chapter 1 introduction - welcome to...
TRANSCRIPT
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-1
Richardson & Cruddas (1972) Ltd.
CHAPTER – 1 INTRODUCTION
1.1 Purpose of the report
The growth of mining / industry significantly contribute towards economic progress of
the country. However, any project progress brings along with it a number of environmental problems. Many of these problems can be avoided, if adequate environmental control considerations are thought of during conceptual stage of the
project. Once the project is set up, it becomes very costly to install pollution control equipment and implement other environmental control measures, if the same are not considered in the conceptual stage. Any project exerts both positive and negative
environmental impacts. Negative impact cause environmental degradation. It is the responsibility of Planners, Scientists and Environmentalists to document these impacts separately so that these can be identified, quantified and attempts may be
made to minimize negative impacts and maximize the positive impacts for better development with least environmental degradation. In view of more industrialization,
the demand of iron ore has increased substantially in the recent past. In accordance with Mission and Objectives of M/s. Steel Authority of India Limited and National Steel Policy, SAIL proposes to develop/expand Mahamaya – Dulki mine with a rated
production capacity from 0.96 to 1.46 Million Ton per annum. The Mining lease area under is 1522.67 Ha. The TOR for preparation of draft EIA document is already obtained from Ministry Environment & Forests (MoEF), New Delhi vides their letter
no.J-11015/11/2007-IA.II (M) dated 13.04.2007. SAIL has entrusted the work of Environmental Impact Assessment (EIA) and Environmental Management Plan (EMP)
study to M/s. Richardson & Cruddas (1972) Ltd (A Govt. of India Undertaking). Accordingly the final EIA / EMP report has been prepared after conducting public hearing and submitted to the Ministry for approval. The Expert Appraisal Committee
meeting held on 25.07.2012 desired to have the updated EIA/EMP report with at least
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-2
Richardson & Cruddas (1972) Ltd.
one month baseline data as the prescribed validity of TOR is more than 4 years. The present EIA/EMP report was updated with one month baseline data (November 2012)
and based on the approved TOR provided by MoEF and Generic structure of Environmental Impact Assessment as per EIA notification 2006. The Index map of the project site is given in Fig. I.1.
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-3
Richardson & Cruddas (1972) Ltd.
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-4
Richardson & Cruddas (1972) Ltd.
1.2 Profile of Project proponent & Background
Steel Authority of India Limited (SAIL) is the leading steel-making company in India.
It is a fully integrated iron and steel maker, producing both basic and special steels
for domestic construction, engineering, power, railway, automotive and defense
industries and for sale in export markets. The company is ranked amongst the top
ten public sector companies in India in terms of turnover. SAIL manufactures and
sells a broad range of steel products, including hot and cold rolled sheets and coils,
galvanized sheets, electrical sheets, structural, railway products, plates, bars and
rods, stainless steel and other alloys. SAIL produces iron and steel at five integrated
plants and three special steel plants, located principally in the eastern and central
regions of India and situated close to domestic sources of raw materials, including
the Company's iron ore, limestone and dolomite mines. The company has the
distinction of being India’s second largest producer of iron ore and of having the
country’s second largest iron ore mines network. This gives SAIL a competitive edge
in terms of captive availability of iron ore, limestone, and dolomite which are inputs
for steel making.
Major Integrated Steel Plants • Bhilai Steel Plant (BSP) in Chhattisgarh
• Durgapur Steel Plant (DSP) in West Bengal
• Rourkela Steel Plant (RSP) in Orissa
• Bokaro Steel Plant (BSL) in Jharkhand
• IISCO Steel Plant (ISP) in West Bengal
Special Steel Plants • Alloy Steels Plants (ASP) in West Bengal
• Salem Steel Plant (SSP) in Tamil Nadu
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-5
Richardson & Cruddas (1972) Ltd.
• Visvesvaraya Iron and Steel Plant (VISL) in Karnataka
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-6
Richardson & Cruddas (1972) Ltd.
About Bhilai Steel Plant
Bhilai Steel Plant (BSP) is India's major producer of rails and heavy steel plates and
structural has won Prime Minister's Trophy for best Integrated Steel Plant in the
country for Nine – times. The plant is the sole supplier of the country's longest rail
tracks of 260 metres. BSP has an annual production capacity of 3.153 MT of
saleable steel, the plant also specializes in other products such as wire rods and
merchant products. BSP is accredited with ISO 9001:2000 Quality Management
System and ISO:14001 has been awarded for Environment Management System in
the Plant, Township and Dalli Mines. The Plant is accredited with SA:8000
certification for social accountability and the OHSAS-18001 certification for
Occupational health and safety. These internationally recognized certifications add
value to Bhilai's products and helps create a place among the best organizations in
the steel industry. Among the long list of national awards it has won, Bhilai has
bagged the CII-ITC Sustainability prize for three consecutive years.
1.3 Genesis and Objectives of the project
In view of more industrialization, the demand of iron ore has increased substantially
in the recent past. BSP has planned to enhance the production capacity of
Mahamaya mine , located about 111 km south-west of Bhilai, linked with state
highway from the existing Dalli-Rajhara mines. Mahamaya-Dulki Mine holding the
Mining Lease of 1522.67 ha. comes under control of Iron Ore Complex of Dalli-
Rajhara.
The deposit is located in the Nos. 64 D/15 and 64 H/3 between longitude 80°57'02”
to 81°00'53"E and between latitude 20°26'06" to 20°30’21"N. The products
(processed lump ore & fine ore) will be used as raw material for Bhilai Steel Plant.
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-7
Richardson & Cruddas (1972) Ltd.
1.4 Nature of project
In accordance with Mission and Objectives of M/s.BSP and National Steel Policy,
BSP proposes to enhance the production capacity of Mahamaya Iron Ore Project,
at Mahamaya and Dulki villages, Durg and Rajnandagaon district, Chhatisgarh state
with an enhanced production capacity of 1.46 MTPA Run off Mine iron ore to meet
the domestic demand of BSP.
1.5 Size of Project
The proposal is enhancement of production capacity at Mahamaya Iron ore mine
with a rated production capacity of 1.46 Million Ton per annum. The Mining lease
area under is 1522.67 Ha. The existing Iron Ore Complex of Dalli- Rajhara will be
utilized for all other secondary mining facilities like Crushing plant, downhill
conveyor, screening plant, tertiary crusher and loading plant. The existing facilities
like Township, Hospital and Training institute available at Dalli-Rajhara Iron ore
complex will be utilized for the proposed enhancement.
1.6 Location and & Accessibility
State : Chhatisgarh
District : Durg and Rajnandagaon
Village : Mahamaya and Dulki
Lease Area : 1522.67 Hect.
The Mahamaya-Dulki lease area is well connected by road lying at a distance of 111
kms. South-West of Bhilai Steel Plant. The Iron ore produced from this mine is being
transported to Dalli-Rajhara Iron ore Complex located at a distance of 23 km.
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-8
Richardson & Cruddas (1972) Ltd.
1.7 Scope of EIA
SAIL has entrusted the work of Environmental Impact Assessment (EIA) and
Environmental Management Plan (EMP) study to M/s. Richardson & Cruddas (1972)
Ltd (A Govt. of India Undertaking). The EIA/EMP have been considered as the most
important tools / documents which can be utilized by the project proponent and
Government Regulating Agencies and Public to clearly understand the
environmental implications of the proposed project with respect to the overall
developmental plan and to take decisions in the interest of environment and the
national economy. It also helps to analyze the techno-environmental feasibility of the
proposed project. This is primarily to ascertain, beforehand the potential impact
areas of the proposed project and initiate necessary corrective actions at the design
stage itself as well as the appraise the environmental protection regulating
authorities for issuing Environmental Clearance for the project, as required under the
relevant provisions of Environment Protection Act, 1986, Rules and EIA Notification
2006.
The TOR for preparation of draft EIA document is already obtained from Ministry
Environment & Forests (MoEF), New Delhi vides their letter no.J-11015/11/2007-IA.II
(M) dated 13.04.2007. SAIL has entrusted the work of Environmental Impact
Assessment (EIA) and Environmental Management Plan (EMP) study to M/s.
Richardson & Cruddas (1972) Ltd (A Govt. of India Undertaking). Accordingly the final
EIA / EMP report has been prepared after conducting public hearing and submitted to
the Ministry for approval. The Expert Appraisal Committee meeting held on 25.07.2012
desired to have the updated EIA/EMP report with at least one month baseline data as
the prescribed validity of TOR is more than 4 years. The present EIA/EMP report was
updated with one month baseline data (November 2012) and based on the approved
TOR provided by MoEF and Generic structure of Environmental Impact Assessment as
per EIA notification 2006
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-9
Richardson & Cruddas (1972) Ltd.
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-10
Richardson & Cruddas (1972) Ltd.
1.8 Methodology of EIA
Environmental Impact Assessment study has been conducted within an area of 10
km radius around the proposed mine. The various steps involved in the study of the
proposed project are divided into the following phases.
• Identification of significant environmental parameters and assessing the status
within the impact zone
• Prediction of Impacts envisaged due to proposed mining and transportation
activity on various environmental parameters
• Quantification / Prediction of impact for the identified activities and to study level
of impact on various environmental components
• Evaluation of impacts after superimposing the predicted scenario over the
baseline scenario.
• Formulation of Environmental Management Plan including waste Management
Plan
Accordingly, field studies were carried out during study period (April 2009 to May
2010) to establish the existing conditions. As per the instruction received from EAC
one month additional data also collected for Air, Noise and Water quality and which
is also included in this report. The details study carried for the preparation of EIA
document is given as under.
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-11
Richardson & Cruddas (1972) Ltd.
Details of Environmental Parameters
Sl. No Attribute Parameters No of
Location Frequency of Monitoring
1 Meteorology Wind Speed and Direction, Temperature Relative Humidity, Rainfall
1
a] Hourly monitoring for Four seasons. b] Collection & Review of Data from secondary sources like IMD
2 Ambient air quality
SPM, PM10, PM2.5, SO2, NOx, CO, NH3, and Heavy metals 12
24 hrs monitoring, twice a week. CO samples shall be collected on 8 Hr. basis for Three seasons
4 Water quality As per IS:10500/ CPCB 10 Four seasons. 5 Hydrology
(Surface and Ground)
Drainage aquifer characteristic recharge & discharge -
Collection and review of data from secondary sources and field investigation during pre and post monsoon
6 Ecology Terrestrial and aquatic ecology -- Field study. Collection and
review of secondary data. 7 a. Noise
b. Vibration Noise levels dB(A) PPV(mm/s)
12 6
Three seasons Once in study period
8 Soil characteristics
Soil type & characteristic, texture class, heavy metal and NPK
6
Three seasons
9 Land use Land use for different categories -
Collection and review of data from census handbooks, 2001.
10 Socio-economic aspects
Socio-economic characteristics
-
Collection and review of data from census handbooks. Feed back through field survey and public hearing
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-12
Richardson & Cruddas (1972) Ltd.
11 Risk assessment, Disaster Management Plan
Identification of risk and disaster.
-
Based on assessment.
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-13
Richardson & Cruddas (1972) Ltd.
1.8 The Compliance of Consent Conditions
The consent for operation of the mines was obtained on 04.08.2012. Copy of the
same along with compliance conditions were given in Annexure-I Sanctions and
Approvals.
The action taken on compliance conditions for Air & Water are given as follows:
Air Consent
• Mahamaya Mine is maintaining and operating the pollution control facilities
properly and regularly:
a. Wet Drilling
b. Water sprinkling on haul roads
c. Provision of sprinkling arrangement at all dust generating points in the
screening plant.
The above arrangements are functioning so that the emission level is within the
prescribed standards.
• Road upto Mahamaya Mine is pucca. Roads within quarry are temporary in
nature. These roads are carpeted with murrum and wetted with water by
sprinklers to control dust. Housekeeping inside mine lease area improved on
regular basis.
• Plantation has been done in the open available area within and outside mining
lease.
• Use of fly ash bricks / blocks will be followed in future construction.
• Environment statement as per provision of environment (Protection) Amendment
Rules 1993 for the year 2012-2011 has been submitted to the Board in Form-V
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-14
Richardson & Cruddas (1972) Ltd.
vide No. Mine/IOC/MM/4-(2)/ENVRNMT/A-RTN/FORM-V/2011/244 dated
24/04/2011.
• Production is within the capacity (i.e. 9,60,000 T/Annum) mentioned in the
consent letter.
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-15
Richardson & Cruddas (1972) Ltd.
Water Consent
• The pollution control facilities are well maintained and operated. No treated
effluent is generated at Mahamaya Mine.
• Total 10 Nos. check dams have been constructed around Mahamaya Mine.
These check dams are maintained and desilted regularly.
• Overburden waste and mineral rejects are scientifically handled, transported and
stored. The dumps are located within mining lease in non-minerailsed area.
• Road upto Mahamaya Mine is pucca. Roads within quarry are temporary in
nature. These roads are carpeted with murrum and wetted with water by
sprinklers to control dust. Housekeeping inside mine lease area improved on
regular basis.
• Plantation has been done in the open available area within and outside mining
lease.
• Use of fly ash bricks / blocks will be followed in future construction.
• Environment statement as per provision of environment (Protection) Amendment
Rules 1993 for the year 2012-2011 has been submitted to the Board in Form-V
vide No. Mine/IOC/MM/4-(2)/ENVRNMT/A-RTN/FORM-V/2011/244 dated
24/04/2011.
• Production is within the capacity (i.e. 9,60,000 T/Annum) mentioned in the
consent letter.
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-16
Richardson & Cruddas (1972) Ltd.
CHAPTER – II PROJECT PROFILE
2.1 Introduction
Steel Authority of India Ltd. (SAIL), a Government of India under taking, produces
Iron Steel products at different integrated steel plants for which various raw materials
such as Iron Ore, Lime stone, Dolomite, coal etc. are required. The raw materials
are supplied either from captive source or purchased. SAIL (Steel Authority of India
Ltd.) is the second largest mining company in the country. Bhilai Steel Plant
(BSP) of SAIL has an annual saleable steel production capacity of 3.15 MTPA for
the year 2009-10 and is a major exporter of steel products. Bhilai Steel Plant
specializes in products like heavy rails, structural & merchant mill products, plates
and wire rods. Mahamaya-Dulki Mine is is located about 111 km south-west of
Bhilai, linked with state highway from Dalli-Rajhara. Mahamaya-Dulki Mine
holding the Mining Lease of 1522.67 ha comes under control of Dalli- Rajhara Iron
Ore Complex of Bhilai Steel Plant, SAIL.
BSP is planning to enhance the production capacity of Mahamaya mine from 0.96
MTPA to 1.46 MTPA to meet the requirement of steel production at Bhilai Steel Plant.
The principal approval from Forest Dept. is obtained. The lease renewal and Forest
Clearance is given in Annexure–I (Sanctions and Approvals).
2.2 Physiography of the area
The whole region is hilly and undulating piece of land. The shift ranges of this region
are formed by Kalwar hills, Dulki hills and Mahamaya hills. The iron ore deposits are
mainly traced at the peak portions of the hills. The ridges are not susceptible to
erosion due to the presence of Banded Hematite Quartzite (BHQ). The Mahamaya-
Dulki lease covers 3 low lying hillocks of Mahamaya hill range. The Dulki range
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-17
Richardson & Cruddas (1972) Ltd.
(consisting of 3 hillocks' namely D1,D2 and D3) lies in the southern continuity of
Mahamaya hill range and it extends over a length of 2.4 Kms. The D1 hill trends in
North-South direction and D2 & D3 in East-West direction. This hill range is
characterized by high peaks and saddles with steep slopes on either side. The
highest peak attains an elevation of 741.69 m above MSL and the general ground
level is being 500 m above MSL.
2.3 Geology of the area
The area under reference is Mahamaya-Dulki lease which lies partly in Mahamaya
and partly in Dulki hills. The rock types exposed in this area belong to Dharwar
group, similar to Dalli-Rajhara and Mahamaya deposits. The iron ores traced here
generally occupy the peaks and BHQ in intervening ridges. Both upper and lower
shale/ phyllites contacts with BHQ in hill sides. The intrusive bodies like thin quartz
veins of younger age also occur within the area.
The soil, laterite capping and ferruginous shale etc. occurring above the ore body
normally contain low iron and high alumina percentages and are considered as
overburden. The iron ore body consists of lateritic ore, shaly ore, silicious ore,
laminated ore, compact ore and soft friable / powdery type of ores. Among these, the
laterite ore, shaly ore and silicious ore are generally low grade. The ore containing
less than 55% Fe content and these ores are not considered for reserve calculation.
The remaining three types of ores viz. Laminated, Pre-Compact Laminated and friable
contain 55% to 67% Fe. The laminated ore constitute about 75% of the total available
reserves. The average grade of ore occurring in the area contains 62.17% Fe, 4.68%
Si02 and 2.83% Al2O3.
2.4 Exploration
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-18
Richardson & Cruddas (1972) Ltd.
Initially, the area was covered under geological investigation by Geological Survey of
India. Later the Iron Ore Prospecting (I.O.P) division of M/s. Bhilai Steel Plant (BSP)
has carried out detailed exploration. The exploration done by the company includes
surveying, geological mapping, out crops sampling and drilling of bore holes etc.
covering both Mahamaya & Dulki sub blocks.
The IOP division of M/s BSP has initially drilled 34 core drill holes at 100m by 100
m staggered Intervals, i.e. 'M' series of holes covering all the three doposits M1, M2
and M3 A total area of 2.5 sq. km. has been explored. The cumulative drilling is
1716.26 mts. Afterwards, till date about 53 boreholes have been drilled to establish
the ore boundaries and continuity of ore body at depths. The boreholes have filled
the gaps of the earlier holes and brought the grid at 50 m X 100 m (approximately).
The average core recovery is recorded 90%. Similarly in D-1 block a total no. of
nine boreholes have been drilled by IOP division of which only three bore holes are
falling in Dulki sub block D1 ( 5 ha. Block), of this lease & remaining six bore Holes
are located in adjacent Kalwar-Nagur lease.
In Mahamaya sub block all the deposits viz. MIA, M1B, M2 and M3 have already
been explored in detail at 50 m x 100 m grid. However the deposits of Mahamaya
sub block is highly heterogeneous in nature, hence in order to gather some more
information on delineation of ore and waste contact, twenty additional bore holes
have been proposed i.e. ten bore hole each in M2 and M3 deposits. Similarly in
Dulki sub block (5 hects.) only 3 boreholes have been drilled so far (i.e. BH Nos.
DK8, DK9 and DKI0). Therefore, it is proposed to drill additional six boreholes to fill
the gaps in the 3rd and 4th year of the mining plan period. This proposed exploration
will prove the lateral and depth continuity of the ore body of Dl deposit. The details of
year wise proposal for drilling in M2, M3 & Dl deposit are given in Table 2.1
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-19
Richardson & Cruddas (1972) Ltd.
Table 2.1 Year-wise Proposal as per scheme of Mining (2006-2011) D-1, M-2 & M-3 Deposits
Year Location of boreholes
Bore holes to be
drilled
Borehole
No.
Borehole-wise proposed
Meterage
Total Meterage
Remarks
1st - Nil Nil Nil Nil In case these holes are not touching the foot-wall, the drilling will continue to further depths.
2nd - Nil Nil Nil Nil
3rd D1 DEPOSIT (5HECT. BLOCK)
2 R-4 R-6
40 M 40 M
80 M
4th D1 DEPOSIT (5HECT. BLOCK)
4 R-7 R-10 R-13 R-17
55 M 45 M 30 M 40 M
170 M
5th M2 DEPOSIT &
M3 DEPOSIT
10 10
PR 11 PR 12 PR 13 PR 14 PR 15 PR 16 PR 17 PR 18 PR 19 PR 20 PR 1 PR 2
20 M 15 M 15 M 20 M 20 M 15 M 20 M 30 M 40 M 15 M 15 M 30 M
210 M 195 M
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-20
Richardson & Cruddas (1972) Ltd.
PR 3 PR 4 PR 5 PR 6 PR 7 PR 8 PR 9 PR 10
20 M 20 M 20 M 20 M 20 M 20 M 20 M 10 M
The year wise details of development (waste removal) for the last five years (Scheme of
mining) from 2006-07 to 2010-11 is given Table 2.2
Table 2.2 Year wise waste excavation plan & actual (M-1, M-2,M-3)
YEAR PLAN ACTUAL
M-1 M-2 M-3 M-1 M-2 M-3
2006-07 141650 77432 99181 12399 103306 145231
2007-08 109478 78438 93059 178463 73558 152842
2008-09 132739 NIL 162949 133366 11115 132781
2009-10 156300 NIL 189011 83819 12414 78937
2010-11 137808 NIL 311342 183275 7481 179338
Year-wise Production plan & actuals (ore) (M-1, M-3, M-3) is given in Table 2.3. The
deviation in excavation due to changed quantities of lumps and fines by BSP
accordingly excavation schedule is modified to achieve the quantity & quality of
products.
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-21
Richardson & Cruddas (1972) Ltd.
Table 2.3 Year wise waste excavation plan & actual (M-1,M-2,M-3)
YEAR PLAN ACTUAL
M-1 M-2 M-3 M-1 M-2 M-3
2006-07 417000 176000 343022 36251 187648 389046
2007-08 408235 175253 362128 419490 135964 330282
2008-09 422209 NIL 500354 351321 66589 240705
2009-10 411000 NIL 501005 195844 101172 162690
2010-11 461104 NIL 498896 337197 37616 362526
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-22
Richardson & Cruddas (1972) Ltd.
Afforestation Programme
Afforestation programme for last five years (mining plan period) & the actual are
given in Table 2.4
Table 2.4 Afforestation programme for last five years
YEAR PLAN ACTUAL
2006-07 NIL NIL
2007-08 NIL NIL
2008-09 4.00 Ha(Top Exhausted benches) NIL
2009-10 5.00 Ha.(Top Exhausted benches) NIL
2010-11 3.00 Ha. Top Exhausted benches). 0.15 Ha. (Back fill area of M2)
Small plots could not be afforested because of inability shown by Chhattisgarh Van Vikas Nigam (CGVVN) to take up afforestation in such a small plots at different locations.
2.5 The Land use of ML area
The mining lease area of Mahamaya-Dulki is 1522.67 Hect. The breakup of the land
use is as follows Table 2.5
Table 2.5 The Land use of ML area
Location Forest Land
Crop Land
Grazing Land
Waste Land
Total (Ha.)
a) Pits & Quarries 53.88 Nil Nil Nil 53.88
b) Dumps of ore waste and Overburden
9.54 Nil Nil Nil 9.54
c) Infrastructure inclusive of offices, workshops plants, WB, Road, etc.
17.34 Nil Nil Nil 17.34
e) Sub-grade material 3.24 Nil Nil Nil 3.24
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-23
Richardson & Cruddas (1972) Ltd.
f) Undisturbed natural forest land
1438.67 Nil Nil Nil 1438.67
Total 1522.67 Nil Nil Nil 1522.67
2.6 Reserves
A summary of block-wise/ deposit-wise reserves are given Table 2.6
Table 2.6 summary of reserves (as on 1/4/2006)
(Qty. in Tonnes)
Name of Block Deposit Name Reserves
Grade Characteristic of Ore
FE SIO2 AL2O3 P
MAHAMAYA BLOCK
M-1 3057370 61.85 5.03 2.79 0.081
M-2 351253 60.26 7.43 3.37 0.085
M-3 2989612 62.68 4.08 2.98 0.091
TOTAL OF M-1, M-2,M-3
6398235 62.17 4.68 2.83 0.085
DULKI BLOCK 5 HECT. D-1 1910464 63.53 4.15 2.70 ---
2.7 Depletion of reserves
Year wise balance quantity of Ore from 2006-2011 given Table 2.7
Table 2.7 Year wise balance quantity of Ore
Year as on Balance reserves
M-1 M-2 M-3 D-1
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-24
Richardson & Cruddas (1972) Ltd.
01-04-2006 3057370 351253 2447817 1910464
01-04-2007 3021119 163587 2058771 1910464
01-04-2008 2529629 470878 1728489 1910464
01-04-2009 2178308 404289 1487784 1910464
01-04-2010 1982464 303117 1325094 1910464
01-04-2011 1344269 414330 1514641 2557172
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-25
Richardson & Cruddas (1972) Ltd.
2.8 Additional reserves established category wise
Additional reserves established in M2 deposit after Geological mapping of the area
in the year 2008. After re-estimation Ore reserves increased from 27623 T to
470878 T. Thus 443255 T of ore reserves increased.
Based on the geological mapping in the year 2010 of the area M1 & M3 and
considering the thresh hold value 45% Fe as circular no. 5/2009 Dt.- 23.10.2009 of
IBM ore reserves estimated 1344269T instead of 1645267 T in M1 area and
1514641 T instead of 962568 T in M3 area.. Thus the ore decrease 300998 T in M1
area & 552073 T increase in M3 area. Similarly considering the thresh hold value
45%Fe the ore reserve is increased 148829 T in M-2 area. Thus the ore reserve in
M-2 area is 414330 T instead of 265501 T.
Similarly in D1 Block the ore reserve estimation is done by level wise and
considering the thresh hold value 45% Fe the ore reserve estimated 2557172 T
instead of 1910464 T. Thus ore increased 646708 T.
2.9 Category wise updated reserves with grade
Updated reserves with grade indicated in table given in Table 2.8
Table 2.8 Category wise updated reserves with grade (As on 1/4/2011)
(Qty. in Tonnes)
Name of block Deposit Name
In-situ reserves
Grade Characteristic of ore (%)
Fe Al2O3 SiO2 P
Mahamaya Block M-1 1344269 59.48 8.47 2.88 0.11
M-2 414330 58.17 10.15 3.65 0.08
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-26
Richardson & Cruddas (1972) Ltd.
M-3 1514641 61.41 6.35 2.58 0.07
Total of M1,M2 & M3 3273240 60.24 7.65 2.82 0.09
Dulki Block (5 Ha) D-1 2557172 63.53 2.70 4.15 0.08
GRAND TOTAL 5830412
The details of level wise and grade wise reserves are given in Table 2.9 -2.12
Table 2.9 reserve (M1 pit) as per UNFC (as on 01.04.2011)
Sl. No.
Bench Level Ore Fe% SiO2% Al2O3% P Waste
From To
1 655 650 9155 58.92 6.68 4.67 0.08 1841
2 650 645 47618 57.66 7.54 5.79 0.06 38648
3 645 640 37040 59.38 7.79 3.43 0.05 63561
4 640 635 124846 58.92 6.68 4.67 0.08 95533
5 635 630 180482 60.98 6.99 2.29 0.07 113915
6 630 625 140145 58.97 10.26 2.70 0.06 129099
7 625 620 155322 58.67 10.70 3.77 0.07 130129
8 620 615 138987 56.01 13.08 3.47 0.07 143866
9 615 610 113460 58.69 9.95 2.73 0.14 87386
10 610 605 105795 57.10 12.35 3.51 0.06 64759
11 605 600 103252 60.23 6.44 4.06 0.09 58717
12 600 595 79021 59.35 8.94 3.52 0.08 45368
13 595 590 63039 57.42 12.28 2.46 0.12 45212
14 590 585 23320 63.87 3.73 1.46 0.15 16405
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-27
Richardson & Cruddas (1972) Ltd.
15 585 580 9871 61.07 8.76 0.83 0.13 11611
16 580 575 6749 62.82 2.94 0.87 0.27 3490
17 575 570 4108 62.23 4.23 0.92 0.35 2482
18 570 565 2059 55.39 17.30 0.64 0.13 0
1344269 58.86 9.33 3.33 0.08 1052024
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-28
Richardson & Cruddas (1972) Ltd.
Table 2.10 reserve (M2 pit) as per UNFC (as on 01.04.2011)
Sl. No.
Bench Level Ore Fe% SiO2% Al2O3% P%
Waste From To
1 650 645 23130 55.77 10.42 5.92 0.12 24767
2 645 640 37790 60.05 5.45 3.76 0.11 27896
3 640 635 35924 60.68 5.33 4.49 0.13 29597
4 635 630 44322 61.53 6.56 2.82 0.06 24494
5 630 625 42510 56.59 11.42 4.55 0.07 19228
6 625 620 25448 56.26 13.37 4.08 0.06 20680
7 620 615 25085 57.23 11.60 3.69 0.06 18280
8 615 610 38793 56.10 15.19 2.41 0.08 23320
9 610 605 62106 55.046 14.76 3.27 0.08 24950
10 605 600 48877 53.19 18.57 2.83 0.09 31331
11 600 595 15768 53.22 11.47 6.60 0.17 9335
12 595 590 12193 51.24 12.38 8.53 0.15 4667
13 590 585 2384 60.18 7.71 3.38 0.08 4667
414330 57.00 11.61 3.78 0.09 263214
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-29
Richardson & Cruddas (1972) Ltd.
