chapter - 3 traffic survey and analysis -...

15
Final Feasibility Report Page 3 - 1 Feasibility study for two-laning of Bhawi-Pipar-Khimsar (H-IV) STUP Consultants Pvt. Ltd. CHAPTER - 3 TRAFFIC SURVEY AND ANALYSIS 3.1 Homogenous Sections Based on the project road features settlements along the road, traffic volume etc. the project road has been divided only in one homogenous section as given in Table 3.1 below: Table 3.1: Homogenous Sections Homogenous Section Chainage (Km-Km) Length (km) HS-1 0.000 - 31.000 (Bhawi - Sathin) 31 HS-2 Km. 31-55(Sathin to Bhopalgarh) 24 HS-3 Km. 55-71(Bhopalgarh to Palri) 16 HS-4 Km. 75-97(Lawari Piou to Khimsar) 22 Based on the above mentioned homogenous section, traffic surveys were conducted at following location and as per schedule given below in Table 3.2: Table 3.2: Traffic Survey locations and Schedule Survey details Chainage Location Period of Survey Remarks (Duration) Classified Traffic 7 days SH-86C KM-1+500 12.12.14 – 18.12.14 7 days SH-86C -KM-55-500 10.12.14 – 16.12.14 7 days SH-86C Mangeria (Km.87) 09.12.14 – 15.12.14 7 days SH-86C Ghana Magra (Km.6) 16.12.14 – 22.12.14 7 days Turning Movement Bhopalgarh Chowk 09.12.14 1 day Lawari Chowk 04.12.14 1 day SH-86C KM-1.300 15.12.14 1 day Palri 04.12.14 1 day Axle load survey SH-86C KM-55+500 11.12.14 1 day SH-86C KM-02 12.12.14 1 day These locations are shown in fig 3.1. 3.2 Classified Traffic Volume Count The classified traffic volume counts were carried out at 3locations along the project road for 7 days. The vehicle classification was done as per IRC: SP 19-1991 and IRC: 9-1972

Upload: vuongtuyen

Post on 19-Aug-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

Final Feasibility Report Page 3 - 1

Feasibility study for two-laning of Bhawi-Pipar-Khimsar (H-IV) STUP Consultants Pvt. Ltd.

CHAPTER - 3

TRAFFIC SURVEY AND ANALYSIS

3.1 Homogenous Sections

Based on the project road features settlements along the road, traffic volume etc. the

project road has been divided only in one homogenous section as given in Table 3.1 below:

Table 3.1: Homogenous Sections

Homogenous Section Chainage

(Km-Km) Length (km)

HS-1 0.000 - 31.000 (Bhawi - Sathin) 31

HS-2 Km. 31-55(Sathin to Bhopalgarh) 24

HS-3 Km. 55-71(Bhopalgarh to Palri) 16

HS-4 Km. 75-97(Lawari Piou to Khimsar) 22

Based on the above mentioned homogenous section, traffic surveys were conducted at

following location and as per schedule given below in Table 3.2:

Table 3.2: Traffic Survey locations and Schedule

Survey details Chainage Location Period of Survey Remarks

(Duration)

Classified Traffic

7 days

SH-86C KM-1+500 12.12.14 – 18.12.14 7 days

SH-86C -KM-55-500 10.12.14 – 16.12.14 7 days

SH-86C Mangeria (Km.87) 09.12.14 – 15.12.14 7 days

SH-86C Ghana Magra (Km.6) 16.12.14 – 22.12.14 7 days

Turning

Movement

Bhopalgarh Chowk 09.12.14 1 day

Lawari Chowk 04.12.14 1 day

SH-86C KM-1.300 15.12.14 1 day

Palri 04.12.14 1 day

Axle load survey SH-86C KM-55+500 11.12.14 1 day

SH-86C KM-02 12.12.14 1 day

These locations are shown in fig 3.1.

