OFFICE OF STRUCTURES STRUCTURAL DETAIL MANUAL
Chapter 11 - Structural Repairs
SECTION 02
CONCRETE REPAIRS (SR-CR)
DATE:
STATE HIGHWAY ADMINISTRATION
DEPARTMENT OF TRANSPORTATION
STATE OF MARYLAND
SHEET OF
APPROVAL
L
L/6 L/6L/3 L/3 Removal limits
for each segment
Deck
Abutment
or pier
A
AGirderAbutment
or pier
CONCRETE GIRDER
ELEVATION
Scale: None
Deck
Remove to sound concrete
Rebuild to these lines (typ.)
6’’ Max.
(typ.)D
W/2 W/2
W
Scale: None
SECTION A-A
A B/3 B/3 B/3
B
B
BCap
ColumncColumnc
F/2 F/2
F
E
6’’ Max. (typ.)
Scale: None
ELEVATION - PIER CAP
Scale: None
SECTION B-B
1.
2.
3.
4.
5.
6.
7.
8.
Section 2Section 1
Section 1 Section 2
Removal limits
for each segment
to these lines, 6’’ maximum (typ.)
DIRECTOR
OFFICE OF STRUCTURES
OFFICE OF STRUCTURES
Verify that the final clearance of all rebar is
2’’ min. The formwork shall be shifted, as
needed to provide 2’’ clearance at all repair areas.
9.
CAST-IN-PLACE CONCRETE
1 2
Note:
D and W are original
girder dimensions.
Note:
E and F are original
pier cap dimensions.
Remove to sound
concrete to these
lines, 6’’ maximum (typ.)
Rebuild to these
lines (typ.)
SR-CR-101
Notes:
Concrete elements are divided into segments. Work
to be performed on sections as provided below.
Refer to Sections 420, 421, and 423.03.
Contractor shall stage the work so that the
worse sections are repaired first.
Contractor shall not work on more than two
nonadjacent sections on each pier cap, column,
or girder at one time.
Contractor shall wait 72 hours after completing
repairs to a section before chipping adjacent
sections, however he may perform
work on other bridge elements.
Contractor shall stop removing
deteriorated concrete when a
maximum depth of 6 in. is reached.
The Engineer shall immediately notify
the Office of Structures if more
removal seems necessary.
Existing reinforcing steel not shown.
For column repair details,
see sheet 2 of 2.
SEQUENCE AND REPAIR DETAILS FOR PIER CAP
ST
RU
CT
UR
AL
RE
PA
IRS
1.0
VERSION
DETAIL NO.
06/28/2017
APPROVAL
H
Vert
ical
rem
ov
al
lim
its
for e
ach s
egm
ent
Bottom of pier cap
CC
ELEVATION
Scale: None
PIER COLUMN
120^
120^ 120^
D6’’ Max. (typ.)
CIRCULAR COLUMN
M
N
6’’ Max. (typ.)
SQUARE COLUMN
Scale: None
SECTION C-C
Section 1
Section 2
Section 3
Section 4
Section 1
Section 3
DIRECTOR
Remove to sound
concrete to these
lines, 6’’ maximum (typ.)
OFFICE OF STRUCTURESSTATE HIGHWAY ADMINISTRATION
DEPARTMENT OF TRANSPORTATION
STATE OF MARYLAND
SHEET OF
OFFICE OF STRUCTURES
CAST-IN-PLACE CONCRETE
2 2
Existing groundline
and/or top of footing
Note:
D is original
diameter
of column.
Rebuild to these
lines (typ.)
Note:
M and N are original
column dimensions.
Horizontal removal
limits for each
section
Horizontal
removal limits
for each
section
Section 2
Remove to sound
concrete to these
lines, 6’’ maximum (typ.)
Rebuild to these
lines (typ.)
SR-CR-101
12
’ M
ax.
12
’ M
ax.
12
’ M
ax.
Notes:
1. When height of columns is more than
12 ft., the Contractor will be
restricted to 12 ft. segments.
2. Refer to Sections 420, 421 and 423.03.
3. For notes, see sheet 1 of 2.
4. The most deteriorated section of
the column shall be repaired first.
5. The engineer shall identify the
order with which the sections are
to be repaired.
DATE:
SEQUENCE AND REPAIR DETAILS FOR PIER COLUMN
ST
RU
CT
UR
AL
RE
PA
IRS
1.0
VERSION
DETAIL NO.
06/28/2017
STATE HIGHWAY ADMINISTRATION
DEPARTMENT OF TRANSPORTATION
STATE OF MARYLAND
OF
OFFICE OF STRUCTURES
Note
s:
1.
2.
3.
Scale
: 1
’’ =
1’-
0’’
SEC
TIO
N
Join
t openin
g
4’’
min
.
*
*
*
*
*
Ex
isti
ng
co
ncrete
deck
See N
ote
5 (
typ.)