Table 2.11 reserve (M3 pit) as per UNFC(as on 01.04.2011)
Sl. No
Bench Level Ore Fe% Sio2% Al2O3% P%
Waste From To
1 655 650 1522 67.80 0.80 0.57 0.053 113542
2 650 645 5488 66.44 1.75 1.44 0.06 146478
3 645 640 38672 61.04 8.08 2.28 0.06 131412
4 640 635 55801 60.46 5.38 3.34 0.08 119903
5 635 630 60259 60.81 4.97 3.19 0.09 122623
6 630 625 103724 64.52 2.30 1.75 0.07 105101
7 625 620 136123 61.12 4.91 3.79 0.07 108443
8 620 615 260554 59.43 5.79 5.00 0.07 126712
9 615 610 211936 59.13 6.85 4.55 0.07 108444
10 610 605 186343 60.43 6.13 3.97 0.06 54879
11 605 600 162647 61.64 5.97 2.68 0.06 48554
12 600 595 101562 59.43 8.71 3.01 0.06 35346
13 595 590 79111 61.07 7.95 1.85 0.07 13399
14 590 585 63336 54.68 15.13 2.96 0.10 17046
15 585 580 28174 52.10 17.25 3.82 0.11 9314
16 580 575 13558 55.69 16.61 1.61 0.05 3912
17 575 570 4002 50.18 24.71 1.33 0.05 1875
18 570 565 1829 46.07 30.30 0.96 0.05 3036
1514641 60.09 6.76 3.56 0.07 1270019
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-30
Richardson & Cruddas (1972) Ltd.
Table 2.12 reserve (D1) as per UNFC (as on 01.04.2011)
Sl. No.
Bench Level ORE
From To Total Reserve Measured Indicated Inferred
1 720 715 5690 0 0 5690
2 715 710 84366 73641 0 10725
3 710 705 123033 75868 0 47166
4 705 700 119518 73562 0 45956
5 700 695 124260 90510 0 33750
6 695 690 162584 133285 9599 19800
7 690 685 136686 107386 9499 19800
8 685 680 139564 110934 9499 19130
9 680 675 149635 131676 9499 8460
10 675 670 138125 119460 9499 9165
11 670 665 145319 126654 9499 9165
12 665 660 151074 106323 36290 8460
13 660 655 156576 71777 73166 11632
14 655 650 182916 99703 73166 10046
15 650 645 168282 87714 73166 7402
16 645 640 124383 46458 73166 4750
17 640 635 141945 66661 73166 2115
18 635 630 127309 65850 61459 0
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-31
Richardson & Cruddas (1972) Ltd.
19 630 625 108286 52680 55606 0
20 625 620 18689 10246 18443 0
21 620 615 21004 2561 18443 0
22 615 610 13832 0 13832 0
23 610 605 4098 0 4098 0
2557172 1651815 630999 274357
Due to grant of forestry permission of about 5 hect. only in the Dulki-Block the ore is
left in the section-AA, which is beyond the granted area.
Year wise balance quantity of Ore from 2001-2006 given in Table 2.13
Table 2.13 Year wise balance quantity of Ore from 2001-2006
Year as on Balance reserves
M-1 M-2 M-3 M-4
01-4-2001 3186576 906710 3523032 1910464
01-04-2002 3186576 792224 3251086 1910464
01-04-2003 3186576 697500 3041973 1910464
01-04-2004 3098770 605568 2880328 1910464
01-04-2005 3057370 490150 2686465 1910464
01-04-2006 3057370 351253 2447817 1910464
Additional Reserves established in M-3 deposit after Geological mapping of the area
in between the cross sections 1 to 4. After re-estimation Ore reserves increased
from 2447817 T to 2989612 T. Thus 541795 T of ore reserves increased.
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-32
Richardson & Cruddas (1972) Ltd.
Category wise updated reserves with grade as well as marginal grades. Updated
reserves with grade indicated in table given in Table 2.14
Table 2.14 Updated reserves with grade
Name of block Deposit Name
Reserves Grade characteristic of Ore
Fe Si02 A1203 P
Mahamaya block
M-l 3057370 61.85 5.03 2.79 0.081
M-2 351253 60.26 7.43 3.37 0.085
M-3 2989612 62.68 4.08 2.98 0.091
Total of M-1, M-2, M-3
6398235 62.17 4.68 2,83 0.085
Dulki block 5 Hect. D-1 1910464 63.53 4.15 2.70 --
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-33
Richardson & Cruddas (1972) Ltd.
2.10 Method of Mining
Brief description about the existing method of working
The Mahamaya sub block has been divided into three hills, which are known as M1
(having two parts A & B), M2 and M3 hill. Presently mining is being done in M1,M2,
M3 blocks of the Mahamaya deposit. In case of Dulki deposit, a virgin deposit falling
in the lease boundary of Mahamaya mine, no mining operations are being performed
in this area. Mahamaya mine was started on 4.11.1971 and is being continued with
semi-mechanised method of working. Presently the mine is producing about 0.70
MT of ROM per year.
In other working blocks i.e. M2 & M3, the semi mechanized operations are being
practiced, which consists of 5.5-6.0 m deep, hole drilling and blasting. Raising by
manual means by the departmental workers and loading & transport of ore to stock
piles / ore processing plant by excavators / loaders & 10 T tippers combination,
Similarly waste excavation is also done. As number of Daily Piece Rate (DPR)
raising mazdoor is decreasing day by day due to their redeployment as attendants
and also through voluntary retirement, hence production is being augmented by
mechanical excavation of ROM (0 to 900 mm) by deploying hydraulic
excavators/pay loaders and 10 T tippers.
Ore is processed in the Dalli- Rajhara crushing and screening plant and segregated to
different grades by crushing and screening and stacked at loading siding. Finally these
products are dispatched to Bhilai Steel Plant by railway wagons from Rajhara stock yard.
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-34
Richardson & Cruddas (1972) Ltd.
Design parameters considered for the existing workings
Semi-mechanised Mining:- All the operations of M2 and M3 hills of Mahamaya
Mine are carried out by the semi-mechanised means as described below.
Drilling & blasting: - Blast holes of 115 mm dia. are used for primary drilling in ore
and waste rock. Jack hammers are used for drilling in tow and boulders respectively.
The blast holes are blasted by using 83 mm dia. explosive. Details are explained at
subsequent chapter.
Loading Equipment:- The loading of stacked material is done by 0.96 cum
capacity excavator / pay loaders into 10 T tippers. This operation is carried out by
contractual agency.
Transport:- The +80mm ore is transported to Rajhara crushing & screening plant /
Dalli crushing, screening & washing plant, by the help of 10 tonner tippers. The high
grade fines (HGF) are transported by 10 tonner tippers. For transportation of waste
similar method is used as in case of lumps & fines. As the number of departmental
workers are getting reduced due to redeployment as attendant or voluntary
retirement, hence production is being augmented by mechanised excavation of
ROM (0 - 900mm) by hydraulic excavator / loader and 10 T tipper combination.
Present Mining Status
In M2 hill working is by semi-mechanised means i.e. drilling & blasting by
departmental means and raising by manual workers. The top most active bench is
at 650 MRL, and the lowest bench at 610 MRL. In this block average bench height
is 4 to 5.5mtr.
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-35
Richardson & Cruddas (1972) Ltd.
Working in M3 hill is also by semi-mechanised means and the top most level where
excavation is going on is at 655 MRL, and the lowest level is 610 MRL. In general
benches are of 4 to 5.5 mtr.
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-36
Richardson & Cruddas (1972) Ltd.
The details of existing equipment deployed in the overall mine are given in following
tables 2.15 – 2.16.
Table 2.15 List of departmental equipment
Equipment Equipment installed
(Nos.)
Equipment Working
(Nos.)
Remarks
Compressors CPT 7 3 4 Undermaintenance
Drills (Atlas copco) 6 4 2 for sell off Tractor 1 0 Under maint Explosive Van 1 1 Tippers (lOt) 2 2 Trucks 2 2 Water tanker 3 2 1 Under maint Jeep 3 3 Canteen Van 1 1 Bus 3 3 Ambulance 1 1 1 under maintenance
Table 2.16 List of contractual equipment
Equipment Equipment installed (Nos.)
Equipment Working (Nos.) Remarks
Excavator 3 3
Pay loaders 2 2
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-37
Richardson & Cruddas (1972) Ltd.
The Yearly pit wise development plan proposed is given in Table 2.17
Table 2.17 Yearly pit wise development plan proposed
(M1 + M2 + M3)
Year ROM Ore Over-burden (Waste)
Sub-grade Ore
Mineral Rejects
Ore to Overburden Ratio
2011-12 891421 645744 Nil Nil 1: 0.72
2012-13 669752 534666 Nil Nil 1: 0.79
2013-14 490860 453746 Nil Nil 1: 0.92
2014-15 504326 396660 Nil Nil 1: 0.78
2015-16 716878 554439 Nil Nil 1: 0.77
TOTAL 3273237 2585256 Nil Nil
D1
Year
ROM Ore Over-burden (Waste)
Sub-grade Ore
Mineral Rejects
Ore to Overburden Ratio
2011-12 Nil Nil Nil Nil Nil
2012-13 290090 222400 Nil Nil 1:0.76
2013-14 469063 250353 Nil Nil 1:0.53
2014-15 455634 345224 Nil Nil 1:0.75
2015-16 243020 213075 Nil Nil 1:0.87
Total 1457807 1031051 Nil Nil
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-38
Richardson & Cruddas (1972) Ltd.
Excavation programme for D-1 block 5 Hect. is not planned in the year 2011-12
because forestry clearance still awaited. Removal of waste rock will be done
simultaneously in a systematic manner to get the adequate exposure of Iron Ore
faces.
Proposed method of mining
The existing method of mining, i.e. open cast mechanised will be continued in future
also for M-1,M-2 & M-3 pits. Proposed ROM @ 0.89 MT in 1st year and @0.96 MT in
remaining four years. Open cast mechanized mining is proposed for M-1,M-2 & M-3 pit
by contractual sources to fulfill the demand of BSP.
ROM produced from M-1 will be crushed at Mahamaya by contractual agencies and
finished product will be directly sent to Rajhara for despatch to Bhilai. Removal of
waste rock will be done simultaneously in a systematic manner to get the adequate
exposure of iron ore faces. It has also proposed to maintain the uniform benches of
5 mtrs. In all the 4 hills .It has been observed that the existing & proposed fleet of
mining equipment is adequate to handle the proposed excavation in all respects. In
case of enhancement in the fleet it can be managed with the contractual sources.
The time-to-time replacements shall be made for the departmental equipment
depending upon the hours consumed by the machine.
Handling of Waste material
Rate of yearly generation of waste and proposal for deposal of waste for
next five year is given in Table 2.18.
Table 2.18 Handling of waste
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-39
Richardson & Cruddas (1972) Ltd.
Year Top Soil Overburden/Waste Mineral Rejects
2011-12 Nil 645744 Nil
2012-13 Nil 757066 Nil
2013-14 Nil 704099 Nil
2014-15 Nil 741884 Nil
2015-16 Nil 767514 Nil
Total Nil 3616308 Nil
Waste generated from the M-1,M-2 ,M-3 & D-1 pits is dumped at the waste dump
located in the south-eastern slope. The area selected is a non-mineralised & away
from any perennial water source. The height of dump during the year 2011-12 will
be 20 mtrs. The waste quantity generated during 2011-12 to 2014-15 is 1723026
tonnes, will be proposed to dumped in the existing dump.
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-40
Richardson & Cruddas (1972) Ltd.
2.11 Conceptual Mining plan
The conceptual plan has been prepared for the period, in stages, after the end of
first 5 years of operation of Scheme of Mining period and after the end of Mining
Scheme period (2011-2016) in mahamaya mine (M-1, M-2 & M-3 block) ore will be
exhausted and in D-1 block (5 hect.) only 802744 T of ore will be left. Balance ore
will be mined out in next two year @ 0.4 MT/Year. Detail are given below.
M-1 BLOCK
Year Overburden
(waste) ROM Ore
Sub-grade Ore
Mineral Rejects
Stripping Ratio
2016-21 NIL NIL NIL Nil NIL
M-2 BLOCK
Year Overburden
(waste) ROM Ore
Sub-grade Ore
Mineral Rejects
Stripping Ratio
2016-21 NIL NIL NIL Nil NIL
M-3 BLOCK
Year Overburden
(waste) ROM Ore
Sub-grade Ore
Mineral Rejects
Stripping Ratio
2016-21 NIL NIL NIL Nil NIL
D-1 BLOCK
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-41
Richardson & Cruddas (1972) Ltd.
Year Overburden
(waste) ROM Ore
Sub-grade Ore
Mineral Rejects
Stripping Ratio
2016-18 271193 802744 Nil Nil 1:0.34
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-42
Richardson & Cruddas (1972) Ltd.
Exploration during Mining Scheme period
Year-wise Proposal as per Mining Scheme period (2011-16) is given in Table 2.19
Table 2.19 Year-wise Proposal as per Mining Scheme period (2011-16)
Year
Location of Bore holes
Boreholes to be drilled
Borehole No.
Boreholewise proposed meterage
Total meterage Remarks
1st (2011-12)
M-1 deposit
24
PR-32 PR-33 PR-34 PR-35 PR-36 PR-37 PR-38 PR-39 PR-40 PR-41 PR-42 PR-43 PR-44 PR-45 PR-46 PR-47 PR-48 PR-49 PR-50 PR-51 PR-52 PR-53 PR-54 PR-55
30 15 50 60 25 25 25 20 20 25 25 20 35 35 35 40 45 15 15 15 30 30 40 40
715
In case these
holes are not
touching the foot wall, the
drilling will continue to further depths
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-43
Richardson & Cruddas (1972) Ltd.
Year
Location of Bore holes
Boreholes to be drilled
Borehole No.
Boreholewise proposed meterage
Total meterage Remarks
1st (2011-12)
M-2 deposit
12
PR-20 PR-21 PR-22 PR-23 PR-24 PR-25 PR-26 PR-27 PR-28 PR-29 PR-30 PR-31
25 20 25 40 20 20 50 30 25 20 15 20
310
In case these
holes are not
touching the foot wall, the
drilling will continue to further depths
1st (2011-12)
M-3 deposit
19
PR-1 PR-2 PR-3 PR-4 PR-5 PR-6 PR-7 PR-8 PR-9 PR-10 PR-11 PR-12 PR-13 PR-14 PR-15 PR-16 PR-17 PR-18 PR-19
30 30 30 30 30 35 35 20 25 20 20 40 35 45 25 35 40 70 25
620
In case these
holes are not
touching the foot wall, the
drilling will continue to further depths
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-44
Richardson & Cruddas (1972) Ltd.
Year
Location of Bore holes
Boreholes to be drilled
Borehole No.
Boreholewise proposed meterage
Total meterage Remarks
1st (2011-12)
D-1 deposit
20
KR-1 KR-2 KR-3 KR-4 KR-5 KR-6 KR-7 KR-8 KR-9 KR-10 KR-11 KR-12 KR-13 KR-14 KR-15 KR-16 KR-17 KR-18 KR-19 KR-20
40 40 40 40 60 90 100 55 50 80 30 70 35 30 35 20 40 30 30 40
955
In case these
holes are not
touching the foot wall, the
drilling will continue to further depths
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-45
Richardson & Cruddas (1972) Ltd.
2.12 Mine drainage
Mahamaya - Dulki area is it part of Dalli hill range and occurring above the ground
water table as revealed from few boreholes i.e. 424 to 432 MSL. The bottom most
bench during the next three years working will be at 690 mRL, which is much more
above the ground water table. The drainage pattern of the mine is such that the run
off during the monsoon goes along the non-perennial water courses.
The mine drainage system will be through open channel to natural drain. These
drains will be made all along with haul road to collect the rain water flowing around
the mine and the hill slope. During the monsoon the surface water may contain
higher concentration of suspended solids. A good number of check dams and water
filter beds will be constructed.
2.13 Use of Minerals
The iron ore mined will be used for consumption in Bhilai Steel Plant for Iron and Steel
making. The Bhilai Steel Plant is situated at about 120 km. No sizing or screening will
be done at the mine head of Mahamaya - Dulki area. The entire ROM (60% lump &
40% fines) will be transported to processing plant of Dalli - Rajhara Mechanised mine.
After crushing and screening the iron ore will be sent to Bhilai Steel Plant. The lumps
will be used for charging the blast furnace to produce the hot metal the high grade
fines will be used for sinter making.
2.14 Other services available at the site
The existing site services provided for Mahamaya iron ore mine will be utilized for the
expansion project also. The preventive and regular maintenance will be done at tipper
garage. This garage will cater the Heels of equipments which will be used during the
course of mining. The major repairs and overhauling will be done at the workshops of
Dalli - Rajhara group of mines. The drilling garage at existing Mahamaya mines will
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-46
Richardson & Cruddas (1972) Ltd.
cater the needs of drills and compressors. The major repairs and overhauling will be
done by garages and workshops of Dalli - Rajhara group of mines. There is a small
township for regular staff and executives of the mine, which will be used for proposed
expansion also.
There is a small health centre for taking care of day to day requirement In case of
serious problem the patients will be referred to Rajhara main hospital. The details of
infrastructure of hospital is mentioned below:-
Staff Nos.
Doctor 1
Lady Doctor 1 (only on Friday)
Pharmacist 1
Male Nurse 1
Dresser 1
Attendant 1
Sweeper 1
The available facilities are treatment lo OPD patients, observation facility for
emergency cases, ambulance for shifting patient to main hospital Immunization,
drugs, injection and a dressing room.
2.15 Facilities available with Dalli-Rajhara Group of Mine
The following facilities are available at Dalli – Rajhara mines
• Earth Moving Machinery Garage
• Central Garage
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-47
Richardson & Cruddas (1972) Ltd.
• Central Repair Shed
• Machine Repair shop/Block Repair shop
• Electrical Repair Shop
• Fire Service Station
• Tele phone Exchange
• Vocational Training Centre
• Canteen facilities
• Water Supply
• Power Supply
2.16 Mineral Processing
The ROM which will be produced at the mine (60% lump and 40% fines) will be
transported in 10 T tipper to the processing plant of Dalli – Rajhara mechanized
mine. Following equipments are being used at the processing plant of Dalli –
Rajhara Mechanised mine.
Nos.
a) Gyratory Crusher – 2100 T/Hour Capacity 1
b) Jaw Crusher 780 T/Hour Capacity 1
(2100 mm, 1500 mm)
c) Cone crusher 2200 mm Dia. – 800 TPH 2
d) Inertia screens 40 x 40/30x30 mm 870 TPH 4
e) Inertia screens double deck 8x10x20 4
f) Scrubbers 8’ dia 20’ 450 TPH 4
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-48
Richardson & Cruddas (1972) Ltd.
g) Duplex Spiral Classifiers 520 TPH 4
The plant can process the ore by dry/wet circuit. However only wet circuit is being
used. It has mainly 3 stages (i) Crushing (ii) Scrubbing and (iii) Screening and
Classification. The feed ore (-1200 mm) after primary and secondary crushing is
separated as BF grade (+40 mm) and conveyed to storage bins. The – 40mm
product is discharged into secondary storage bunker and fed to wet circuit. In the
wet circuit the – 40 mm ore is subjected to washing and scrubbers, then wet
screened and separated as BF grade (+10-40 mm). The remaining – 10mm is
passed through duplex spiral classifiers and +0.2 – 10 mm fraction is obtained as
SF (sinter fines). The – 0.2 mm fraction goes as slime to Radial settling tank for
recirculation of water.
Recently the Gyratory crusher of 2100 T/hour capacity has been installed feeding to
the main plant bunker for further processing through main plant. The product size of
gyratory crusher is 0-300 mm. This unit is having water and oil mixed water dust
suppression system including pressurization, ventilation system and plenum
ventilation system.
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-49
Richardson & Cruddas (1972) Ltd.
Dry Screening Bunker
For processing high grade fines from the manual working which contains substantial
amount of micro fines which would be lost in slime if processed through wet circuits.
Beneficiation
Average Analysis Report of the processed ore from the plant is as follows
(Ore from other mine)
I. Feed % 2.Conccntrate % 3.Tailings %
ROM Lumps Fines
Fe 62.76 65.33 64.54 49.63
SiO2 4.08 2.33 2.97 12.75
Al2O3 3.39 1.97 2.45 10.57
P 0.053 0.053 0.054 0.053
The ore after processing in the plant will be transported to Bhilai Steel Plant by
rakes. Lumps are loaded through overhead bunkers and fines loading are done
through excavators and loaders.
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-50
Richardson & Cruddas (1972) Ltd.
CHAPTER - III
DESCRIPTION OF ENVIRONMENT
The present environmental status of the proposed projects has been studied covering 10 Km radius and presented in this chapter. It is necessary to know the present quality of the environment with respect to the various aspects considered under impact identification. These factors include air, water, noise, soil, meteorology, land use, flora & fauna, socio-economic and demographic pattern. For this purpose, monitoring schedule covering the four seasons in the year 2009-2010 as per the details given below to generate baseline environmental data. The environmental monitoring was also carried out as per NAAQ 2009 standards during Pre-monsoon 2011 (March-May). As per the instructions given by the Expert Appraisal Committee one month additional data in 12 locations covering 10 km radius was carried out for Ambient Air Quality during November 2012. The water and noise level monitoring was also carried out during November 2012.
Table 3.1 Calendar of environmental monitoring of the study area
S.No. Monitoring period Season Details of monitoring
1 01st aPRIL`09-30TH jUNE`09
Pre-monsoon Ambient Air quality monitoring, Continuous meteorology, Noise level, Water quality, Soil quality, Hydrogeology
2 August – September`2009
Monsoon Water quality
3 01st October`09- 31st December`09
Post-monsoon
Ambient Air quality monitoring , Continuous meteorology, Noise level, Water quality, Soil quality, Hydrogeology
4 01st January`10-31st March`10
Winter season
Ambient Air quality monitoring , Continuous meteorology, Noise level, Water quality, Soil quality, Hydrogeology, Flora- Fauna, Socio-economic survey
5 March – May 2011 Pre-monsoon Ambient air quality as per NAAQS 2009
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-51
Richardson & Cruddas (1972) Ltd.
dtd .18.11.2009 standards
6 November 2012 Postmonsoon Ambient Air Quality, Noise Level and Water Quality.
The baseline data on flora & fauna, socio-economic and demographic factors, land use pattern, forests, geology, hydro-geology, soil and agriculture, mineral resources etc. was carried out by field survey and secondary data has been collected from the State Government authorities and compilation of all season are presented in this chapter.
3.1 Air Environment
Identification of different pollutants, which are expected to be released into the atmosphere and having significant impact on the neighborhood, is an essential component in impact assessment of the air environment. The ambient air quality status of the study area of 10 km radial distance from the existing project will form the baseline information. The predicted impacts due to the project will be superimposed to find out the net (final) impacts (post-project scenario) on environment.
If the final impacts due to the proposed project are known at the planning stage of the project, a viable Environmental Management Plan (EMP) can be proposed to mitigate and minimize adverse effects on the environment. The design of the ambient air quality-monitoring network in the air quality surveillance programme is based on the following considerations.
- Micro-meteorological conditions of the study area on synoptic scale
- Topography of the study area
- Representation of regional background levels
- Representation of core zone
- Representation of cross sectional distribution in the downwind directions
- Influences of the existing sources, if any.
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-52
Richardson & Cruddas (1972) Ltd.
3.1.1 CLIMATE AND METEOROLOGY
Regional climate and meteorology:
The study area lies in sub-tropical region where climate is characterized by hot summer, moderate monsoon and mild winter seasons. Summer is typically from March to mid June, when temperature ranges from a maximum of 45°C during daytime to a minimum of 27°C at night. Winter from January to February, when the maximum temperature during day time goes upto 36°C and minimum temperature 17°C at night. The area receives max annual rainfall of 1100mm. The rains predominantly occur between mid June to September due to south-west monsoon. Table3.2 presents month-wise average rainfall for the last six years (Source : IMD,Govt. of India).
TABLE - 3.2 MONTHLY RAINFALL (mm)
Month 2004 2005 2006 2007 2008 2009
January 0 0 0 0 0 0
February 0 - 0 5.8 0 0
March 0 3.5 26.8 1.8 6.8 0
April 0 6.2 18.2 0 0 0
May 0 29.3 44.8 0 0 0
June 291.8 98.2 27.4 229.6 240.0 21.5
July 306.4 326.0 251.7 298.4 138.3 405.2
August 300.5 236.4 392.6 328.8 287.9 213.0
September 85.9 353.5 120.5 202.1 231.8 51.8
October 13.3 48.2 4.4 2.0 0 4.2
November 0 0 0 0 0 0
December 0 2.6 0 0 0 0
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-53
Richardson & Cruddas (1972) Ltd.
Total 997.9 1103.9 886.4 1068.5 904.8 695.7
The pattern of rainfall is irregular and varies significantly from year to year.
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-54
Richardson & Cruddas (1972) Ltd.
Wind speed and wind direction have a significant role on the dispersion of atmospheric pollutants and therefore the air quality of area. Ground level concentrations for the pollutants are inversely proportional to the wind speed in down wind direction while in upwind direction no effect will be observed and in cross wind directions partial effect due to the emission source is observed.
Micrometeorology at site
Prevailing micro-meteorological conditions at site regulate the dispersion (and hence dilution) of air pollutants in the atmosphere. Therefore, study of meteorological conditions is an integral part of environmental impact assessment studies. Accordingly, a meteorological station was set up at project site. The following parameters were recorded at hourly intervals during all the seasons viz. Summer, Post-monsoon & Winter
Air temperature (°C)
Relative humidity (%)
Wind speed (m/s)
Wind direction (eight quadrants)
The data collected on wind speed and wind direction was used for computation of wind percentage frequencies in all the sixteen directions for wind speed in the range of 1.0 -5.0, 5.1-11.0, 11.0-19.0 and 19-29 kmph. Wind speed <1.0 kmph was considered as calm condition. Table 3.3 through 3.6 show the wind distribution pattern of 0-24 hours in each season. The seasonal and shift-wise wind rose diagrams for Pre-monsoon 2009, Post-monsoon 2009 & Winter 2009-10 seasons are presented in Fig. III.1-6.The season and shift-wise windrose for Pre-monsoon 2011 is given in Fig.III.7-8.
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-55
Richardson & Cruddas (1972) Ltd.
TABLE - 3.3 WIND FREQUENCY, DISTRIBUTION (0-24 hrs) (Pre-monsoon 2009)
Direction of wind
Wind frequency (%)
Calm 1-5 km/h
5-11 km/h
11-19 km/h
19-29 km/h Total
N
3.43
1.28 0.60 0.09 - 1.97
NNE 3.07 0.69 0.27 - 4.03
NE 4.99 1.47 0.64 - 7.10
ENE 1.14 0.46 - - 1.60
E 0.09 - - - 0.09
ESE 0.05 0.05 - - 0.10
SE 2.75 0.87 0.37 - 3.99
SSE 0.92 0.27 0.09 - 1.28
S 0.69 0.18 - 0.87
SSW 6.55 3.39 1.37 - 11.31
SW 20.97 10.12 3.53 - 34.62
WSW 11.58 4.12 1.42 - 17.12
W 4.80 2.15 0.73 - 7.68
WNW 1.10 0.55 0.18 - 1.83
NW 2.11 0.27 0.09 - 2.47
NNW 0.41 0.05 0.05 - 0.51
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-56
Richardson & Cruddas (1972) Ltd.
TABLE - 3.4
WIND FREQUENCY, DISTRIBUTION (0-24 HRS) (Post-monsoon 2009)
Direction of wind
Wind frequency (%)
Calm 1-5 km/h
5-11 km/h
11-19 km/h
19-29 km/h Total
N
9.74
13.81 2.76 0.91 - 17.48
NNE 10.78 3.08 1.04 - 14.9
NE 16.30 5.16 0.91 - 22.37
ENE 2.22 0.72 0.14 - 3.08
E 0.95 - - - 0.95
ESE 1.36 0.05 - - 1.41
SE 2.90 0.23 - - 3.13
SSE 0.99 0.14 - - 1.13
S 0.90 - - - 0.9
SSW 3.49 0.54 - - 4.03
SW 3.08 0.58 - - 3.66
WSW 0.77 0.23 0.09 - 1.09
W 0.91 0.09 - - 1
WNW 1.13 0.14 - - 1.27
NW 5.70 0.95 0.23 - 6.88
NNW 5.71 1.13 0.14 - 6.98
TABLE – 3.5 WIND FREQUENCY, DISTRIBUTION (0-24 HRS) (Winter)
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-57
Richardson & Cruddas (1972) Ltd.