3.2 Classified Traffic Volume Count

The classified traffic volume counts were carried out at 3locations along the project road for

7 days. The vehicle classification was done as per IRC: SP 19-1991 and IRC: 9-1972

Final Feasibility Report Page 3 - 2

Feasibility study for two-laning of Bhawi-Pipar-Khimsar (H-IV) STUP Consultants Pvt. Ltd.

guidelines and vehicle category added / revised as per toll policy. The seven day count will

give average Daily Traffic (ADT). The value is then converted to passenger car units (PCUs)

for capacity Analysis. The vehicle type and PCU factors adopted are presented in Table

3.3below:

Table 3.3: Classification of vehicle for Traffic Surveys

Motorized Vehicles

Vehicle Type PCU Factor

Car / Jeep / Taxi 1.00

2-Wheeler 0.50

3-Wheeler 1.00

Bus 3.00

Mini Bus 1.50

LCV 1.50

2-Axle Truck 3.00

3-Axle Truck 3.00

MAV (4-6 Axle 4.50

MAV > 6 Axle 4.50

EME / HCM 4.50

Tractor Without Trailer 1.50

Tractor with Trailer 4.50

Non Motorised Vehicle

Cycle 0.50

Cycle Riskshaw 2.00

Animal drawn 4.00

The traffic count data would be used to interpret the existing trends regarding traffic flow at

mid blocks to determine average daily traffic, peak hour traffic, traffic composition and

variation of hourly traffic / day wise.

Final Feasibility Report Page 3 - 3

Feasibility study for two-laning of Bhawi-Pipar-Khimsar (H-IV) STUP Consultants Pvt. Ltd.

3.3 Mid Block Volume Analysis

The magnitude of traffic at each mid block (7 days) is represented in Table 3.4:

Table 3.4– ADT

Average Daily Traffic (ADT)

Vehicle Type PCU

Factor

SH-86C KM-1+500

SH-86C KM-55+500

SH-86C Mangeria

(Km. 87.000)

SH-86C Ghana Magra

(Km. 6.000)

ADT PCU ADT PCU ADT PCU ADT PCU

Tolled

Car / Jeep / Taxi / Van / utility

1.0 536 536 343 306 45 45 36 36

Mini Buses 1.5 4 6 1 1 0 0 0 0

Standard Buses 3.0 84 252 33 80 13 39 11 32

Mini LCV 1.5 164 246 158 211 31 47 28 41

LCV 1.5 24 36 54 66 1 2 1 2

Trucks - 2 Axle 3.0 205 615 221 544 12 36 10 31

Trucks - 3 Axle 3.0 219 657 67 164 4 12 3 10

MAV (4-6 Axle) 4.5 153 689 23 86 0 0 0 0

MAV (6+ Axle) 4.5 0 0 0 2 0 0 0 0

HCM / EME 4.5 5 23 5 19 0 0 0 0

Tractor 1.5 11 17 13 17 2 3 2 2

Tractor with Trailer

4.5 133 599 66 244 28 126 22 97

Total 1538 3674 984 1739 136 309 112 251

Exempted

2-Wheeler 0.5 1776 888 1762 787 224 112 118 59

3-Wheeler 1.0 31 31 2 2 1 1 1 1

Cycle 0.5 48 24 13 6 15 8 11 6

Cycle Rickshaw 2.0 0 0 0 0 1 2 1 1

Animal Cart 6.0 0 0 0 1 1 6 1 3

Total 1855 943 1777 797 242 129 131 70

Final Feasibility Report Page 3 - 4

Feasibility study for two-laning of Bhawi-Pipar-Khimsar (H-IV) STUP Consultants Pvt. Ltd.

