chapter 2 - bill of quantity and specification

18
Construction Contract Administration  and Project Management (CON4371) Chapter 2  _____________________________________________________ ______________________________  ________________________________________________________ ___________________________ ©VTC2013 Page 1 of  18 Chapter 2 Preparation of  Bills of  Quantities and the use of  Specifications 1. Bill of  Quantities for Civil Engineering Work  This type of  contract incorporates a bill  of  quantities  to be priced by the contractor and is one of  most commonly used form of  contract  for civil engineering work.  A bill of  quantities  is prepared in accordance with the CESMM,  giving as accurately as possible the quantities  of  each item of  work to be executed,  and the contractor enters a unit rate against each item of  work. Quantity x Unit Rate = $Tender Total   Item description only identifies work whose nature and extent is defined by the contract documents  as a whole, including the Drawings,  Specification and Conditions of  Contract.  This encourage the complete design of  work prior to tender and the cost of  civil engineering work frequently depends extensively on the shape and location of  the work, and the terrain. This information is best extracted from the drawings.   The use of  bill of  quantities offers  the following advantages:  (a) It enables all contractors tendering for a contractor to price on exactly the same information.  The use of  bill  of  quantities  avoids the need for all the tenderers  to measure the quantities themselves before preparing the estimate.  If  all tenderers  have to measure the works, there is a wasteful  duplication of  efforts and increase in the contractors’  overhead,  which will eventually be passed to the employers/clients.  (b) The bill of  quantities  is prepared in accordance with the Standard method of  Measurement,  ensuring that tendering contractors have a clear conception of  the work involved.  (c) The contractor  is paid for the actual amount of  work done and thus limits the risk borne by the contractor.  (d) While providing a fair basis for payment, it also provides a basis for the valuation of  variations,  which occur during the progress of  the work. 

Upload: terwabe-wapagovski

Post on 03-Jun-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Chapter 2 - Bill of Quantity and Specification

8/12/2019 Chapter 2 - Bill of Quantity and Specification

http://slidepdf.com/reader/full/chapter-2-bill-of-quantity-and-specification 1/18

Construction Contract Administration  and Project Management (CON4371) 

Chapter 2 

 ___________________________________________________________________________________

 ___________________________________________________________________________________

©VTC2013  Page 1 of  18 

Chapter 2 

Preparation of  Bills of  Quantities and the use of  Specifications 

1. 

Bill of  Quantities for Civil Engineering Work 

‐  This type of  contract incorporates a bill of  quantities to be priced by the 

contractor and is one of  most commonly used form of  contract for civil 

engineering work. 

‐  A bill of  quantities is prepared in accordance with the CESMM, giving as 

accurately  as  possible  the  quantities  of   each  item  of   work  to  be 

executed, 

and 

the 

contractor 

enters 

unit 

rate 

against 

each 

item 

of  

work. 

Quantity x Unit Rate = $Tender Total 

‐  Item  description  only  identifies  work  whose  nature  and  extent  is 

defined by the contract documents as a whole, including the Drawings, 

Specification and Conditions of  Contract. 

‐  This  encourage  the  complete  design  of   work  prior  to  tender  and  the 

cost  of   civil  engineering  work  frequently  depends  extensively  on  the 

shape and location of  the work, and the terrain. This information is best 

extracted from

 the

 drawings.

 

‐ 

The use of  bill of  quantities offers the following advantages: 

(a) It enables all contractors tendering for a contractor to price on exactly 

the same  information. The use of  bill of  quantities avoids the need  for 

all the tenderers to measure the quantities themselves before preparing 

the  estimate.  If   all  tenderers  have  to  measure  the  works,  there  is  a 

wasteful duplication of  efforts and increase in the contractors’ overhead, 

which will

 eventually

 be

 passed

 to

 the

 employers/clients.

 

(b) The  bill  of   quantities  is  prepared  in  accordance  with  the  Standard 

method  of   Measurement,  ensuring  that  tendering  contractors  have  a 

clear conception of  the work involved. 

(c) The  contractor  is  paid  for  the  actual  amount  of   work  done  and  thus 

limits the risk borne by the contractor. 

(d) While providing a fair basis for payment, it also provides a basis for the 

valuation of  variations, which occur during the progress of  the work. 

