations for changes for subsequent
projects
8-9
Friday, April 21, 2023 BA 424 Project Management in Practice
The Audit Report, continued
Critical management issues• issues senior management should monitor
Risk analysis and risk management• potential for project failure and monetary loss
Final comments• caveats, assumptions, limitations
8-10
Friday, April 21, 2023 BA 424 Project Management in Practice
Determining Whether or Not to Terminate a Project
Sunk cost - the extent to which the organization is willing to invest the additional time and cost required to complete the project given the investment already committed
The degree to which the project qualifies against a set of factors (technical, economic, market share and other) that show either success or failure
8-11
Friday, April 21, 2023 BA 424 Project Management in Practice
Determining Whether or Not to Terminate a Project, continued
Which projects have a legal or strategic imperative?
Which projects are luxuries? Which projects are likely to drive future revenue
and growth? Which projects best match our skill sets and
strengths? What are the risks to the business if we do not
service the project’s deliverables?
8-11
8-12
Friday, April 21, 2023 BA 424 Project Management in Practice
Types of Project Termination Project Extinction
• project activity suddenly stops because it has been successfully completed or has a high expectation of failure
Termination-by-addition
• when an in-house project is successfully executed and is institutionalized as a new formal part of the organization
Termination-by-integration
• the output of the project becomes a standard part of the operating system of the sponsoring firm or the client
Termination-by-starvation
• occurs when it is impolitic to terminate a project but it’s budget can be squeezed until it is a project in name only
One special type of termination is termination by “murder”
8-13
Friday, April 21, 2023 BA 424 Project Management in Practice
The Termination Process
Decision should be made by a broad based committee of senior managers
Termination process should be specified in project plan
A termination manager should be appointed
8-14
Friday, April 21, 2023 BA 424 Project Management in Practice
A WBS for a Termination Project 8-15
Friday, April 21, 2023 BA 424 Project Management in Practice
The Project Final Report Project performance
• what was achieved and reasons for resulting performance
Administrative performance• review of how well administrative practices
worked Organizational structure
• identify modifications to help future projects Project management techniques
• recommendations for improvements in future projects
8-16
Friday, April 21, 2023 BA 424 Project Management in Practice
Summary 8-17
Evaluation Project Auditing Project Termination