Exempted

Car / Jeep / Van 1.0 7 7 3 3 1 1 1 1

Ambulance / Fire Tenders / Funeral

Vans 1.0 0 0 0 0 0 0 0 0

Bus 3.0 1 3 1 2 0 0 0 0

LCV 1.5 0 0 0 0 0 0 0 0

Truck 3.0 0 0 0 0 0 0 0 0

Total 8 10 4 5 1 1 1 2

Grand Total (Tolled+Exempted)

3401 4627 2765 2541 379 439 245 323

The traffic variations at all locations are given in fig. 3.2:

Fig.: 3.2

Car /Taxi

MiniBuses

Standard

Buses

MiniLCV

LCVTrucks

- 2Axle

Trucks- 3

Axle

MAV(4-6Axle)

MAV(6+

Axle)

HCM /EME

Tractor

Tractor withTrailer

MDR-75 KM-1+500 536 4 84 164 24 205 219 153 0 5 11 133

MDR-90 KM-55+500 343 1 33 158 54 221 67 23 0 5 13 66

MDR - 90 Mangeria 45 0 13 31 1 12 4 0 0 0 2 28

MDR-90 Ghana Magra 36 0 11 28 1 10 3 0 0 0 2 22

0

100

200

300

400

500

600

Traf

fic

No

s.

Traffic Variation at All Locations

Final Feasibility Report Page 3 - 5

Feasibility study for two-laning of Bhawi-Pipar-Khimsar (H-IV) STUP Consultants Pvt. Ltd.

Tollable traffic compositions at all locations are given in fig 3.3 to 3.5:

Fig.: 3.3

Fig.: 3.4

Car /Taxi34.85%

Mini Buses0.26%

Standard Buses5.46%

Mini LCV10.66%

LCV1.56%

Trucks - 2 Axle13.33%

Trucks - 3 Axle14.24%

MAV (4-6 Axle)9.95%

MAV (6+ Axle)0.00%

HCM / EME0.33%

Tractor0.72%

Tractor with Trailer8.65%

Tollable Traffic Composition at SH-86C KM-1+500

Car /Taxi34.86%

Mini Buses0.10%

Standard Buses3.35%

Mini LCV16.06%

LCV5.49%

Trucks - 2 Axle22.46%

Trucks - 3 Axle6.81%

MAV (4-6 Axle)2.34%

MAV (6+ Axle)0.00%

HCM / EME0.51%

Tractor1.32%

Tractor with Trailer6.71%

Tollable Traffic Composition at SH-86C KM-55+500

Final Feasibility Report Page 3 - 6

Feasibility study for two-laning of Bhawi-Pipar-Khimsar (H-IV) STUP Consultants Pvt. Ltd.

Fig.: 3.5

Average Day Hourly variation of traffic / daywise variation of Traffic / Average Day Traffic

Composition of all locations are shown in Fig. 3.6to3.14

Fig.: 3.6

Car /Taxi33.09%

Mini Buses0.00%

Standard Buses9.56%

Mini LCV22.79%

LCV0.74%

Trucks - 2 Axle8.82%

Trucks - 3 Axle2.94%

MAV (4-6 Axle)0.00%

MAV (6+ Axle)0.00%

HCM / EME0.00%

Tractor1.47%

Tractor with Trailer20.59%

Tollable Traffic Composition at SH-86C Mangeria (Km. 87.000)

0

50

100

150

200

250

300

350

8:0

0 t

o 9

:00

9:0

0 t

o 1

0:0

0

10

:00

to

11

:00

11

:00

to

12

:00

12

:00

to

13

:00

13

:00

to

14

:00

14

:00

to

15

:00

15

:00

to

16

:00

16

:00

to

17

:00

17

:00

to

18

:00

18

:00

to

19

:00

19

:00

to

20

:00

20

:00

to

21

:00

21

:00

to

22

:00

22

:00

to

23

:00

23

:00

to

24

:00

24

:00

to

1:0

0

1:0

0 t

o 2

:00

2:0

0 t

o 3

:00

3:0

0 t

o 4

:00

4:0

0 t

o 5

:00

5:0

0 t

o 6

:00

6:0

0 t

o 7

:00

7:0

0 t

o 8

:00

Average Day Hourly Variation of Traffic at SH-86C KM-1+500

Vehicle

PCU

Final Feasibility Report Page 3 - 7

Feasibility study for two-laning of Bhawi-Pipar-Khimsar (H-IV) STUP Consultants Pvt. Ltd.