Page 2: Chapter 2 - Bill of Quantity and Specification

8/12/2019 Chapter 2 - Bill of Quantity and Specification

http://slidepdf.com/reader/full/chapter-2-bill-of-quantity-and-specification 2/18

Construction Contract Administration  and Project Management (CON4371) 

Chapter 2 

 ___________________________________________________________________________________

 ___________________________________________________________________________________

©VTC2013  Page 2 of  18 

2. Contents in the Bill of  Quantities 

There are various forms in which bills of  quantities can be prepared, but no 

matter which

 format

 is

 used;

 there

 will

 be

 certain

 aspects,

 which

 are

 

common to all types. 

All bills will contain the following sections: ‐

• Preliminaries 

• Preambles 

• Measured  Work  

• Prime cost  and  Provisional  Sums 

• 

Daywork  

Schedule 

Preliminaries section 

The preliminaries section usually placed at the beginning of  the bill. 

Preliminaries will provide:‐

• Particulars of  the type of  contract to be used and; 

• Details of  general matters, which may affect the price of  the work. 

The items are mainly comprised of  three categories: ‐

(a) 

Headings of 

 Clauses

 contained

 in

 the

 Conditions

 of 

 Contract

 for

 example:

 

Obligation of  the Contractor, Commencement of  Work etc. 

(b) Matters contained  in Section 1 Part V of  the CESMM for example: Site 

Office, Hoarding, Protection for the Works, Site Photographs, etc. 

(Refer  to the Section 1 Preliminaries of  the CESMM). 

(c) Any  specific  matters  not  covered  in  (a)  or  (b)  above  but  cover  many 

important financial matters which relate to the contract as a whole, and 

are not confined  to  any particular  work  section,  and  the  contractor  is 

given the

 opportunity

 to

 price

 them.

 

For example: the Client may require his own contractors to enter the site to 

do renovation works during the progress of  works and the Main Contractor 

will have to allow for all cost and time implication in the Preliminaries item. 

Preamble Section 

The preamble in a civil engineering bill of  quantities is to indicate 

• To the tendering contractors whether methods of  measurement other 

than CESMM

 have

 been

 used

 for

 any

 parts

 of 

 the

 works

 and;

 

Page 3: Chapter 2 - Bill of Quantity and Specification

8/12/2019 Chapter 2 - Bill of Quantity and Specification

http://slidepdf.com/reader/full/chapter-2-bill-of-quantity-and-specification 3/18

Construction Contract Administration  and Project Management (CON4371) 

Chapter 2 

 ___________________________________________________________________________________

 ___________________________________________________________________________________

©VTC2013  Page 3 of  18 

2. Contents in the Bill of  Quantities (cont’d) 

• Whether any modifications have been made in applying CESMM to meet 

special needs.

 

Example:‐

(i)  CESMM  requires  that  excavation  in  rock  is  measured  separately  but  if  

there is difficult in doing so, then the rule of  measurement maybe modified 

to include all measurement of  excavation in natural soil. 

(ii)  A  Preamble  will  be  provided  stating  that  the  Contractor’s  rates  shall 

include excavation in rock if  they encountered rocks during the excavation 

works. This method will place the risks on the Contractor but will simplify 

the 

measurement 

process. 

The following main points are usually included in a Preamble: ‐

a)  Attention  is  directed  to  other  parts  of   the  contract  documents  in 

addition to the bills 

b)  The bills are prepared  in accordance with the CESMM, any special 

method of  measurement should be stated 

c)  Prices and  rates  inserted  in  the bills are  full,  inclusive of  wastage, 

overhead, profit and other sundry items 

d)  Items  with  no  price  inserted  will  be  considered  to  be  covered  by 

prices of 

 other

 items

 

Measured Works Bill 

• The measured work section of  a bill of  quantities set out in a systematic 

manner,  the  quantities  and  full  description  of   the  item  required  to 

construct and complete the work for example:‐

Description Quantity Unit of  Measurement Unit Rate 

R.C grade 30/20D in fdn 100 m3 $950/m3 

• The

 level

 of 

 detail

 at

 which

 the

 work

 is

 described

 and

 measured

 is

 

controlled by a set of  measurement rules in the CESMM. 

• The rate of  $950/m3 is  inserted by  the Contractor as his price  for doing 

the reinforced concrete work. 

Provisional Sums 

Provisional  sums  are  sums  provided  for  items  of   works,  which  the 

requirement is uncertain at the time of  tender and the works shall only be 

carried out

 on

 the

 instruction

 of 

 the

 Engineer.