Direction of wind
Wind frequency (%)
Calm 1-5 km/h
5-11 km/h
11-19 km/h
19-29 km/h Total
N
13.05
4.40 0.14 0.04 - 4.58
NNE 19.50 0.65 0.37 - 20.52
NE 15.84 1.02 0.28 - 17.14
ENE 1.30 0.23 - - 1.53
E 0.42 0.04 - - 0.46
ESE 0.33 - - - 0.33
SE 1.48 0.18 - - 1.66
SSE 1.48 0.14 - - 1.62
S 0.83 0.04 - - 0.87
SSW 3.47 0.42 - - 3.89
SW 5.19 0.46 0.04 - 5.69
WSW 10.56 0.74 0.09 - 11.39
W 3.25 0.66 - - 3.85
WNW 4.90 0.33 - - 5.23
NW 4.30 0.46 - - 4.76
NNW 3.29 0.14 - - 3.43
TABLE – 3.6
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-58
Richardson & Cruddas (1972) Ltd.
WIND FREQUENCY, DISTRIBUTION (0-24 HRS) (Pre-monsoon 2011)
Direction of wind
Wind frequency (%)
Calm 1-5 km/h
5-11 km/h
11-19 km/h
19-29 km/h Total
N
2.40
1.22 0.54 0.09 - 1.86
NNE 3.13 0.54 0.18 - 3.85
NE 5.12 1.49 0.36 - 6.98
ENE 1.22 0.50 0.00 - 1.72
E 0.14 0.00 0.00 - 0.14
ESE 0.09 0.05 0.00 - 0.14
SE 2.94 0.77 0.32 - 4.03
SSE 0.82 0.23 0.09 - 1.13
S 0.54 0.18 0.00 - 0.72
SSW 6.12 3.40 1.22 - 10.74
SW 19.16 8.43 3.90 2.13 33.61
WSW 12.14 4.67 1.68 - 18.48
W 5.12 2.36 0.77 - 8.24
WNW 2.08 0.41 0.27 - 2.76
NW 1.90 0.50 0.09 - 2.49
NNW 0.52 0.09 0.09 - 0.70
Fig. III.1
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-59
Richardson & Cruddas (1972) Ltd.
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-60
Richardson & Cruddas (1972) Ltd.
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-61
Richardson & Cruddas (1972) Ltd.
Fig. III.2
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-62
Richardson & Cruddas (1972) Ltd.
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-63
Richardson & Cruddas (1972) Ltd.
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-64
Richardson & Cruddas (1972) Ltd.
Fig. III.3
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-65
Richardson & Cruddas (1972) Ltd.
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-66
Richardson & Cruddas (1972) Ltd.
Fig. III.4
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-67
Richardson & Cruddas (1972) Ltd.
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-68
Richardson & Cruddas (1972) Ltd.
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-69
Richardson & Cruddas (1972) Ltd.
Fig. III.5
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-70
Richardson & Cruddas (1972) Ltd.
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-71
Richardson & Cruddas (1972) Ltd.
Fig. III.6
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-72
Richardson & Cruddas (1972) Ltd.
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-73
Richardson & Cruddas (1972) Ltd.
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-74
Richardson & Cruddas (1972) Ltd.
Fig. III.7
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-75
Richardson & Cruddas (1972) Ltd.
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-76
Richardson & Cruddas (1972) Ltd.
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-77
Richardson & Cruddas (1972) Ltd.
Fig. III.8
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-78
Richardson & Cruddas (1972) Ltd.
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-79
Richardson & Cruddas (1972) Ltd.
The abstract of micro-meteorological status is furnished in Table 3.7. The daily abstract and micro-meteorological data are given in Annexure–I (Baseline Environmental data).
Table 3.7 ABSTRACT OF MICRO-METEOROLOGICAL DATA
Sl. No. Parameters
Season
Pre-monsoon 2009
Monsoon 2009
Post
Monsoon 2009
Winter 2010
Pre-monsoon 2011
Post-monsoon (Nov.2012)
1 Predominant Wind Direction (From) SW WSW NE ENE SW NE/NNE
2 Calm Condition (%) 3.43 - 9.74 13.05 2.40 10.50
3 Predominant Prevailing Wind Range (Kmph)
1-5 1-5 1-5 1-5 1-5 1-5
4 Wind Speed (Kmph)
i. Minimum <1.0 - <1.0 <1.0 <1.0 <1.0
ii. Maximum 18.0 - 14.7 17.7 20.4 12.7
5 Temperature (°C) -
i. Minimum 24.5 - 13.5 10.0 25.0 16.5
ii. Maximum 46.0 - 32.0 39.0 44.0 30.5
6 Relative Humidity (mean)(%) -
i. Minimum 37.9 - 58.4 52.8 35.4 58.0
ii. Maximum 70.3 - 74.2 75.5 68.4 72.0
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-80
Richardson & Cruddas (1972) Ltd.
7 Total Rainfall (cm) 3.3 80.2 7.8 0.2 0.0 0.0
Data Analysis
Meteorological data collected during the study period reveals the following status.
Pre-monsoon 2009 : Predominant wind was from South-west quadrant. Wind velocity was ranging from <1.0 to 18.0 Kmph. Temperature values were ranging from 24.5 °C to 46.0°C. The mean relative humidity value was found to be ranging from 37.9 - 70.3 %.Sky was clear during the study period. A total rainfall of 3.3 cm was recorded during the study period.
Monsoon`09 : A total rainfall of 80.2 cm was recorded during the study period.
Post-monsoon`09: Predominant wind was from North-east quadrant. Wind velocity was ranging from <1.0 to 14.7 Kmph. Temperature values were ranging from 24.5 °C to 46.0°C. The mean relative humidity value was found to be ranging from 37.9-70.3%.Sky was clear during the study period. A total rainfall of 3.3 cm was recorded during the study period.
Winter 2010 : Predominant wind was from East Northeast quadrant. Wind velocity was ranging from <1.0 to 17.7 Kmph. Temperature values were ranging from 10.0 °C to 39.0.0°C. The mean relative humidity value was found to be ranging from 52.8-75.5 %.Sky was clear during the study period. A total rainfall of 0.2 cm was recorded during the study period.
Pre-monsoon 2011 : Predominant wind was from South-west quadrant. Wind velocity was ranging from <1.0 to 20.4 Kmph. Temperature values were ranging from 25.0 °C to 44.0°C. The mean relative humidity value was found to be ranging from 35.4 – 68.4 %.Sky was clear during the study period. No rainfall was recorded during the study period.
Post-monsoon (November 2012): Predominant wind was from NE/NNE. Wind velocity was ranging from <1.0 to 12.7 Kmph. Temperature values were ranging from 16.5 °C to 30.5°C. The mean relative humidity value was found to be ranging from 58 – 72 %. Sky was clear during the study period. No rainfall was recorded during the study period.
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-81
Richardson & Cruddas (1972) Ltd.
3.1.2 Existing Ambient Air Quality
Methodology for Ambient Air Quality
Based on the project activities the parameters chosen for assessment of ambient air quality were Suspended Particulate Matter (SPM), Respirable Particulate Matter (RPM), Sulphur di-oxide (SO2), Oxides of Nitrogen (NOx), and Heavy metals. The sampling and analysis of ambient air quality parameters was carried out as per the procedures detailed in relevant parts of IS 5182 (Indian Standards for Ambient Air Quality parameters).Brief of these testing procedures are given in Table 3.8.The ambient air quality monitoring stations are shown in Fig. III.9 -12 and given in Table 3.9.
Table – 3.8
Procedures for Determining Various Air Quality Parameters
PM10 Gravimetric method using Respirable dust sampler
PM2.5 Gravimetric method using Fine particulate sampler
SPM Gravimetric method using Respirable dust sampler IS:5182
NOx Absorption in dilute NaOH for colorimetric estimation with sulphanilamide and N(1-Naphthyl) Ethylene Diamine Dihydrochloride and Hydrogen Peroxide (IS:5182, 1975, Part V)
SO2 Absorption in Sodium Tetra Chloromercurate followed by colorimetric estimation using p-Rosaniline Hydrochloride and Formaldehyde (IS:5182 Part II, 1969)
CO GC-FID method IS: 5182 ( Part XVII)
Heavy Metals High volume sampling through EPM 2000 Filter paper and analysis through AAS
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-82
Richardson & Cruddas (1972) Ltd.
A field laboratory for the purpose of calibration of equipments and standardization of analytical procedures was established and the samples were analyzed on the day of sample collection.
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-83
Richardson & Cruddas (1972) Ltd.
Table - 3.9
Ambient air quality monitoring stations
Sl.No Location name Monitoring season Distance in Km Direction
1 Core zone (Mine pit 3) S,P,W & Nov.’12 - -
2 Corezone (Canteen) S,P,W & Nov.’12 - -
3 Gajjitola S 4.9 NW
4 Dongarbhar S, P,W 6.2 SW
5 Kanikasur S, P,W 2.5 W
6 Nergaon S, P,W 6.4 SSW
7 Kumarkatta S 1.6 NE
8 Kopedera S 1.8 ENE
9 Dupkatola S,P,W & Nov.’12 3.9 E
10 Katrel S 1.7 SE
11 Tuedand P,W & Nov.’12 4.4 NE
12 Dulki P,W & Nov.’12 1.0 W
13 Markamtola P,W & Nov.’12 1.1 NW
14 Resuli P,W & Nov.’12 6.3 SSW
15 Kalangpur Nov. 2012 7.2 S
16 Bodra Nov. 2012 4.7 WSW
17 Kalwar Nov. 2012 4.5 S
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-84
Richardson & Cruddas (1972) Ltd.
18 Dorba Nov. 2012 8.1 WNW
19 Nagbur Nov. 2012 8.3 SSW
S - PRE-MONSOON P- POSTMONSOON W- WINTER
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-85
Richardson & Cruddas (1972) Ltd.
Fig.III.9 Location Map of Ambient air Quality (Pre-monsoon)
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-86
Richardson & Cruddas (1972) Ltd.
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-87
Richardson & Cruddas (1972) Ltd.
Fig.III.10 Location Map of Ambient air Quality (Post-monsoon)
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-88
Richardson & Cruddas (1972) Ltd.
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-89
Richardson & Cruddas (1972) Ltd.
Fig.III.11 Location Map of Ambient air Quality (Winter)
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-90
Richardson & Cruddas (1972) Ltd.
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-91
Richardson & Cruddas (1972) Ltd.
Fig.III.12 Location Map of Ambient air Quality (November 2012)
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-92
Richardson & Cruddas (1972) Ltd.
Data Analysis
The Ambient air quality status is given in Table 3.10-3.12 and summary of Ambient Air quality data is given in Annexure – II (Baseline Environmental data).
Pre-monsoon season (Apr.09-Jun.09)
Corezone : SPM and RPM values were ranging between 200 and 321 µg/m3 and 83 and 128 µg/m3 respectively. The SO2 and NOx values were ranging between 8.2 and 14.2 µg/m3 and 8.9 and 15.8 µg/m3 respectively.
Bufferzone : SPM and RPM values were ranging between 77 and 184 µg/m3 and 24 and 83 µg/m3 respectively. The SO2 and NOx values were ranging between 5.5 and 9.7 µg/m3 and 6.8 and 11.2 µg/m3 respectively.
Post-monsoon Season (Oct-Dec.09)
Corezone : SPM and RPM values were ranging between 205 and 321 µg/m3 and 59 and 90 µg/m3 respectively. The SO2 and NOx values were ranging between 8.7 and 10.8 µg/m3 and 10.6 and 12.9 µg/m3 respectively.
Bufferzone : SPM and RPM values were ranging between 90 and 172 µg/m3 and 34 and 74 µg/m3 respectively. The SO2 and NOx values were ranging between 5.2 and 9.2 µg/m3 and 6.3 and 11.5 µg/m3 respectively.
Winter season (Jan – Mar.10)
Core-zone : SPM and RPM values were ranging between 185 and 293 µg/m3 and 62 and 96 µg/m3 respectively. The SO2 and NOx values ere ranging between 7.1 and 9.7 µg/m3 and 9.0 and 11.5 µg/m3 respectively.
Buffer-zone : SPM and RPM values were ranging between 102 and 177 µg/m3 and 34 and 74 µg/m3 respectively. The SO2 and NOx values were ranging between 5.6 and 9.9 µg/m3 and 6.9 and 12.3 µg/m3 respectively.
Pre-monsoon season (March – May 2011)
Core zone : PM10 and PM2.5 values were ranging between 77 and 125 µg/m3 and 28 and 46 µg/m3 respectively. The SO2 and NOx values were ranging between 8.8 and 14.8 µg/m3 and 9.3 and 16.7 µg/m3 respectively. The Ammonia and Ozone values were ranging between 18 and 38 µg/m3 and 6 and 17 µg/m3 respectively.
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-93
Richardson & Cruddas (1972) Ltd.
Buffer zone : PM10 and PM2.5 values were ranging between 30 and 65 µg/m3 and 8 and 21 µg/m3 respectively. The SO2 and NOx values were ranging between 4.1 and 10.2 µg/m3 and 4.1 and 16.1 µg/m3 respectively. The Ammonia and Ozone values were ranging between 10 and 40 µg/m3 and 4 and 14 µg/m3 respectively.
Postmonsoon (November 2012)
Core zone : PM10 and PM2.5 values were ranging between 58 and 82µg/m3 and 19 and 28 µg/m3 respectively. The SO2 and NOx values were ranging between 6.4 and 10.2 µg/m3 and 9.2 and 16.3 µg/m3 respectively. CO values were ranging between 285 and 410 µg/m3. The heavy metals values are found to be negligible.
Buffer zone : PM10 and PM2.5 values were ranging between 44 and 64 µg/m3 and 14 and 23 µg/m3 respectively. The SO2 and NOx values were ranging between 5.8 and 9.1 µg/m3 and 9.1 and 15.6 µg/m3 respectively. CO values were ranging between 210 and 355 µg/m3. The heavy metals values are found to be negligible
3.2 Noise Levels
Methodology
Noise levels were monitored at twelve locations within and outside the project premises. Noise readings were taken for daytime as well as night time. CYGNET 100X data logging Sound level meter was used for recording noise levels.
Data Analysis
The noise level abstract is given in Table 3.14 and Noise level data is given in Annexure – II (Baseline Environmental data).
Summer: The Day and night time Leq Noise levels were ranging from 39.6 dB(A) to 57.7 dB(A) and 30 dB(A) to 47.4 dB(A) respectively.
Post-monsoon: The Day and night time Leq Noise levels were ranging from 41.3 dB(A) to 55.3 dB(A) and 29.8 dB(A) to 46.6 dB(A) respectively
Winter: The Day and night time Leq Noise levels were ranging from 43.2 dB(A) to 56.9 dB(A) and 33.8 dB(A) to 49.3 dB(A) respectively.
November 2012: The Day and night time Leq Noise levels were ranging from 42.3 dB(A) to 54.8 dB(A) and 32.3 dB(A) to 45.0 dB(A) respectively.
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-94
Richardson & Cruddas (1972) Ltd.
The Noise level values were found to be well within the CPCB limit prescribed by CPCB.
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-95
Richardson & Cruddas (1972) Ltd.
Table 3.10
Ambient Air quality status
Location Name
SUSPENDED PARTICULATE MATTER (SPM) (microgram/m3)
PRE-MONSOON`09
POSTMONSOON`09 WINTER`10
Min. Max. Avg. Min
. Max. Avg. Min. Ma
x. Avg.
Core zone (Mine pit 3) 200 321 269.0 195 261 228.
9 209 293 293
Corezone (Canteen) 205 281 252.5 196 255 227.0
185 258 258
Gajjitola 77 112 93.8 - - - - -
Dongarbhar 98 110 104.5 98 138 120.9
112 152 134.9
Kanikasur 89 124 106.4 134 172 149.0
139 177 151.9
Nergaon 96 122 108.6 98 156 129.3
111 169 141.7
Kumarkatta 131 176 143.2 - - - - - -
Kopedera 139 184 152.0 - - - - - -
Dupkatola 127 172 139.2 90 125 112.3
102 137 124.3
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-96
Richardson & Cruddas (1972) Ltd.
Katrel 111 123 117.5 - - - - - -
Tuedand - - - 98 110 104.5
102 114 108.5
Dulki - - - 132 152 142.5
137 157 147.5
Markamtola - - - 101 161 135.3
109 169 143.3
Resuli - - - 97 132 114.1
111 146 128.1
RESPIRABLE PARTICULATE MATTER (RPM) (microgram/m3)
Core zone Mine Pit 3) 83 128 106.3 59 89 76.8 70 96 83.0
Corezone (Canteen) 88 117 103.9 70 90 80.1 62 80 70.1
Gajjitola 24 36 29.2 - - - - - -
Dongarbhar 42 49 44.9 34 56 42.8 40 64 48.8
Kanikasur 37 48 42.5 37 60 44.0 42 65 49.0
Nergaon 46 57 51.2 31 49 41.1
Kumarkatta 56 75 60.9 - - - - - -
Kopedera 64 83 69.7 - - - - - -
Dupkatola 50 69 54.9 40 53 48.2 46 59 54.2
Katrel 33 41 36.5 - - - - - -
Tuedand - - - 42 49 44.9 44 51 46.9
Dulki - - - 55 74 59.5 59 78 63.5
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-97
Richardson & Cruddas (1972) Ltd.
Markamtola - - - 36 57 47.5 44 65 55.5
Resuli - - - 36 47 41.0 50 61 55.0
Table 3.10
Ambient Air quality status (contd.,)
Location Name
SULPHUR DI-OXIDE (SO2) (microgram /m3)
PRE-MONSOON 09
POSTMONSOON`09 WINTER`10
Min. Max. Avg. Min
. Max. Avg. Min. Ma
x Avg.
Core zone (Mine pit 3) 8.2 14.2 10.6 9.2 10.8 10.1 8.1 9.7 9.0
Corezone (Canteen) 8.6 11.3 9.8 8.7 10.2 9.4 7.1 8.6 7.8
Gajjitola 5.5 6.9 6.1 - - - - - -
Dongarbhar 6.1 8.6 7.4 5.2 9.1 7.8 6.0 9.9 8.6
Kanikasur 7.0 8.4 7.8 6.9 8.6 7.9 8.1 9.8 9.1
Nergaon 7.2 8.7 8.0 6.5 7.8 7.3 6.8 7.9 7.2
Kumarkatta 7.5 9.0 8.4 - - - - - -
Kopedera 7.2 8.7 7.9 - - - - - -
Dupkatola 7.4 9.7 8.7 5.0 7.3 6.1 5.6 7.9 6.7
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-98
Richardson & Cruddas (1972) Ltd.
Katrel 6.4 7.2 6.9 - - -
Tuedand - - - 8.1 8.6 7.4 7.2 9.7 8.5
Dulki - - - 8.2 10 9.1 7.1 8.9 8.0
Markamtola - - - 7.5 9.2 8.4 6.7 8.4 7.6
Resuli - - - 7.1 8.6 7.8 6.3 7.8 7.0
OXIDES OF NITROGEN (NOX) (microgram/m3)
Core zone Mine Pit 3) 9.0 15.8 12.5 10.
9 12.9 12.1 9.8 11.5 10.6
Corezone (Canteen) 8.9 13.2 11.2 10.6 12.3 11.3 9.0 10.
7 9.7
Gajjitola 6.8 9.0 7.7 - - - 7.3 12.0 10.1
Dongarbhar 7.6 8.9 7.8 6.7 11.0 9.5
Kanikasur 8.8 10.4 9.7 9.1 11.5 9.9 9.9 12.3 10.7
Nergaon 7.5 10.6 9.4 8.8 10.1 9.4 8.5 10.2 9.2
Kumarkatta 9.5 11.5 10.3 - - - - - -
Kopedera 7.8 10.9 9.7 - - - - - -
Dupkatola 9.2 11.2 10.7 6.3 9.8 8.5 6.9 10.4 9.1
Katrel 8.4 9.9 9.0 - - -
Tuedand - - - 7.6 11.1 9.8 8.4 11.9 10.6
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-99
Richardson & Cruddas (1972) Ltd.
Dulki - - - 10.2 11.7 11.1 9.1 10.
6 10.0
Markamtola - - - 8.1 11.2 10.0 7.3 10.4 9.2
Resuli - - - 8.8 10.5 9.6 8.0 9.7 8.8
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-100
Richardson & Cruddas (1972) Ltd.
Table 3.11
Ambient Air quality status (Pre-monsoon 2011)
Location name Parameters (µg/m3)
PM10 PM2.5 SO2 NOX Ammonia Ozone
Core zone (Mine pit 3)
Min 77 31 8.8 9.9 18.0 6.0
Max 116 46 14.8 16.7 34.0 14.0
Avg. 101.9 40.8 11.2 13.4 24.7 10.0
Corezone (Canteen)
Min 96 28 9.0 9.3 20.0 9.0
Max 125 38 11.9 13.8 38.0 17.0
Avg. 113.4 33.1 10.3 11.7 27.7 13.0
Gajjitola
Min 30 10 6.0 7.6 24.0 6.0
Max 41 13 7.7 9.8 40.0 14.0
Avg. 34.3 11.0 6.9 8.4 31.5 10.0
Dongarbhar
Min 32 8 4.8 6.9 16.0 8
Max 46 12 6.4 9.6 28.0 10
Avg. 38.7 10.1 5.5 8.8 22.0 8.7
Kanikasur
Min 38 9 6.2 7.2 15.0 10
Max 59 14 7.8 9.4 34.0 11
Avg. 47.1 11.3 6.8 8.4 23.4 10.5
Nergaon Min 36 9 6.6 4.2 17 6
Max 55 13 10.2 16.1 19 15
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-101
Richardson & Cruddas (1972) Ltd.
Avg. 49.8 11.9 9.0 11.8 18.1 11.8
Kumarkatta
Min 47 12 4.2 4.8 14 10
Max 62 16 6.0 7.1 16 12
Avg. 54.7 14.2 5.3 6.0 15.0 10.3
Kopedera
Min 48 16 6.4 7.7 17 6
Max 65 21 9.0 9.8 21 8
Avg. 57.0 18.8 7.4 8.6 19.0 7.1
Dupkatola
Min 33 9 4.8 4.1 10 4
Max 58 16 6.6 10.1 16 6
Avg. 48.9 13.7 5.6 7.5 13.5 5.0
Katrel
Min 36 13 4.1 4.8 12 5
Max 54 19 6.9 7.9 16 6
Avg. 44.9 16.2 5.7 6.2 14.4 5.5
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-102
Richardson & Cruddas (1972) Ltd.
Table 3.12
Ambient Air quality status (Postmonsoon – November 2012)
Location name Parameters (µg/m3)
PM10 PM2.5 SO2 NOX CO
Corezone (Mine Pit 3)
Min 62.0 22.0 8.4 9.2 285.0
Max 73.0 25.0 9.6 16.3 405.0
Avg. 67.9 23.9 9.0 13.4 336.9
Corezone (Canteen)
Min 58.0 19.0 6.4 12.2 310.0
Max 82.0 28.0 10.2 18.2 410.0
Avg. 69.0 23.8 8.5 14.4 341.3
Tuedand
Min 47.0 15.0 5.8 9.2 210.0
Max 56.0 18.0 7.2 14.2 355.0
Avg. 51.8 16.0 6.6 11.3 291.9
Dupkatola
Min 44.0 15.0 6.4 11.6 245.0
Max 52.0 18.0 9.1 13.4 305.0
Avg. 47.4 16.6 7.6 12.6 285.0
Dulki
Min 46.0 16.0 6.4 12.6 250.0
Max 56.0 19.0 7.4 15.4 325.0
Avg. 51.8 17.9 6.9 14.2 299.4
Markamtola Min 46.0 16.0 6.3 9.1 210.0
Max 56.0 18.0 7.2 13.2 305.0
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-103
Richardson & Cruddas (1972) Ltd.
Avg. 51.3 17.1 6.9 11.4 265.6
Kalangpur
Min 46.0 16.0 6.3 10.2 210.0
Max 64.0 23.0 7.2 14.8 305.0
Avg. 54.5 18.8 6.7 11.9 232.5
Rasuli
Min 45.0 14.0 6.2 12.3 230.0
Max 56.0 18.0 7.2 14.2 310.0
Avg. 50.9 16.0 6.5 12.9 268.1
Bodra
Min 48.0 15.0 6.2 9.8 285.0
Max 56.0 19.0 7.2 14.2 320.0
Avg. 53.4 17.4 6.7 12.7 307.5
Kalwar
Min 58.0 16.0 6.2 9.2 210.0
Max 64.0 19.0 8.6 15.2 305.0
Avg. 61.3 17.4 7.5 13.2 226.3
Dorba
Min 52.0 15.0 6.8 9.6 210.0
Max 62.0 20.0 7.2 15.6 310.0
Avg. 55.1 17.1 7.0 11.4 242.5
Nagbur
Min 46.0 18.0 5.8 9.6 210.0
Max 52.0 21.0 7.6 11.6 305.0
Avg. 48.5 19.0 6.7 10.6 225.6
Table 3.13
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-104
Richardson & Cruddas (1972) Ltd.
Heavy Metals in SPM Samples
Unit : ng/m3
Locations As Cd Cr Cu Mn Ni Fe Pb Zn
Corezone (Mine Pit 3) 0.05 0.01 0.05 0.11 0.07 0.43 4.27 0.18 3.20
Corezone (Canteen) 0.06 0.02 0.04 0.13 0.04 0.52 5.18 0.07 3.42
Tuedand 0.08 0.01 0.02 0.12 0.08 0.12 1.12 0.06 1.24
Dupkatola 0.05 0.01 0.05 0.12 0.05 0.12 1.24 1.06 1.23
Dulki 0.21 0.01 0.10 0.12 0.06 0.08 1.40 0.08 1.26
Markamtola 0.22 0.01 0.05 0.14 0.08 0.12 1.20 0.06 1.28
Kalangpur 0.08 0.02 0.06 0.12 0.06 0.12 1.40 0.07 1.26
Rasuli 0.12 0.01 0.02 0.12 0.05 0.12 1.52 0.10 2.01
Bodra 0.12 0.02 0.02 0.08 0.08 0.14 1.62 0.10 1.28
Kalwar 0.14 0.02 0.05 0.04 0.06 0.16 2.02 0.06 1.24
Dorba 0.14 0.02 0.05 0.08 0.08 0.14 1.52 0.06 1.45
Nagbur 0.12 0.01 0.06 0.10 0.10 0.18 1.56 0.05 1.25
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-105
Richardson & Cruddas (1972) Ltd.
Table – 3.14 Noise Level status
S. No Location Name
Noise Level, dB(A)
Day Time Night Time
Summer
Post-monsoon
Winter
Summer
Post-monsoon
Winter
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-106
Richardson & Cruddas (1972) Ltd.
1 Corezone (Mine Pit 3) (N1) 57.7 55.3 56.4 47.4 46.6 49.3
2 Corezone (Canteen) (N2) 55.9 54.7 56.9 45.6 45.0 46.0
3 Gajjitola (N3) 43.2 42.1 45.8 34.8 35.6 34.1
4 Dongarbhar (N4) 41.9 41.5 43.2 33.5 29.8 34.3
5 Kanikasur (N5) 39.6 41.3 44.9 30.3 35.7 33.8
6 Nergaon (N6) 43.1 45.5 48.3 34.7 39.1 40.2
7 Kumarkatta (N7) 53.6 53.0 55.5 43.3 44.4 46.0
8 Kopedera (N8) 54.7 50.7 49.9 35.6 38.2 43.3
9 Dupkatola (N9) 52.9 52.7 52.8 32.8 40.2 40.2
10 Katrel (N10) 46.2 48.9 49.2 35.1 36.7 38.5
11 Dulki (N11) 40.9 49.4 51.7 30.0 42.9 40.7
12 Bomboni (N12) 43.6 47.7 46.5 32.5 34.9 36.7
Sl. No.
Location Name Noise Level, dB(A), November 2012
Day time Night Time
1 Corezone (Mine Pit 3) 54.8 44.6
2 Corezone (Canteen) 54.2 45.0
3 Tuedand 42.3 32.3
4 Dupkatola 42.5 33.3
5 Dulki 42.7 34.4
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-107
Richardson & Cruddas (1972) Ltd.
6 Markamtola 44.3 36.2
7 Kalangpur 46.7 38.4
8 Rasuli 48.2 38.2
9 Bodra 50.1 40.2
10 Kalwar 47.8 40.1
11 Dorba 48.2 41.4
12 Nagbur 47.5 40.4
3.2.1 Vibration Monitoring
Vibrations were monitored at existing mines before blasting and during blasting. Also, vibrations were monitored nearby residential areas. Impact of vibrations if any, on residential areas and workers in the plant were evaluated in comparison with vibration standards as suggested by DGMS.