Fig.: 3.7

Fig.: 3.8

0

50

100

150

200

250

8:0

0 t

o 9

:00

9:0

0 t

o 1

0:0

0

10

:00

to

11

:00

11

:00

to

12

:00

12

:00

to

13

:00

13

:00

to

14

:00

14

:00

to

15

:00

15

:00

to

16

:00

16

:00

to

17

:00

17

:00

to

18

:00

18

:00

to

19

:00

19

:00

to

20

:00

20

:00

to

21

:00

21

:00

to

22

:00

22

:00

to

23

:00

23

:00

to

24

:00

24

:00

to

1:0

0

1:0

0 t

o 2

:00

2:0

0 t

o 3

:00

3:0

0 t

o 4

:00

4:0

0 t

o 5

:00

5:0

0 t

o 6

:00

6:0

0 t

o 7

:00

7:0

0 t

o 8

:00

Average Day Hourly Variation of Traffic at SH-86C KM-55+500

Vehicle

PCU

0

5

10

15

20

25

30

35

40

45

8:0

0 t

o 9

:00

9:0

0 t

o 1

0:0

0

10

:00

to

11

:00

11

:00

to

12

:00

12

:00

to

13

:00

13

:00

to

14

:00

14

:00

to

15

:00

15

:00

to

16

:00

16

:00

to

17

:00

17

:00

to

18

:00

18

:00

to

19

:00

19

:00

to

20

:00

20

:00

to

21

:00

21

:00

to

22

:00

22

:00

to

23

:00

23

:00

to

24

:00

24

:00

to

1:0

0

1:0

0 t

o 2

:00

2:0

0 t

o 3

:00

3:0

0 t

o 4

:00

4:0

0 t

o 5

:00

5:0

0 t

o 6

:00

6:0

0 t

o 7

:00

7:0

0 t

o 8

:00

Average Day Hourly Variation of Traffic at SH-86C Mangeria (Km. 87.000)

Vehicle

PCU

Final Feasibility Report Page 3 - 8

Feasibility study for two-laning of Bhawi-Pipar-Khimsar (H-IV) STUP Consultants Pvt. Ltd.

Fig.: 3.9

Fig.: 3.10

0

1000

2000

3000

4000

5000

6000

Friday Saturday Sunday Monday Tuesday Wednesday Thursday

Day Wise Traffic Variation at SH-86C KM-1+500

Vehicle

PCU

0

500

1000

1500

2000

2500

3000

3500

4000

4500

Wednesday Thursday Friday Saturday Sunday Monday Tuesday

Day Wise Traffic Variation at SH-86C KM-55+500

Vehicle

PCU

Final Feasibility Report Page 3 - 9

Feasibility study for two-laning of Bhawi-Pipar-Khimsar (H-IV) STUP Consultants Pvt. Ltd.

Fig.: 3.11

Fig.: 3.12

0

100

200

300

400

500

600

Tuesday Wednesday Thursday Friday Saturday Sunday Monday

Day Wise Traffic Variation at SH-86C Mangeria (Km. 87.000)

Vehicle

PCU

Car /Taxi15.97%

Mini Buses0.12%

Buses2.50%

Mini LCV4.82%

LCV0.71%

Trucks - 2 Axle6.03%

Trucks - 3 Axle6.44%

MAV (4-6 Axle)4.50%MAV (6+ Axle)

0.00%HCM / EME

0.15%Tractor0.32%

Tractor with Trailer3.91%

2-Wheeler52.22%

3-Wheeler0.91%

Slow1.41%

Average Daily Traffic Composition at SH-86C KM-1+500 Car /Taxi

Mini Buses

Buses

Mini LCV

LCV

Trucks - 2 Axle

Trucks - 3 Axle

MAV (4-6 Axle)

MAV (6+ Axle)

HCM / EME

Tractor

Tractor withTrailer2-Wheeler

3-Wheeler

Slow

Final Feasibility Report Page 3 - 10

Feasibility study for two-laning of Bhawi-Pipar-Khimsar (H-IV) STUP Consultants Pvt. Ltd.