 

Page 4: Chapter 2 - Bill of Quantity and Specification

8/12/2019 Chapter 2 - Bill of Quantity and Specification

http://slidepdf.com/reader/full/chapter-2-bill-of-quantity-and-specification 4/18

Page 5: Chapter 2 - Bill of Quantity and Specification

8/12/2019 Chapter 2 - Bill of Quantity and Specification

http://slidepdf.com/reader/full/chapter-2-bill-of-quantity-and-specification 5/18

Construction Contract Administration  and Project Management (CON4371) 

Chapter 2 

 ___________________________________________________________________________________

 ___________________________________________________________________________________

©VTC2013  Page 5 of  18 

2. Contents in the Bill of  Quantities (cont’d) 

• Examples

 of 

 works

 which

 are

 not

 suitable

 to

 be

 measured

 at

 the

 bill

 rates

 

are works which are labour intensive such as demolition. 

• Daywork is the method of  valuing work on the 

(i) Time spent by operatives (Labour), 

(ii) Materials used and 

(iii) Plants employed, 

(iv) Additional percentage allowance to cover Profit & Overhead. 

• 

Normally 

list 

of  

various 

types 

of  

labour, 

material 

and 

plant 

are 

prepared 

for which daywork rates or prices are to be inserted by the Tenderers. 

3. Types of  bills categorized by the accuracy of  the quantities 

Bill of  Firm Quantities 

• In the preparation of  a firm bill of  quantities, design must be completed 

and drawings

 must

 be

 full

 and

 details

 available

 for

 measurement

 prior

 to

 

tender. 

• The Engineer will measure the quantities from the finalised drawings and 

thus the quantities should reflect the work in the drawings. 

• The quantities  are  firm  quantities  and usually  this kind  of  bill will  form 

part of   the contract and  the quantities should not be altered unless with 

the Engineer’s instructions. 

Bill of 

 Approximate

 Quantities

 

• There are circumstances when the quantities  in the bill are not firm but 

approximate. 

•  In such cases, the designs or drawings are not completed but the bill of  

approximate quantities is prepared for tendering purposes. 

• The approximate quantities shall subject to a final remeasurement upon 

finalization of  design drawings. 

Circumstances when to use this type of  Bill:‐

Page 6: Chapter 2 - Bill of Quantity and Specification

8/12/2019 Chapter 2 - Bill of Quantity and Specification

http://slidepdf.com/reader/full/chapter-2-bill-of-quantity-and-specification 6/18

Construction Contract Administration  and Project Management (CON4371) 

Chapter 2 

 ___________________________________________________________________________________

 ___________________________________________________________________________________

©VTC2013  Page 6 of  18 

3. Types of  bills categorized by the accuracy of  the quantities 

a) 

Where 

time 

is 

the 

essence 

and 

the 

general 

drawings 

have 

been 

formulated, and the Employer wishes to select a contractor before the 

detail drawings can be completed. 

In  this  situation,  it  is  probable  that  sufficient  design  information  is 

available  to  enable  approximate  quantities  to  be  produced  to  form  a 

bill. 

b)  With work below ground, the available information is likely to be too 

imprecise for the preparation of  accurate quantities. 

The 

building 

can 

be 

established 

but 

the 

depth 

of  

foundations 

and 

extent 

of  soft areas will be uncertain. 

c)  Provisional quantities maybe included in a firm bill of  quantities to 

cover work that is uncertain in extent and is subject to remeasurement 

where the work is carried out. 

Excavating in rock, the removal of  underground obstruction maybe 

classified under this category. 

4. 

Formats of 

 Bills

 

Trade Bills 

‐  This is a traditional method which arisen due to the way the 

construction industry has conventionally been organised. 

‐  The trade format groups similar items together to avoid repetition. The 

work items are grouped according to trade works. 

‐  The arrangement of  the trades usually follows the order in the SMM. 

For example:

‐Excavator 

‐Concretor 

‐Drain layer 

‐Brickwork and Masonry 

Advantage 

1.  The subdivision of  the BQ  according to trades allowed the estimator to 

quickly break up the BQ  and send out sections to trade sub‐contractor 

for separate

 quotations.

 

Page 7: Chapter 2 - Bill of Quantity and Specification

8/12/2019 Chapter 2 - Bill of Quantity and Specification

http://slidepdf.com/reader/full/chapter-2-bill-of-quantity-and-specification 7/18

Construction Contract Administration  and Project Management (CON4371) 

Chapter 2 

 ___________________________________________________________________________________

 ___________________________________________________________________________________

©VTC2013  Page 7 of  18 

4. Formats of  Bills (cont’d) 

2. 

