chapter 2 - bill of quantity and specification
TRANSCRIPT
8/12/2019 Chapter 2 - Bill of Quantity and Specification
http://slidepdf.com/reader/full/chapter-2-bill-of-quantity-and-specification 1/18
Construction Contract Administration and Project Management (CON4371)
Chapter 2
___________________________________________________________________________________
___________________________________________________________________________________
©VTC2013 Page 1 of 18
Chapter 2
Preparation of Bills of Quantities and the use of Specifications
1.
Bill of Quantities for Civil Engineering Work
‐ This type of contract incorporates a bill of quantities to be priced by the
contractor and is one of most commonly used form of contract for civil
engineering work.
‐ A bill of quantities is prepared in accordance with the CESMM, giving as
accurately as possible the quantities of each item of work to be
executed,
and
the
contractor
enters
a
unit
rate
against
each
item
of
work.
Quantity x Unit Rate = $Tender Total
‐ Item description only identifies work whose nature and extent is
defined by the contract documents as a whole, including the Drawings,
Specification and Conditions of Contract.
‐ This encourage the complete design of work prior to tender and the
cost of civil engineering work frequently depends extensively on the
shape and location of the work, and the terrain. This information is best
extracted from
the
drawings.
‐
The use of bill of quantities offers the following advantages:
(a) It enables all contractors tendering for a contractor to price on exactly
the same information. The use of bill of quantities avoids the need for
all the tenderers to measure the quantities themselves before preparing
the estimate. If all tenderers have to measure the works, there is a
wasteful duplication of efforts and increase in the contractors’ overhead,
which will
eventually
be
passed
to
the
employers/clients.
(b) The bill of quantities is prepared in accordance with the Standard
method of Measurement, ensuring that tendering contractors have a
clear conception of the work involved.
(c) The contractor is paid for the actual amount of work done and thus
limits the risk borne by the contractor.
(d) While providing a fair basis for payment, it also provides a basis for the
valuation of variations, which occur during the progress of the work.
8/12/2019 Chapter 2 - Bill of Quantity and Specification
http://slidepdf.com/reader/full/chapter-2-bill-of-quantity-and-specification 2/18
Construction Contract Administration and Project Management (CON4371)
Chapter 2
___________________________________________________________________________________
___________________________________________________________________________________
©VTC2013 Page 2 of 18
2. Contents in the Bill of Quantities
There are various forms in which bills of quantities can be prepared, but no
matter which
format
is
used;
there
will
be
certain
aspects,
which
are
common to all types.
All bills will contain the following sections: ‐
• Preliminaries
• Preambles
• Measured Work
• Prime cost and Provisional Sums
•
Daywork
Schedule
Preliminaries section
The preliminaries section usually placed at the beginning of the bill.
Preliminaries will provide:‐
• Particulars of the type of contract to be used and;
• Details of general matters, which may affect the price of the work.
The items are mainly comprised of three categories: ‐
(a)
Headings of
Clauses
contained
in
the
Conditions
of
Contract
for
example:
Obligation of the Contractor, Commencement of Work etc.
(b) Matters contained in Section 1 Part V of the CESMM for example: Site
Office, Hoarding, Protection for the Works, Site Photographs, etc.
(Refer to the Section 1 Preliminaries of the CESMM).
(c) Any specific matters not covered in (a) or (b) above but cover many
important financial matters which relate to the contract as a whole, and
are not confined to any particular work section, and the contractor is
given the
opportunity
to
price
them.
For example: the Client may require his own contractors to enter the site to
do renovation works during the progress of works and the Main Contractor
will have to allow for all cost and time implication in the Preliminaries item.
Preamble Section
The preamble in a civil engineering bill of quantities is to indicate
• To the tendering contractors whether methods of measurement other
than CESMM
have
been
used
for
any
parts
of
the
works
and;
8/12/2019 Chapter 2 - Bill of Quantity and Specification
http://slidepdf.com/reader/full/chapter-2-bill-of-quantity-and-specification 3/18
Construction Contract Administration and Project Management (CON4371)
Chapter 2
___________________________________________________________________________________
___________________________________________________________________________________
©VTC2013 Page 3 of 18
2. Contents in the Bill of Quantities (cont’d)
• Whether any modifications have been made in applying CESMM to meet
special needs.
Example:‐
(i) CESMM requires that excavation in rock is measured separately but if
there is difficult in doing so, then the rule of measurement maybe modified
to include all measurement of excavation in natural soil.