Vibration can be characterized by various parameters such as Peak Particle Velocity (PPV), Peak Vector Sum (PVS), Peak Displacement (Pk Disp.), Peak Acceleration (pk Accl.), Peak Sound Pressure Level (PSPL) and Zero Crossing (ZC) frequency. Vibrations were monitored at various locations in and around (residential areas) the mine. The background vibrations recorded at mine at a distance of 320m and 640m from the blasting site is given in Table 3.15. The ground vibrations generated during blasting operations at a distance of 320m and 640m from the blasting site is given in Table 3.16.The vibrations monitored at various residential areas are give in Table 3.17. All these values are observed to be below the stipulated limits of DGMS and BIS.
Table 3.15
Baseline Ground Vibrations Recorded within Mahamaya - Dulki mine (March 2011)
Sr. Location PPV PVS Peak Peak PSPL ZC
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-108
Richardson & Cruddas (1972) Ltd.
No. (mm/s) (mm/s) disp.
(mm)
Accel.
(g)
dB(L) (Hz)
1. Blasting site 0.06T 0.0674 0.0002 0.0099 118.1 >200
2. 320 m from Blasting site
0.0794L 0.0809 0.0004 0.0099 104.2 >200
3. 640 m from Blasting site
0.175V 0.198 0.0 0.0099 111.2 -
Table 3.16
Vibrations Generated By Blasting Operations within Mahamaya-Dulki mine (March 2011)
Sr. No.
Name of mine / location
PPV
(mm/s)
PVS
(mm/s)
Pk disp
(mm)
Pk
Accel.(g)
PSPL
dB(L)
ZC (Hz)
1 Mine I (320 m away from blasting site)
1.29T 1.31 0.037 0.013 129.3 4.3
2 Mine I (640 m away from blasting site)
0.222T 0.253 0.019 0.0099 107.9 3.5
Table 3.17
Vibration Monitoring at Residential Areas around the Mahamaya-Dulki mine (March 2011)
Sr. Location name PPV PVS Peak Peak PSPL ZC
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-109
Richardson & Cruddas (1972) Ltd.
No. (mm/s) (mm/s) disp.
(mm)
Accel.
(g)
dB(L) (Hz)
1. Gajjitola (N3) 0.651V 0.756 0.0 0.0099 91.5 -
2. Dongarbhar (N4)
0.619V 0.747 0.0 0.0099 95.9 -
3. Kanikasur (N5) 0.698V 0.799 0.0 0.0099 94.0 -
4. Nergaon (N6) 0.175T 0.175 0.0002 0.013 94.0 102
5. Kumarkatta (N7)
0.0635T 0.0979 0.0562 0.0099 101.9 8.9
6. Kopedera (N8) 0.317V 0.342 0.0 0.0099 98.8 -
7. Dupkatola (N9) 0.429V 0.508 0.0 0.0099 91.5 -
8. Katrel (N10) 0.206L 0.239 0.0 0.0099 91.5 -
9. Dulki (N11) 0.381V 0.434 0.0 0.0099 98.8 -
10. Bomboni (N12) 0.730V 0.899 0.0 0.0099 91.5 -
3.3 Water Environment
Detailed survey was carried out based on the location of ground and surface water bodies, which represent baseline condition. A total of 10 water samples Viz., 8 ground/drinking water samples (W1 – W8) and 2 surface water samples (W9–W10) were collected and analyzed as per standard methods during all the seasons. The water quality monitoring stations are shown in Fig. III.13 &14 and Table 3.18. The
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-110
Richardson & Cruddas (1972) Ltd.
ground/surface water quality status is given in Table 3.19 - 3.20 and data are given Annexure – II (Baseline Environmental data).
Methodology
Eight nos. of water samples and two no of surface water were collected during the study period for Physico-chemical and Bacteriological parameters after taking suitable precautions and analyzed as per Standard methods. Samples were collected for Chemical analysis as per procedure outlined in IS: 2488. Sterilized bottles were used for collection of water samples for bacteriological analysis, stored in icebox and transported to the laboratory for the analysis. Parameters like pH, Temperature, DO etc. were measured in the field while collecting the samples. MPN index of coliforms were determined in the laboratory as per Standard methods.
Table – 3.18 Water / Surface water quality monitoring stations
S.No. Location name Location Code
1 Drinking Water, Mine Canteen W1
2 Openwell, Kumarkatta W2
3 Handpump, Markamtola W3
4 Hanpump,Dulki W4
5 Handpump,Bodra village W5
6 Hanpump, Katrel W6
7 Handpump, Kalwar W7
9 Handpump, Bosewara W8
9 Pond Water, Bhamani W9
10 Boirdih Reservoir W10
11 Bore well, Takartola WN1
12 Open well,Dorba WN2
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-111
Richardson & Cruddas (1972) Ltd.
13 Bore well, Kalangpur WN3
14 Bore well, Resuli WN4
15 Check dam No.1 WN5
16 Check dam No.3 WN6
17 Check dam No.7 WN7
Fig. III.13
Location Map of Water Quality Monitoring stations
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-112
Richardson & Cruddas (1972) Ltd.
Fig. III.14
Location Map of Water Quality Monitoring stations
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-113
Richardson & Cruddas (1972) Ltd.
Table 3.19 Ground water quality status (2009 to 2010)
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-114
Richardson & Cruddas (1972) Ltd.
I – summer II – Monsoon III- Postmonsoon IV - Winter
Surface water quality status
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-115
Richardson & Cruddas (1972) Ltd.
Table 3.20 Water quality status (November 2012)
Ground Water
Location Name pH Turbidit
y (NTU)
Total Dissolved Solids (mg/l)
Total alkalinity (mg/l)
Total Hardness (mg/l)
Iron (mg/l)
Chloride (mg/l)
Sulphate (mg/l)
W1 7.25 5 241 102 61 0.04 45 24
W2 7.42 5 988 326 350 0.02 252 89
W3 7.51 6 892 302 298 0.01 212 79
W4 7.72 5 1088 325 320 0.01 302 82
W5 7.32 5 850 256 254 0.02 230 65
W6 7.22 4 282 100 74 0.08 71 24
W7 7.12 7 942 290 340 0.04 254 69
W8 7.10 8 860 280 270 0.01 226 52
WN1 7.22 4 221 86 56 0.01 42 19
WN2 7.02 5 564 180 144 0.01 94 22
WN3 7.42 3 862 289 264 0.03 242 82
WN4 7.2 4 922 284 322 0.02 232 72
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-116
Richardson & Cruddas (1972) Ltd.
2
Surface Water
Location Name pH
Suspended Solids (mg/l)
Total Dissolved Solids (mg/l)
Dissolved Oxygen (mg/l)
BOD (mg/l)
Chloride (mg/l)
Sulphate (mg/l)
Nitrates (mg/l)
Iron (mg/l)
W9 7.28 6 222 6.1 2 20 16 11.8 0.42
W10 7.46 5 324 5.8 2 60 14 10.2 0.50
WN5 7.34 12 212 5.6 2 18 14 8.4 0.80
WN6 7.22 18 242 5.4 3 24 17 6.8 0.76
WN7 7.12 24 256 5.6 3 26 21 5.9 0.82
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-117
Richardson & Cruddas (1972) Ltd.
Data Analysis :
Pre-monsoon season
Ground water: At all locations, pH values were in the range of 7.44 – 8.12 with agreeable colour, taste and odour. Chloride and Sulphate values were in the range of 42 – 412 mg/l and 22 – 122 mg/l respectively. Hardness values were found to be in the range of 76–420 mg/l. At all locations, oil and grease, phenolic compounds, cyanides, sulphides and insecticides were found to be absent and all heavy metal such as nickel, cadmium, chromium, copper, lead, iron, manganese, zinc and cobalt, except iron values were found to be below the detection limit.
Surface water : pH values were found to be in the range of 7.34 - 7.79. At all locations Oil & Grease, Phenols, Cyanides, Sulphides and insecticides were found to be absent and all heavy metals such as nickel, cadmium, chromium, copper, lead, iron, manganese, zinc and cobalt except iron were found to be below the detectable limits.
Monsoon season
Ground water
At all locations, pH values were in the range of 7.24 –7.94 with agreeable colour, taste and odour. Chloride and Sulphate values were in the range of 42 – 324 mg/l and 24 – 104 mg/l respectively. Hardness values were found to be in the range of 60 – 368 mg/l. At all locations, oil and grease, phenolic compounds, cyanides, sulphides and insecticides were found to be absent and all heavy metal such as nickel, cadmium, chromium, copper, lead, iron, manganese, zinc and cobalt except iron values were found to be below the detection limit.
Surface water
pH values were found to be in the range of 7.22 - 7.66. At all locations Oil & Grease, Phenols, Cyanides, Sulphides and insecticides were found to be absent and all heavy metals such as nickel, cadmium, chromium, copper, lead, iron, manganese, zinc and cobalt except iron were found to be below the detectable limits.
Post-Monsoon season
Ground water
At all locations, pH values were in the range of 7.14 –7.74 with agreeable colour, taste and odour. Chloride and Sulphate values were in the range of 40 – 294 mg/l and 20 – 96 mg/l respectively. Hardness values were found to be in the range of 54–362 mg/l. At all locations, oil and grease, phenolic compounds, cyanides, sulphides
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-118
Richardson & Cruddas (1972) Ltd.
and insecticides were found to be absent and all heavy metal such as nickel, cadmium, chromium, copper, lead, iron, manganese, zinc and cobalt except iron values were found to be below the detection limit.
Surface water
pH values were found to be in the range of 7.28 - 7.48. At all locations Oil & Grease, Phenols, Cyanides, Sulphides and insecticides were found to be absent and all heavy metals such as nickel, cadmium, chromium, copper, lead, iron, manganese, zinc and cobalt except iron were found to be below the detectable limits.
Winter season
Ground water
At all locations, pH values were in the range of 7.34 –7.88 with agreeable colour, taste and odour. Chloride and Sulphate values were in the range of 42 – 366 mg/l and 22 – 112 mg/l respectively. Hardness values were found to be in the range of 54–362 mg/l. At all locations, oil and grease, phenolic compounds, cyanides, sulphides and insecticides were found to be absent and all heavy metal such as nickel, cadmium, chromium, copper, lead, iron, manganese, zinc and cobalt except iron values were found to be below the detection limit.
Surface water
pH values were found to be in the range of 7.32 - 7.54. At all locations Oil & Grease, Phenols, Cyanides, Sulphides and insecticides were found to be absent and all heavy metals such as nickel, cadmium, chromium, copper, lead, iron, manganese, zinc and cobalt except iron were found to be below the detectable limits.
Post-Monsoon season ( November 2012)
Ground water
At all locations, pH values were in the range of 7.02 –7.72 with agreeable colour, taste and odour. Chloride and Sulphate values were in the range of 42 – 302 mg/l and 19 – 89 mg/l respectively. Hardness values were found to be in the range of 56–350 mg/l. At all locations, oil and grease, phenolic compounds, cyanides, sulphides and insecticides were found to be absent and all heavy metal such as nickel, cadmium, chromium, copper, lead, iron, manganese, zinc and cobalt except iron values were found to be below the detection limit.
Surface water
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-119
Richardson & Cruddas (1972) Ltd.
pH values were found to be in the range of 7.12 - 7.46. At all locations Oil & Grease, Phenols, Cyanides, Sulphides and insecticides were found to be absent and all heavy metals such as nickel, cadmium, chromium, copper, lead, iron, manganese, zinc and cobalt except iron were found to be below the detectable limits.
Summary
Ground water : While comparing with IS: 10500 – 1991 norms, all values except total coliforms were found to be well within the limits.
Surface Water : Low BOD/COD values and good D.O. content at these locations indicate that the natural restoration of water quality is maintained. While comparing with IS 2296 all values were found to be well within the norms for Surface water quality.
3.4 Soil quality
In order to assess the baseline status of soil quality of the project site and neighborhood, four sampling locations were selected. At each location, samples were collected using augers and analyzed for nutrient and engineering parameters. The location of Soil Sampling station is shown in III.12.The soil quality status is given in Table No. 3.21.
Table - 3.21 Soil quality status
Sl. No Parameters Min Max
1 pH 7.02 7.28
2 Electrical Conductivity (milli mhos/cm) 0.09 0.68
3 Nitrogen (Kg/ha) 136 576
4 Phosphorus (Kg/ha) 3.1 6.8
5 Potassium (Kg/ha) 61 164
6 Available Magnesium (%) 98 480
7 Organic Carbon (%) 1.2 3.7
9 Textural Class Sandy Loam
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-120
Richardson & Cruddas (1972) Ltd.
At all locations, pH ranges from 7.02 to 7.28. Nitrogen, Potassium and Phosphorus are found to be in the range of 136–576 Kg/Ha, 61–164 Kg/Ha and 3.1 –6.8 Kg/Ha respectively. Organic Carbon was found to be in the range of 1.2-3.7 %. Texture Class was found to be Sandy Loam.
3.5 Land Environment
Topography
The whole region is hilly and undulating piece of land. The hill ranges of this region are formed by Kalwar hills, Dulki hills and Mahamaya hills. The iron ore deposits are mainly traced at the peak portions of the hills. The ridges are not susceptible to erosion due to the presence of BHQ. The Mahamaya-Dulki lease also covers 3 low lying hillocks of Mahamaya hill range. The Dulki range (consisting of 3 hillocks namely D1,D2 and D3) lies in the southern continuity of Mahamaya hill range and it extends over a length of 2.4 Kms. This hill range is characterized by high peaks and saddles with steep slopes on either side. The highest peak attains an elevation of 741.69 m above MSL and the general ground level is being 500 m above MSL.
Drainage and water bodies
The area is it part of Dalli hill range and occurring above the ground water table as revealed from few boreholes i.e. 424 to 432 MSL. The bottom most bench during the next three years working will be at 690 MSL, which is much more above the ground water table.
The drainage pattern of the Mahamaya - Dhulki mine is such that the run off during the monsoon goes along the non-perennial water courses.
The mine drainage system will have been through open channel to natural drain. These drains will be made all along with haul road to collect the rain water flowing around the mine and the hill slope. There are 14 Nos. of Check dams were already under operations for the existing Mahamaya mine. During the monsoon the surface water may contain higher concentration of suspended solids and good number of check dams and water filter beds will be constructed.
There is no perennial river or channel within the mining lease area. Rain water flows down through shalslow seasonal nallahs and stream.
Geology
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-121
Richardson & Cruddas (1972) Ltd.
The iron ore deposits of this region are associated with the metamorphosed banded ferrugenous formations consisting of Banded Hematite Quartzite/Jasperite belonging to Pre-cambrine age generally known as 'Iron Ore Series' of Dharwar group.
The iron ores traced here generally occupy the peaks and BHQ in intervening ridges upper and lower shales/phyllites contacts with BHQ can be seen in hill sides. The intrusive bodies like thin quartz veins of younger age also occur within the country rock in criss cross forms.
The sequence of rock types exposed in this particular area is given as follows.
STRATIGRAPHY SUCCESSION OF THE AREA
Order of Deposition Lithological sequence
Top cover : Soil
Laterate
Igneous Intrusion : Quartz veins
Meta sediments : Shales / Ferr. shales & clays
Banded Hematite Quartzite
Shales/ ferruginous shales
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-122
Richardson & Cruddas (1972) Ltd.
Land-use Pattern
Remote sensing satellite Imageries were collected and interpreted for the 10 Km radius study area with project site as center. Based on the satellite data land -use / land cover maps have been prepared.
Land –use / Land cover classification system
The present land–use / land cover maps were prepared based on the classification system of National standards. For explanation for each of the land –use category the two references were used. Viz. 1.Manual of land use/ land cover mapping satellite imagery and 2. Manual procedures for waste land mapping.
Data requirement
IRS-1B Geo Coded False colour composite (FCC) products on 1:50000 scale of path 30 and row 45 with data were acquired from National Remote Sensing Agency, Hyderabad and used for the mapping and interpretation. Besides other collateral data as available in the form of maps, charts, census records other reports and especially topographical survey of India maps on 1:50000 were used. In addition to this, ground truth survey was also collected to verify and confirm the ground features.
Methodology
The methodology adopted for preparation of land use / land cover maps is mono-scopic interpretation of geo-coded scenes of IRS -1B satellite, Sensor L2A2, L2B2 and field observations taken. The various steps involved in the study area are preparatory fieldwork, field survey and post fieldwork.
Pre-field interpretation of Satellite details
The false colour Composite (FCC) of IRS-1B Satellite data at 1:50000 scale has been used for pre-field interpretation work. Taking the help of topo sheets, geology, geo-morphology and by using the image elements the features were identified and delineated the boundaries roughly. Each feature is identified on image by their image elements like tone, texture, colour, shape, size, pattern and association. A tentative legend in terms and erosion was formulated. The sample areas for field check were selected covering all the physio-graphic land-use / land cover features cum image characteristics.
Ground Truth Collection
Ground truth field verification was conducted using both topo sheets and imagery. Representative sample areas were traversed to observe the broad land–use features and the sample areas were adjusted according to the field conditions. Detailed field
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-123
Richardson & Cruddas (1972) Ltd.
observations and investigations were carried out and land–use features on the imagery were recorded.
Post field work
The base maps of the study area were prepared with the help of Survey of India Topo sheet at 1:50000 scale. Preliminary interpreted land use and the land cover features boundaries from IRS-1B FCC were modified in light of field information and the final thematic details were transferred on to the base maps. The tentative legend during the pre-field work were finalized. The final interpreted and classified thematic map was prepared using standard colour coding and detailed description of features with Standard symbols. All the classes are noted and marked by the standard legend on the map. Visual interpretation of multi-sensor false colour imagery composite of the area was prepared using LANDSAT satellite data. The landuse map is shown in Fig. III.15.
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-124
Richardson & Cruddas (1972) Ltd.
FIG. III.15 LANDUSE MAP
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-125
Richardson & Cruddas (1972) Ltd.
Percentage of area covered by each Landuse class
5
32.1
3.8
14.8
24.6
3.4 4.2 3.46.4
2.3
0
5
10
15
20
25
30
35
Built up Crop Land Plantation Land w ith Land Forest Deciduous Barren Mines Water
Final output
The final output would be the land use / land cover on 1:50000 scale numerals are given different colour code for each category as shown in map. Area estimation of all the features of land –use / land cover categories are noted.
Observations
The main interpreted Land use / land cover classes of the study area are presented in Table 3.22 and in Fig. III.16.
Table 3.22 Land-Use in buffer zone
%age Area in Sq.m
Built up Land 5 35.325
Crop Land 32.1 226.7865
Plantation 3.8 26.847
Land with Scrub 6.4 45.216
Land without Scrub 2.3 16.2495
Forest Plantation 14.8 104.562
Deciduous Forest 24.6 173.799
Barren Land 3.4 24.021
Mines 4.2 29.673
Water bodies 3.4 24.021
100 706.5
Fig.III.16 Landcover
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-126
Richardson & Cruddas (1972) Ltd.
3.6 Biological Environment
Biological environment
Stepping up towards the developmental activities for the benefit and sophistication of human life leads to undesirable changes on our biological wealth. Therefore, it is a prerequisite to maintain the biological wealth during the exploitation of energy sources. The ecological goods, and services which include the cultural benefits such as religious, aesthetic, recreational, or inspirational values that humans derive from ecosystems are the result of energy flow and related bio-geochemical cycling and hence is essential in view of maintaining the ecological goods and services not only for the present and future generations but also to all living organisms, including animals and plants.
Developmental activities such as agriculture, urbanization, industrialization, mining, other activities like the introduction of exotic species, elimination of local species etc., also have influence over the local biodiversity. Mining, one of an essential industry which generally provides energy and other minerals to the society and undoubtedly creates a destructive and damaging activity to the biodiversity in such a way that a total change and transformation of flora and fauna in all those areas. Mining is a process of digging that eliminates all plants and animals in the area of greatest impact while dumping buries them alive. Apart from direct damage due to digging and dumping, the dust and noise generated during mining are also capable of adversely impacting the local flora and fauna. Hence it is equally important to recognize and increase understanding of the industries environmental impacts, both negative and positive, and understand management techniques to both mitigate in the former and enhance in the latter. Therefore the baseline understanding of the local biodiversity is also essential in order to their management and conservation in natural environment during the operation of the project. Such a good environmental management in this industry can result in the creation of habitats for a variety species, including endangered species and specialist habitats and also in good publicity and public relations, increase in business etc.,
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-127
Richardson & Cruddas (1972) Ltd.
Biological environmental assessment plays a significant role in environmental impact assessment for any developmental projects. As a measure of biological diversity assessment, detailed survey was undertaken to catalogue the plant and animal species present in the core zone and the area which are likely to be indirectly affected by the developmental activities, termed as Buffer zone, which lies within 10 km radius circle from the boundary of the core zone of the project, excluding the core zone and the mining impacts were predicted and management plans are prepared to minimize the adverse impact on the biodiversity.
Assessment of Flora
In order to assess the baseline status of the flora of the core and the buffer zones, a detailed survey of flora and fauna of the Mine lease area (MLA) and its environs extending up to a radius of 10 km was carried out during January 2010.
The survey of the floral diversity was carried out at 10 sites in the core zone. Each site was segregated into 4 quadrates measured about 15 × 15 mts square. In order to determine the floristic composition, diversity, dominance, and to calculate the Importance Value Indices (IVI) as well as the Biodiversity indices, standard ecological and phyto-sociological methods were adapted. All plants / trees available in the site were identified up to species level by referring various authentic floral checklists (Gambel, 1935). The species of vegetation found in each of the stations were identified and listed according to their families (Table 3.23). Number of individual species was catalogued and the Diversity Indices were calculated.
[I]. Shannon diversity index (H) was calculated using the following equation.
Where ni - the number of individuals in species i; the abundance of species i. ; S - number of species (species richness); N - total number of all individuals; pi - relative abundance of each species (calculated as the proportion of individuals of a given species to the total number of individuals in the community).
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-128
Richardson & Cruddas (1972) Ltd.
[2]. Shannon Evenness index was calculated from the following equation
E = H'/In (S)
Where H'- Shannon diversity index; S - number of species (species richness);
[3]. Simpson diversity index was calculated by the following equation
.
where S is the number of species, N is the total percentage cover or total number of organisms and n is the percentage cover of a species or number of organisms of a species.
The results of the diversity indices are presented in Table 3.24. The Shannon diversity index value of about 1.1243 and the low index value for Simpson diversity (0.1644) resulted from ten random samplings in the core zone indicating the high species richness of the core zone. The evenness index value for the floral diversity of the core zone was calculated to be about 0.6155 which exhibits the near equal distribution of the plant species.
In order to exhibit the relationship between S (species richness), H(Shannon-Wiener diversity index) and E (evenness as measured using the Shannon-Wiener evenness index), SHE analysis is performed. SHE analysis therefore considered as an approach to look at the contribution of species number and equitability to changes in diversity.
Based on present SHE analysis, cumulative ln(E)/ ln(S) remained relatively constant in each plot, indicating that each sample community was best fit by log normal species abundance. The diversity of all the quadret studied showed almost similar type vegetation and such similarity is generally attributed to the topographic similarity of the core zone (Project area).
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-129
Richardson & Cruddas (1972) Ltd.
Rarefaction analysis
Rarefaction analysis was applied to evaluate whether sampling at 10 quadrate was sufficient to estimate the diversity within samplings. The rarefaction curves reached a clear plateau, indicating that the sampling was sufficient for the complete diversity analysis .
The species distribution of Mahamaya core zone was also calculated. The results indicated that majority of the species belongs to the category herbs and shrubs and were found to be aggregated in distribution whereas most of the tree species were present in random distribution at the level of significance.
All the sampling sites studied in the core zone, exhibited a sparse herbaceous flora and those are common for almost all the terrestrial environments. Heteropogon sp is the naturalized plant species of those sites along with other tree species. The proposed project site of Mahamaya for Iron ore mining activities comprised mainly of natural vegetation consisting patches of scrubs and a dense mixed Sal forest, dominated by Buchanania lanzan, Terminalia arjuna, Terminalia tomentosa, and Diospyros melanoxylon Roxb and also covered partly by plantations of Pongamia pinnata, Vent.
Generally these sites are rich in the tree species which are found in dry deciduous forest such as Acacia catechu, Anogeissus latifolia, Bamboosa indica, Butea monosperma, Diospyros melanoxylon, Bassia latifolia, Lagerstroemia parviflora, Lannea coromandelica, Shorea robusta, Terminalia bellirica, Boswellia serrata, Holarrhena antidysenterica and Dendrocalamus strictus. These tree species are endowed with a very high regenerative capacity. A small part of the core zone was occupied by open type forest endowed with agricultural fields which primly supports the cultivation of rice and very commonly available scrubs. These open type forests are generally dominated by Bassia latifolia, Roxb trees.
The abundant shrubs are Helicteres isora and Zizyphus nimularia while the Nerium odorum and Tecoma stans, ornamental shrubs, which were also present with a good frequency.
To assess the important Value Index of the three species found in the core zone, The frequency, density and cover of the tree species were measured by Point centered quarter method (PCQ). The Density, Total cover, Frequency and Important value of the tree species present at the core zone were tabulated.
The importance value gives equal weight to the three factors of relative density, cover, and frequency. This means that small trees (i.e., with small basal area) can be dominant only if there are enough of them widely distributed across transects. The
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-130
Richardson & Cruddas (1972) Ltd.
importance value can range from 0 to 300. Among the tree species Terminalia arjuna, W.&A. (Important Value - 19.13476) and Buchanania lanzan (Important Value - 19.05414) were turn out to be the most important species within the community present in and around the project site because of their size and abundance and was followed by Terminalia tomentosa, (Important Value – 17.734) and Bauhinia sp. (Important Value – 17.2099) respectively where as Dichrostachys cinerea, W&A..,(Important Value - 0.7874) was considered to be the rare species of the community.
Food crops are often cultivated by the people of the buffer zones. The major crops cultivated in the buffer zones are Abelmoschus esculentus, Brassica oleraceae, Brassica oleraceae var. Botritus, Brassica rapa L., Dolichos lablab, L., Gajanus gajan, L., Helianthus annus, Momordica charantia, L., Musa sp., Oryze sativa, Raphanus sativus L., Sesamum indicum, L., Solanum melongen, L., Solanum tuberosum, Triticum sp. and Zea mays, L.
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-131
Richardson & Cruddas (1972) Ltd.
Table 3.23 Checklist of floral diversity in Mahamaya core and buffer zone
Botanical name Local/Common name Family Name Core
zone Buffer zone
Herbs
Abutilon indicum, G. Don. Khangi Malvaceae - +
Acanthus sp Hargoza Acanthaceae + +
Achyranthes aspera, L Apang Amaranthaceae - +
Ageratum conyzoides ---------- Astraceae - +
Alternanthera sessilis, L. Washer woman
Amaranthaceae + +
Amarantus sp. Raamadaanaa Amaranthaceae - +
Argemone mexicana, L Bharbhand Papaveraceae + +
Aristida depressa, Retz. Tam Graminae + +
Boerhaavia diffusa, L. Gadahpurna Nyctaginaceae + +
Boerhaavia rependa, Willd ---------- Nyctaginaceae + +
Cleome gynandra, L. ---------- Capparidaceae - +
Cleome viscosa, L. Hurthur Capparidaceae - +
Coldenia procumbens, L. Boraginaceae - +
Commelina sp. L. Gandolgi (English)
Commlinaceae + +
Celosia cristata L. Kolikondai - +
Gomphrena decumbens, Jacq. --------- Amaranthaceae + +
Heliotropium indicum --------- Boraginaceae - +
Hyptis suaveolens, Poit. Wilayati tulsi Labiatae + +
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-132
Richardson & Cruddas (1972) Ltd.
Botanical name Local/Common name Family Name Core
zone Buffer zone
Impatiens balsamina L. Balsom Balsaminaceae + +
Ipomaea carnea, Jacq. Kalmua Convolulaceae - +
Justicia simplex, D. Don ---------- Acanthaceae + +
Martynia sp. Bichu Martyniaceae + +
Melochia umbellate, Stapf. ---------- Sterculiaceae - +
Paspalum conjugatum, Berg. Carabao grass Graminae + +
Paspalum longifolium, Roxb Kodo, Kodra Graminae + +
Pavonia zelanica, Cav. ------- Malvaceae + +
Physalis minima, Linn. Tulatipati Solanaceae - +
Ruellia prostrata, Poir Acanthaceae + +
Salvia sp. Bathu ka sag Lamiaceae + +
Sida acuta, L. Broom grass Malvaceae + +
Sida cordifolia, L Khiraiti Malvaceae + +
Sida rhombifolia, L. Khas khas Malvaceae + +
Tiliacora acumunata ,L ----------- Minispermeace
ae + +
Trianthema decandra, L. Gadabani Aizoaceae + +
Vernonia cinera, Lees. Iron weed Compositae + +
Xanthium indicum, Roxb. Banokra Compositae + +
Medicinal herbs
Agave Americana, L. Bans-keora Agavaceae + +
Acalypha indica, L. Khokali Euphorbiaceae + +
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-133
Richardson & Cruddas (1972) Ltd.