More simple

 to

 prepare

 as

 there

 is

 less

 working

 up

 process

 and

 less

 

repetition work 

Disadvantage 

1. Not very good for showing the cost of  various element. 

Elemental Bills 

‐  Elemental  bills  are  divided  into  elements  that  correspond  to  the 

functional part of  the building. 

‐ 

The 

elemental 

bill 

groups 

similar 

elements 

together 

for 

ease 

of  

cost 

planning. 

‐  Hence;  trades such as Excavator, Concretor, Drainlayer, Brickwork, etc 

will  be  replaced  by  headings  such  as  Foundation,  Structural  Frame, 

Suspended Slabs, Bridge Structure, etc 

‐  The principal objective  is  to  secure a precise  tendering by making  the 

location  of   the  work  more  readily  identifiable  and  to  provide a  closer 

link to the cost plan. 

Advantages 

1.  It will be easier to extract from the bills the total cost for an elemental 

item thus facilitate the use of  priced BQ  for cost planning. 

2.  Estimating  can  be  made  more  accurate  as  items  are  related  to  a 

particular part of  a project. 

3.  It provides more reliable information for the contractor in their project 

management works 

4. Help to simplify the works of  the Engineer in preparation of  interim 

payment especially

 stage

 payment

 

Disadvantages 

1.  This type of  bills need more time as it involves a considerable repetition 

of  billed items 

2.  Bills can be extremely large and bulky 

3.  Additional expenses due to the extra repetitive work 

Page 8: Chapter 2 - Bill of Quantity and Specification

8/12/2019 Chapter 2 - Bill of Quantity and Specification

http://slidepdf.com/reader/full/chapter-2-bill-of-quantity-and-specification 8/18

Construction Contract Administration  and Project Management (CON4371) 

Chapter 2 

 ___________________________________________________________________________________

 ___________________________________________________________________________________

©VTC2013  Page 8 of  18 

5. Other Type of  Contract that is used in Civil Engineering 

Schedule of  Rates 

• A

 schedule

 of 

 rates

 is

 similar

 to

 a bill

 of 

 quantities

 but

 without

 the

 

quantities. 

• In other words, it consists of  a list of  items with full descriptions, units of  

measurement and unit rates. 

• This type of  contract is normally suited for maintenance and repair work 

where the extent and nature of  the works may not be known until the work 

is executed. 

‐  Generally the contractor  is required to  insert the rates  in the schedule 

of  

the 

listed 

items 

of  

works. 

Description  Unit of  Measurement  Unit Rate 

R.C grade 30/20D in fdn  m3  $950/m3 

(inserted by the contractor) 

OR 

‐  The  rates  maybe  predetermined  by  the  Employer  whereby  the 

contractor will  then enter an addition or deduction percentage  to  the 

listed rates. 

Description  Unit  Unit Rate  % Adjustment 

R.C grade 30/20D in fdn  m3  $800/m3  (+15%) 

Advantage: 

(1) The use of  this type of  contract is that work on site can commence well 

before the completion of  the design. 

Disadvantages: 

(1) 

Total cost

 of 

 the

 work

 is

 not

 known

 at

 the

 time

 of 

 tender.

 

(2) The total cost of  a project is only calculated by measuring the work as it 

proceeds on site and pricing at the appropriate rates in the schedule. 

Page 9: Chapter 2 - Bill of Quantity and Specification

8/12/2019 Chapter 2 - Bill of Quantity and Specification

http://slidepdf.com/reader/full/chapter-2-bill-of-quantity-and-specification 9/18

Construction Contract Administration  and Project Management (CON4371) 

Chapter 2 

 ___________________________________________________________________________________

 ___________________________________________________________________________________

©VTC2013  Page 9 of  18 

6. Use of  Specification 

The  specification  is  read  in  conjunction  with  drawings  and  a  bill  of  

quantities to

 supply

 the

 contractor

 with

 all

 the

 necessary

 information

 he

 

needs to submit a tender and to execute the works. 

The main functions of  the specification are to: 

1) Describe fully the workmanship and materials required to carry out the 

contract. 

The  specification  lays  down  the  quality  of   material,  standard  of  

workmanship,  testing  methods  and  acceptance  criteria  for  construction 

work. 