Depth
of d
ete
rio
rati
on
vari
es
4.
5.
6.
*D
iap
hra
gm
rein
forc
em
en
t sh
ow
n i
s
typic
al.
The r
ein
forcem
ent
patt
ern
may v
ary
.
The c
ontr
acto
r s
hall
conta
ct
the
engin
eer i
f t
he d
ela
min
ate
d c
oncrete
in t
he e
nd
dia
ph
rag
m i
s d
eep
er t
han
the b
ott
om
of t
he d
eck
.
Ex
isti
ng
bars a
s
sh
ow
n
Exis
ting t
russ b
ars
Exis
ting S
IP f
orm
and
dia
ph
rag
m
Ex
isti
ng
sti
rru
ps
Salv
age e
xis
ting s
teel
rein
forcm
ent
bars
.
Cle
an a
nd e
poxy c
oat
exis
ting
rein
fo
rcem
en
t b
ars.
Ad
d a
dd
itio
nal
rein
forc
men
t as i
n
acco
rdan
ce w
ith
Secti
on
42
1.0
3.0
7.
Pie
r deta
il show
n, abutm
ent
deta
il
sim
ilar.
Anchor
edge o
f re
main
ing S
IP f
orm
wit
h
5/8
’’
dia
. g
alv
an
ized
co
ncre
te
anchors
@ 2
’-0’’
c/c
,
4’’
em
bedm
ent.
Refe
r to
Secti
on
42
3.0
3.0
3.
SHEET 1 1SR-CR-102
APPROVAL
DIRECTOR
OFFICE OF STRUCTURES
DATE:
CAST-IN-PLACE CONCRETE REPAIR TOCONCRETE DIAPHRAGM
SECTION AT PIER
Rem
ov
e S
IP t
o r
ep
lace
co
ncrete
to
th
e b
ott
om
of t
he d
iap
hrag
m
Ex
isti
ng
dete
rio
rate
d
concrete
to b
e r
em
oved
and r
epla
ced w
ith t
row
el
grad
e m
orta
r o
r c
ast-
in-p
lace
Mix
No
. 5
co
ncre
te (
or
eq
ual)
.
Ex
isti
ng
ste
el
str
inger/g
irder
*U
se t
ro
wel
grad
e m
orta
r w
hen
th
e
depth
of t
he c
oncrete
rem
oval
or
spall
is l
ess t
han 1
" d
eep, or t
he
volu
me o
f t
he c
oncrete
rem
oval
an
d/o
r s
pall
is l
ess t
han
1 c
ub
ic f
t.
oth
erw
ise, use M
ix N
o. 5 (
or
equal)
co
ncrete
.
1.0
VERSION
DETAIL NO.
06/28/2017
ELEVATION
Scale: None
Existing
pier
Scale: None
SECTION B-B
Remove to sound
concrete to these
lines, 6’’ maximum (typ.)
B B
Scale: None
Remove to sound
concrete to these
lines, 6’’ maximum (typ.)
A A
SECTION A-A
T
T
STATE HIGHWAY ADMINISTRATION
DEPARTMENT OF TRANSPORTATION
STATE OF MARYLAND
SHEET OF
APPROVAL
1.
2.
3.
4.
5.
6.
7.
ST
RU
CT
UR
AL
RE
PA
IRS
OFFICE OF STRUCTURES
DIRECTOR
OFFICE OF STRUCTURES
2 Pier2 Pier
1
2
2 12
2
Sequence of
construction
(typ.)
1
CONCRETE PIER WALLDenotes location of
deteriorated concrete
1
The limits of
removal and
repair at the
interior of the
pier wall shall
be determined
by the Engineer
Length of pier
cap repair
A
C
B
Repair
sections
(typ.)
A
B
B
C
6’’ Max. (typ.)
C
6’’ Max. (typ.)
Sequence of
construction (typ.)
Note:
T is the original
thickness of the
pier.
Removal limits for
each section of
concrete repair (typ.)
6’’ max. (typ.)
see Section
B-B
6’-0’’ min.6’-0’’ min.3’-0’’ max. 3’-0’’ max.
3’-0’’ max.
Repair sections (typ.)
SR-CR-103
Notes:
Concrete elements are divided into segments. Work to be
performed on sections as provided above.
Refer to Sections 420, 421, and 423.03.
Contractor shall stage the work so that repair sections
are completed following the number sequence: 1, 2, 3, ....,
shown in the Elevation View, and the letter sequence:
A, B, C, ..., shown in the Section Views.
Contractor shall wait 72 hours after completing repairs to
a section before chipping adjacent sections, however he
may perform work on other bridge elements.
The existing concrete shall be removed to
2’’ min. behind the existing reinforcement.
Contractor shall stop removing
deteriorated concrete when a
maximum depth of 6 in. is reached.