Botanical name Local/Common name Family Name Core
zone Buffer zone
Croton sparsiflorus, Mor Wild chilli Euphorbiaceae - +
Cynodon dactylon, Pers Dub Graminae + +
Datura stramonium, L Habaq el- ayalet
Solanaceae + +
Evolvulus alsinoides, L. Slender Dwarf-Morning Glory
Convolulaceae + +
Hybanthus enneaspermus Ratanpurus Violaceae + +
Indigofera tinctoria, L Gali Fabaceae + +
Leucas aspera, Spr. Guma Labiatea - +
Ocimum sanctum, L. Baranda Labiatea - +
Phyllanthus neruri, L. --------- Euphorbiacea + +
Phyllanthus rediculatus, Poir. --------- Euphorbiacea + +
Ruellia prostrata, Poir. --------- Acanthaceae - +
Tephrosia purpurea, Pers. Sarphonka Fabaceae + +
Tridax procumbens, L. Khal-muriya Astraceae + +
Cuminum cyminum, Linn. Karpoora valli Labiatae - +
Climbing herbs
Argyreia nervosa (Burm. f.) Bojer
Samudrasos Convolvulaceae + +
Ichnocarpus sp. R. Br Vakeri mul Apocynaceae + +
Ipomaea staphylina R.&S. Sakarkand Convolvulaceae + +
Jasminum sp. Jasmin Oleaceae - +
Oxystelma esculentum Kirni Asclepidaceae + +
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-134
Richardson & Cruddas (1972) Ltd.
Botanical name Local/Common name Family Name Core
zone Buffer zone
Climbing medicinal herbs
Crdiospermum helicacabum, L.
Kanphuti Sapindaceae
- +
Cissus quadrangularis, L Hadjora Ampelidaceae - +
Hemidesmus indicus, R. Br ---------- Peripolaceae + +
Passiflora edulis, Sims Jhumka-Lata Passifloraceae - +
Tinospora cardifolia Gurch Minispermacea
e + +
Pergularia pallida, W. & A. ---------- Asclepiadaceae + +
Abrus precatorius, L Erra-gurja Asclepiadaceae + +
Gymnema sylvestre, R,Br Gurmara Asclepiadaceae + +
Parasitic plants
Cuscuta, L. Akashabela Cuscutaceae + +
Vanda sp. Banda, Orchidaceae + +
Phoradendron sp Viscaceae + +
Exotic invasive weed
Parthenium hysterophorus L ----------- Asteraceae - +
Aquatic herbs
Cyperus sp. L. Koda, Kodaka Cyperaceae + +
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-135
Richardson & Cruddas (1972) Ltd.
Botanical name Local/Common name Family Name Core
zone Buffer zone
Aschynomin aspera Pith plant Fabaceae + +
Hygrophila spinosa Talmakhana Acanthaceae + +
Nymphaea sp Kokaa Nymphaeaceae - +
Nelumbo nucifera Water lilly Nelumbonaceae - +
Typha angustata, B.& Ch Patera Typhaceae - +
Agricultural crops
Abelmoschus esculentus Bhendi Malvaceae - +
Brassica oleraceae Cabbage Brassicaceae - +
Brassica oleraceae var. Botritus
Cauliflower Brassicaceae - +
Brassica rapa L. Mustard Brassicaceae - +
Dolichos lablab, L. Lobia Fabaceae - +
Gajanus gajan, L. Dhal Fabaceae - +
Helianthus annus Sun flower Asteraceae - +
Momordica charantia, L Karela Cucurbitaceae - +
Musa sp Khela Musaceae - +
Oryze sativa Rice Graminae - +
Raphanus sativus L. Muulii Brassicaceae - +
Sesamum indicum, L Jingilee Pedaliaceae - +
Solanum melongen, L. Baigan, Solanaceae - +
Solanum tuberosum Alu /Potato Solanaceae - +
Triticum sp. Wheat Graminae - +
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-136
Richardson & Cruddas (1972) Ltd.
Botanical name Local/Common name Family Name Core
zone Buffer zone
Zea mays, L. Maize Graminae - +
Woody climbers
Ipomoea obscura, K. Gawl. Zaqqume Convolulaceae + +
Ventilago maderaspatana Gaertn
Papara Rhamnaceae
+ +
Shrub
Ehretia buxifolia, Roxb Pala Boraginaceae + +
Fluggea luecophyrus, Willd Hartho Euphorbiaceae + +
Dichrostachys sp, W. &A Kunali Fabaceae + +
Helicteres isora, L Maror phal Sterculiaceae + +
Zizyphus nimularia, L. Vilayti, pardesi Rhamnaceae + +
Opuntia, sp. --------- Cactaceae + +
Grewia asiatica, Mast --------- Tiliaceae + +
Medicinal shrubs
Adhatoda vasica Asgand Acanthaceae - +
Caparis aphyllus ---------- Caparidaceae + +
Capparis zeylanica Hins Caparidaceae + +
Holarrhena antidysenterica Korea Apocynaceae + +
Jatropha glandulifera Jangli-Erandi Euphorbiaceae + +
Phyllanthus rediculatus, Poir. Panjoli Euphorbiaceae + +
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-137
Richardson & Cruddas (1972) Ltd.
Botanical name Local/Common name Family Name Core
zone Buffer zone
Ricinus communis, L. Arand, Euphorbiaceae - +
Vitex negundo, L. ---------- Verbinaceae - +
Zizyphus jujuba, Lam Badara Rhamnaceae + +
Solanum tarvum, Tit-Baigun Solanaceae - +
Cassia alata ---------- Fabacae - +
Sesbania sesban Merr --------- Caesalpiniacea
e - +
Jatropha gossypifolia L --------- Euphorbiaceae + +
Ornamental shrub
Bougainvillaea glabara, Choisy
---------- Nyctaginaceae - +
Gardenia latifolia Papura Rubiaceae - +
Hibiscus rosasinensis, L. Jasum Malvaceae - +
Nerium odorum, Soland. Kaner, Chandni
Apocynaceae - +
Pedilanthus tithymaloides, L. Slipper flower Euphorbiaceae - +
Tecoma stans (L.) Juss. ex Kunth
Yellow bells Bignoniaceae + +
Exotic shrubs
Lantana camara, L Spanish Flag Verbinaceae + +
Prosopis spicigera. L Salpan, salpani Mimosaceae + +
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-138
Richardson & Cruddas (1972) Ltd.
Botanical name Local/Common name Family Name Core
zone Buffer zone
Trees
Acacia arabica, Willd Babul Mimosaceae - +
Acacia melanoxylon, R. Br Black wattle Mimosaceae + +
Aegle marmelos, Corr. Beli Rutaceae - +
Ailanthus excelsa, L., Marukh Simaroubaceae + +
Alangium platanifolium -------- Alangiaceae - +
Anacardium occidentale, L. Cashew Anacardiacae - +
Anogeissus latifolia, Wall. Dhawda Combretaceae + +
Anthocephalus indicus Kadam Rubiaceae - +
Artobotrys odoratissimus Linn Madmanti Annonaceae - +
Artocarpus hirsute, Lam Phanas Moraceae - +
Azadirachta indica, A. Juss. Nimb Meliaceae + +
Bambusa arundinacea, Willd. Bamboo Graminae + +
Bassia latifolia, Roxb Mahua Sapotaceae + +
Bauhinia purpurea, L. Apta Caesalpiniaceae
- +
Bauhinia sp. Mahwa Caesalpinaceae + +
Bombax malabaricum DC. Simal Malvaceae - +
Boswellia serrata Salai Burseraceae + +
Buchanania lanzan Char Anacardiaceae + +
Butea monosperma (Lam.) Ta Palash Fabaceae + +
Callistemon citrinus Bottlebrush Myrtaceae - +
Carica papaya, L. Papaya Caricaceae - +
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-139
Richardson & Cruddas (1972) Ltd.
Botanical name Local/Common name Family Name Core
zone Buffer zone
Cassia fistula, L Bahawa Caesalpinioidea
e + +
Cassia siamea, Lam. Torki Caesalpinioidea
e + +
Chloroxylon sweitenia Bhirra Meliaceae + +
Citrus sp. Tanaka Rutaceae - +
Dalbergia sissoo, Roxb Sisham Fabaceae + +
Delonix regia, Raf. Rai, Mohari Caesalpinioidea
e + +
Dendrocalamus strictus, Nees. Bamboo Ebenaceae - +
Dichrostachys cinerea, W&A. -------- Fabaceae + +
Diospyros melanoxylon Roxb Thendu Caesalpinioidea
e + +
Enterolobium saman (Jacq.) Prain
Prain Caesalpinioideae
+ +
Eucalyptus globules, Labill. Nilgiri Moraceae + +
Ficus bengalensis.L Wad Moraceae - +
Ficus Cretovara, Roxb. Anjeer Moraceae + +
Ficus glomerata Fig Moraceae + +
Ficus religiosa, L Pipal Labiatae + +
Gmelina arborea Roxb. Gumhar Lythraceae + +
Kigelia pinnata, Dc Jhar phanoos Bignoniaceae - +
Lagerstromia speciosa (Linn.) Pers.
Jarul Lythraceae + +
Lannea coromandelica L. Thingan Fabaceae + +
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-140
Richardson & Cruddas (1972) Ltd.
Botanical name Local/Common name Family Name Core
zone Buffer zone
Madhuca indica, J.F. Gmel Mohwa Sapotaceae + +
Mangifera indica, L. Amba Annonaceae + +
Millingtonia hartensis, L Akas-Nim Bignonaceae - +
Mitragyna parvifolia, Korth Kaini Rubiaceae + +
Moringa olefera, Lam Soujna Moringaceae + +
Parkinsonia aculeata L. Vilaiti kikar Fabaceae - +
Peltophorum pterocarpum, DC Yellow flame Leguminosae + +
Phoenix sylvestris, Roxb. Khajur, Arecaceae + +
Polyalthia longifolia, Hk.F&T Asok Annonaceae - +
Pongamia pinnata, Vent. Karanj Fabaceae + +
Psidium guajava, L Amaruuda Myrtaceae - +
Shorea robusta Roth Sal Dipterocarpace
ae - +
Syzigium jombolanum, DC. Jamoon Myrtaceae - +
Tectona grandis, L. Sagwan Verbenaceae + +
Terminalia arjuna, W.&A. Arjun Kahua Combretaceae + +
Terminalia bellarica, Roxb. Baheda Combretaceae + +
Terminalia chebula, Roxb. - Combretaceae + +
Terminalia tomentosa, Roxb. Saja Combretaceae + +
Wrightia tinctoria, R. Br. Kala- Asclapiaedacea
e + +
Zizyphus oenoplia, Mill Makai Rhamnaceae + +
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-141
Richardson & Cruddas (1972) Ltd.
Botanical name Local/Common name Family Name Core
zone Buffer zone
Plantations of core zone
Acacia auriculiformis, A. Cunn. ex Benth
Australian babul
Mimosaceae
Callistemon citrinus Bottlebrush Myrtaceae
Cassia siamea, Lam. Torki Caesalpinioideae
Dalbergia sissoo, Roxb. Seesam Fabaceae
Eucalyptus globules, Labill . Nilgiri Moraceae
Gmelina arborea Roxb. Gumhar Lythraceae
Leucaena leucocephala Lam. Subabul Mimosaceae
Pongamia pinata, Vent. Karanj Combretaceae
Shorea robusta Roth Sal Dipterocarpaceae
Syzigium jombolanum, DC. Jamoon Myrtaceae
Tectona grandis, L. Sagwan Verbenaceae
Terminalia arjuna, W.&A. Arjun Combretaceae
Terminalia bellarica, Roxb. Baheda Combretaceae
Peltophorum pterocarpum Yellow flame tree
Caesalpinioideae
Dominant plants
Buchanania lanzan Char Anacardiaceae + +
Diospyros melanoxylon Roxb Thendu Caesalpinioidea
e + +
Bassia latifolia, Roxb. Mahua Sapotaceae + +
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-142
Richardson & Cruddas (1972) Ltd.
Botanical name Local/Common name Family Name Core
zone Buffer zone
Rare occurrence
Phoenix sylvestris, Roxb. Khajur, Arecaceae + +
Grass land- Nil
Endangered and Endemic flora – Nil
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-143
Richardson & Cruddas (1972) Ltd.
Table-3.24 Shannon – Weiner and Simpson diversity Indices
Index Sample 1
Sample
2
Sample 3
Sample
4
Sample
5
Sample
6
Sample
7
Sample
8
Sample
9
Sample
10
Overall
Index
Shannon H' Log Base 10. 1.245 1.089 0.992 1.119 1.184 1.251 1.086 0.988 1.177 1.112 1.1243
Shannon Hmax Log Base 10. 1.881 1.813 1.806 1.748 1.886 1.881 1.813 1.799 1.881 1.748 1.8256
Shannon J' (Evenness – E) 0.662 0.601 0.549 0.64 0.628 0.665 0.599 0.549 0.626 0.636 0.6155
Simpsons Diversity (D) 0.115 0.212 0.218 0.147 0.127 0.115 0.213 0.22 0.128 0.149 0.1644
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-144
Richardson & Cruddas (1972) Ltd.
Fauna assessment
The core zone exhibited a very few species of Mammals, Fishes, Amphibians, Reptiles and Birds, which are quite common for all the terrestrial environments. Among the buffer zones, the human settlement areas exhibited some animals which are domesticated where as the natural forests of the buffer zone are often dominated by a few plant species which supports very few wild fauna. The identified Fauna is tabulated in Table 3.25.
Table 3.25. Check list of fauna in the core and buffer zone of Mahamaya Iron ore mine
Zoological name Local/Common name Family Name
Status in wild life protection Act, 1972
Core zone
Buffer zone
Shedule Part
Mammals
Bandicota bengalensis
Lesser bandicoot rat
Muridae V - - +
Bos sp. Cow Bovidae - +
Bubalus arnee Buffalo Bovidae - +
Canis lupus familiaris
Dog Canidae II II + +
Capra aegagrus hircus
Goat Bovidae
- +
Felis chaus Jungle cat Felidae I - +
Equus caballus × Equus asinus
Mule Equidae - +
Herpestes edwardsi (Geoffroy)
Indian mongoose
Herpestidae II II - +
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-145
Richardson & Cruddas (1972) Ltd.
Melursus ursinus Sloth bear Ursidae I I - +
Presbytis entellus Grey langur Cercopithecidae
II I + +
Rattus rattus (Linnaeus)
Black rat Muridae V - + +
Vulpes benghalensis (Shaw)
Lomri (fox) Canidae II II - +
Fishes
Anabas testudineus Keu Anabantidae - - - +
Catla catla Thaila Cyprinidae - - - +
Channa punefatus Daulla Channidae - - - +
Clarias batrachus Catfish Clariidae - - - +
Heteropneustes fossilis
Singhi Clariidae - - - +
Mystus cavasius Tengna Bagridae - - - +
Puntius sophore Kotri Cyprinidae - - - +
Amphibians
Bufo melanostictus (Schneider)
Common toad
Bufonidae IV - - +
Geoclemys hamiltoni (Gray)
Tortoises Geoemydidae I I - +
Kachuga dhongoka (Gray)
Tortoises Geoemydidae I I - +
Rana breviceps (Schneider)
Indian burrowing frog
Ranidae IV - - +
Rana Limnocharis (Neigman)
Indian cricket frog
Ranidae IV - - +
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-146
Richardson & Cruddas (1972) Ltd.
Rana tigrina (Daudin)
Indian bull frog
Ranidae IV - - +
Reptails
Calotes versicolour (Daudin)
Garden lizard Agamidae II + +
Enhydris enhydris Smmoth water snake
Colubridae IV - - +
Hemidactylus brooki (Gray)
Common lizards
Gekkonidae - - + +
Hemidactylus flaviviridis
Common lizards
Gekkonidae - - + +
Python molurus Pyton Pythonidae I II + +
Naja naja Cobra Elapidae II II - +
Xenochrophis piscator
Checkered backed water snake
Colubridae IV - - +
Aves
Apus affinis Ababeel Apodidae IV - + +
Ardeola grayii Pond heron Ardeidae IV - + +
Centropus sinensis Parroti Cuculidae IV - - +
Columbia livia Dove Columbidae IV - - +
Corvus splendens Crow Sturnidae V - + +
Eudynamys scolopacea
Indian koel Cuculidae IV - - +
Galles gallus Chicken Phasianidae - -- - +
Prodiceps ruficollis Little grebe Podicipedidae IV - - +
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-147
Richardson & Cruddas (1972) Ltd.
Vanellus indicus Red-wattled
lapwing
Charadriidae IV - - +
Sturnus pagodarun Myna, Black-headed
- -
Acridothers trists Myna, common
-
- - - +
Amauromis phoenicurus
Water hen IV - - +
Theskiornis aethopica
White Ibis IV - - +
Pavo cristatus Common Peafowl
IV - - +
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-148
Richardson & Cruddas (1972) Ltd.
3.7 Socio Economic Study
Socio-economic development is closely linked with the growth of industrialization. The industrial policy resolution in the year 1956 stressed the need of reducing regional disparities in levels of development in order that industrialization may benefit the country as a whole. This view was further endorsed in the new industrial policy statement (1980) which further felt that revival of the economy was inhibited by infrastructure gaps such as shortage in major industries. The policy also emphasized the need to promote suitable industries in rural areas. The process of industrial transitions where new industrial units are setup in a primarily agrarian economy is bound to create its impact on the socio-economic aspects of the local people. Therefore studies on the socio-economic impact of industrialization on the local population no doubt deserve considerable attention. The present study is being carried out to ascertain the impacts of proposed plant on the socio-economic conditions of local people. The data required to study the above aspects has been collected from secondary sources.
3.7.1 Methodology
The methodology adopted for the study is based on Review of secondary data (2001 District Census) with respect to population, occupational structure and infrastructure facilities available in the region.
3.7.2 Review of Socio-economic Profile
The information on socio-economic aspects of the study area has been compiled from secondary sources, which include information from various public and semi-public offices. The demographic data has mainly been compiled from Census of India 2001 data as this document is comprehensive and authentic. The sociological aspects like human settlements, demography and other socio-economic aspects in the study area have been covered in this study. The socio-economic details are briefly described in the following sections.
Major portion of the study area comprises only rural area. Study area contains 37 villages. The villages that come within study area of 10 km are covered in the present study.
3.7.3 Demography
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-149
Richardson & Cruddas (1972) Ltd.
As per 2001 census, the study area consisted of 17538 persons inhabited in 37 villages. The statistics regarding the list of villages, number of households and human population is given in Table 3.26.
TABLE- 3.26 DEMOGRAPHY IN STUDY AREA
Sr. No. Name of Village No of Households Population
Total Male Female
1 Akola 42 250 116 134
2 Bamhani 143 678 330 348
3 Belargondi 239 1338 662 676
4 Bhatgaon 117 650 325 325
5 Bhirawahi 207 1051 543 508
6 Bodra 32 167 90 77
7 Boirdih 8 38 21 17
8 Chhindgaon 268 1363 656 707
9 Dorba 150 853 445 408
10 Dulki 24 143 64 79
11 Gainji 205 1166 569 597
12 Goyanda 44 219 97 122
13 Hinganjhar 72 402 200 202
14 Jhitkatola 94 432 208 224
15 Kalwar 28 150 72 78
16 Kamkasur 25 113 53 60
17 Katrel 26 112 54 58
18 Kodagaon 110 578 293 285
19 Kopedera 134 670 341 329
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-150
Richardson & Cruddas (1972) Ltd.
Sr. No. Name of Village No of Households Population
Total Male Female
20 Kosmi 99 473 242 231
21 Kumudkatta 28 196 113 83
22 Kusumtola 161 876 404 472
23 Markatola 255 1287 631 656
24 Murar Gota 48 260 134 126
25 Naghur 88 481 248 233
26 Nalkasa 30 169 83 86
27 Nalkasa 15 78 37 41
28 Paindhur 55 288 150 138
29 Paiwani 69 372 181 191
30 Poswar 61 328 150 178
31 Pujari Para 92 458 223 235
32 Pusewada 98 549 249 300
33 Rasuli 13 89 45 44
34 Salhe Tola 21 87 48 39
35 Seoni 48 296 143 153
36 Tamora 99 531 252 279
37 Tarunnagar 64 347 186 161
Total: 3312 17538 8658 8880
Source: Census of India 2001
The distribution of population in the study area is shown in Table-3.27.
TABLE- 3.27 DISTRIBUTION OF POPULATION
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-151
Richardson & Cruddas (1972) Ltd.
Particulars Total
Total Population 17538
Male Population
(% with total population) 8658 (49.37%)
Female Population
(% with total population)
8880 (50.63%)
No. of Households 3312
Average Household Size 5.3
Sex ratio (Female/1000 male) 1025
The configuration of male and females indicates that the males constitute to about 49.37% and females to about 50.63% of the study area population. The study area at an average has 1025.64 females per 1000 males.
3.7.4 Social Structure
Majority of the people in the study area belong to Hindu religion. The study area also contains Scheduled Castes (SC) and Scheduled Tribes (ST). The distribution of population of socially weaker sections in the study area is shown in Table-3.28 &3.29 .
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-152
Richardson & Cruddas (1972) Ltd.
TABLE –3.28 SOCIAL STRUCTURE
Sr. No. Name of Village Total Population Total SC Total ST
1 Akola 250 0 213
2 Bamhani 678 10 629
3 Belargondi 1338 10 1191
4 Bhatgaon 650 23 535
5 Bhirawahi 1051 7 884
6 Bodra 167 0 166
7 Boirdih 38 0 7
8 Chhindgaon 1363 42 609
9 Dorba 853 44 710
10 Dulki 143 0 136
11 Gainji 1166 135 539
12 Goyanda 219 3 201
13 Hinganjhar 402 18 325
14 Jhitkatola 432 10 332
15 Kalwar 150 0 149
16 Kamkasur 113 0 113
17 Katrel 112 0 112
18 Kodagaon 578 13 476
19 Kopedera 670 1 580
20 Kosmi 473 16 339
21 Kumudkatta 196 1 163
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-153
Richardson & Cruddas (1972) Ltd.
Sr. No. Name of Village Total Population Total SC Total ST
22 Kusumtola 876 11 794
23 Markatola 1287 31 920
24 Murar Gota 260 15 219
25 Naghur 481 3 368
26 Nalkasa 169 0 167
27 Nalkasa 78 0 78
28 Paindhur 288 10 272
29 Paiwani 372 0 344
30 Poswar 328 8 251
31 Pujari Para 458 30 377
32 Pusewada 549 4 523
33 Rasuli 89 0 89
34 Salhe Tola 87 0 87
35 Seoni 296 2 225
36 Tamora 531 41 478
37 Tarunnagar 347 0 0
Total: 17538 488 13601
Source: Census of India 2001
TABLE-3.29 Distribution of Population by Social Structure
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-154
Richardson & Cruddas (1972) Ltd.
Category Total
Total Population 17538
Scheduled Castes 488
% to total population 2.78%
Scheduled Tribes 13601
% to total population 77.55%
Total SC and ST 14089
% to total population 80.33%
In the study area 2.78% of the population belongs to Scheduled Castes (SC) while 77.55% to Scheduled Tribes (ST), thus indicating that about 80.33% of the population is formed by SC and ST population. Scheduled Caste and Scheduled Tribe sections are predominant in this area.
3.7.5 Literacy Levels
The distribution of literates and literacy rates in the study area are given in Table- 3.30 and Table 3.31.
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-155
Richardson & Cruddas (1972) Ltd.
Table – 3.30 Literacy Levels
Sr. No.
Name of Village
Total Population Total Literacy
Male Literacy
Female Literacy
1 Akola 250 155 76 79
2 Bamhani 678 318 195 123
3 Belargondi 1338 891 503 388
4 Bhatgaon 650 428 237 191
5 Bhirawahi 1051 738 403 335
6 Bodra 167 110 66 44
7 Boirdih 38 24 13 11
8 Chhindgaon 1363 855 506 349
9 Dorba 853 492 312 180
10 Dulki 143 82 37 45
11 Gainji 1166 822 449 373
12 Goyanda 219 170 84 86
13 Hinganjhar 402 198 121 77
14 Jhitkatola 432 304 151 153
15 Kalwar 150 81 41 40
16 Kamkasur 113 68 37 31
17 Katrel 112 45 32 13
18 Kodagaon 578 404 225 179
19 Kopedera 670 375 240 135
20 Kosmi 473 311 169 142
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-156
Richardson & Cruddas (1972) Ltd.
Sr. No.
Name of Village
Total Population Total Literacy
Male Literacy
Female Literacy
21 Kumudkatta 196 85 47 38
22 Kusumtola 876 586 325 261
23 Markatola 1287 668 405 263
24 Murar Gota 260 166 89 77
25 Naghur 481 244 142 102
26 Nalkasa 169 111 61 50
27 Nalkasa 78 18 15 3
28 Paindhur 288 182 97 85
29 Paiwani 372 174 111 63
30 Poswar 328 204 92 112
31 Pujari Para 458 298 149 149
32 Pusewada 549 349 162 187
33 Rasuli 89 38 20 18
34 Salhe Tola 87 49 35 14
35 Seoni 296 208 109 99
36 Tamora 531 288 162 126
37 Tarunnagar 347 260 149 111
Total: 17538 10799 6067 4732
Source : Census of India 2001
TABLE-3.31 LITERACY RATES
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-157
Richardson & Cruddas (1972) Ltd.
Particulars Total
Total Population 17538
Male population 8658
Male literates 6067
Female population 8880
Female literates 4732
Total literates 10799
% of study area literates to total population 61.57%
Male literacy rate 70.07 %
Female literacy rate 53.29%
The study area experiences a moderate literacy rate of 61.57%. The male literacy i.e. the percentage of literate males to the total males of the study area is observed as 70.07% while female literacy rate, which is an important indicator for social change, is observed as 53.29% in the study area.
3.7.6 Occupational Structure
The occupational structure of the study area is studied with reference to main workers, marginal workers and non-workers. The main workers include 10 categories of workers defined by the Census Department consisting of cultivators, agricultural laborers, those engaged in live-stock, forestry, fishing etc. mining and quarrying; manufacturing, processing and repairs in household industry; and other than household industry, construction, trade & commerce, transport & communication and other services.
Due to boom in Iron Ore in recent years majority of farmers as well as agriculture laborers are engaged in the mining activity. This information is not forthcoming from the Published Census Data.
The marginal workers are those engaged in some work for a period of less than six months during the reference year prior to the census survey. The non-workers include those engaged in unpaid household duties, students, retired persons, dependents, etc.; institutional inmates or all other non-workers who do not fall under
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-158
Richardson & Cruddas (1972) Ltd.
the above categories. The occupational structure of the study area is shown in Table-3.32 and Table 3.33.
Table -3.32 Occupational Structure
Sr. No.
Name of Village
Total Population
Total Workers
Total Main Workers
Total main Cultivated Labors
Total Main Agricultural Labors
Total Marginal Workers
Total Non Workers
1 Akola 250 134 131 95 33 3 0
2 Bamhani 678 455 430 322 25 25 2
3 Belargondi 1338 738 733 598 96 5 0
4 Bhatgaon 650 336 336 273 37 0 0
5 Bhirawahi 1051 571 273 249 13 298 0
6 Bodra 167 100 49 42 2 51 0
7 Boirdih 38 22 21 9 0 1 0
8 Chhindgaon 1363 803 735 432 144 68 0
9 Dorba 853 493 491 478 6 2 0
10 Dulki 143 70 39 37 1 31 0
11 Gainji 1166 593 522 324 130 71 1
12 Goyanda 219 139 115 96 9 24 0
13 Hinganjhar 402 249 205 130 74 44 0
14 Jhitkatola 432 277 243 149 48 34 1
15 Kalwar 150 84 75 54 17 9 0
16 Kamkasur 113 62 36 25 9 26 0
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-159
Richardson & Cruddas (1972) Ltd.
Sr. No.