2)  Avoids  duplication  of   descriptive  information  as  full  descriptions 

appear in a single document which is the specification. 

On  a  construction  job,  the  descriptions  of   items  contained  in  the  bills  of  

quantities should be 

‐  as  brief   as  possible  and  with  frequent  references  to  the  specification 

clauses. 

3) Provide

 details

 of 

 not

 included

 in

 the

 Conditions

 of 

 Contract

 

In  addition  to  the  above,  the  specification  also  contains  details  of   any 

special  responsibilities  of   the  contractor  which  are  not  covered  by  the 

conditions of  contract. 

4) To supplement the information in the drawings 

It is obviously not possible to show everything on the drawings, e.g. specific 

details  of   the  way  materials  are  jointed  or  fixed,  details  of   standard  of  

workmanship required

 etc.

 

Nevertheless  the  information  is  important  for  pricing  and  for  quality 

control and so must be given in the Specification. 

For a well written Specification, it is therefore important that: 

i)  The  specification  and  drawings  are  complete  but  without  excessive 

duplication. Drawings and specification must not contradict each other. 

Page 10: Chapter 2 - Bill of Quantity and Specification

8/12/2019 Chapter 2 - Bill of Quantity and Specification

http://slidepdf.com/reader/full/chapter-2-bill-of-quantity-and-specification 10/18

Construction Contract Administration  and Project Management (CON4371) 

Chapter 2 

 ___________________________________________________________________________________

 ___________________________________________________________________________________

©VTC2013  Page 10 of  18 

6. Use of  Specification (cont’d) 

ii) The specification writer must know what is required‐ this implies a good 

knowledge of 

 construction

 technology,

 both

 the

 way

 in

 which

 works

 fit

 

together and of  construction materials 

iii) The information is presented clearly. 

7. General Arrangement of  Specification 

(a) General Clauses 

Most  specifications  for  civil  engineering  work  begin  with  a  selection  of  

‘general 

clauses’ 

which 

relate 

to 

the 

contract 

as 

whole 

and 

are 

not 

confined to any particular trade or works section. The nature and content 

of  these clauses will vary from project to project. 

An example of  a typical general clause is as follow: ‐. 

Heading: General  Requirements 

• The works to be executed under this Contract are to be carried out in 

accordance with the Conditions of  Contract, Specification, Bill of  Quantities 

and Contract Drawings. 

• If 

 in

 construing

 the

 Contract,

 there

 shall

 appear

 to

 be

 any

 inconsistency

 

between  the  Specification  and  Conditions  of   Contract,  the  Condition  of  

Contract shall prevail. 

• This  clause  draws  the  Contractor’s  attention  to  the  requirements  of   all 

the  Contract  Documents  and  emphasizes  that  the  Conditions  of   Contract 

have precedence over the other contract documents. 

(b) Technical Material and Workmanship Clauses 

The specification

 clauses

 are

 normally

 followed

 by

 materials

 and

 work

 

clauses, which are  related  to  the various  sections of  work making up  the 

 job. 

Material  Descriptions 

Considerable  care  must  be  exercised  in  the  drafting of  a  specification,  to 

prepare clauses, which are concise, complete, and free form ambiguity. 

The  following  alternative  methods  of   describing  materials,  or  a 

combination of 

 them,

 can

 be

 used

 in

 a specification.

 

Page 11: Chapter 2 - Bill of Quantity and Specification

8/12/2019 Chapter 2 - Bill of Quantity and Specification

http://slidepdf.com/reader/full/chapter-2-bill-of-quantity-and-specification 11/18

Construction Contract Administration  and Project Management (CON4371) 

Chapter 2 

 ___________________________________________________________________________________

 ___________________________________________________________________________________

©VTC2013  Page 11 of  18 

7. General Arrangement of  Specification (cont’d) 

Methods of  Describing Materials in Specification Clauses:‐

(1) A

 full

 description

 of 

 the

 material

 is

 given

 with

 details

 of 

 desirable

 and

 

undesirable characteristic and appropriate test requirements 

(2)  Relevant  standard  reference,  together  with  details  of   type  or  class 

required. The contractor can then refer to the specified standard 

(3)  Name  of   manufacturer,  proprietary  brand  or  source  of   supply  stated 

and the contractor can obtain further particulars from the manufacturer or 

supplier. 

(4) Provide the Prime Cost of  the material with brief  description of  supply 

and 

delivery 

of  

certain 

quantity 

of  

the 

material 

to 

the 

site. 