(ii) A Preamble will be provided stating that the Contractor’s rates shall
include excavation in rock if they encountered rocks during the excavation
works. This method will place the risks on the Contractor but will simplify
the
measurement
process.
The following main points are usually included in a Preamble: ‐
a) Attention is directed to other parts of the contract documents in
addition to the bills
b) The bills are prepared in accordance with the CESMM, any special
method of measurement should be stated
c) Prices and rates inserted in the bills are full, inclusive of wastage,
overhead, profit and other sundry items
d) Items with no price inserted will be considered to be covered by
prices of
other
items
Measured Works Bill
• The measured work section of a bill of quantities set out in a systematic
manner, the quantities and full description of the item required to
construct and complete the work for example:‐
Description Quantity Unit of Measurement Unit Rate
R.C grade 30/20D in fdn 100 m3 $950/m3
• The
level
of
detail
at
which
the
work
is
described
and
measured
is
controlled by a set of measurement rules in the CESMM.
• The rate of $950/m3 is inserted by the Contractor as his price for doing
the reinforced concrete work.
Provisional Sums
Provisional sums are sums provided for items of works, which the
requirement is uncertain at the time of tender and the works shall only be
carried out
on
the
instruction
of
the
Engineer.
8/12/2019 Chapter 2 - Bill of Quantity and Specification
http://slidepdf.com/reader/full/chapter-2-bill-of-quantity-and-specification 4/18
8/12/2019 Chapter 2 - Bill of Quantity and Specification
http://slidepdf.com/reader/full/chapter-2-bill-of-quantity-and-specification 5/18
Construction Contract Administration and Project Management (CON4371)
Chapter 2
___________________________________________________________________________________
___________________________________________________________________________________
©VTC2013 Page 5 of 18
2. Contents in the Bill of Quantities (cont’d)
• Examples
of
works
which
are
not
suitable
to
be
measured
at
the
bill
rates
are works which are labour intensive such as demolition.
• Daywork is the method of valuing work on the
(i) Time spent by operatives (Labour),
(ii) Materials used and
(iii) Plants employed,
(iv) Additional percentage allowance to cover Profit & Overhead.
•
Normally
a
list
of
various
types
of
labour,
material
and
plant
are
prepared
for which daywork rates or prices are to be inserted by the Tenderers.
3. Types of bills categorized by the accuracy of the quantities
Bill of Firm Quantities
• In the preparation of a firm bill of quantities, design must be completed
and drawings
must
be
full
and
details
available
for
measurement
prior
to
tender.
• The Engineer will measure the quantities from the finalised drawings and
thus the quantities should reflect the work in the drawings.
• The quantities are firm quantities and usually this kind of bill will form
part of the contract and the quantities should not be altered unless with
the Engineer’s instructions.
Bill of
Approximate
Quantities
• There are circumstances when the quantities in the bill are not firm but
approximate.
• In such cases, the designs or drawings are not completed but the bill of
approximate quantities is prepared for tendering purposes.
• The approximate quantities shall subject to a final remeasurement upon
finalization of design drawings.
Circumstances when to use this type of Bill:‐
8/12/2019 Chapter 2 - Bill of Quantity and Specification
http://slidepdf.com/reader/full/chapter-2-bill-of-quantity-and-specification 6/18
Construction Contract Administration and Project Management (CON4371)
Chapter 2
___________________________________________________________________________________
___________________________________________________________________________________
©VTC2013 Page 6 of 18
3. Types of bills categorized by the accuracy of the quantities
a)
Where
time
is
the
essence
and
the
general
drawings
have
been
formulated, and the Employer wishes to select a contractor before the
detail drawings can be completed.
In this situation, it is probable that sufficient design information is
available to enable approximate quantities to be produced to form a
bill.
b) With work below ground, the available information is likely to be too
imprecise for the preparation of accurate quantities.
The
building
can
be
established
but
the
depth
of
foundations
and
extent
of soft areas will be uncertain.
c) Provisional quantities maybe included in a firm bill of quantities to
cover work that is uncertain in extent and is subject to remeasurement
where the work is carried out.
Excavating in rock, the removal of underground obstruction maybe
classified under this category.
4.
Formats of
Bills
Trade Bills
‐ This is a traditional method which arisen due to the way the
construction industry has conventionally been organised.
‐ The trade format groups similar items together to avoid repetition. The
work items are grouped according to trade works.
‐ The arrangement of the trades usually follows the order in the SMM.