Fig.: 3.13

Fig.: 3.14

Car /Taxi12.51%

Mini Buses0.04%

Buses1.23%

Mini LCV5.71%

LCV1.95%

Trucks - 2 Axle7.99%

Trucks - 3 Axle2.42%

MAV (4-6 Axle)0.83%

MAV (6+ Axle)0.00%

HCM / EME0.18%

Tractor0.47%

Tractor with Trailer2.39%

2-Wheeler63.73%

3-Wheeler0.07%

Slow0.47%

Average Daily Traffic Composition at SH-86C KM-55+500Car /Taxi

Mini Buses

Buses

Mini LCV

LCV

Trucks - 2 Axle

Trucks - 3 Axle

MAV (4-6 Axle)

MAV (6+ Axle)

HCM / EME

Tractor

Tractor withTrailer2-Wheeler

3-Wheeler

Slow

Car /Taxi12.14%

Mini Buses0.00%

Buses3.43%

Mini LCV8.18%

LCV0.26%

Trucks - 2 Axle3.17%

Trucks - 3 Axle1.06%

MAV (4-6 Axle)0.00%

MAV (6+ Axle)0.00%

HCM / EME0.00%

Tractor0.53%

Tractor with Trailer7.39%

2-Wheeler59.10%

3-Wheeler0.26%

Slow4.49%

Average Daily Traffic Composition at SH-86C Mangeria (Km. 87.000)Car /Taxi

Mini Buses

Buses

Mini LCV

LCV

Trucks - 2 Axle

Trucks - 3 Axle

MAV (4-6 Axle)

MAV (6+ Axle)

HCM / EME

Tractor

Tractor withTrailer2-Wheeler

3-Wheeler

Slow

Final Feasibility Report Page 3 - 11

Feasibility study for two-laning of Bhawi-Pipar-Khimsar (H-IV) STUP Consultants Pvt. Ltd.

3.4 Average Annual Daily Traffic (AADT)

For the analysis, traffic data in terms of Average Annual Daily Traffic (AADT) is needed. This

is obtained by applying Seasonal Correction Factor (SCF) to ADT. The SCF has been

calculated based on Petrol / Diesel Sales Data as collected from the Petrol pumps along the

Project Road. This data and the working out of SCF is given in Table 3.5 calculation of SCF

based on Diesel / Petrol sales date:

Table 3.5A Calculation of SCF based on Diesel / Petrol Data

Month Year

IOCL Pump At Pipar City(Km.21.000)

Seasonal Correction Factor (SCF)

Diesel (in KL)

Petrol (in KL)

Total Fuel Sale in (KL)

Diesel Petrol

April 2013 139 28 167 1.07 1.17

May 2013 147 30 177 1.02 1.09

June 2013 163 35 198 0.92 0.94

July 2013 137 20 157 1.09 1.64

August 2013 112 29 141 1.33 1.13

September 2013 135 40 175 1.11 0.82

October 2013 261 37 298 0.57 0.89

November 2013 184 38 222 0.81 0.86

December 2013 115 35 150 1.30 0.94

January 2014 147 36 183 1.02 0.91

February 2014 112 34 146 1.33 0.97

March 2014 140 32 172 1.07 1.03

Total 1792 394

Average 149 33

Table 3.5B Calculation of SCF based on Diesel / Petrol Data

Month Year

Indian oil Petrol Pump At Bhopalgarh(Km54.400)

Seasonal Correction Factor(SCF)

Diesel (in KL)

Petrol (in KL)

Total Fuel Sale in

(KL) Diesel Petrol

April 2013 138 38 176 1.01 1.16

May 2013 148 49 197 0.94 0.90

Final Feasibility Report Page 3 - 12

Feasibility study for two-laning of Bhawi-Pipar-Khimsar (H-IV) STUP Consultants Pvt. Ltd.

