Chapter 13Progress and Performance
Measurement and Evaluation
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 2/94
Earned Value Glossary of TermsAC The actual cost of the work completed. The sum of the costs incurred
in accomplishing work. (Also called ACWP — actual cost of the work performed).
BAC Budgeted cost at completion. The total budgeted cost of the baseline or project cost accounts.
BCWP Older acronym for EV: Budgeted cost of the work performed. The earned valueor original budgeted cost for work actually completed.
BCWS Budgeted cost of the work scheduled. A cost estimate of theresources scheduled in a time-phased cumulative baseline.
CV Cost variance - the difference between the earned value and the actual costsfor the work completed to date where CV=EV-AC. (or BCWP - ACWP).
EAC Estimated costs at completion. Includes cost to-date plus
revised estimated costs for the work remaining.
ETC Estimate to complete
EV Percent complete times its original budget. The percent of the original budget that has been earned by actual work completed.
The older acronym for this value was BCWP — budgeted cost of the work
performed.
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 3/94
Glossary of Terms (Continued)
FAC Computed forecasted costs at completion
PV Planned Value - the time-phased baseline of the value of the work scheduled. Anapproved cost estimate of the resources scheduled in a time-phasedcumulative baseline (or old: BCWS).
SV Schedule variance - the difference between the earned value and the baseline line to date where SV=EV-PV.
(or old: BCWP - BCWS).
VAC Cost variance at completion (BAC-EACe), where EACe is derived by estimatorsin the field.
Or, alternatively, cost variance at completion (BAC-EACf ), where EACf isderived from a formula using actual and earned value costs.
(or BAC - FAC).Indicates expected actual over or underun at completion
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 4/94
Project Management System
Overview
FIGURE 13.3
Earned Value Process
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 5/94
Project Monitoring and Control
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 6/94
Project Control Monitoring System
Data Needed• Current status of project
• Cost to compete project
• Date of Completion
• Potential problems
• Out-of-control activities
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 7/94
Project Monitoring System… (cont’d)
Data Collection
• Who
• How
• When
Data Analysis
– Reports and reporting
• Receiver
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 8/94
Project Progress Report
• Progress since last report
• Current status of project –
• Cumulative trends
• Problems and issues since last report
• Corrective action planned
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 9/94
Project Control Process
• Control Definition
– Process of comparing actual
performance against the original plan toidentify:
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 10/94
Project Control Process (Cont’d)
• Project Control Steps
1.Set a baseline plan
2.Measure progress and performance
3.Compare plan against actual
• 4.
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 11/94
Time Performance
• Tools to catch negative variances from plan
and communicate project schedule status:
– Tracking and baseline Gantt charts
• Show expected, actual, and trend data for event
duration performance.
– Control charts
• Plot the difference in scheduled time on the critical
path with the actual point on the critical path.
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 12/94
Baseline and Tracking Gantt Charts
FIGURE 13.1
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 13/94
Project Schedule Control Chart
FIGURE 13.2
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 14/94
Earned Value (EV) System
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 15/94
Project Monitoring System
(Earned Value - EV)• Current status of project (Schedule and
cost)
• Cost to complete
• Project Completion
• Potential problems addressed now
• Causes for cost / schedule overruns
• Value for dollars spent
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 16/94
Earned Value (EV)
• Earned Value Cost/Schedule System
– An integrated project management system
based on the earned value concept that uses atime-phased budget baseline to compare actual
and planned schedule and costs.
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 17/94
Earned Value (EV)
• Depends on data from
– WBS
• Time phased budget ofr each task
• New estimates of percent complete (realistic)
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 18/94
Earned Value (EV)
• % of original budget that has been earned
by actual work completed
– Old - BCWP – Budgeted cost of work performed
– The anchor for comparing to baseline
• EV Usage
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 19/94
Steps in an EV Control Process
• Step 1: Set a baseline
• Step 2: Measure progress and performance
• Step 3: Comparing actual against a baseline plan
• Step 4: Taking action
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 20/94
Project Baselines
• Purposes of a Baseline (EV) (also BCWP) – A point for measuring performance
• A planned cost and expected schedule against which
actual cost and schedule are measured.• A basis for cash flows and awarding progress payments.
• A summation of time-phased budgets (cost accounts as
summed work packages) along a project timeline.
