Page 1: Chapter 11: Controlling Work Results

PMP Study Guide

Chapter 11: Controlling Work Results

Page 2: Chapter 11: Controlling Work Results

Chapter 11 Controlling Work Results

• Monitor and Control Risks• Control Costs• Control Schedule• Perform Quality Control• Verify Scope• Control Scope

Page 3: Chapter 11: Controlling Work Results

Monitor and Control Risk

• Involves implementing response plans, tracking and monitoring identified risks, and identifying and responding to new risks as they occur

Page 4: Chapter 11: Controlling Work Results

Monitor and Control Risk

• Tools and techniques:– Risk reassessment– Risk audits– Variance and trend analysis– Technical performance

measurement– Reserve analysis– Status meetings

Page 5: Chapter 11: Controlling Work Results

Monitor and Control Risk

• Risk Monitoring and Control outputs– Risk register updates– Organizational process asset

updates– Change requests– Project management plan updates– Project document updates

Page 6: Chapter 11: Controlling Work Results

Chapter 11 Controlling Work Results

• Monitor and Control Risks• Control Costs• Control Schedule• Perform Quality Control• Verify Scope• Control Scope

Page 7: Chapter 11: Controlling Work Results

Control Costs

• Earned value technique– Planned Value (PV) = Budgeted Cost

of Work Scheduled (BCWS)– Actual Cost (AC) = Actual Cost of Work

Performed (ACWP)– Earned Value (EV) = Budgeted Cost of

Work Performed (BCWP)

Page 8: Chapter 11: Controlling Work Results

Earned Value

Figure 10.1

Page 9: Chapter 11: Controlling Work Results

Earned Value Formulas

• Cost VarianceCV = EV – AC

• Schedule VarianceSV = EV – PV

• Performance Indexes– Cost Performance Index (CPI ) = EV/AC– Cumulative CPI = cumulative

EV/cumulative AC– Schedule Performance Index (SPI) =

EV/PV– Cumulative SPI = cumulative

EV/cumulative PV

Page 10: Chapter 11: Controlling Work Results

Earned Value Formulas (cont.)

• Estimate at Completion– EAC = AC + bottom-up ETC– EAC = AC + BAC – EV– EAC = BAC/cumulative CPI– EAC = AC + [BAC – EV/(cumulative

CPI x cumulative SPI)]

Page 11: Chapter 11: Controlling Work Results

Earned Value Formulas (cont.)

• Estimate to Completion (ETC)– ETC = (BAC – cumulative EV

)/cumulative CPI – ETC = BAC – cumulative EV

• To-complete Performance Index– (BAC – EV)/(BAC – AC)– (BAC – EV)/(EAC – AC)

• Variance at Completion– VAC = BAC – EAC

Page 12: Chapter 11: Controlling Work Results

Chapter 11 Controlling Work Results

• Monitor and Control Risks• Control Costs• Control Schedule• Perform Quality Control• Verify Scope• Control Scope

Page 13: Chapter 11: Controlling Work Results

Control Schedule

• Control Schedule involves determining status of project schedule, if changes have occurred or should occur, and influencing and managing schedule changes

Page 14: Chapter 11: Controlling Work Results

Control Schedule

• Tools and techniques:– Performance reviews– Variance analysis– Project management software– Resource leveling– What-if scenario analysis– Adjusting leads and lags– Schedule compression– Scheduling tool

Page 15: Chapter 11: Controlling Work Results

Chapter 11 Controlling Work Results

• Monitor and Control Risks• Control Costs• Control Schedule• Perform Quality Control• Verify Scope• Control Scope

Page 16: Chapter 11: Controlling Work Results

Perform Quality Control

• Concerned with monitoring work results to assure they comply with standards set out in the quality management plan

• Perform Quality Control should be performed throughout the project to identify and remove causes of unacceptable results

• End result of this process is the end product conforms to the requirements and product description

Page 17: Chapter 11: Controlling Work Results

Perform Quality Control

• Cause-and-effect diagram

• Control charts• Flowcharting• Histogram• Pareto chart

• Run chart• Scatter diagram• Statistical

sampling• Inspection• Approved

change requests review

Tools and Techniques:

Page 18: Chapter 11: Controlling Work Results

Control Chart

Page 19: Chapter 11: Controlling Work Results

Frequency of Failures

11.1

Page 20: Chapter 11: Controlling Work Results

Pareto Diagram

11.2

Page 21: Chapter 11: Controlling Work Results

Scatter Diagram

Page 22: Chapter 11: Controlling Work Results

Chapter 11 Controlling Work Results

• Monitor and Control Risks• Control Costs• Control Schedule• Perform Quality Control• Verify Scope• Control Scope

Page 23: Chapter 11: Controlling Work Results

Verify Scope

• Determines if the work is complete and if it satisfies the project objectives

• Concerned with accepting work results

• Formalizes the acceptance of project scope

Page 24: Chapter 11: Controlling Work Results

Verify Scope

• Inputs include:– Project management plan – Requirements documentation– Requirements traceability matrix– Validated deliverables

• Inspection is the only tool and technique

• Outputs include:– Accepted deliverables– Change requests– Project document updates

Page 25: Chapter 11: Controlling Work Results

Chapter 11 Controlling Work Results

• Monitor and Control Risks• Control Costs• Control Schedule• Perform Quality Control• Verify Scope• Control Scope

Page 26: Chapter 11: Controlling Work Results

Control Scope

• Any changes to agreed-upon WBS is considered a scope change

• Changes in product scope require changes to project scope

Page 27: Chapter 11: Controlling Work Results

Control Scope

• Inputs include:– Project management plan – Work performance information– Requirements documentation– Requirements traceability matrix– Organizational process assets

• Variance analysis is the only tool and technique

• Outputs include:– Work performance measurements– Organizational process assets updates– Change requests– Project management plan updates– Project document updates

Page 28: Chapter 11: Controlling Work Results

Chapter 11 Summary

• Monitor and Control Risks

• Control Costs

• Earned Value Formulas

• Control Schedule

• Control Schedule tools and techniques

• Perform Quality Control

• Verify Scope

• Control Scope