For example: Prime Cost of  to be $2500/m2 (supplied and delivered to site) 

For example, a material description on brick: ‐

Material  Description 

Bricks  Clay bricks 

Name of  manufacturer  as approved by the Engineer 

Or Source of  Supply 

Prime cost  $500.00 per thousand, delivered to 

site 

Desirable characteristics  Well burnt, hard, square, clean, 

sound 

Undesirable characteristic  Free from cracks 

Tests  Minimum compressive strength 

7.0 Mpa. 

Workmanship clauses 

Specification clauses

 covering

 constructional

 work

 and

 workmanship

 

requirement are generally drafted in the imperative and should give a clear 

and concise description of  the character and extent of  the work involved. 

For example as in Clause 25:144(1):‐

Brickwork shall be flushed up with cement mortar to form a level and even 

bed to receive horizontal damp proof  course. 

Page 12: Chapter 2 - Bill of Quantity and Specification

8/12/2019 Chapter 2 - Bill of Quantity and Specification

http://slidepdf.com/reader/full/chapter-2-bill-of-quantity-and-specification 12/18

Construction Contract Administration  and Project Management (CON4371) 

Chapter 2 

 ___________________________________________________________________________________

 ___________________________________________________________________________________

©VTC2013  Page 12 of  18 

8. Classification of  Specification 

(1) Standard

 Specification

 

•  These  are  specification  devised  by  experts  in  their  fields  in  the 

government  departments  and  consulting  engineering  firms  and  they  are 

accepted as authoritative by the construction industry. 

• In Hong Kong, some particular authorities for eg. ASD, Housing 

Authority,  Civil  Engineering  Department  has  comprehensive  standard 

specification which will be issued for every project. 

•  These  standard  requirements  establish  a  uniformity  of   administrative 

procedures 

and 

quality 

in 

material 

and 

workmanship 

for 

constructing 

their 

projects. 

(2) Particular Specification 

•  Standard  specification  is  unable  to  provide  all  of   the  requirements 

needed for a specific contract. 

•  To  fill  this  gap,  another  set  of   specification  called  the  particular 

specifications  are  prepared  by  the  specification  writer  for  the  specific 

project. 

• The

 particular

 specification

 clauses

 present

 requirements

 applicable

 only

 

to that specific contract. 

• This  is often achieved by amending the standard specification by adding 

to them, deleting from them, or modifying them. 

•  The  combined  use  of   the  above  two  specifications  enables  the  speedy 

readiness of  specification suitable to the project. 

9. Types of  Specification 

1) Performance Specification 

•  Performance  specifications  are  sometimes  called  End  Product 

Specifications or End Result Specifications. 

• They specify standards and criteria, and the end results to be obtained. 

•  Performance  specification  does  not  normally  prescribe  dimensions, 

materials or methods of  manufacture, instead, the desired quality; function 

and other

 characteristics

 of 

 the

 product

 are

 specified.

 

Page 13: Chapter 2 - Bill of Quantity and Specification

8/12/2019 Chapter 2 - Bill of Quantity and Specification

http://slidepdf.com/reader/full/chapter-2-bill-of-quantity-and-specification 13/18

Construction Contract Administration  and Project Management (CON4371) 

Chapter 2 

 ___________________________________________________________________________________

 ___________________________________________________________________________________

©VTC2013  Page 13 of  18 

9. Types of  Specification (cont’d) 

•  By  specifying  the  performance  requirements,  it  becomes  the 

responsibility of 

 the

 contractor

 to

 select

 the

 materials

 and

 methods

 to

 

achieve the end result. 

Advantages: 

(a) Some control of  design passes to the contractor. 

(b) Many new ideas are encouraged. 

(c) New materials or component can be incorporated. 

(d) Contractor uses methods or plant familiar to himself  

(e) 

Period 

for 

design 

may 

be 

reduced 

as 

helpful 

in 

eliminating 

lot 

of  

detailed instructions for construction procedures. 

Disadvantages 

(a)  Comparison  of   tenders  is  less  certain  due  to  variation  in  contractors’ 

specification. 

(b) Cost of  project may await tenders, as Engineer’s guide prices may not 

apply 

2) Proprietary Specification 

•  It  restricts  products  to  be  manufactured  in  accordance  with  a  defined 

method or system 

•  An  Engineer  will  after  many  years  in  business,  acquire  first  hand 

knowledge  on  the  performance  of   various  products  and  items  of  

equipment. 