For example:
‐
‐Excavator
‐Concretor
‐Drain layer
‐Brickwork and Masonry
Advantage
1. The subdivision of the BQ according to trades allowed the estimator to
quickly break up the BQ and send out sections to trade sub‐contractor
for separate
quotations.
8/12/2019 Chapter 2 - Bill of Quantity and Specification
http://slidepdf.com/reader/full/chapter-2-bill-of-quantity-and-specification 7/18
Construction Contract Administration and Project Management (CON4371)
Chapter 2
___________________________________________________________________________________
___________________________________________________________________________________
©VTC2013 Page 7 of 18
4. Formats of Bills (cont’d)
2.
More simple
to
prepare
as
there
is
less
working
up
process
and
less
repetition work
Disadvantage
1. Not very good for showing the cost of various element.
Elemental Bills
‐ Elemental bills are divided into elements that correspond to the
functional part of the building.
‐
The
elemental
bill
groups
similar
elements
together
for
ease
of
cost
planning.
‐ Hence; trades such as Excavator, Concretor, Drainlayer, Brickwork, etc
will be replaced by headings such as Foundation, Structural Frame,
Suspended Slabs, Bridge Structure, etc
‐ The principal objective is to secure a precise tendering by making the
location of the work more readily identifiable and to provide a closer
link to the cost plan.
Advantages
1. It will be easier to extract from the bills the total cost for an elemental
item thus facilitate the use of priced BQ for cost planning.
2. Estimating can be made more accurate as items are related to a
particular part of a project.
3. It provides more reliable information for the contractor in their project
management works
4. Help to simplify the works of the Engineer in preparation of interim
payment especially
stage
payment
Disadvantages
1. This type of bills need more time as it involves a considerable repetition
of billed items
2. Bills can be extremely large and bulky
3. Additional expenses due to the extra repetitive work
8/12/2019 Chapter 2 - Bill of Quantity and Specification
http://slidepdf.com/reader/full/chapter-2-bill-of-quantity-and-specification 8/18
Construction Contract Administration and Project Management (CON4371)
Chapter 2
___________________________________________________________________________________
___________________________________________________________________________________
©VTC2013 Page 8 of 18
5. Other Type of Contract that is used in Civil Engineering
Schedule of Rates
• A
schedule
of
rates
is
similar
to
a bill
of
quantities
but
without
the
quantities.
• In other words, it consists of a list of items with full descriptions, units of
measurement and unit rates.
• This type of contract is normally suited for maintenance and repair work
where the extent and nature of the works may not be known until the work
is executed.
‐ Generally the contractor is required to insert the rates in the schedule
of
the
listed
items
of
works.
Description Unit of Measurement Unit Rate
R.C grade 30/20D in fdn m3 $950/m3
(inserted by the contractor)
OR
‐ The rates maybe predetermined by the Employer whereby the
contractor will then enter an addition or deduction percentage to the
listed rates.
Description Unit Unit Rate % Adjustment
R.C grade 30/20D in fdn m3 $800/m3 (+15%)
Advantage:
(1) The use of this type of contract is that work on site can commence well
before the completion of the design.
Disadvantages:
(1)
Total cost
of
the
work
is
not
known
at
the
time
of
tender.
(2) The total cost of a project is only calculated by measuring the work as it
proceeds on site and pricing at the appropriate rates in the schedule.
8/12/2019 Chapter 2 - Bill of Quantity and Specification
http://slidepdf.com/reader/full/chapter-2-bill-of-quantity-and-specification 9/18
Construction Contract Administration and Project Management (CON4371)
Chapter 2
___________________________________________________________________________________
___________________________________________________________________________________
©VTC2013 Page 9 of 18
6. Use of Specification
The specification is read in conjunction with drawings and a bill of
quantities to
supply
the
contractor
with
all
the
necessary
information
he
needs to submit a tender and to execute the works.
The main functions of the specification are to:
1) Describe fully the workmanship and materials required to carry out the
contract.
The specification lays down the quality of material, standard of
workmanship, testing methods and acceptance criteria for construction
work.
2) Avoids duplication of descriptive information as full descriptions
appear in a single document which is the specification.
On a construction job, the descriptions of items contained in the bills of
quantities should be
‐ as brief as possible and with frequent references to the specification
clauses.
3) Provide
details
of
not
included
in
the
Conditions
of
Contract
In addition to the above, the specification also contains details of any
special responsibilities of the contractor which are not covered by the
conditions of contract.
4) To supplement the information in the drawings
It is obviously not possible to show everything on the drawings, e.g. specific
details of the way materials are jointed or fixed, details of standard of
workmanship required
etc.