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 21/94
Baseline Costs
• Labor
• Equipment
• Materials
• Project direct overhead costs (DOC)
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 22/94
Baseline Data Relationships
FIGURE 13.4
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 23/94
Rules for Costs in Baseline
• Percent Complete
– Most common on larger projects
• Will use for this course
• 0-100 Percent Rule
– Credit earned after work is complete
• Ie: 100% of budget earned at completion
– Used on projects with very short duration
• 50/50 Rule
– 50% of money up front
– 50% of money at completion
• Used on projects with short duration and small total costs
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 24/94
Variance Analysis Control
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 25/94
Variance Analysis• Earned Value Comparison
• With the expected schedule value.
• With the actual costs.
• Assessment Status of a Project
• Required data elements – Data Budgeted cost of the work scheduled (PV)
– Budgeted cost of the work completed (EV)
– Actual cost of the work completed (AC)
• Schedule and cost variance calculation – Positive variance - a desirable condition,
– Negative variance - problems
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 26/94
Methods of Variance Analysis
• Cost Variance (CV)
– Indicates if:
• Work accomplished using labor and materials costsmore or less than planned at any point in the project
• Schedule Variance (SV)
– Presents:• Overall assessment in $ of the progress of all WP’s in
the project scheduled to date.
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 27/94
Cost Variance
• Difference between earned value and actual
costs
– ACWP – Actual cost of work performed
• CV = EV – AC
Anchor
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 28/94
Schedule Variance
• Difference between earned value to date
and the baseline schedule (BCWS)
– BCWS – Budgeted cost of work scheduled
• SV = EV - PV
Anchor
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 29/94
New
Cost/Schedule Graph
FIGURE 13.5
Old13 7
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 30/94
OldCost/Schedule Graph
13-7
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 31/94
Old vs New Cost Schedule Graph
New Old
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 32/94
NewEarned Value Review
FIGURE 13.6Make Sure to Understand
13-8
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 33/94
OldEarned-Value Review
13-8
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 34/94
Status Report:A Hypothetical Example
• Assumptions to the hypothetical example
– Each cost account has only one work package, and
each cost account will be represented as an activity on
the network. – The project network early start times will serve as the
basis for assigning the baseline values.
– Baseline value will be assigned linearly, unless stated
differently.
– From the moment work on an activity begins, some
actual costs will be incurred each period until the
activity is completed.
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 35/94
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 36/94
5 steps - A Must For:
Integration of Cost/Schedule SystemStep 1: Define work with WBS
• Scope
• Work packages
• Deliverables
• Budgets for each work package
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 37/94
5 steps - A Must For:
Integration of Cost/Schedule SystemStep 2: Develop work and resource schedules
– Time phased work packages into network
– Schedule resources to activities
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 38/94
5 steps - A Must For:
Integration of Cost/Schedule SystemStep 3: Develop a time phased budget
– Use Work Packages
– Accumulation of these values becomes a baseline PV (or BCWS)
– Collect budgeted cost for work accomplished
• E V (or BCWP)
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 39/94
5 steps - A Must For:
Integration of Cost/Schedule System• Step 4: Collect actual costs at WP level
– Costs that are actually experienced
• Actual cost of work performed AC (or ACWP)
– Collect earned value or budgeted cost of work
performed
• (EV)
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 40/94
5 steps - A Must For:
Integration of Cost/Schedule SystemStep 5: Compute SC and CV
– SV = EV – PV
– CV = EV – AC
– Prepare Reports for management
• Project roll-ups
– Organization – Deliverable
– Actual time performance of project checked against the
network schedule
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 41/94
Baseline
• Anchor
• Set in concrete
• Building blocks
– Placement of work packages into network
• Establishes start times of work packages
• Time phases budgets from work package estimates
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 42/94
Baseline Budget
• Budgeted cost of work performed
– EV or BCWP
– Sum of all cost accounts• Sum of all work packages for the cost account
• Three typical costs
– Materials
– Labor and Equipment
– Level of Effort (LOE)
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 43/94
Level of Effort
• LOE
– Administrative support
– Computer support
– Legal support
– Public Relations
• Often 10 to 20% of a project
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 44/94
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 45/94
Digital Camera Prototype Project Baseline
FIGURE 13.9
Di it l C P t t St t
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 46/94
Digital Camera Prototype Status
Reports: Periods 1 – 3
TABLE 13.2
Digital Camera Prototype Status
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 47/94
Digital Camera Prototype StatusReports: Periods 4 – 6
TABLE 13.2 (cont’d)
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 48/94
Digital Camera Prototype Status
Reports: Period 7
TABLE 13.2 (cont’d)
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 49/94
Digital Camera Prototype Summary
Graph (in $000)
FIGURE 13.10
Digital Camera Project Tracking Gantt
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 50/94
Digital Camera Project Tracking Gantt
Chart
Showing Status — Through Period 7
FIGURE 13.11
Digital Camera
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 51/94
Digital Camera
Project Rollup at End
Period 7 (000)
FIGURE 13.12
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 52/94
Indexes to Monitor Progress
• Performance Indexes
– Cost Performance Index (CPI)
• Measures the cost efficiency of work accomplished todate.