•  He  utilises  this  knowledge  to  guide  him  in  specifying  projects.  He  will 

specified certain

 methods,

 or

 products

 or

 item

 of 

 equipment

 by

 its

 brand

 

name, manufacture. 

• Sometimes, in order to avoid any chance of  favouritism and minimise the 

restriction on competition, the phrase “equal and approved” is used in the 

Specification. 

Advantages 

a) The Engineer exercises maximum control 

b) All

 tenders

 are

 on

 the

 same

 basis

 

Page 14: Chapter 2 - Bill of Quantity and Specification

8/12/2019 Chapter 2 - Bill of Quantity and Specification

http://slidepdf.com/reader/full/chapter-2-bill-of-quantity-and-specification 14/18

Construction Contract Administration  and Project Management (CON4371) 

Chapter 2 

 ___________________________________________________________________________________

 ___________________________________________________________________________________

©VTC2013  Page 14 of  18 

9. Types of  Specification (cont’d) 

c) Cost of  project based on the Engineer’s method or specified proprietary 

system of 

 products

 

d) Ensure Engineer’s familiarity with the design 

Disadvantages 

(a) The specified method may not be familiarised by the Contractor 

(b) Reduced the opportunity for other alternatives which may be more cost 

effective 

(c)  There  may  be  time  where  is  it  impossible  or  impractical  to  make  an 

exhaustive 

study 

within 

the 

design 

period 

to 

draw 

up 

list 

of  

proprietary 

system 

3) Descriptive Specification 

•  Descriptive  specifications  are  most  common  in  civil  engineering 

construction works. 

•  This  type  of   Specification  will  provide  detailed  description  of   required 

materials and their properties without specifying brand names. 

• 

It 

will 

also 

provide 

construction 

details 

and 

the 

desired 

quality 

of  

workmanship. 

•  Descriptive  specifications  are  sometimes  called  Material  and 

Workmanship Specification. 

Advantages 

(a) Control can be imposed on both quality and performance 

(b) Contractor can use material and equipment familiar to himself  

(c) Common

 basis

 has

 been

 provided

 for

 comparison

 of 

 tenders

 

Disadvantages 

(a) Cost of  project can be affected largely by the material or equipment 

used by the Contractor 

(b) Greater supervision is needed. 

Page 15: Chapter 2 - Bill of Quantity and Specification

8/12/2019 Chapter 2 - Bill of Quantity and Specification

http://slidepdf.com/reader/full/chapter-2-bill-of-quantity-and-specification 15/18

Construction Contract Administration  and Project Management (CON4371) 

Chapter 2 

 ___________________________________________________________________________________

 ___________________________________________________________________________________

©VTC2013  Page 15 of  18 

10. Format of  Specification for Material 

In specifying for material, there are two formats which are in use: 

1) Close Specification 

•  A  close  specification  is  one  which  the  description  of   material  is  so 

detailed that only one product can qualify for use. 

•  A  specification  provided  by  the  Manufacturer  is  usually  a  closed 

specification, or 

• In cases whereby the contract has specified for materials to be provided 

by Nominated Supplier is also a closed specification. 

• 

Its 

purpose 

is 

to 

ensure 

that 

only 

construction 

products 

of  

desired 

quality are provided by the Contractor. 

• However, close specification will reduce competition in prices. 

2) Open Specification 

•  An  open  specification  is  worded  in  such  a  way  that  the  products  of  

various  Manufacturers  are  acceptable,  provided  that  they  can  meet  the 

specified function and quality standards. 

•  It allows substitution by specifying materials  followed by wordings such 

as “approved

 equal”.

 

•  It  is  useful  when  cost  savings  is  possible  or  when  the  availability  of  

material is uncertain. 

•  This  type  is  usually  often  used  in  Government  contracts  where  open 

competition is preferred. 

Sources of  Writing for Specification Writing 

Information for use in civil engineering specifications can be obtained from 

a variety

 of 

 sources.

 The

 principal

 sources

 of 

 information

 are

 as

 described:

 

(1) Previous Specification 

In the majority of  cases, specification for past projects is used as a basis in 

the preparation of  a new specification for a  job of  similar type. 

When  looking  for  a  previously  prepared  specification,  one  should  be 

selected to commensurate with the magnitude of  the future project. 