June 2013 162 47 209 0.86 0.94

July 2013 138 57 195 1.01 0.77

August 2013 122 50 172 1.14 0.88

September 2013 135 48 183 1.03 0.92

October 2013 160 43 203 0.87 1.02

November 2013 170 42 212 0.82 1.05

December 2013 132 25 157 1.05 1.76

January 2014 115 42 157 1.21 1.05

February 2014 113 44 157 1.23 1.00

March 2014 138 43 181 1.01 1.02

Total 1671 528

Average 139 44

Table 3.5C Calculation of SCF based on Diesel / Petrol Data

Month Year

IOCLl Pump at Lavarl (km 64.250)

Seasonal Correction Factor(SCF)

Diesel (in KL)

Petrol (in KL)

Total Fuel Sale in KL

Diesel Petrol

April 2013 28 8 36 1.07 1.01

May 2013 24 10 34 1.25 0.81

June 2013 45 8 53 0.66 1.01

July 2013 22 5 27 1.36 1.62

August 2013 21 8 29 1.42 1.01

September 2013 25 10 35 1.20 0.81

October 2013 65 9 74 0.46 0.90

November 2013 36 8 44 0.83 1.01

December 2013 26 9 35 1.15 0.90

January 2014 22 8 30 1.36 1.01

February 2014 15 6 21 1.99 1.35

March 2014 30 8 38 1.00 1.01

Total 359 97

Average 30 8

Final Feasibility Report Page 3 - 13

Feasibility study for two-laning of Bhawi-Pipar-Khimsar (H-IV) STUP Consultants Pvt. Ltd.

Since the consultant conducted the survey in Dec. 2014, the SCF and consequently the AADT

have been calculated based on the sale in the month of Nov. The values of AADT (at all

locations) thus calculated are given in the Table 3.6:

Table 3.6: AADT

Average Annual Daily Traffic (AADT)

Vehicle Type

PCU Factor

SH-86C KM-1+500 SH-86C

KM-55+500 SH-86C Mangeria

(Km. 87.000)

SH-86C Ghana Magra

(Km. 6.000)

SCF AADT PCU SCF AADT PCU SCF AADT PCU SCF AADT PCU

Tolled

Car / Jeep / Taxi

1.00 1.03 552 552 1.02 350 350 1.01 45 45 1.03 37 37

Mini Buses 1.50 1.07 4 6 1.01 1 2 1.00 0 0 1.07 0 0

Standard Buses

3.00 1.07 90 270 1.01 33 100 1.00 13 39 1.07 11 34

Mini LCV 1.50 1.03 169 253 1.02 161 242 1.01 31 47 1.03 28 43

LCV 1.50 1.07 26 39 1.01 55 82 1.00 1 2 1.07 1 2

Trucks - 2 Axle

3.00 1.07 219 658 1.01 223 670 1.00 12 36 1.07 11 33

Trucks - 3 Axle

3.00 1.07 234 703 1.01 68 203 1.00 4 12 1.07 3 10

MAV (4-6 Axle)

4.50 1.07 164 737 1.01 23 105 1.00 0 0 1.07 0 0

MAV (6+ Axle)

4.50 1.07 0 0 1.01 0 0 1.00 0 0 1.07 0 0

HCM / EME 4.50 1.07 5 24 1.01 5 23 1.00 0 0 1.07 0 0

Tractor 1.50 1.07 12 18 1.01 13 20 1.00 2 3 1.07 2 3

Tractor with Trailer

4.50 1.07 142 640 1.01 67 300 1.00 28 126 1.07 23 104

Total 1618 3900 999 2094 137 310 118 266

Non Tolled

2-Wheeler 0.5 1.03 1829 915 1.02 1797 899 1.01 226 113 1.03 122 61

3-Wheeler 1.0 1.03 32 32 1.02 2 2 1.01 1 1 1.03 1 1

Cycle 0.5 48 24 13 7 15 8 15 8

Cycle Rickshaw

2.0 0 0 0 0 1 2 1 2

Animal Cart 6.0 0 0 0 0 1 6 1 6

Total 1909 971 1812 907 244 130 139 77

Final Feasibility Report Page 3 - 14

Feasibility study for two-laning of Bhawi-Pipar-Khimsar (H-IV) STUP Consultants Pvt. Ltd.