Name of Village
Total Population
Total Workers
Total Main Workers
Total main Cultivated Labors
Total Main Agricultural Labors
Total Marginal Workers
Total Non Workers
17 Katrel 112 70 65 57 8 5 0
18 Kodagaon 578 326 79 50 8 247 0
19 Kopedera 670 382 352 217 104 30 0
20 Kosmi 473 259 211 141 49 48 0
21 Kumudkatta 196 117 39 37 0 78 0
22 Kusumtola 876 464 443 318 100 21 1
23 Markatola 1287 713 693 495 139 20 2
24 Murar Gota 260 153 92 75 6 61 0
25 Naghur 481 281 217 160 29 64 0
26 Nalkasa 169 80 2 0 1 78 0
27 Nalkasa 78 53 36 27 6 17 0
28 Paindhur 288 162 133 95 32 29 0
29 Paiwani 372 196 184 135 36 12 3
30 Poswar 328 174 174 104 62 0 0
31 Pujari Para 458 292 276 243 29 16 0
32 Pusewada 549 291 150 105 35 141 1
33 Rasuli 89 52 40 36 3 12 0
34 Salhe Tola 87 50 29 29 0 21 0
35 Seoni 296 213 170 143 11 43 0
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-160
Richardson & Cruddas (1972) Ltd.
Sr. No.
Name of Village
Total Population
Total Workers
Total Main Workers
Total main Cultivated Labors
Total Main Agricultural Labors
Total Marginal Workers
Total Non Workers
36 Tamora 531 296 140 120 3 156 1
37 Tarunnagar 347 249 125 122 0 124 0
Total: 17538 9999 8084 6022 1305 1915 12
Source : Census of India 2001
TABLE-3.33 Occupational Structure of Study Area
Occupation Total
No. % to population
Total Workers 9999 57.01
Cultivators 6022 34.34
Agricultural laborers 1305 7.44
Total main workers 8084 46.09
Marginal workers 1915 10.91
Non-workers 12 0.006
Total population 17538 100
Altogether the main workers work out to be 46.09% of the area population. The marginal workers and non-workers constitute to 10.91% and 0.006% of the population respectively. The cultivators and agricultural laborers together form 57.01% of the total population.
3.7.7 Amenities Available
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-161
Richardson & Cruddas (1972) Ltd.
Amenities available in the villages considered in the Study Area have been collected from Census Book for the District. Educational facilities, Healthcare facilities, Water supply, Communication facilities, Banking facilities, Road and Transportation facilities, availability of news papers & magazines etc., are covered in these amenities. It is noticed that villages have majority of all these facilities. The facilities available for all the villages in the Study Area is furnished in Table : 3.34. Health details and morbidity pattern is given in Table 3.35 & 3.36.
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-162
Richardson & Cruddas (1972) Ltd.
TABLE 3.34 AMENITIES AVAILABLE IN THE STUDY AREA
Sl. No. Village Name AREA House
holds Educational Institutions
Medical Facilities
Drinking Water Supply
Communi-cation
Transpor-tation
Approach Road
Power Supply
1 Akola 142 42 P,M PHS W,HP PH BS PR,MR,FP ED,EA
G
2 Bamhani 1157 143 P,M PHS W,HP PH BS PR,MR,FP ED,EA
G
3 Belargondi Alias Sattaitola 681 239
P,M PHS W,HP PH BS PR,MR,FP ED,EAG
4 Bhatgaon 702 117 P,M PHS W,HP PH BS PR,MR,FP ED,EA
G
5 Bhirawahi 585 207 P,M PHS W,HP PH BS PR,MR,FP ED,EA
G
6 Bodra 140 32 P,M PHS W,HP PH BS PR,MR,FP ED,EA
G
7 Boirdih 329 8 P,M PHS W,HP PH --- PR,MR,FP ED,EA
G
8 Chhindgaon 370 268 P,M PHS W,HP PH --- PR,MR,FP ED,EA
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-163
Richardson & Cruddas (1972) Ltd.
G
9 Dorba 838 150 P,M PHS W,HP PH --- PR,MR,FP ED,EA
G
10 Dulki 180 24 P,M PHS W,HP PH --- PR,MR,FP ED,EA
G
11 Gainji 659 205 P,M PHS W,HP PO,PT --- PR,MR,FP ED,EA
G
12 Goyanda 233 44 P,M PHS W,HP ---- --- PR,MR,FP ED,EA
G
13 Hinganjhar 452 72 P,M PHS W,HP ---- --- PR,MR,FP ED,EA
G
14 Jhitkatola 361 94 P,M PHS W,HP ---- --- PR,MR,FP ED,EA
G
15 Kalwar 478 28 P,M PHS W,HP PH BS PR,MR,FP ED,EA
G
16 Kamkasur 111 25 P,M PHS W,HP PH BS PR,MR,FP ED,EA
G
17 Katrel 540 26 P,M PHS W,HP PO,PT BS PR,MR,FP ED,EA
G
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-164
Richardson & Cruddas (1972) Ltd.
18 Kopedera 788 134 P,M PHS W,HP PH BS PR,MR,FP ED,EA
G
19 Kosmi 426 99 P,M PHS W,HP PH BS PR,MR,FP ED,EA
G
20 Kumudkatta 245 28 P,M PHS W,HP PH BS PR,MR,FP ED,EA
G
21 Kusumtola 364 161 P,M PHS W,HP PH BS PR,MR,FP ED,EA
G
22 Markatola 665 255 P,M PHS W,HP PH BS PR,MR,FP ED,EA
G
23 Murar Gota 231 48 P,M ---- W,HP ---- ---- PR,MR,FP ED
24 Naghur 733 88 P(2),M PHS,CH
W W,HP PO,PT ---- PR,MR,FP EA
25 Nalkasa 244 30 P,M CHW W,HP ---- ---- PR,MR,FP ED,EA
G
26 Nalkasa 35 15 P PHS,CH
W W,HP ---- ---- PR,MR,FP ED
27 Paindhur 246 55 P,M PHS W,HP PH BS PR,MR,FP ED,EA
G
Comprehensive EIA / EMP studies for Mahamaya – Dulki expn. Iron Ore mining Project of M/s. Bhilai Steel Plant
III-165
Richardson & Cruddas (1972) Ltd.
28 Paiwani 428 69 P,M PHS W,HP PH BS PR,MR,FP ED,EA
G
29 Poswar 172 61 P,M PHS W,HP PH BS PR,MR,FP ED,EA
G
30 Pujari Para 551 92 P,M PHS W,HP PH BS PR,MR,FP ED,EA
G
31 Pusewada 360 98 P,M PHS W,HP PH BS PR,MR,FP ED,EA
G
32 Rasuli 298 13 P(2),M PHS,CH
W W,HP PH ---- MR EA
33 Salhe Tola 212 21 P(2),M PHS T,W,HP PO ---- MR EA
34 Seoni 345 48 P ---- W,HP ---- ---- PR,MR,FP ED
35 Tamoda 516 99 P ---- W,HP ---- ---- MR,FP EA
36 Tarunnagar 505 64 P,M PHS W,HP PH ---- PR,MR,FP ED,EA
G
Amenities if not available within the village, a dash (-) is shown in the column. Source: Village Directory CD–2001, Durg district, Chhattisgarh.
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-1
Abbreviations:
Educational Institutions Medical
Facilities
Drinking
Water Supply
P : Primary School PHC : Primary Health Centre
W : Well Water
M : Middle School PHS : Primary health sub centre
HP : Hand pump
S : Secondary School
MCW : Maternity & child Welfare
T : Tap Water
HS : Higher/ Senior Secondary School
CWC : Community Health Worker
TW : Tube well Water
Communication Transportation Power Supply
PO : Post Office Bs : Bus ED : Electricity for domestic use
PT : Post & Telegraph Office
RS : Railway Station EAG : Electricity for agriculture use
PH : Telephone Connection
EO : Electricity for other purposes
EA : Electricity for all purposes
Table 3.35 Morbidity Pattern of the Study Area
Sr. No. Diseases Month/ Year Registered No. of Patient
1. Malaria Jan – Dec 2009 208
Jan – Dec 2008 368
Jan – Dec 2007 196
2. Leprosy Jan – Dec 2009 27
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-2
3. Tuberculosis Jan – Dec 2009 231
Source: Block Medical Officer Community Health Centre, Rajnandgaon tehsil, Durg district, Chattisgrah
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-3
Table - 3.36 Details of Most Prevalent Disease in the region
Source: BSP Mines Hospitals
Sr.No. Diseases
1 Viral fewer
2 Gastroenteritis
3 Malaria
4 UTI (Urinary Tract Infection)
5 Asthma
6 Sickling (Sickle Cell)
7 High per tension
8 Diabetes Mellitus
9 Dyslipidmia (high cholesterol)
10 CAD (Coronary Artri Diseases)
11 Febrile Convulsion
12 Epilepsy
13 Alcoholism
14 Psychiatric problem (minor, major)
15 CVA (Ceribro Vascular Accidents)
16 Cancer
17 Accidents (Road Traffic)
18 Gyneac Cancer, Infertility, abortion
19 Kidney stone
20 Gallbladder
21 Common dental problem
22 Eye cataract problem
23 Skin Diseases (Tanea infection)
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-4
CHAPTER-IV
ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
4.1 Anticipated Environmental Impacts
4.1.1 Preamble
The mining activities proposed will have both positive and negative effects on the
surroundings. This change is called an impact. The impact could be either useful
or detrimental to the environment. The net impact could be determined by
evaluating the impact on various parameters. The parameters with adverse
impact due to unavoidable reasons have to be nullified, kept to the minimum or
brought to have positive effects by taking suitable corrective measures, to create
better environment. The project being considered will have a bearing on the
socio-economic aspects as well as on the environment due to mining and other
incidental activities. The impact depends upon the extent of mechanization,
method of mining, infrastructure facilities, environmental profile and
characteristics of environment.
The impact prediction due to the project has been made in respect of the
parameters considered in the present scenario. The quality parameters of
ambient air, water, socio-economic aspects, soil and solid waste, Health
aspects, inventory of flora and fauna due to mining operations in the buffer zone
over a period are available. These help in prediction of the impact more
correctly. Identification of environmental impacts is one of the basic analytical
steps in EIA for subsequent prediction and evaluation of impacts.
4.1.2 Construction Phase
The proposed project is only capacity enhancement of the existing mine and
impact due to construction work / activity is not anticipated except laying of
approach roads and haul road pits. During dry season, there would be the
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-5
problem of dust emission and noise production. The wildlife near the mining area
may be disturbed due to noise and dust pollution. Some trees needs to be cut in
forest area for construction.
The unstabilised excavated soil may responsible for water pollution. However, air
pollution is occurred due to transport of materials and the construction would be
insignificant considering the high assimilative capacity of this pristine environment and
dense forest cover around it.
4.1.3 Operational phase
4.1.3.1 Impact on Land use
The impact on land use pattern in the region can be divided into two distinct
domains, namely within and outside the mining area. The topography within the
mining area will have marked changes in the quarry area, the dump area and the
mining equipment area. No appreciable change in the topography is anticipated
outside mining area. The landscape and landuse pattern will have a change
within the mining area due to excavation, waste dumps and other allied mining
activities. The surface drainage in the mining area and outside mining area will
change due to mining activities and construction of Check dams.
4.1.3.2 Air Environment
Climate
Micro-climatic conditions such as temperature, rainfall, wind-speed and relative
humidity, etc are regional phenomenon and are affected only if there are
significant variations in the environmental set up.
Impact on Air Quality
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-6
The major source of air pollution into the atmospheric environment are:
1. Removal and dumping of over burden
2. Drilling and blasting operations
3. Extraction of ore by machinery.
4. Loading of ore into trucks.
5. Dump yard waste material.
6. Ore Transportation
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-7
Anticipated Impacts
In the open cast mine envisaged, mining operations such as drilling, blasting,
excavation, loading and unloading and movement of dumpers on haul roads are
expected to generate air-borne fugitive dusts. The fugitive dust released may
cause immediate effect on the mine workers, who are directly exposed to the
fugitive dust. Smaller size dust particles (<2µm) may be transported longer
distances by wind and may cause impact on the people residing nearby villages.
Dust Emission sources
Fugitive and non-fugitive dust emission sources during the iron ore mining are presented in Table 4.1.
TABLE: 4.1 Fugitive and Non-Fugitive Dust Emissions during Iron Ore Mining
S. No. Source Nature of
emission Frequency of
emission Nature of air
pollution
1. Top soil stripping
Fugitive and area source
Infrequent and pre-mining
Particulate matter (PM)
2. Drilling Fugitive and point source
Infrequent and operational phase
Particulate matter (PM)
3. Blasting Fugitive and point source
Frequent and Operational phase
CO, NOx, SO2, H2S (slurry explosives)
4. Excavation of ore
Fugitive and area source
Very frequent and Operational phase
Particulate matter (PM)
5. Waste rock dumping
Non-fugitive and point source
Very frequent and Operational phase
Particulate matter (PM)
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-8
6. Loading and unloading of ore
Non-fugitive and point source
Very frequent and Operational phase
Particulate matter (PM)
7. Material transport
Fugitive and line source
Very frequent and Operational phase
Particulate matter (PM)
8. Heavy equipment exhaust
Non-fugitive and line source
Very frequent and Operational phase NOx, SO2, HC
Emission factors in opencast mining
The fugitive emissions from a mining activity are most frequently determined
from an emission factor method, although typical emission factors may be
significantly less accurate. Despite this in accuracy, emission factors are widely
used to estimate pollutant emission rates because there is at present no better
quantification method. Silt content, moisture content, drop height, wind speed,
wet days, precipitation evaporation index are the major factors governed in
fugitive emission rates. Some of the emission factors of interest in iron ore
mining are presented below:
1. Top soil stripping and dumping = 18.5 g/MT
2. Drilling = 75.0 g/hole
3. Blasting
The emission factor for blasting is given in Table 4.2.
Table 4.2 Emission Factor for Blasting
Nature of Dust particle Gaseous factor (g/kg of
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-9
pollutant size in µm pollutants explosive)
Dust
< 2.5
2.5 – 15
15 – 30
-
-
-
5.1
41.0
49.9
Gaseous pollutants
- CO
NOx
SO2
34
8
1
4. Excavation of iron ore = 25 g/MT
5. Waste rock dumping = 20 g/MT
6. Haulage emissions = 980 g/ VKT (uncontrolled)
(Material transport) = 98 g/VKT (controlled)
7. Heavy mine equipment exhaust (grams per liter of diesel) is given in Table
4.3.
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-10
Table - 4.3 Emission factors for heavy equipment
Sl. No. Pollutant Wheeled
dozer Scraper Grader Front-end loader
Haul truck
1. CO 14.73 10.185 6.590 11.86 14.738
2. HC 1.557 2.276 1.557 5.15 1.557
3. NOx 34.27 31.03 30.43 38.46 34.27
4. SO2 3.714 3.714 3.714 3.714 3.74
5. SPM 1.797 3.235 2.636 3.474 2.156
Combination of emission sources for air quality modeling
The worst scenario of simultaneous operations of mining includes (1)
drilling, (2) extraction, (3) waste rock dumping are given in Table 4.4.
TABLE - 4.4 AIR QUALITY MODEL APPLICABILITY
Sl. No. Mine operation Nature of emission Air quality model
1. Drilling Point source FDM
2. Blasting Point source Puff model
3. Extraction of ore Area source FDM
4. Waste rock transport Line source FDM
5. Waste rock dumping Point source Puff model
Fugitive dispersion model (FDM)
The fugitive dispersion model (FDM) is a computerized air quality model
specifically designed for computing concentrations and deposition impacts of
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-11
fugitive dust sources. The model is based on the well known Gaussian plume
formulation for computing concentrations and also the model specifically transfer
deposition algorithm. Emissions for each source are apportioned into a series of
particle size classes. Gravitational settling velocity and deposition velocity are
calculated by FDM for each class. The model is designed to work on hourly
meteorological data.
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-12
The main equation is the FDM model is:
= β Vg - β 2 h)-(zVg -e
.u. ZQC 22
zzy σσπσ
++
−−2
2
2
2
22 zhze
zhze
σσ)()(
2
121 y 2
2V.e2
hz- V 4
++
+
−σσσ
βπ hzzuz
e 2.k2
z V erf 1
++
zhzσ
σ
where
β = u.2 .z
xσ
; V1 = ug – 2
gV . K =
xuz
2
2.σ
C = Concentration (g/m3)
Q = Emission rate (g/s)
σy, σz = Standard deviation of concentration in Y and Z direction (m)
x, y, z = Receptor coordinates (m)
Vg = Gravitational settling velocity (m/s)
h = Plume center line height (m)
k = Eddy diffusivity (m2/s)
Ug = Deposition velocity (m/s)
Puff model:
This model can be employed when the dust and gaseous pollutants are released
instantaneously into the atmosphere. The main equation in the puff model is
zyx
1
.. 2 σσσ∧= m
tyxQC ),,( exp.
+
−
− 2
22 y 21
yxutx
σσ
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-13
Where,
C (x, y, t) : The pollutant concentration of coordinates x and y at time
t (mg/m3)
1mQ : The mass of pollutant released (mg)
U : Wind velocity (m/s)
σx, σy, σz : The dispersion coefficients in the x, y an z directions
respectively (m)
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-14
Predicted Ambient Air Quality - Basic Input data requirements
The basic data inputs include the run stream set up file and the meteorological
data file. The run stream set up file contains the selected modeling options,
source location and parameter data receptor locations, meteorological data
specifications and output options. The meteorological data file contains the
hourly data on wind speed, wind direction, ambient temperature, atmospheric
stability class and mixing height. The meteorological for each season are given
in the Table - 4.5.
Table 4.5 Meteorology Inputs
Meteorology Inputs – Pre-monsoon season
Hour Wind speed
(m/s) Wind
direction Temperatur
e Stability
class Mixing
height (m)
1. 1.14 SW 301.5 F 300
2. 1.28 SW 304.0 F 320
3. 1.40 S 307.5 F 340
4. 1.68 SW 309.5 F 350
5. 2.14 SW 312.5 F 350
6. 2.74 SW 313.5 F 350
7. 2.86 SW 314.5 F 350
8. 2.94 SSW 315.0 B 750
9. 3.24 SW 315.5 A 1200
10. 3.64 SW 315.5 A 1400
11. 4.14 SW 314.0 A 1750
12. 3.64 SW 313.0 A 2200
13. 3.18 SSW 311.0 A 2400
14. 2.74 SW 310.0 A 2500
15. 2.62 SW 308.0 B 2700
16. 2.50 SW 307.0 B 2600
17. 2.40 SW 305.0 C 2500
18. 2.30 SSW 303.0 C 2500
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-15
19. 2.14 S 302.0 F 2300
20. 2.10 S 301.5 F 2000
21. 1.86 S 301.0 F 1400
22. 1.72 SW 300.5 F 1000
23. 1.52 SSW 300.0 F 750
24. 1.34 SSW 300.0 F 500
Post-monsoon season
1. 1.08 NE 288.0 F 90
2. 1.12 ENE 289.5 F 120
3. 1.12 ENE 291.0 F 140
4. 1.4 ENE 292.5 F 140
5. 1.86 NE 294.0 F 150
6. 2.46 NE 296.5 F 150
7. 2.58 NE 298.0 F 250
8. 2.66 NE 300.0 B 400
9. 2.96 NE 301.5 A 500
10. 3.36 NE 302.5 A 700
11. 3.86 NE 299.0 A 800
12. 3.36 NE 297.0 A 950
13. 2.9 ENE 294.0 A 1100
14. 2.46 NE 292.0 A 1200
15. 2.34 NE 291.5 B 1100
16. 2.22 ENE 290.5 B 1050
17. 2.12 NNE 290.0 C 950
18. 2.02 NNE 289.5 C 650
19. 1.86 ENE 289.0 F 400
20. 1.82 NNE 288.5 F 300
21. 1.58 NE 288.0 F 250
22. 1.44 NNE 287.5 F 180
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-16
23. 1.24 NNE 287.0 F 150
24. 1.06 NNE 286.5 F 100
Winter season
1. 1.04 NE 282.0 F 50
2. 1.08 ENE 283.0 F 50
3. 1.08 ENE 285.5 F 50
4. 1.36 ENE 288.5 F 60
5. 1.82 ENE 291.0 F 75
6. 2.42 ENE 293.5 F 90
7. 2.54 ENE 296.5 F 100
8. 2.62 ENE 298.0 B 160
9. 2.92 NE 299.5 A 220
10. 3.32 NNE 300.0 A 350
11. 3.82 E 299.0 A 800
12. 3.32 E 298.0 A 1200
13. 2.86 E 297.5 A 1300
14. 2.42 NNE 295.5 A 1500
15. 2.3 ENE 291.0 B 1500
16. 2.18 ENE 289.0 B 1400
17. 2.08 ENE 287.0 C 1300
18. 1.98 ENE 286.0 C 750
19. 1.82 ENE 285.0 F 550
20. 1.78 E 284.0 F 200
21. 1.54 NE 283.0 F 150
22. 1.4 NE 282.0 F 100
23. 1.2 NE 282.0 F 50
24. 1.1 NNE 282.0 F 50
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-17
Output data
The output may be obtained for short term (hourly, daily or monthly) averages or
long term (annual) averages. The predicted values are given in Table 4.6 – 4.8.
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-18
Predicted ground level concentrations Pre-monsoon season
Table – 4.6 Air Environment in the study area - Post project Scenario (PM10) (µg/m3)
S. No. Location name Baseline
scenario (max) Predicted
values Post Project
scenario
1 Core zone (Mine pit 3) 128 10.2 138.2
2 Corezone (Canteen) 117 9.2 126.2
3 Gajjitola 36 1.4 37.4
4 Dongarbhar 49 0 49
5 Kanikasur 48 0.8 48.8
6 Nergaon 57 0.3 57.3
7 Kumarkatta 75 2.8 77.8
8 Kopedera 83 4.1 87.1
9 Dupkatola 69 1.9 70.9
10 Katrel 41 3.2 44.2
11 Tuedand - -
12 Dulki - -
13 Markamtola - -
14 Resuli - -
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-19
Post Monsoon season
Table 4.7 Air Environment in the study area - Post project Scenario (PM10) (µg/m3)
S. No. Location name Baseline
scenario (max) Predicted
values Post Project
scenario
1 Core zone (Mine pit 3) 89 8.3 97.3 2 Corezone (Canteen) 90 7.2 97.2 3 Gajjitola - - - 4 Dongarbhar 56 0.8 56.8 5 Kanikasur 60 0.5 60.5 6 Nergaon 49 1.2 50.2 7 Kumarkatta - - - 8 Kopedera - - - 9 Dupkatola 53 0 53
10 Katrel - - - 11 Tuedand 49 0 49 12 Dulki 74 5.1 79.1 13 Markamtola 57 4.9 61.9 14 Resuli 47 4.2 51.2
Winter season
Table s4.8 Air Environment in the study area - Post project Scenario ((PM10) (µg/m3)
S. No. Location name Baseline scenario
(max) Predicted
values Post Project
scenario
1 Core zone (Mine pit 3) 96 9.1 105.1
2 Corezone (Canteen) 80 12.4 92.4
3 Gajjitola - - -
4 Dongarbhar 64 1.1 65.1
5 Kanikasur 65 0.5 65.5
6 Nergaon 54 1.8 55.8
7 Kumarkatta - - -
8 Kopedera - - -
9 Dupkatola 59 0.0 59
10 Katrel - - -
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-20
11 Tuedand 51 0.0 51
12 Dulki 78 5.2 83.2
13 Markamtola 65 5.1 70.1
14 Resuli 61 3.6 64.6
Post Monsoon season ( Nov.2012)
Table 4.7 Air Environment in the study area - Post project Scenario (PM10) (µg/m3)
S. No. Location name Baseline
scenario (max) Predicted
values Post Project
scenario
1 Corezone (Mine Pit 3) 73 8.8 81.8
2 Corezone (Canteen) 82 7.1 89.1
3 Tuedand 56 0.2 56.2
4 Dupkatola 52 0.2 52.2
5 Dulki 56 6.2 62.2
6 Markamtola 56 5.4 61.4
7 Kalangpur 64 0.5 64.5
8 Rasuli 56 0.8 56.8
9 Bodra 56 1.8 57.8
10 Kalwar 64 1.1 65.1
11 Dorba 62 0 62.0
12 Nagbur 52 0 52.0
It is clear from the predicted values that the concentrations of PM10 are below
the limits of NAAQS in the buffer zone (residential and rural area). However in
the pre-monsoon season, core zone values were found to be exceeding the
NAAQ standards (residential and rural area). However It is clear from the predicted values with baseline data, the concentrations of PM10 are below
the limits of NAAQS in the buffer zone and core zone. The air pollution
control measures discussed in this Chapter may be implemented to control the
fugitive dust emission in the corezone mining area. The isopleths of PM10 is
given for different season are shown in Fig. IV.1-3.
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-21
Prediction for vehicular emissions
In the present case, prediction of impacts has been carried out on 8 hourly basis
upto a distance of 500 m on either side of the roads of mines. It is predicted that
the maximum contribution to ground level concentrations of CO, HC, NOx and
SPM due to vehicular movement will be less than 3 µg/m3 beyond 500 m from
the road as the vehicular density is very less and is only due to mining activities.
So there will not be any significance impact due to vehicular emission at various
receptors within the study area, when taking into consideration the stipulated
standards of 80 µg/m3, 80 µg/m3 and 2000 µg/m3 for SO2, NOx and CO
respectively.
4.1.3.3 Impact on Noise Level
Once the mine becomes operational, there would be various sources of noise in
the area. These sources would be Drilling,Blasting,Operation of HEMM and
Vehicular Movement. Mining operations is the main sources of noise pollution.
Noise due to vehicular movement will be intermittent, but will also add to the
background noise level. It has been observed that mechanization of mining
technology generally leads to higher noise levels if not properly controlled.
Operation of drills, shovels, dumpers, pay loaders and dozers involve noise
generation above 90 dB(A),which is the prescribed Threshold Limit Value
(TLV).The anticipated Noise level in opencast mines due to Heavy Earth Moving
Machinery (HEMM) equipment is given in the Table 4.9.
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-22
Fig IV.1 Isopleths for SPM (Pre-monsoon)
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-23
Fig IV.2 Isopleths for SPM (Post monsoon)
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-24
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-25
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-26
Fig IV.3 Isopleths for SPM (Winter)
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-27
Table 4.9 Anticipated Noise level due to HEMM
Equipment Measurement
Location Noise Level dB (A)
Shovel, Operating Operator's Position 80-82
Shovel, Operating 03 m away 94-100
Electric Shovel Operating 10 m away 87-92
Dozer, Operating Operator's position 92-98
Equipment Measurement
Location Noise Level dB (A)
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-28
Dozer, Operating 10 m away 87-96
Drill, Operating Operator's position 94-98
Dumper, operating (50 t) 12 m away 88-102
Dumper, operating (80 t) 12 m away 70
Dumper, operating 03 m away 98-100
Dozer & Dumper both, operating 06 m away 95-110
.
It is being observed that at the mine site where heavy earth moving machinery is
in operation, noise level is more than the stipulated 90 dB (A) per DGMS Circular,
No 18 (Tech) of 1975. The noise level is within the tolerance limit at a distance of
15 to 20 m or so. The sound pressure level generated by a noise source
decreases with increasing distance from the source due to wave divergence.
Noise attenuation with respect to distance in all directions over horizontal distance
can be given by the following equation:
Sound level dB(A) = Lw - 20 log10 R-8
Where Lw = Sound level of source, dB(A)
R = Source distance, m
4.1.3.4 Impact on Water quality
Surface Water
There is no perennial water stream within or outside the mine lease area and
hence there is no impact on surface water quality.
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-29
Ground Water
The potential impact of mining would have negligible impact on the ground water,
as the site and its adjoining areas are, located at an elevated topography coupled
with mine run-off management planning and regional geology. The likely chances
of the contaminants reaching the groundwater are very rare. In general, no
significant on ground water quality in the study area.
4.1.3.5 Impact on Soil Quality
The soil fertility will have impact due to Surface mining operations comprising
removal of vegetation and topsoil disturbs the natural ecosystem due to land
degradation and dumping of overburden, and where erection and development of
plants, service /allied services buildings, colony, roads and drains are to be
executed. The impact assessment of various soil parameters are given in Table
4.10.
Table – 4.10 Impact Assessment of soil parameters
Parameters Impact Assessment
pH Existing pH of the soil level is neutral indicative and the
mining activities are mainly opencast, therefore, the likely
effect on surface soil quality will be to a few extent.
Electrical conductivity (EC)
Existing EC being <1.00 milli-mho/cm is not going to an
appreciable change as the mining activities are mainly
opencast, therefore, the likely effect on surface soil quality
will be to some extent. It will hardly attain harmful
germination condition level of EC in this project.
N, K & P The mining activities are mainly opencast therefore, dump
leachate may have to some extent the likely effect on
surface soil quality.