The Engineer shall immediately notify
the Office of Structures if more
removal seems necessary.
Existing reinforcing steel not shown.
DATE:
CAST-IN-PLACE CONCRETE SEQUENCE AND REPAIR DETAILS FOR CONCRETE PIER WALL
1
1.0
VERSION
DETAIL NO.
06/28/2017
L
L/6 L/6L/3 L/3 Removal limits
for each segment
Deck
Abutment
or pier
A
AGirderAbutment
or pier
CONCRETE GIRDER
ELEVATION
Scale: None
Deck
Remove to sound concrete
Rebuild to these lines (typ.)
6’’ Max.
(typ.)D
W/2 W/2
W
Note:
D and W are original
girder dimensions.
Scale: None
SECTION A-A
A B/3 B/3 B/3
B
B
BCap
ColumncColumnc
F/2 F/2
F
E
6’’ Max. (typ.)
New wire
fabric
Scale: None
ELEVATION - PIER CAP
Scale: None
SECTION B-B
1.
2.
3.
4.
5.
6.
7.
8.
Section 2Section 1
Note:
E and F are original
pier cap dimensions.
Section 1 Section 2
Removal limits
for each segment
to these lines, 6’’ maximum (typ.)
Remove to sound
concrete to these
lines, 6’’ maximum (typ.)
Rebuild to these
lines (typ.)
New wire fabric
Note:
For new wire fabric
refer to 908.08.
DATE:
STATE HIGHWAY ADMINISTRATION
DEPARTMENT OF TRANSPORTATION
STATE OF MARYLAND
SHEET OF
APPROVAL
ST
RU
CT
UR
AL
RE
PA
IRS1
Notes:
Concrete elements are divided into segments. Work
to be performed on sections as provided below.
Refer to Section 423.
Contractor shall stage the work so that the
worse sections are repaired first.
Contractor shall not work on more than two
nonadjacent sections on each pier cap, column,
or girder at one time.
Contractor shall wait 72 hours after completing
repairs to a section before chipping adjacent
sections, however he may perform
work on other bridge elements.
Contractor shall stop removing
deteriorated concrete when a
maximum depth of 6 in. is reached.
The Engineer shall immediately notify
the Office of Structures
if more removal seems necessary.
Existing reinforcing steel not shown.
For column repair details,
see sheet 2 of 2.
OFFICE OF STRUCTURES
DIRECTOR
OFFICE OF STRUCTURES
SR-CR-201
PNEUMATICALLY APPLIED MORTARSEQUENCE AND REPAIR DETAILS FOR PIER CAP
2
1.0
VERSION
DETAIL NO.
06/28/2017
2
DATE:
STATE HIGHWAY ADMINISTRATION
DEPARTMENT OF TRANSPORTATION
STATE OF MARYLAND
SHEET
APPROVAL1.
2.
H
Vert
ical
rem
ov
al
lim
its
for e
ach s
egm
ent
Bottom of pier cap
CC
Existing groundline
and/or top of footing
ELEVATION
Scale: None
PIER COLUMN
120^
120^ 120^
D
New wire
fabric
6’’ Max. (typ.)
CIRCULAR COLUMN
Note:
D is original
diameter
of column.
M
N
6’’ Max. (typ.)
Rebuild to these
lines (typ.)
SQUARE COLUMN
Note:
M and N are original
column dimensions.
Scale: None
SECTION C-C
Horizontal removal
limits for each
section
Section 1
Section 2
Section 3
New wire
fabric
Section 4
Section 1
Horizontal
removal limits
for each
section
Section 2
Section 3
Remove to sound
concrete to these
lines, maximum (typ.)
Note:
For new wire fabric
refer to 908.08.
3.
Remove to sound
concrete to these
lines, 6’’ maximum (typ.)
Rebuild to these
lines (typ.)
ST
RU
CT
UR
AL
RE
PA
IRS
DIRECTOR
OFFICE OF STRUCTURES
OFFICE OF STRUCTURES
12’
MA
X.
12’
MA
X.
12’
MA
X.
Notes:
When height of columns is more than
12 ft., the Contractor will be
restricted to 12 ft. segments.
Refer to Section 423.
For notes, see sheet 1 of 2.
SR-CR-201
PNEUMATICALLY APPLIED MORTARSEQUENCE AND REPAIR DETAILS FOR PIER COLUMN
OF 2
1.0
VERSION
DETAIL NO.
06/28/2017
STATE HIGHWAY ADMINISTRATION
DEPARTMENT OF TRANSPORTATION
STATE OF MARYLAND
SHEET OF
OFFICE OF STRUCTURES
Note
s:
1.
2.
3.
Scale
: 1
’’ =
1’-
0’’
SEC
TIO
N
Join
t openin
g
4’’
min
.