Nevertheless the information is important for pricing and for quality
control and so must be given in the Specification.
For a well written Specification, it is therefore important that:
i) The specification and drawings are complete but without excessive
duplication. Drawings and specification must not contradict each other.
8/12/2019 Chapter 2 - Bill of Quantity and Specification
http://slidepdf.com/reader/full/chapter-2-bill-of-quantity-and-specification 10/18
Construction Contract Administration and Project Management (CON4371)
Chapter 2
___________________________________________________________________________________
___________________________________________________________________________________
©VTC2013 Page 10 of 18
6. Use of Specification (cont’d)
ii) The specification writer must know what is required‐ this implies a good
knowledge of
construction
technology,
both
the
way
in
which
works
fit
together and of construction materials
iii) The information is presented clearly.
7. General Arrangement of Specification
(a) General Clauses
Most specifications for civil engineering work begin with a selection of
‘general
clauses’
which
relate
to
the
contract
as
a
whole
and
are
not
confined to any particular trade or works section. The nature and content
of these clauses will vary from project to project.
An example of a typical general clause is as follow: ‐.
Heading: General Requirements
• The works to be executed under this Contract are to be carried out in
accordance with the Conditions of Contract, Specification, Bill of Quantities
and Contract Drawings.
• If
in
construing
the
Contract,
there
shall
appear
to
be
any
inconsistency
between the Specification and Conditions of Contract, the Condition of
Contract shall prevail.
• This clause draws the Contractor’s attention to the requirements of all
the Contract Documents and emphasizes that the Conditions of Contract
have precedence over the other contract documents.
(b) Technical Material and Workmanship Clauses
The specification
clauses
are
normally
followed
by
materials
and
work
clauses, which are related to the various sections of work making up the
job.
Material Descriptions
Considerable care must be exercised in the drafting of a specification, to
prepare clauses, which are concise, complete, and free form ambiguity.
The following alternative methods of describing materials, or a
combination of
them,
can
be
used
in
a specification.
8/12/2019 Chapter 2 - Bill of Quantity and Specification
http://slidepdf.com/reader/full/chapter-2-bill-of-quantity-and-specification 11/18
Construction Contract Administration and Project Management (CON4371)
Chapter 2
___________________________________________________________________________________
___________________________________________________________________________________
©VTC2013 Page 11 of 18
7. General Arrangement of Specification (cont’d)
Methods of Describing Materials in Specification Clauses:‐
(1) A
full
description
of
the
material
is
given
with
details
of
desirable
and
undesirable characteristic and appropriate test requirements
(2) Relevant standard reference, together with details of type or class
required. The contractor can then refer to the specified standard
(3) Name of manufacturer, proprietary brand or source of supply stated
and the contractor can obtain further particulars from the manufacturer or
supplier.
(4) Provide the Prime Cost of the material with brief description of supply
and
delivery
of
a
certain
quantity
of
the
material
to
the
site.
For example: Prime Cost of to be $2500/m2 (supplied and delivered to site)
For example, a material description on brick: ‐
Material Description
Bricks Clay bricks
Name of manufacturer as approved by the Engineer
Or Source of Supply
Prime cost $500.00 per thousand, delivered to
site
Desirable characteristics Well burnt, hard, square, clean,
sound
Undesirable characteristic Free from cracks
Tests Minimum compressive strength
7.0 Mpa.
Workmanship clauses
Specification clauses
covering
constructional
work
and
workmanship
requirement are generally drafted in the imperative and should give a clear
and concise description of the character and extent of the work involved.
For example as in Clause 25:144(1):‐
Brickwork shall be flushed up with cement mortar to form a level and even
bed to receive horizontal damp proof course.
8/12/2019 Chapter 2 - Bill of Quantity and Specification
http://slidepdf.com/reader/full/chapter-2-bill-of-quantity-and-specification 12/18
Construction Contract Administration and Project Management (CON4371)
Chapter 2
___________________________________________________________________________________
___________________________________________________________________________________
©VTC2013 Page 12 of 18
8. Classification of Specification
(1) Standard
Specification
• These are specification devised by experts in their fields in the
government departments and consulting engineering firms and they are
accepted as authoritative by the construction industry.
• In Hong Kong, some particular authorities for eg. ASD, Housing
Authority, Civil Engineering Department has comprehensive standard
specification which will be issued for every project.
• These standard requirements establish a uniformity of administrative
procedures
and
quality
in
material
and
workmanship
for
constructing
their
projects.