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-30
Parameters Impact Assessment
Soil characteristics,
erosion aspects and
Engineering parameters
The mining activities are mainly opencast, therefore, the
likely effect on surface soil quality will be in few extent.
4.1.3.6 Socio economical impacts and infrastructural developments
In terms of the major socio-economic impacts, the project will provide more direct
and indirect job opportunities and better economic standards to the people and
others, through improved infrastructural, community facilities etc. creation of civic
and welfare amenities like primary health care, communications, educational
institutes, recreational facilities, etc, that will develop along with the project will
ensure better quality of life for the local population. The increase in income
opportunities and employment potentialities in this sector is anticipated as the
mining activities increase, the other economic sectors starts gaining in
momentum. New avenues of employment in the sectors such as construction,
trade & commerce and service is also getting on the move resulting in shooting up
demand of workers and others. Population growth in the project area as well as in
the buffer zone is already accelerated owing to immigration of people from
outside resulting in increased job and income opportunities. The incoming
population to the project is already moved in search of jobs and thereby, a
problem of new human settlement come into existence, and additional worker
colonies start growing in. In view of that the existing civic amenities such as water
supply, power supply etc. is in improvement with the ongoing of the project. With
added educational, medical and communication facilities developed in the areas,
the standard of living has improved. With ongoing of mining activities additional
facilities for local population by way of better communication, postal services,
educational facilities, advanced medical services etc. are on in the area. There is
a marked change in social status of the area with opening of the project. State
Government is benefited through financial revenues in crores of rupees by way of
royalty, sales tax etc. from the -direct and indirect operations in the project area.
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-31
Central exchequer is also getting financial revenues by way of Income tax,
Central Sales Tax etc.
4.1.3.7 Impact on flora and fauna
There will be positive impact on flora and fauna due to the proposed plantation
activities and the conservation plan proposed for the forest and wild life. The
negative impacts are mainly due to Mining activities such as excavation for quarry.
This activity will guide to forest degradation, lost of vegetation cover. The
plantation work and forest and wild life conservation in scientific way by project
authorities will increase astheticity of the area and reduces impact due to air and
noise pollution.
4.1.3.8 Hazard assessment
Ground Vibration
Due to blasting, the vibrations can cause damage to the nearby structures if
appropriate control measures are not adopted. Blasting will also result in fly rocks.
The factors, which influence fly rock production, are long explosive column with
little stemming column, improper burden, loose material or pebbles near the holes
and long water column in the hole. The actual blasts at the mines are to be closely
monitored for any fly rocks and precautions against fly rock are to be taken. When
an explosive charge is fired in a hole, stress waves propagate radically in all
directions and cause the rock particles to oscillate. This oscillation is felt as ground
vibration. The existing mining operations using deep hole drilling and blasting
using delay detonators are bound to produce ground vibrations. Blasting, in
addition to easing the hard strata, generates ground vibrations and instantaneous
noise. Ground vibrations from mine blasting may be expressed by amplitude,
frequency and duration of blast. The variables, which influence ground vibrations
are controllable and non-controllable. The vibrations are measured as per the
assessment criteria given under Bureau of Indian Standard Criteria for Safety and
Design Structures Subject to Underground Blasts – IS : 6922 – 1973 (Reaffirmed
1995).Per the Standard, for safety of structures from threshold damage, the
ground particle velocity should not exceed the following:
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-32
• Soil, Weathered or Soft rock 50 mm/sec
• Hard Rock 70 mm/sec
The main impacts due to ground vibration are may be due to
• Development of cracks in the houses located in the neighboring areas.
• During blasting rock fragments mayfly up to a distance of about 150 m.
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-33
Possible accidents
The possible chances of accident in opencast mining operation are due to slope
failure of mine pit, OB dump slope failure, explosive handling, blasting operation ,
mine inundation., fire etc. These may cause severe impacts on life and property
unless proper care and mitigative measures have been adopted. The possible
accident and risk assessment with proper mitigative measures are as follows:
Slope failure in Mine Pit
The exposed ends of the mine benches and OB will be left with a safe slope to
avoid slope failure and collapse of benches. Similarly, at the end of mining
operation safe terminal pit slope-will be provided to avoid failure.
All the working benches will be under the direct supervision of project level
officials and all the necessary precautions will be taken to make the workings
safe.
Blasting
The risks involved in storage of explosives and its handling are:
• Accidental explosion due to adopting unsafe practices
• Poor blasting parameters leading to excessive ground vibrations, noise, air
blast and fly rock during blasting.
Accidental Explosion Due to Adopting Unsafe Practices:
All activities involving storage, handling and transportation will be in accordance
with the rules made under the Indian Explosive Act and conducted with proper
licences and approval from concerned authorities. All blasting operations will be
performed by competent persons taking adequate precautions to make the
operation totally safe. A detailed code of procedures for storage, handling and use
of explosives will be prepared and strictly followed. All the employees will be
trained and made conscious of adopting safe practices as per the safety policy
and procedures laid down by the company.
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-34
Poor Blasting Parameters Leading to Excessive Ground Vibrations, Noise, Air
Blast and Fly Rock During Blasting. The frequency of blasting will be optimized by
conducting blasting once a week and also adopting multi-row blasting using delay
detonators. The blasting pattern, stemming column, charge per hole, etc. will be
designed so as to control the fly rock and the ground vibrations. Non-electric
shock tube initiation systems will be deployed to enhance safety of operations,
better blasting control and reduce noise due to air blast. Depending on the actual
experience once the excavation commences, blasting parameters can be
changed suitably to adhere to strict safety measures.
The following precautions have been suggested to avoid dangerous situation:
• The optimal blast design parameters will be implemented.
• A safety zone of 100m beyond the quarry limit is envisaged and controlled
blasting will be done keeping this aspect in mind.
• The blasting will be done at a fixed time as far as possible.
• All necessary precautions will be taken while blasting.
• Regular monitoring of vibration will be carried out and necessary precautions
will be taken while blasting.
• Before blasting is done, warning siren will be activated so that people can
move over to safe places.
Mine inundation
The mine pit will receive water from three sources namely, direct precipitation
over excavated area, surface run-off from the surrounding area and seepage
from the strata. During heavy rainstorms, there may be a situation when the
mine may get flooded due to ingress of water from the higher ground through
natural drainage. This may cause loss of human life, equipment etc. To guard
against this eventuality, the following steps will be taken.
• Provision of garland drain around the mine to prevent ingress of precipitation,
run off & keeping the same.
• Provision of sufficient number of pumps to pump out mine water during the
critical rainfall period.
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-35
Road Accidents
Sufficient arrangements for illumination of road including haul roads will be
undertaken. Properly planned and designed road crossing will be implemented to
prevent vehicular accidents. Further haul roads have been planned in such a way
that the HEMM traffic will be away from the passenger traffic. These are likely to
prevent road accidents. All the dumpers are fitted with sound warning while
reversing, thereby preventing accident
4.1.4 Mitigative measures
4.1.4.1 Hazardous and accidents
Steps to be taken by the project authority to avoid hazards/accidents are as under
a) Mining
(i) Machinery maintained properly giving emphasis on preventive maintenance
(Replacing all worn out parts)
(ii) Imparting proper training to all the operators
(iii) Following strict traffic discipline
(iv) Not allowing unauthorized persons to enter the mine or traveling in the
dumpers or other units
(v) Storage, transport and use of explosives as per the provisions of
Explosives Act , Rules and DGMS issued in this regard.
(b) Slope failure of benches :
i) Regular bench geometry so as to keep the near all pit slope less than 45o .
ii) Regular inspection for cracks and crevices in benches and bench
movement including dumps.
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-36
(c) Inundation :
Inundation of lower benches of the mine is a remote possibility. But this hamper
the mining operations on those benches but it is not likely to cause any
casualties.
(d) Fire :
To avoid occurrence of fire accidents within the mine the following management
measures shall be undertaken :
1. Proper maintenance of equipment including the electrical fittings
2. To have fire lines cut to avoid spreading of forest fires during summer seasons.
3. Provision of firefighting equipment at various installations
4. Training of personnel in fire fighting.
(e) Gaseous Pollutants :
The precautions such as proper maintenance of equipment shall reduce
gaseous emissions such as SO2, NOx and CO so that their emissions are below
the permissible limit in the mine environment.
4.1.4.2 Employment opportunities
There will be spontaneous economic stimulus in the area with the
commencement of opencast mine. Traders and private enterprises will grow in
the area with this economic growth. Besides, the State exchequer will derive
financial revenues through levy of royalty, sales tax etc. and Central Government
will also be, benefited by way of Central Sales Tax, Income Tax, Cess's etc.
4.1.4.3 Medical Facilities
Medical facilities are required to be increased by the project for their workers and
the people of the area. Every worker is to be periodically checked up once in
every five years keeping proper record of their health profile including X-ray and
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-37
laboratory tests by establishing and extending pathological facilities.The
importance of such periodical medical examination is to detect and prevent
occupational diseases like Pneumoconiosis and Tuberculosis. The mining
activities expose workers to some injuries and health hazards. Incidence of
occupational disease and injuries and health hazards has not been recorded in
those health centers / hospitals.
Preventive measures
The project authorities have adopted following measures to prevent occupational
diseases and health hazards.
• Pre-employment, periodic medical examination of employees.
• Regular monitoring of working environment and implementation of safety and
control measures, to prevent hazards.
• Use of protective equipments, clothing, helmets, Gas mask, shoes, etc.
• Periodical medical examination-of every worker is done once in five years to
detect preventable and curable diseases at an early stage.
• Lung Function Test (LFT)
• Cases suspected having Pneumoconiosis is examined by a Special Board
constituted by the Chief Medical Officer. Established cases are suitably
compensated and their job is changed if required.
4.1.4.5 Solid Waste Disposal and Its Management
Planning of OB dumps
Rate of yearly generation of waste and proposal for deposal of waste for
next five year.
Year Top Soil Overburden/Waste Mineral Rejects
2011-12 Nil 645744 Nil
2012-13 Nil 757066 Nil
2013-14 Nil 704099 Nil
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-38
2014-15 Nil 741884 Nil
2015-16 Nil 767514 Nil
Total Nil 3616308 Nil
Waste generated from the M-1,M-2 ,M-3 & D-1 pits is dumped at the waste
dump located in the south-eastern slope. The area selected is a non-mineralised
& away from any perennial water source. The height of dump during the year
2011-12 will be 20 mtrs. The waste quantity generated during 2011-12 to 2014-
15 is 1723026 tonnes, will be proposed to dumped in the existing dump.
Rate of yearly generation of sub-grade mineral is given as below:-
YEAR SUBGRADE MINERAL (G.F.)
2011-12 154929
2012-13 116403
2013-14 85311
2014-15 87652
2015-16 124593
Total 568889
Around 45-55 % Fe content mineral being encountered during mining
considered as sub-grade mineral and being stacked separately for future
consumption in dump. The height of the dump will be 5 mtrs. Around 55-58 % Fe
content is available in sub-grade material and quantity of total G.F. accumulated
in G.F. dump is approx. 2 MT. It is also dumped in non-mineralized zone.
4.1.4.5 Control measures for air pollution
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-39
Following air pollution control measures are being done and will be practiced
within the mining area and at ore handling plants.
• Saplings planted on OB dump, road side and colony to arrest dust.
• Mobile water sprinklers deployed in mine.
• Stationary sprinkler installed in the mine haul road from mine entry.
• Overloading of trucks is strictly prohibited.
• Ore transportation through covered trucks
• Optimum blast hole geometry will be followed to reduce the dust during
blasting.
• Regular monitoring of ambient air quality of the project area & its surroundings
villages
4.1.4.6 Water management
Management of surface water drainage
Garland drains will be made around the periphery of the quarry. These garland
drains will be connected to the local nalla which is not likely to be disturbed by
mining operation. In the workings, heavy duty pumps will be deployed in rainy
season which will throw the accumulated water from the working face into these
garland drains. As the extraction of the quarry advances, the position of garland
drain will also advance. Thus these garland drains will drain of the rain water away
from the workings. There are 14 nos. of check dams were already constructed and
10 nos. are proposed in earmarked area
Mine Water Discharge
The mine water discharge which needs treatment before discharge to the surface
water drainage. The collected water at the floor of mine sump will be pumped to
the settling tank where suspended solids will get settled. The clear water after
sedimentation will be reused for water sprinkling, plantation etc.
Water Conservation
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-40
The waste water recycling after due treatment for the purpose mentioned above
will enable conservation of water. Storage of conserved water in mine pits will be
given due emphasis to provided water round the year and quality of water will be
maintained before and after storage.
Rainwater Harvesting Scheme in Study Area
The general range of ground water levels in the phreatic aquifer varies from 4.25
to 10.2 meter below ground level in pre-monsoon period, while in post-monsoon
period it varies from 0.60 to 7.20 meter below ground level.
The recharge ponds will be developed and minimum distance between two
structures within same pond should be kept as 50 m. Rainwater Harvesting
(Percolation) structures will also be made along road side or in open areas
wherever feasible as per physiographic gradient. The minimum spacing between
two such structures shall be at least 100 m.Existing defunct/abandoned
wells/tubewells may be connected to the recharge structures. Rain water
harvesting structure shall be made in all office buildings of Mahamaya mine.
4.1.4.7 Control measures for Noise
The present noise levels are below the prescribed limits. If the impulsive noise
levels increase due to mining operation, suitable measures will be adopted to
maintain the noise level within permissible limits at working zone.
To keep the ambient noise levels within the permissible limits of 65 dB(A), the
following measures should be adopted:
• Innovative approaches of using improvised plant and machinery designs, with
in-built mechanism to reduce sound emissions like improved silencers,
mufflers and closed noise generating parts
• procurement of drill, loaders and dumpers and other equipment with noise
proof system in operator's cabin
• confining the equipment with heavy noise emissions in soundproof cabins, so
that noise is not transmitted to other areas
• regular and proper maintenance of noise generating machinery including the
transport vehicles and belt conveyors, to maintain the noise levels
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-41
• blasting operations to be carried out only during daytime so as to avoid high
noise intensity in night time
• provision should be made for noise absorbing pads at foundations of
vibrating equipment to reduce noise emissions
• thick green belt should be provided at the mine periphery, within the mine
lease area along the roads and all around the working areas, to screen the noise.
Blasting Vibration Control Plan
Vibration standard
Ground vibrations due to blasting and its impact on various mine structures, to be
studied in details when the mine becomes operational, especially the charge per
delay factor. Drilling and charging pattern should accordingly modified based on
this study. A proper management plan should be designed and administered. The
general measures to reduce ground vibration & flyrocks resulting from blasting are
given below:
• Peak particle velocity or ground vibrations for safety of nearby structures and
residential buildings should be well within 12.5 mm/sec
• to contain fly rocks, stemming column should not be less than the burden of the
hole, and the blasting area should be muffled
• short delay detonators should preferably be used in blasting rounds rather than
detonating fuse as trunk line
• detonating fuse, if used, should be covered at least with 150 mm thick cover of
sand or drill cuttings
• blasting should be carried out in the daytime, as during the night time the sound
intensity becomes higher
• blasting should not be carried out when strong winds are blowing towards the
inhabited areas
• each blast should be carefully planned, checked, and executed under the
supervision of a responsible officer. Blasting data/observations should be
recorded
• Bruggs mesh shall be provided as and when required for arresting any fly rocks
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-42
and boulders from mining operation
As per the mining plan, in order to ensure slope stabilization, controlled production
blasting shall be adopted to avoid tension cracks and back breaks. Such cracks
may get filled with water, which reduces the stability of excavated slopes and the
angle of slopes.
Warning
Before blasting is carried out, warning sound will be given so that people can move
to safe place.
4.1.4.8 Green Belt Development
Plantations including Dust Filtering Trees
The tree and shrub vegetation will be grow around the beneficiation plant and by
the side of roads which act as dust filters and sink to the fumes coming from
blasting, heavy machinery and heavy vehicles.
Dust filtering trees will be planted by the side of roads including haul roads in
mining lease area, at infrastructural facilities like crushing plant, beneficiation
plant. Green belt will be developed around crushing plant, beneficiation plant.
The green belt will be developed by making use of diverse local tree species,
fodder plants, fruit trees and grass species of fodder importance.
The plantation and green belt would provide habitat for birds and arboreal
animals as well as natural environment for wildlife and may not scare away due
to aesthetic environment.
Selection of Plant Species for Greenbelt
The plant species suitable for green belt development will be selected based on
the following characteristics.
• Diverse fast growing local plants
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-43
• They should have thick canopy cover
• They should be perennial and evergreen
• They should have high sink potential for pollutants
• They should be efficient in absorbing pollutants without significantly affecting
their growth.
Plan for Plantation
The plant species identified for greenbelt development will be planted using
pitting technique. The pit size will be either 45 cm x 45 cm x 45 cm or 60 cm x 60
cm x 60 cm. Bigger pit size is prepared on marginal and poor quality soil. Soil
used for filling the pit will be mixed with well decomposed farm yard manure or
sewage sludge at the rate of 2.5 kg (on dry weight basis) and 3.6 kg (on dry
weight basis) for 45cm x 45 cm x 45 cm and 60 cm x 60 cm x 60 cm size pits
respectively. The filling of soil will be completed at least 5-10 days before actual
plantation. Healthy sapling of identified species will be planted in each pit. The
list of air borne dust collector trees are as follows..
• Azadirachta indica (Neem)
• Bauhinia purpurea (Keolar)
• Butea monosperma (Palas)
• Cassia fistula (Amaltas)
• Delonix elata
• Ficus benghalensis (Bargad)
• Ficus religiosa (Peepal)
• Lagerstroemia parviflora (Lendia)
• Mangifera indica (Aam)
• Polyalthia longifolia (Ashok)
• Tamarindus indica (Imli)
• Tectona grandis (Teak)
• Terminalia arjuna (Sagwan)
• Thespesia populnea (Karra)
4.1.4.9 Mine closure plan
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-44
This progressive mine closure plan has been prepared as a statuary document
required with the mining plan required to be for renewal of mining lease.M/s
Bhilai Steel Plant (BSP), a subsidiary of Steel Authority of India Ltd (SAIL), is
having a mining lease of 1522.67 Ha. known as Mahamaya - Dulki lease situated
in the Durg district of Chattisgarh State.This is an opencast mine being worked
manually. At present the mine is producing @ 0.96 million tonnes of ROM per
year. The ore produced is feed to Bhilai steel plant at Bhilai, Chattisgarh State.
The production is proposed to increase 1.460 MT per year.
Considering the availability of reserves, rate of production and the demand of
iron ore, at present there is no any proposal to close the mine. The item wise
explanation for this is as follows:
a. Exhaustion of mineral
Considering the availability of reserves and the present rate of production the
life, of the mine is more than 10 years. Hence the mine will be closed only after
complete exhaustion of mineral in the leasehold.
b. Lack of demand
At present the iron ore demand is very high and the rates in the national and
international market are also showing a rising trend, thus there is no iogical
reason for ceasing the mining activity.
c. Uneconomic operations
At present the iron ore is in high demand and is fetching a high sales price, thus
will fetch a good profit. It is expected that this trend will continue for another 10
years.
d. Natural calamity
Since the leasehold is not in a seismic zone, and situated on top of the hill, the
possibility of closure due to natural calamity like earthquake or flood is not
expected.
e. Directives from statutory organisation or court
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-45
No directives have been issued for closure of the mine from any statuary
organization or court for this lease.The calculated life of the mine based on
available reserves and the proposed production plan is about 10 years and shall
be abandoned during the year 2020. A final mine closure plan incorporating time
schedule for abandonment shall be submitted before one year of its closure as
per rule
Abandonment Cost
The activity wise cost estimation for abandonment area as under:-
a) The protective and rehabilitation measure cost @ Rs.1.5 lakhs/ hect.
- 0.30 crores
b) Desilting of check dams for 2 years - 0.20 crores
c) Environment monitoring mechanism for 2 years - 0.10 crores
d) Unforseen expenditure towards corrective measures for safety & environmental protection measures & statutory payment
- 0.20 crores
e) Dismanting of structures - 0.10 crores
f) Miscellaneous expenditures - 0.20 crores
Total Estimated cost - 1.10 crores
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-46
Mine Closure Monitoring & Auditing
The mine authority shall comply with the closure plan approved. Monitoring of the
plan will be carried out at the project site during the life of the project and at each
stage of the closure. The mine authority has an ongoing responsibility for
rehabilitation of its mine site to the point where the site can be returned to the
concerned. The company should create organization at mine, area and
headquarter level to monitor the operation of mine closure.
There will be an organization / team of supervisory officers / staff and workman for
implementing and carrying out various activities of mine closure. A team of
employees will continue at the mine site even after the mine is closed, to see
that completion criteria are met or not. The last phase of the closure may take 4
to 5 years of time even after production of ore is stopped. The mine authority will
finally withdraw from the area after the implementation of closure plan.
CHAPTER V ENVIRONMENTAL MONITORING PROGRAMME
5.1 Preamble
Several measures have been suggested in the Environment Management Plan
(EMP) for mitigation of identified adverse environmental impacts. These have to
be implemented to ensure compliance with the environmental regulation and
also to maintain a healthy environmental conditions in and around the project.
A monitoring strategy is required to ensure that all environmental resources
which may be subject to contamination are kept under review and hence
monitoring of the individual elements of the environment is necessary. The
Environment Lab at Dalli – Rajhara will be entrusted with this responsibility. The
officers of EMD will assess the progress and analyze the data periodically. In
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-47
addition to the above, the project will take all necessary steps to implement the
safety measures as per DGMS guidelines.
5.2 Meteorological Station
It is necessary to monitor the meteorological parameters regularly for
assessment and interpretation of air quality data by installing a weather station to
record the following data
• Wind speed and direction
• Rainfall
• Temperature and humidity
5.3 Air Quality
BSP will monitor the ambient air quality for the parameters PM10, PM2.5, SO2,
NOx,CO,NH3,Ozone and Heavy metals regularly at 6 locations in and around the
mine (downwind direction and where Max. GLC of Particulate Matter) as per the
NAAQ Standards 2009.
5.4 Water Quality
Ground water will be sampled regularly once in a season from various locations
around the mine site to ascertain the trend of variation in the water quality, if
any. The surface water quality in the nearby nallah and check dams will be
analyzed once in a month as per GSR 422E.The drinking water will be monitored
and analysed as per IS.10500 norms once in a month.
5.5 Drainage System
The effectiveness of the drainage system depends on proper maintenance of all
drainage pipes/channels. Regular cleaning of drains will be done to remove
accumulated sludge/sediments. The catch-pits linked to the storm water drainage
system from the areas will also be regularly cleaned to ensure their effectiveness.
This exercise will be carried out during the pre monsoon.
5.6 Noise Levels
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-48
Noise levels will be measured at the source of generation on quarterly basis- It is
desirable that the noise attenuation measures are taken at the design stage
itself. However, in case of high noise generating equipment which are not
frequented by the project personnel, the area may be clearly marked as `High
Noise" area and the employees be provided with personal protective equipment
like ear plugs/ear muffs.
5.7 Plantation Monitoring
The project authority at field level will continuously monitor the growth and
survival/mortality rates of the plantations till the end of 3 years ".Once trees
attain desired growth, no further monitoring will be required.
5.8 Socio-Economic Development
BSP will undertake various social welfare programmes for up-liftment of
surrounding villages.BSP will have structured interactions with the plant
surrounding villages people to disseminate the measures taken by the proponent
and also to elicit suggestions for overall improvement of the surrounding villages.
5.9 Action Plan for Land Reclamation and Plantation
Details of action should be made for systematic land reclamation and plantation
on a regular time schedule. The action plan should delineate the quantum of
overburden to be excavated, backfilled, the plantation schedules etc. Interaction
with different Government Departments like Department of Agriculture,
Chhattisgarh State forest department, Forest Research Institute would give
additional technical guidelines. Guidelines from State and Central Ministry of
Environment and Forest will be obtained for effective implementation of EMP.
5.10 Health Monitoring
A regular system exists under which all the new appointees are subject to IME
(Initial Medical Examination) and regular employees are covered by PME
(Periodic Medical Examination) for monitoring health of the workers and staff
associated with the mining operations and other connected industrial activities
for identifying occupational diseases etc. in time and initiating remedial
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-49
measures. Mobile ambulance will also be used for such programmers to monitor
the health of the population around the area.
5.11 Emergency procedures
In the process of regular monitoring as per the schedule discussed in the
preceding sections if any environmental parameters such as air quality, water
quality, noise levels etc. found to be above the prescribed levels of standards
immediate control measures are adopted at the source of generation of
pollutions.
5.12 Budget
The total budget for environmental monitoring shall be 20 Lakhs / Annum.
CHAPTER VI
6.0 Additional Studies
6.1 Public consultation during EIA Studies
The proposed ML area of Mahamaya–Dulki Mines falls under the districts of
Rajnandgaon and Durg in Chhattisgarh state. Two separate Public hearings
were conducted on 17.02.2011 and 02.05.2011. Around 195 and 231 public
were attended in the above public hearings at Rajnandgaon and Durg districts
respectively.
Chhattisgarh Environmental Conservation Board in their letter Nos.
TSCECB/2011 dated 10.03.2011 and 28.06.2011 has forwarded the
proceedings of PH for the two districts separately along with other documents
and CD’s of video recording to MOEF, GOI.
6.1.1 Comments of Responders on key issues
The proponent has identified the following issues,
Employment
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-50
Most of the responders of the two districts were asked about the job
opportunities. The main queries raised were as under
• The villagers are highly unemployed and employment should be given to the
local persons. Dulki mine should be opened to resolve the unemployment
problem.
• Provide jobs for unemployed youths in mine
• The mechanization of the mines to be closed and mine workers are to be
employed for Iron ore excavation
• As far as possible avoid appointment on contract basis and provide regular
jobs.
• The Outsiders should not be entertained to get jobs in the Mahamaya mines
• ITI centres are to be opened at Kumarkatta
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-51
Socio-economic issues
• Education is most backward in this area and schools may be opened.
• Primary Health Centres and Hospitals to be provided
• Education to be provided as per the choice of the people
• Improve infrastructures like road, electricity & water supply
• New Bridges across the water bodies to be constructed for transportation
• Hand pump and drinking water facilities may be made to the location people
• Mahamaya Temple and road from Mahamaya to Nalkasa should be
developed
• Health facilities should be made within the Grama Panchayat, Kurumkela
• There should be plan for physically disabled peoples
Land Acquisition issues (of the existing other mines of BSP)
• No compensation is paid to the land losers.
• Compensation should be provided for the affected farmers due to the project
• The crops were damaged and compensation to be given
Pollution aspects
• Air pollution will be increase due to blasting and Transportation
• The nearby nallahs and fields were polluted due to mining
• The water is contaminated with Iron ore
• The proposal for overburden waste may be explained
• The fields become barren due to red soil
• The proper water sprinkling is not done and all the roads were polluted
• Iron ore fines entering to the crop fields may be avoided
Green belt development
• The existing tree plantation may be made
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-52
6.1.2 Reply and Action Plan
After observing the above comments and suggestions raised during public
hearing, the following solutions / action plan were made by BSP. The details of
Public Hearing, proceedings and action plans were given in Annexure III.
Rajnandgaon district
• New mines being opened to increase the production of steel
• Opening of Mines will not harm to anyone.
• Industry has experience of mining in the last 60 years. Therefore, during
mining pollution or any other losses will be taken care of.
• The contaminated water produced from Dulki mines will not released through
the nallah or else it will be prevented through check dam. Already 14 check
dams were constructed and 10 more is proposed. The EMP given in the EIA
/EMP report will be strictly followed to control the water pollution
• Control Blasting will be adopted
• Pollution is mainly generated during crushing. Crushing will be at Dalli-
Rajhara, so it will not cause pollution
• Pollution will not be built. By cleaning the indoor streets from time to time
• Camp and other facilities would be provided in terms of health.
• According to the plan 20 children of rural areas will be provided with Living,
dining as well as education in Bhilai by BSP.
• More capacity stoves will be made available to villagers to reduce fuel
consumption according to CSR
• There will not be any displacement of habitation and no revenue land will be
acquired
• It is mentioned that the pollution due to Hitkasa dam in relation to water
pollution is to be prevented by making check dam to prevent red water
entering to farms.
• The affected have been given compensation of Rs. 2.5 crore so far.
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-53
• Village street light burning is to be done through the solar energy system
• The development of community is taken care by the industry with CSR
activities.
• To prevent the air and water pollution impacts due to the proposed mines will
be prevented / controlled by strictly following the EMP and the conditions of
Consent from State Pollution Control Board / EC conditions by MoEF,
New Delhi.
Durg district
• Industrialization is essential for the development of the country.