*
*
*
*
*
Ex
isti
ng
co
ncrete
deck
See N
ote
5 (
typ.)
Depth
of d
ete
rio
rati
on
vari
es
4.
5.
6.
*D
iap
hra
gm
rein
forc
em
en
t sh
ow
n i
s
typ
ical.
Th
erein
fo
rcem
en
t p
att
ern
may v
ary
.
The c
ontr
acto
r s
hall
conta
ct
the
engin
eer i
f t
he d
ela
min
ate
d c
oncrete
in t
he e
nd
dia
ph
rag
m i
s d
eep
er t
han
the b
ott
om
of t
he d
eck
.
Ex
isti
ng
bars a
s
sh
ow
n
Exis
ting t
russ b
ars
Exis
ting S
IP f
orm
and
dia
ph
rag
m
Ex
isti
ng
sti
rru
ps
Rem
ov
e S
IP t
o r
ep
lace
co
ncrete
to
th
e b
ott
om
of t
he d
iap
hrag
m
Ex
isti
ng
dete
rio
rate
d
concrete
to b
e r
em
oved
an
d r
ep
laced
wit
h
Pn
eu
mati
call
y
ap
pli
ed
mo
rtar.
Ex
isti
ng
ste
el
str
inger/g
irder
Salv
age e
xis
ting s
teel
rein
forcm
ent
bars
.
Cle
an a
nd e
poxy c
oat
exis
ting
rein
fo
rcem
en
t b
ars.
Ad
d a
dd
itio
nal
rein
forc
men
t as i
n
acco
rdan
ce w
ith
Secti
on
42
1.0
3.0
7.
Pie
r deta
il show
n, abutm
ent
deta
il
sim
ilar.
Anchor
edge o
f re
main
ing S
IP f
orm
wit
h
5/8
’’
dia
. g
alv
an
ized
co
ncre
te
anchors
@ 2
’-0’’
c/c
,
4’’
em
bedm
ent.
Refe
r to
Secti
on
s 4
23
an
d 4
23
.03
.03
.
APPROVAL
DIRECTOR
OFFICE OF STRUCTURES
DATE:
SR-CR-202 1 1
PNEUMATICALLY APPLIED MORTAR REPAIR TO CONCRETE DIAPHRAGM
SECTION AT PIER 1.0
VERSION
DETAIL NO.
06/28/2017
ELEVATION
Scale: None
Existing
pier
Scale: None
SECTION B-B
Remove to sound
concrete to these
lines, 6’’ maximum (typ.)
B B
Scale: None
Remove to sound
concrete to these
lines, 6’’ maximum (typ.)
A A
SECTION A-A
T
T
STATE HIGHWAY ADMINISTRATION
DEPARTMENT OF TRANSPORTATION
STATE OF MARYLAND
SHEET OF
APPROVAL
1.
2.
3.
4.
5.
6.
7.
ST
RU
CT
UR
AL
RE
PA
IRS
OFFICE OF STRUCTURES
DIRECTOR
OFFICE OF STRUCTURES
2 Pier2 Pier
1
2
2 12
2
Sequence of
construction
(typ.)
1
Note:
For new wire fabric
refer to 908.08.
CONCRETE PIER WALLDenotes location of
deteriorated concrete
1
The limits of
removal and
repair at the
interior of the
pier wall shall
be determined
by the Engineer
Length of pier
cap repair
A
C
B
Repair
sections
(typ.)
A
B
B
C
6’’ Max. (typ.)
C
6’’ Max. (typ.)
Sequence of
construction (typ.)
PNEUMATICALLY APPLIED MORTAR SEQUENCE AND REPAIR DETAILS FOR CONCRETE PIER WALL
Note:
T is the original
thickness of the
pier.
Removal limits for
each section of
concrete repair (typ.)
6’’ max. (typ.)
see Section
B-B
6’-0’’ min.6’-0’’ min.
Notes:
Concrete elements are divided into segments. Work to be
performed on sections as provided above.
Refer to Section 423.
Contractor shall stage the work so that repair sections
are completed following the number sequence: 1, 2, 3, ....,
shown in the Elevation View, and the letter sequence:
A, B, C, ..., shown in the Section Views.
Contractor shall wait 72 hours after completing repairs to
a section before chipping adjacent sections, however he
may perform work on other bridge elements.
If CIP concrete is used in lieu of PAM, the existing concrete
shall be removed to 2’’ min. behind the existing reinforcement.
Contractor shall stop removing
deteriorated concrete when a
maximum depth of 6 in. is reached.
The Engineer shall immediately notify
the Office of Structures if more
removal seems necessary.
Existing reinforcing steel not shown.
3’-0’’ max. 3’-0’’ max.
New wire fabric
3’-0’’ max.
New wire fabric
Repair sections (typ.)
SR-CR-203
DATE:
1
1.0
VERSION
DETAIL NO.
06/28/2017