(2) Particular Specification
• Standard specification is unable to provide all of the requirements
needed for a specific contract.
• To fill this gap, another set of specification called the particular
specifications are prepared by the specification writer for the specific
project.
• The
particular
specification
clauses
present
requirements
applicable
only
to that specific contract.
• This is often achieved by amending the standard specification by adding
to them, deleting from them, or modifying them.
• The combined use of the above two specifications enables the speedy
readiness of specification suitable to the project.
9. Types of Specification
1) Performance Specification
• Performance specifications are sometimes called End Product
Specifications or End Result Specifications.
• They specify standards and criteria, and the end results to be obtained.
• Performance specification does not normally prescribe dimensions,
materials or methods of manufacture, instead, the desired quality; function
and other
characteristics
of
the
product
are
specified.
8/12/2019 Chapter 2 - Bill of Quantity and Specification
http://slidepdf.com/reader/full/chapter-2-bill-of-quantity-and-specification 13/18
Construction Contract Administration and Project Management (CON4371)
Chapter 2
___________________________________________________________________________________
___________________________________________________________________________________
©VTC2013 Page 13 of 18
9. Types of Specification (cont’d)
• By specifying the performance requirements, it becomes the
responsibility of
the
contractor
to
select
the
materials
and
methods
to
achieve the end result.
Advantages:
(a) Some control of design passes to the contractor.
(b) Many new ideas are encouraged.
(c) New materials or component can be incorporated.
(d) Contractor uses methods or plant familiar to himself
(e)
Period
for
design
may
be
reduced
as
helpful
in
eliminating
lot
of
detailed instructions for construction procedures.
Disadvantages
(a) Comparison of tenders is less certain due to variation in contractors’
specification.
(b) Cost of project may await tenders, as Engineer’s guide prices may not
apply
2) Proprietary Specification
• It restricts products to be manufactured in accordance with a defined
method or system
• An Engineer will after many years in business, acquire first hand
knowledge on the performance of various products and items of
equipment.
• He utilises this knowledge to guide him in specifying projects. He will
specified certain
methods,
or
products
or
item
of
equipment
by
its
brand
name, manufacture.
• Sometimes, in order to avoid any chance of favouritism and minimise the
restriction on competition, the phrase “equal and approved” is used in the
Specification.
Advantages
a) The Engineer exercises maximum control
b) All
tenders
are
on
the
same
basis
8/12/2019 Chapter 2 - Bill of Quantity and Specification
http://slidepdf.com/reader/full/chapter-2-bill-of-quantity-and-specification 14/18
Construction Contract Administration and Project Management (CON4371)
Chapter 2
___________________________________________________________________________________
___________________________________________________________________________________
©VTC2013 Page 14 of 18
9. Types of Specification (cont’d)
c) Cost of project based on the Engineer’s method or specified proprietary
system of
products
d) Ensure Engineer’s familiarity with the design
Disadvantages
(a) The specified method may not be familiarised by the Contractor
(b) Reduced the opportunity for other alternatives which may be more cost
effective
(c) There may be time where is it impossible or impractical to make an
exhaustive
study
within
the
design
period
to
draw
up
a
list
of
proprietary
system
3) Descriptive Specification
• Descriptive specifications are most common in civil engineering
construction works.
• This type of Specification will provide detailed description of required
materials and their properties without specifying brand names.
•
It
will
also
provide
construction
details
and
the
desired
quality
of
workmanship.
• Descriptive specifications are sometimes called Material and
Workmanship Specification.
Advantages
(a) Control can be imposed on both quality and performance
(b) Contractor can use material and equipment familiar to himself
(c) Common
basis
has
been
provided
for
comparison
of
tenders
Disadvantages
(a) Cost of project can be affected largely by the material or equipment
used by the Contractor
(b) Greater supervision is needed.
8/12/2019 Chapter 2 - Bill of Quantity and Specification
http://slidepdf.com/reader/full/chapter-2-bill-of-quantity-and-specification 15/18
Construction Contract Administration and Project Management (CON4371)
Chapter 2
___________________________________________________________________________________
___________________________________________________________________________________
©VTC2013 Page 15 of 18
10. Format of Specification for Material
In specifying for material, there are two formats which are in use:
1) Close Specification
• A close specification is one which the description of material is so
detailed that only one product can qualify for use.
• A specification provided by the Manufacturer is usually a closed
specification, or
• In cases whereby the contract has specified for materials to be provided
by Nominated Supplier is also a closed specification.