Exempted

Car / Jeep / Van

1.0 1.03 7 7 1.02 3 3 1.01 1 1 1.03 1 1

Ambulance / Fire

Tenders / Funeral

Vans

1.0 1.03 0 0 1.02 0 0 1.01 0 0 1.03 0 0

Bus 3.0 1.07 1 3 1.01 1 3 1.00 0 0 1.07 0 0

LCV 1.5 1.07 0 0 1.01 0 0 1.00 0 0 1.07 0 0

Truck 3.0 1.07 0 0 1.01 0 0 1.00 0 0 1.07 0 0

Total 8 10 4 6 1 1 2 2

Grand Total (Tolled+Non

Tolled+Exempted) 3535 4881 2815 3008 382 441 259 345

3.5 Intersection Data Analysis

3.5 Approach Traffic

The location wise traffic at sathin intersection is presented in Table 3.7. The traffic

flow diagram at intersection location is presented in figure 3.15 – 3.18below.

Table 3.7 : Location wise traffic at each intersection

S.

No. Location Location Name

Approach

Roads

Total

Vehicles Total PCU

Approach

Traffic

1 INT – 01 Bhopalgarh

Sathin 1130 1316

8905 Asop 2860 3690

Palri 3025 3899

2 INT – 02 Palri

Bhopalgarh 433 539

3396 Gotan 838 1107

Ratri 1073 1431

Asanda 374 320

3 INT - 03 Lawari Piou

Palri 635 719

1627 Asop 596 708

Gaj Singh

pura 216 200

4 INT – 04 Pipar Bypass

Sathin 1500 1918

6301 Merta City 942 1488

Jodhpur 2055 2895

Final Feasibility Report Page 3 - 15

Feasibility study for two-laning of Bhawi-Pipar-Khimsar (H-IV) STUP Consultants Pvt. Ltd.

3.6 Axle Load Survey

Axle load Survey was conducted at the same location where TVC was done i.e. at MDR-75

KM-37+500. The Axle load Spectrum is generated by preparing a frequency distribution of

axle loads. By multiplying the respective axle load with the equivalent factor, the vehicle

damage factor (VDF) is estimated. The VDF so calculated are tabulated in table 3.8 below:

Table 3.8 Axle Load Survey

Location

Vehicle Type

Bus Mini

Bus

Mini

LCV LCV

2-Axle

truck

3-Axle

Truck

4-6 Axle

vehicle

SH-86C KM-1+500 1.27 0.28 0.045 1.61 8.87 6.64 4.83

SH-86C KM-55+500 1.11 - 0.055 1.86 11.62 9.72 6.50

3.7 Million Standard Axle (MSA)

The design traffic is considered in terms and cumulative number of standard Axle to be

carried out during the design life of the road.

Design traffic in Million Standard Axle for 10 years and 15 years (post construction) is given

belowin table 3.9:

Table 3.9 Million Standard Axle (MSA)

Homogenous Section

Km. 0.00 –Km. 31.000 Length (Km.)

10 years (Design

traffic) into MSA

15 years Design

traffic in MSA

SH-86C KM-1+500 31 12.173 20.270

SH-86C KM-55+500 41 10.220 17.018

3.8 Traffic Projections

7 days classified traffic survey has been carried out at 3locations. The traffic (AADT) at these

locations has been projected adopting growth rate of 5%.

The projection of traffic, vehicle / location wise is shown in Table 3.12 to 3.15 and the

projection in total AADT / PCU (all Traffic & tollable Traffic) are shown in Table 3.10 & 3.11.