Page 16: Chapter 2 - Bill of Quantity and Specification

8/12/2019 Chapter 2 - Bill of Quantity and Specification

http://slidepdf.com/reader/full/chapter-2-bill-of-quantity-and-specification 16/18

Construction Contract Administration  and Project Management (CON4371) 

Chapter 2 

 ___________________________________________________________________________________

 ___________________________________________________________________________________

©VTC2013  Page 16 of  18 

10. Format of  Specification for Material (cont’d) 

For example:

 a concrete

 specification

 for

 a dam

 construction

 would

 not

 be

 

appropriate to use for construction of  a simple building. 

The use of  previous specification expedites the task of  specification writing 

but  care  must  be  taken  to  bring  the  specification  clauses  to  date  by  the 

incorporation  of   the  latest  developments  and  techniques  for  the  work 

concerned. 

In 

addition, 

clauses 

have 

to 

be 

modified 

to 

suit 

the 

design, 

construction 

in 

the current  job. Generally, details which are not applicable are omitted and 

to insert information on additional features. 

(2) Contract Drawings 

The draft contract drawings will be prepared in advance of  the specification 

and these will show the character and extent of  the work. 

The specification writer will extract a considerable amount of   information 

from  the  drawings  and  will  work  systematically  through  them  when 

compiling the

 specification.

 

(3) Employer’s Requirement 

The  employer  or  client  often  lays  down  requirements  in  connection  with 

the  project  and  these  will  probably  need  to  be  incorporated  in  the 

specification. 

Typical requirements of  this kind are the programming of  the works as to 

provide for

 completion

 of 

 certain

 sections

 of 

 works,

 taking

 of 

 precautions

 

so as to minimize interference with existing facilities etc. 

Requirements of  this nature will be reflected in the General Clauses of  the 

specification and should be to notice of  the contractors they may result in 

increased cost. 

Page 17: Chapter 2 - Bill of Quantity and Specification

8/12/2019 Chapter 2 - Bill of Quantity and Specification

http://slidepdf.com/reader/full/chapter-2-bill-of-quantity-and-specification 17/18

Construction Contract Administration  and Project Management (CON4371) 

Chapter 2 

 ___________________________________________________________________________________

 ___________________________________________________________________________________

©VTC2013  Page 17 of  18 

10. Format of  Specification for Material (cont’d) 

(4) Site

 Investigation

 

Some  of   the  information  inserted  in  a  specification  will  arise  from  site 

investigation such as  information on soil conditions and water  table  level 

and site clearance work. 

The contractor should be supplied with any relevant information to reduce 

the risks and the number of  uncertain factors in his tender. 

(5) 

British 

Standards 

The  use  of   British  standard  in  the  specification  clause  permits  a 

considerable  reduction  in  the  length  of   clauses  relating  to  materials  and 

components and products. 

It also eliminates the contractor from reading lengthy descriptive clauses in 

the  specification.  The  standards  are  prepared  by  the  British  Standards 

Institution  which  is  the  approved  body  for  the  preparation  of   a  national 

standard  covering  methods  for  tests,  terms,  definitions,  standards  of  

quality, of 

 performance,

 dimensions

 etc.

 

British  Standards  prescribe  the  recognised  standards  of   quality  and  of   a 

great  value  in  drafting  specification  as  they  reduce  the  amount  of  

descriptive works yet at the same time ensure a good quality product. 

(6) Codes of  Practice 

Specification clauses sometimes refer to relevant codes of  practice to 

ensure good

 standard

 of 

 construction

 and

 workmanship

 without

 the

 need

 

for lengthy specification clauses. 

Codes of  Practice cover design, construction and maintenance aspect. Their 

contents are widely known and recognised as a mean to secure  improved 

standards of  works in the respective field. 

Page 18: Chapter 2 - Bill of Quantity and Specification

8/12/2019 Chapter 2 - Bill of Quantity and Specification

http://slidepdf.com/reader/full/chapter-2-bill-of-quantity-and-specification 18/18

Construction Contract Administration  and Project Management (CON4371) 

Chapter 2 

 ___________________________________________________________________________________

 ___________________________________________________________________________________

©VTC2013  Page 18 of  18 

10. Format of  Specification for Material (cont’d) 

(7) Trade

 Catalogues

 

When materials of  proprietary brands are used in a  job, reference is often 

made  to  the  manufacturers’  catalogues  for  specifying  the  necessary 

information in the specification. 

This procedure will shorten the length of  the specification clause and at the 

same time ensured the use of  a specific material with which the Engineers 

familiar and in which he has full confidence.