•
Its
purpose
is
to
ensure
that
only
construction
products
of
a
desired
quality are provided by the Contractor.
• However, close specification will reduce competition in prices.
2) Open Specification
• An open specification is worded in such a way that the products of
various Manufacturers are acceptable, provided that they can meet the
specified function and quality standards.
• It allows substitution by specifying materials followed by wordings such
as “approved
equal”.
• It is useful when cost savings is possible or when the availability of
material is uncertain.
• This type is usually often used in Government contracts where open
competition is preferred.
Sources of Writing for Specification Writing
Information for use in civil engineering specifications can be obtained from
a variety
of
sources.
The
principal
sources
of
information
are
as
described:
(1) Previous Specification
In the majority of cases, specification for past projects is used as a basis in
the preparation of a new specification for a job of similar type.
When looking for a previously prepared specification, one should be
selected to commensurate with the magnitude of the future project.
8/12/2019 Chapter 2 - Bill of Quantity and Specification
http://slidepdf.com/reader/full/chapter-2-bill-of-quantity-and-specification 16/18
Construction Contract Administration and Project Management (CON4371)
Chapter 2
___________________________________________________________________________________
___________________________________________________________________________________
©VTC2013 Page 16 of 18
10. Format of Specification for Material (cont’d)
For example:
a concrete
specification
for
a dam
construction
would
not
be
appropriate to use for construction of a simple building.
The use of previous specification expedites the task of specification writing
but care must be taken to bring the specification clauses to date by the
incorporation of the latest developments and techniques for the work
concerned.
In
addition,
clauses
have
to
be
modified
to
suit
the
design,
construction
in
the current job. Generally, details which are not applicable are omitted and
to insert information on additional features.
(2) Contract Drawings
The draft contract drawings will be prepared in advance of the specification
and these will show the character and extent of the work.
The specification writer will extract a considerable amount of information
from the drawings and will work systematically through them when
compiling the
specification.
(3) Employer’s Requirement
The employer or client often lays down requirements in connection with
the project and these will probably need to be incorporated in the
specification.
Typical requirements of this kind are the programming of the works as to
provide for
completion
of
certain
sections
of
works,
taking
of
precautions
so as to minimize interference with existing facilities etc.
Requirements of this nature will be reflected in the General Clauses of the
specification and should be to notice of the contractors they may result in
increased cost.
8/12/2019 Chapter 2 - Bill of Quantity and Specification
http://slidepdf.com/reader/full/chapter-2-bill-of-quantity-and-specification 17/18
Construction Contract Administration and Project Management (CON4371)
Chapter 2
___________________________________________________________________________________
___________________________________________________________________________________
©VTC2013 Page 17 of 18
10. Format of Specification for Material (cont’d)
(4) Site
Investigation
Some of the information inserted in a specification will arise from site
investigation such as information on soil conditions and water table level
and site clearance work.
The contractor should be supplied with any relevant information to reduce
the risks and the number of uncertain factors in his tender.
(5)
British
Standards
The use of British standard in the specification clause permits a
considerable reduction in the length of clauses relating to materials and
components and products.
It also eliminates the contractor from reading lengthy descriptive clauses in
the specification. The standards are prepared by the British Standards
Institution which is the approved body for the preparation of a national
standard covering methods for tests, terms, definitions, standards of
quality, of
performance,
dimensions
etc.
British Standards prescribe the recognised standards of quality and of a
great value in drafting specification as they reduce the amount of
descriptive works yet at the same time ensure a good quality product.
(6) Codes of Practice
Specification clauses sometimes refer to relevant codes of practice to
ensure good
standard
of
construction
and
workmanship
without
the
need
for lengthy specification clauses.
Codes of Practice cover design, construction and maintenance aspect. Their
contents are widely known and recognised as a mean to secure improved
standards of works in the respective field.
8/12/2019 Chapter 2 - Bill of Quantity and Specification
http://slidepdf.com/reader/full/chapter-2-bill-of-quantity-and-specification 18/18
Construction Contract Administration and Project Management (CON4371)
Chapter 2
___________________________________________________________________________________
___________________________________________________________________________________
©VTC2013 Page 18 of 18
10. Format of Specification for Material (cont’d)
(7) Trade
Catalogues
When materials of proprietary brands are used in a job, reference is often
made to the manufacturers’ catalogues for specifying the necessary
information in the specification.
This procedure will shorten the length of the specification clause and at the
same time ensured the use of a specific material with which the Engineers
familiar and in which he has full confidence.