• CPI = EV/AC
– Scheduling Performance Index (SPI)
• Measures scheduling efficiency
• SPI = EV/PV
– Percent Complete Indexes
• Indicates how much of the work accomplished
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 53/94
Interpretation of Indexes
TABLE 13.3
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 54/94
Indexes
Periods 1 – 7
FIGURE 13.13
13-9
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 55/94
Hypothetical Work Organizational Structure
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 56/94
Example
Example Project Network Plan13-10
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 57/94
Example Project Network Plan
Total Cost = 6
Total Cost = 20
Total Cost = 30
Total Cost = 24
Total Cost = 16
Total Cost = 9
Total Cost = 16Total Cost = 18
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 58/94
E l P j t B li B d t
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 59/94
Example Project Baseline Budget
PV
EV
EV
Example Project Baseline Budget
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 60/94
p j g
PV
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 61/94
Example Project Baseline Budget
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 62/94
p j g
PV
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 63/94
Example Project Baseline Budget
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 64/94
PV
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 65/94
Example Project Baseline Budget
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 66/94
PV
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 67/94
Example Project Baseline Budget
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 68/94
Estimated
Cost at
Completion
PV
PV
PV
Example Project
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 69/94
Example Project Now work has begun, are at the end of
time period 4
Example ProjectStatus Report at The End of Time Period 4
13-12
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 70/94
Status Report at The End of Time Period 4
PVEV
AC
Example ProjectStatus Report at The End of Time Period 4
13-12
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 71/94
Status Report at The End of Time Period 4
EVPV
EV
AC
Example ProjectStatus Report at The End of Time Period 4
13-12
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 72/94
Status Report at The End of Time Period 4
EVPV
EV
AC
Example ProjectStatus Report at The End of Time Period 4
13-12
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 73/94
Status Report at The End of Time Period 4
EVPV
EV
AC
Example ProjectStatus Report at The End of Time Period 4
13-12
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 74/94
Status Report at The End of Time Period 4
EVPV
EV
AC
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 75/94
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 76/94
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 77/94
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 78/94
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 79/94
Example ProjectStatus Report at The End of Time Period 4
13-12
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 80/94
p
EVPV
EV
AC
AC
AC
EV (CV= EV – AC)
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 81/94
Example Project Baseline Budget
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 82/94
Example Project Baseline Budget
PV
EV
EV
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 83/94
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 84/94
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 85/94
Scope Changes to a Baseline13-17
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 86/94
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 87/94
Forecasting Final Project Cost
• Methods used to revise estimates of future
project costs:
– EACe• Allows experts in the field to change original baseline
durations and costs because new information tells
them the original estimates are not accurate.
– EACf • Uses actual costs-to-date plus an efficiency index to
project final costs in large projects where the original
budget is unreliable.
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 88/94
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 89/94
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 90/94
Performance Equations
• CPI – Cost performance index
– CPI = EV / AC – Worth of work planned to date for each dollar actually
spent» Greater than one - good
• SPI – Scheduling performance index
– SPI = EV / PV – Worth of work accomplished for each dollar worth of
scheduled work to date
» Greater than one - good
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 91/94
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 92/94
Percent Complete Index
• PCI-C –
– Percent complete in terms of actual dollarsspent to accomplish the work to date and theactual expected dollars for the completed
project (EAC).
– PCI-C = AC/EAC
• Indicates percent of project completed, when viewedfrom the actual dollars spent to complete the work todate and the revised actual expected costs tocomplete the project.
7/30/2019 Chapter 13 g3 2005 Student 5 12
http://slidepdf.com/reader/full/chapter-13-g3-2005-student-5-12 93/94
Scope Creep
• Minor Refinements
1 + 1 + 1 becomes 4 or greater
Build to big problems
7/30/2019 Chapter 13 g3 2005 Student 5 12