• The village infrastructure is also important to the BSP government. BSP will
work with the local administration to provide infrastructure facilities as per the
CSR activities of SAIL
• The convenience of local residents expected to increase employment after
opening of Dulki mines
• mechanization is required to run Mines as far as possible we will do the work
manually
• SAIL – BSP have its own R&R policy and it is not possible that BSP
management has not given compensation after acquiring the land of a poor
people. However any complaints received will be re-examined by the
management.
• The employment will be given to the local residents as per qualifications and
skills as per government rules as BSP is a Public Sector Undertaking. It is not
possible to give full employment but BSP management will try to reduce the
unemployment
• BSP management will try to do work manually
• Education will be adequate. Special attention will be given in collaboration
with State and Central Government
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-54
• Two percent of mines gain will be spent in rural areas which will facilitate
them is decided by BSP management
• Iron ore fines went to many villages which destroyed the fields. The fields
have been reclaimed by giving 1.72 crs. And the villagers are happy and the
remaining land will be rectified after getting the written complaints
• After opening of mines the land which will be affected, will be given
compensation till now 2.5 crore has been given
• About 10 lakhs plantation has been done.10 times plantation will be done by
management
• BSP make their own road as well as roads are made for convenience for
other people as per the CSR Initiatives
• The maintenance for jharan temple road is under discussion, in few days the
work will be completed.
• Water is sprinkled on the road for dust and which will be done regularly
• There will be facility for hand pump
• For better education the schools are handed to BSP in contract basis
• There is a need for ITI in Mahamaya which will be established soon after
discussion with the Management and local administration
• The area of health center in hospital will be increased. The treatment which is
not possible here will be taken to Rajhara or else to BSP, Bhilai
• Culverts, community buildings, etc. will be made in the nearby villages as per
the CSR activities
• To prevent the air and water pollution impacts due to the proposed mines will
be prevented / controlled by strictly following the EMP and the conditions of
Consent from State Pollution Control Board / EC conditions by MoEF, New
Delhi
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-55
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-56
6.13 Action plan to address the issue rose during public hearing with time frame and financial allocation
The main issues in the Public Hearing were identified as education, health, road,
employment, infrastructure, development and environment have been discussed and
the response/clarification is given below:
Sr. No.
Component Issues of Public Hearing Response by BSP
1. Education - Enhance education facilities
- Open more school,
- Budget of Rs. 25/- lakhs provided for EMP.
- BSP provides financial aid to DAV public school which allows admission of children of local people.
- Special quota for children of local people is provided in all BSP managed school.
- Every year 20 children from local community selected by BSP for educational facilities. Some of them are now players of national levels.
2. Health - Improvement of health and medical facilities
- Improve drinking water facilities
- Primary health centers and hospitals has to be started
- For health and family welfare scheme Rs. 25/- lakhs is allotted for EMP.
- BSP owned hospital provide good and subsidised medical facility for local community.
- Till date 52 medical camps have been organized in the study area.
3. Road /Rail - Proper road management of PWD road
- Lack of pucca road - The road from Mahamaya
to Nalaksha should be developed
- Rs. 170/- Lakhs allocated for improvement of the village road.
- Under CSR scheme, BSP allocated Rs. 430/-Lakhs for road construction Amount submitted to Government of Chhattisgarh
- The budget allocation for the project for infrastructure development is 100 Lakhs
4. Employment - Provide employment to the youth
- Provide regular employment instead of contract jobs
- A budget of Rs. 80/- Lakhs has been allocated for improvement of the economic up-liftment activities such as dairy development, poultry farming and improvement of agricultural practices in the region.
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-57
Sr. No.
Component Issues of Public Hearing Response by BSP
- Proposed project improve the job opportunity in the area.
5. Infrastructure - Lack of infrastructure and its development
- Improve basic amenities
- New bridges across the water bodies
- Provide hand pumps to local people
- Under CSR scheme Rs. 8/- Crores has been spent for construction of bore well, road culvert, murum road and Chiklakasa high school.
- In addition to that Rs.100/- lakhs of budgetary provision has been made for improvement of infrastructure facilities.
- Till date 50 Nos. of water bore wells have been drilled in the study area.
6. Environment - Affect the flora and fauna
- Dust emission from mine road
- Plantation around the plant
- Occasionally discharge of red water
- Air pollution due to transportation and blasting
- Red water does not get mixed in natural source. 10 check dams have been provided for this purpose.
- Pollution control activities such as air pollution, water pollution, tailing pond facilities, occupational health, biological environment, greenbelt development, socioeconomic development, rainwater harvesting and other cost of environmental control and monitoring measures is envisaged with an amount of Rs. 678.00 Llakhs.
Oppose - Oppose for mechanical processing facilities as it will reduce job opportunity.
- Oppose to engage external contractor
- Harassment by contractors to common people.
- Suitable measures shall be taken so the local people can not be harassed by contractors.
Support - Mining work should continue
- No shortage of iron ore - BSP- glory of India - Benefit to local people
by new plant due to employment
- Development due to BSP plant
- Thanks for the valuable support from the local people during the public hearing
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-58
Financial Allocations
Sr. No. Activities Amount Allocated (Rs. in Lakhs)
1. Infrastructure 100.00
2. Economic upliftment 80.00
3. Environmental Control & Monitoring 20.0
4. Pollution control 678
9. Rainwater harvesting 50.00
Total Rs. 928.0
6.2 Risk Assessment and Disaster Management Plan
It is presumed that the proposed mining would be designed and engineered with
all possible safety measures and standard code of practices. In spite of this,
there may be some design deficiency or due to operation and maintenance faults
which may lead to accidental events causing damage to life and property. This
chapter presents an over view of environmental risk associated with various
mining operations, suggested remedial measures and outlines of the emergency
preparedness plan.
6.2.1 Risk assessment
The objectives of environmental risk assessment are governed by the following,
which excludes natural calamites.
a. To identify the potential hazardous areas so that necessary design safety
measures can be adopted to minimize the probability of accidental events.
b. To identify the potential areas of environmental disaster this can be
prevented by proper design of the installations and its control operation.
c. To manage emergency situation or a disastrous event, if any from the mining
operation.
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-59
6.2.2 Identification of hazards
During the operation of the proposed open-cast mechanized mine, the following
risks have been identified.
1. Filling up the mine pit due to excessive rains.
2. Failure of slope in the pit.
3. Failure of slope of external dump.
4. Fly Rock Fragment from Blasting Operations.
5. Accidents of heavy machinery.
6. Surface fire (Electrical and Oil).
7. Possible Danger due to Storage of Explosives.
The hazard potential and consequences of hazards are presented in Table 6.1
Table 6.1: Hazard potential of various mining operations
Sl. No.
Item Hazard Potential
Remarks
1. Failure of slopes in mine-pit Moderate Land Slides
2. Failure of slopes of external waste dumps
Moderate Erosion of solids during precipitation surface water pollution
3. Accidents due to blasting operations Major Flying of rock
fragments, injury damage to property
4. Accidents due to mining machinery Major Permanent disability/death
5. Surface fire Major Fire and injuries
6. Sabotage of explosive magazine Major Explosion/ Property damage injuries/death
7. Filling-up of the mine pit due to excess rains
Major Inundation/stagnation of mining work
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-60
6.2.3 Risk Management
Filling up the mine pit due to excessive rains
Filling up the mine pit due to excessive rains in the worked out area is a remote
possibility. Normally there will be sufficient warning time before such as incident
takes place harming equipment and human life. However, as a precautionary
measure, interceptor ditches along the outer boundary of the pit area
constructed to control inflow of runoff into the mine pits. Water that collects in the
mine pit from rainfall will be pumped out from the pits, using submergible pumps,
if required.
Failure of slope in the pit
In order to allay dangers due to open cast slope failure, slope stability
estimations have been made after determining various physical parameters of
the ground mass like uni-axial compressive strength, tri-axial compressive
strength, cohesion, angle of friction, specific gravity of the rock, water pressure
etc. Besides, all the discontinuities have been plotted in stereo plots, which
indicate that there is no chance of any planer failure or wedge failure. Even then,
factor of safety has been determined against overall slope failure as well as
against individual bench slope by circular failure, planer failure, wedge failure.
Besides determining factor of safety the slopes are monitored at regular intervals
to check for any possible failure. The well-developed drainage system over the
lease area ensures that storm water does not accumulate in the lease area and
therefore hydrostatic pressure remains at a low level.
Thus all types of measurements and inspections will be carried out. The mine
has been designed based on the above considerations with sufficient safety
margins to eliminate any chances of slope failure in the pit.
Fly rock fragments and vibrations due to blasting
Trial blasting results from nearby mines have been used to arrive at the field
empirical equations based on which the charge per delay has been regulated to
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-61
protect the nearby structures. All precautions related to control of fly rock will be
taken during the blasting operations. Safety zones of 500 m as per statute are
being maintained. The nearest habitation is too far to be affected by fly rock.
Accidents of heavy machinery
Most of the accidents during transfer of dumpers, trucks and other vehicles are
often attributed to mechanical failures, in which the factor of human errors can
not be ruled out. Regular maintenance and testing of all mine equipment as per
manufacturers guide lines can largely eliminate accidents of heavy machinery.
Surface fire
Spillage of HSD and resultant fire constitutes a potential risk. The quantity of the
maximum oil, which can spill, is not much and can be easily controlled. Sufficient
numbers of portable fire extinguishers have been provided at strategic locations
to take care of any eventuality.
Danger due to storage of explosives
Adequate safety zone has been provided as per statutory requirements while
locating the magazine. The magazine has been constructed as per plan
approved by Department of Explosives. The following have been considered in
the design of the magazine.
Ø All dry vegetation within a 15 m radius cleared.
Ø Lighting arrestor installed on the magazine roof.
Ø A safety zone around the magazine created.
Ø In summer, the temperature inside the magazine is monitored to guard
against spontaneous fire.
Ø The manufacturing dates of all explosives stored in the magazine are
carefully recorded so that no explosive whose shelf life has expired is kept
in stock.
In case of any fire, whosoever notices the fire will sound the alarm and inform
the shift-in-charge. The shift-in-charge will inform security personnel and arrange
to evacuate all personnel, except those who are required for fire fighting, from
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-62
the area. The fire brigade shall be summoned to deal with the emergency.
Concerned district officials will be informed. Nearby hospitals will be informed to
standby to handle casualties.
6.2.4 Preparedness Plan
A major emergency is one, which has the potential to cause serious injury or loss
of life. It may cause extensive damage to property and serious disruption both
inside and outside the work zone area. Sometimes, it would require the
assistance of outside agencies. The aim of disaster Management is concerned
with preventing accidents through good design, operation, maintenance and
inspection, by which it is possible to reduce the risk of an accident. An important
element of mitigation is emergency planning, i.e recognizing accidents that are
possible, assessing the consequences of such accidents and deciding on the
emergency procedures, both onsite and offsite, that would need to be
implemented in the event of an emergency. Emergency planning is a critical
aspect of safety and cannot be considered in isolation.
The on-site plan is called Disaster Management Plan (DMP) and the off-site plan
is called Emergency preparedness Plan (EPP). Both the elements recognize
clearly the responsibility of line and staff to necessitate immediate action when
need arises.
Onsite Emergency
Types of emergency in respect of Donimalai Iron ore mine are classified into the
following three categories.
1. Fire
2. Explosion
The following are the measures proposed to be undertaken in respect of onside
emergency management plan i.e., Disaster Management.
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-63
Fire and Explosion
1. The quantity of explosives will not be stored in excess of the licensed
capacity of each magazine at any time.
2. Opening, weighing and packing of explosives will not be carried out in the
magazine house.
3. First in - First out method of usage of explosive is envisaged. Further, the
un-used explosives returned back from the mine site to the magazine
house will be re-used immediately during the next available opportunity.
4. The interiors of the magazine houses will be constructed in such a way
that all the fittings including that of doors, ventilators, shelves, benches,
etc., shall be as per requirement of Explosives Act, 1884 and Rules
thereof. They shall not possess any exposure of iron or steel, grit or any
such material making a possible spark with the explosives. Brass hinges
will be used for doors.
5. Lighting conductor as recommended by the Controller of Explosives
would be installed at rooftop of each magazine house to prevent any
incidence of natural electric discharge on to the magazine house. In no
case, the resistance would be more than 10 ohms. This resistance will be
measured monthly once by competent electrician appointed for the
purpose and suitable records be maintained.
6. All materials capable of producing fire viz., cotton, match boxes, polyester
or similar clothes, etc. will not be allowed into the magazine houses.
Further, smoking will be banned in the premises of the magazine and
blasting sites.
7. The magazines will be well maintained and "Z" ventilation with mesh wires
will be done as to ventilate the area only to the desired level and avoid
excess oxygenation inside the houses.
8. Adequate security of armed personnel from Central Industrial Security
Force has been provided for the magazines.
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-64
9. The explosive packages will be stacked to maximum height of 3m with a
free board of at least 1m to the roof in such a way so as to allow the
movement of at least one person to check the condition of all packages
stored and to read the manufacturing particulars of each package.
10. A distance of 15m surrounding each magazine house will be kept clear of
grass or brush or flammable materials within the fenced areas.
11. Every packet of explosive at the time of bringing inside the magazine will
be examined for its sound condition.
12. Not more than 4 persons will be allowed inside any magazine house at
any given time.
13. Only authorized persons nominated by the Mines Manager will be allowed
to enter the premises.
14. For charging and stemming a shot hole, only wooden tamping kits will be
adopted.
15. No re-boring or tampering of a charged hole will be done either before
firing or after mis-fire.
16. Before commencing the shot firing, sufficient warning to the public by an
efficient system of signals, sirens and by putting up red flags in the danger
zone will be given so as to restrain men entering into the active area.
17. The work personnel will be allowed to enter the danger zone area only
after the "all-clear signal" is given.
18. In the event of mis-fire, all provisions as per regulation no.167 of
Metalliferrous Mines Regulations (MMR) 1961, framed under mines
act,1952 will be followed. The holes will be fired by duly qualified
personnel only taking all standard precautions.
19. Regulation No.162 of MMR 1961 dealing with the procedure for drilling,
charging, stemming and firing of shot holes will be strictly compiled with.
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-65
20. The transport of explosives to and from the magazines will be arranged
utilizing an approved explosive van.
21. No person will be allowed to take any naked light other than an enclosed
light or electric torch into any of the explosive magazine houses.
22. Arrangements will be made for using the explosives at the first available
opportunity or for return the same to the magazine, if any, found at the
mine face due to mis-fire during mineral excavation operations utilizing
the services of properly qualified blasting personnel.
23. Water in a small sump will be provided at the entrance of each magazine
house for cleaning the feet of persons entering into it, to avoid any chance
of entry of grit particles.
For the above listed emergencies, a systematic response plan is worked out.
The salient feature of the response plan is given below.
The following control and co-ordination locations are identified to provide contact
points for the various services involved.
1. Initial emergency action calling fire tender, medical assistance and
security.
2. The shift incharge to coordinate the emergency initially.
3. Sounding of alarm, sirens etc.
Duties and Responsibilities
The prime and foremost responsibility of the management in the event of
occurrence of any major accident is to avoid creating panic in the work force and
neighborhood.
The emergency organization is prepared so that responding persons are clear
about various actions required to be taken by them. It is proposed to give wide
publicity about this plan to the employees through the safety and training
department along with learning programmes. The emergency situation will be
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-66
initially managed by shift personnel and when the Mines Manager / Addl.
General Manager (production) arrives at the site, the emergency organization
will be taken over by him. The responsibilities of the emergency officers are
listed below:
Shift In charge
v To Inform mines manager about the emergency and site of accident
v To inform time office for ambulance
v To inform security officer for Siren/Fire brigade
v To inform project hospital to alert doctor/Medical Administrator
v To arrange water tanker, transport vehicles etc.
v To rush to the site for evacuation and relief works
Mines Manager
v To inform General Manager / E.D. / Agent
v To rush to site to oversee relief works
v To inform DGMS, Controller of explosives
v to inform State Environment Control Board authorities
v To inform Civil / Electrical departments to maintain Fire Water Supply and
Power supply
v Key personnel representative to handle Emergency Plan are:
Shift Personnel
v Shift Incharge in the mine
v The time office personnel on duty
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-67
v Shift Maintenance Engineer
v Telephone exchange incharge
v Medical Officer or Nurse on duty
v CISF Security Officer on duty
Senior Officers
v General Manager / Executive Director
v Mines Manager / Additional General Manager (Production)
v Manager, Fire and Safety at Training Institute
v Personnel Manager for Administration and Security
v Medical Officer / Medical Administrator
Disaster Information Flow
In case any disaster due to fire or explosion, minimum information shall reach
the control points. Every person who comes to know about disaster first informs
the emergency officer (Shift in charge) and the time office/security; office
concerned. The channels for passing the above information are made available
as follows:
Flow of disaster information is shown in Plate VI.1.
Emergency Response Plan
The nominated emergency officer, once gets the information shall take charge of
the situation and arrange for the rescue and other facilities like Ambulance, Fire
Tender and he will also inform Mines Manager, Electrical and Water Supply
sources, Hospitals etc. for the rescue work.
On-site Emergency plan initially to be dealt by shift in charge and then by Mines
Manager. The on-site emergency plan showing the response mechanism is
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-68
depicted in the flow chair (Plate VI.2). The following services shall also be
arranged for taking up the emergency work.
A. Fire Services
Call for the fire fighting tender by special siren, mobilization for firewater from
storage, etc. Request for outside Fire Brigade from Dalli – Rajhara if needed.
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-69
Plate VI.1 - Disaster Information flow, DIOM
Channels § Telephone § Wireless § Messenger
Plate IV.2 - Response Mechanism-Onsite Emergency Plan Preparation
Magazine /
Emergency Officer
(Shift In-charge)
Time Office / Security Office
Security Office / Fire Brigade District Authority
/ Police
Project Taluk & District Hospitals
Emergency Officer
(Shift In-charge / Mines Manager)
ED / GM / Agent Electricity &
Water
Transport Administration
Dept. Pit Safety Committee
Time Office / Ambulance
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-70
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-71
Organization for meeting emergency
Key Person Organization position
Telephone No.
Office Residence
Chief Controller Agent & MM 07748 – 259340 07748 – 285069
Site Controller Sectional Head 07748 – 259186 07748 – 285190
Liaison Officer Personal Officer 07748 – 259186 07748 – 283092
Communication Officer
Production Control
07748 – 259186
Security Officer I/C CISF, IOC 4229 3496
Asst. Security Officer I/C CISF, Mine Gate
4121
Fire Officer Fire Officer 3000 3000
Medical Officer Medical Officer Rajhar Male Hospital,
3020,
07748 – 283717
3041
Elect. Supervisor Elect. I/C. 07748 – 259186 07748 – 259186
Safety Officer Mine Foreman (Safety)
07748 – 259186 07748 – 259186
Transport Officer Garage I/C 07748 – 259186 7748 – 259186
B. Medical Services
Arrange for Ambulance van to the site, call for the medical and para-medical
staff to attend emergency at hospital and site. Arrange for casualty transport to
the Hospital, alternate medical facility outside if needed.
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-72
C. Security
Mobilization of manpower for rescue work, traffic control, blow special siren for
calling Fire Brigade, evacuation, security of the area and liaison with police,
mode control.
D. Transport
Transport in charge to arrange transport vehicles like Bus, Car, Van etc.
Maintenance and upkeep of Ambulance and Fire Tender of all types render
assistance to Site in charge and Personnel officer for transporting the
causalities.
8.6 Offsite Emergency Plan
The off-site emergency plan deals with those incidents, which might have the
potential to harm the persons or affecting the surrounding community outside the
boundary. The off-site emergency plan provides guidelines for the individual role
and/or collective role during an emergency under overall directions of the
Executive Director / General Manager of the Project; it also serves as a ready
reference to all the agencies like fire fighting, medical services, civil defense,
district administration etc. for taking immediate actions.
The key feature of a good off-site plan is its flexibility in its application to various
emergencies. The responsibility for the off-site plan will be likely to rest either
with the mine management or with the local authority.
Some of the aspects to be included in off-site management plan are as follows:
Organization
Names and designation of incident controller, site main controller, their duties
and other key personnel are identified for immediate action in the matter.
Further, details of the command structure, warning systems, implementation
procedures, emergency control centers are as follows:
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-73
Communication
Identification of personnel involved, communication center, call signs, network,
list of telephone numbers.
Special emergency equipment
Details of availability and location of heavy lifting gear, bulldozers, specified fire-
fighting equipment, fireboats.
Voluntary Organization
Details of organizers, telephone numbers, resources etc.
Information on Hazardous material storage etc.
Details of the hazardous substances stored or processed on each site and a
summary report of the risks associated with them.
Meteorological Information
Arrangements for obtaining details of weather conditions prevailing at the time
and weather forecasts.
Humanitarian arrangements
Transport, evacuation centers, emergency feedings, treatment of injured, first
aid, ambulances, temporary mortuaries.
Public Information
Arrangements for (a) dealing with the media-press officers, (b) informing
relatives etc.
Assessment
(a) Collecting information on the causes of the emergency, (b) reviewing the
efficiency and effectiveness of all aspects of the emergency plan.
Role of the Emergency Co-ordination Officer
The various emergency services will be coordinated by an emergency
coordinating officer (ECO), who will be designated by the district collector. The
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-74
ECO will liaise closely with the site main controller. Again depending on local
arrangements, for every severe incident with major or prolonged off-site
consequences, the external control will be passed to a senior local authority
administrator or even an administrator appointed by the central or state
government.
Role of the Local Authority
The duty to prepare the off-site plan lies with the local authorities. The
emergency planning officer (EPO) appointed will carry out his duty in preparing
for a whole range of different emergencies within the local authority areas. The
EPO will liaise with the Works, to obtain the information to provide the basis for
the plan. This liaison will ensure that the plan is continually kept upto date.
It will be the responsibility of the EPO to ensure that all those organizations,
which will be involved in handling the off-site emergency, know their role and are
able to accept it by having for example, sufficient staff and appropriate
equipment to cover their particular responsibilities. Rehearsals for off-site plans
will be organized by the EPO.
Role of Police
Formal duties of the police during an emergency include protecting life and
property and controlling traffic movements. Their functions will include controlling
by-standers, evacuating the public, identifying the dead and dealing with
casualties and informing relatives of death or injury.
Role of Fire Authorities
The control of a fire will be normally the responsibility of the senior fire brigade
officer who would take over the handling of the fire from the site incident
controller on arrival at the site. The senior fire brigade officer will also have a
similar responsibility of other events, such as explosions and toxic materials
release. Fire authorities in the region will be appraised about the location of all
sorts of flammable materials, water and foam supply points, and fire fighting
equipment. They will be involved in on-site emergency rehearsals both as
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-75
participants and, on occasion, as observers of exercises involving only site
personnel.
Role of Health Authorities
Health authorities, including doctors, surgeons, para-medical staff, mobile
hospitals, ambulances etc. will have a vital part to play following a major
accident, and they will form an integral part of the emergency plan.
For major fires, injuries will be the result of the effects of thermal radiation to a
varying degree, and the knowledge and experience to handle this in all but
extreme cases may be generally available in most hospitals.
Major off-site incidents are likely to require medical equipment and facilities
additional to those available locally, and a medical “mutual aid” scheme should
exist to enable the assistance of neighboring authorities to be obtained in the
event of an emergency.
Training
The training of mine personnel is conducted regularly with respect to environmental
protection. Training facilities are also extended to equipment maintenance and
operation also to the operators. Training will cover the following fields.
v Awareness regarding pollution control and environmental protection.
v Operation and maintenance of pollution control equipment.
v Afforestation / plantation and post care of plants.
v Field monitoring, maintenance and calibration of pollution monitoring
instruments.
v Chemical analysis of various environmental parameters at laboratory.
v Repair of pollution monitoring instruments.
v Knowledge of norms, regulations and procedures.
v Occupational health and safety.
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-76
v Risk assessment and disaster management plan.
CHAPTER VII
PROJECT BENEFITS
7.1 Preamble
In view of more industrialization, the demand of iron ore has increased
substantially in the recent past. In accordance with Mission and Objectives of
M/s. Steel Authority of India Limited and National Steel Policy, SAIL proposes to
enhance its production capacity of Mahamaya mines from 0.96 MTPA to 1.46
million Tone per annum. Steel Authority of India Limited (SAIL) is the leading
steel-making company in India. It is a fully integrated iron and steel maker,
producing both basic and special steels for domestic construction, engineering,
power, railway, automotive and defense industries and for sale in export
markets. The company is ranked amongst the top ten public sector companies in
India in terms of turnover, SAIL manufactures and sells a broad range of steel
products, including hot and cold rolled sheets and coils, galvanized sheets,
electrical sheets, structural’s, railway products, plates, bars and rods, stainless
steel and other alloy steels. SAIL produces iron and steel at five integrated
plants and three special steel plants, located principally in the eastern and
central regions of India and situated close to domestic sources of raw materials,
including the Company's iron ore, limestone and dolomite mines. The company
has the distinction of being India’s second largest producer of iron ore and of
having the country’s second largest mines network. This gives SAIL a
competitive edge in terms of captive availability of iron ore, limestone, and
dolomite which are inputs for steel making.
Bhilai Steel Plant (BSP) is India's sole producer of rails and heavy steel plates
and major producer of structural has won Prime Minister's Trophy for best
Integrated Steel Plant in the country for Nine – times. The plant is the sole
supplier of the country's longest rail tracks of 260 metres. BSP has an annual
production capacity of 3.153 MT of saleable steel, the plant also specializes in
other products such as wire rods and merchant products. BSP is accredited with
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-77
ISO 9001:2000 Quality Management System and IS0:14001 has been awarded
for Environment Management System in the Plant, Township and Dalli Mines. It
is the only steel plant to get certification in all these areas. The Plant is
accredited with SA: 8000 certification for social accountability and the OHSAS-
18001 certification for Occupational health and safety. These internationally
recognized certifications add value to Bhilai's products and helps create a place
among the best organisations in the steel industry. Among the long list of
national awards it has won, Bhilai has bagged the CII-ITC Sustainability award
for three consecutive years.
7.2 Following aspects of State Industrial & Mining Policy favours the establishment of the proposed project
• Government accords highest priority to the objectives of dispersal of
industrial investments in various backward regions / districts of the State so
that the fruits of economic development and employment opportunities are
shared by all segments of society and in all parts of the state in as equitable
manner as possible.
• To focus on strengthening of the manufacturing industry in the state and to
increase its percentage share in the GSDP from the present average of
16.70% to over 20% by the end of the policy period.
• Special incentives for entrepreneurs setting up units in backward areas.
Additional incentives for units promoted by entrepreneurs from the category
of SC/ST, Minority, Women, Physically challenged & Ex-servicemen.
• To maximize value addition to the mineral extracted, the state is encouraging
maximum investments in down stream industries.
• Priority will be given to the entrepreneurs who propose establishment of
industries for value addition with in the vicinity of the mineral bearing areas.
• To promote indigenous utilization of Iron Ore fines and Beneficiation of low
grade ore.
7.3 Employment and income effects
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-78
Employment and income generation are the most important aspects that need
detailed investigation in case of any project. The present project has some
positive employment and income effect. A sizable number of local persons are
likely to be involved in different activities. For execution of the project, a large
number of people will be required directly and indirectly. This will create a huge
employment and income effect on the socio-economy of the study area. So far
indirect employment is concerned, the effect is very strong and widespread. The
project is expected to generate indirect employment and income which is 4-5
times higher than the direct employment.
The project will generate revenues to the State and Central governments. Some
of the potential economic benefits likely to be accrued from the project are as
follows:
• Earnings by the Govt. by way of taxes levies and duties like ED, IT, VAT,
TDS etc
• Business opportunities for the local entrepreneurs to set up small and
medium scale industries
• Business opportunities for the local entrepreneurs serving as service
providers, suppliers, contractors
• Investment opportunity for local infrastructure development
Thus, the proposed project will facilitate in catalyzing the development of
infrastructure, health care, upliftment of civic amenities, education for economic
upliftment of the locals and improvement in their living standards.
7.4 Improvement in the Physical Infrastructure
Road
Improvement and extension of the existing network is, essential to develop remote
areas, better connection between the economic centers of state, and also cross-
border transport and for personal mobility of the masses.
Rail Network
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-79
Railways provided an important mode of transportation in the public sector
spreading over the entire country. It contributes to the country’s economic
development by catering to the needs of large-scale movement of freight as well
as passenger traffic and is a major source of promoting integration among the
masses. Railway provides transport facility to people and handles freight above
600 million tons annually. The Indian railway is intended to modernize the vast
railway network, keeping both the economic and social dimensions in mind.
7.5 Other Tangible Benefits
The other tangible benefits will be in the form of township hospital and schooling
facilities which will also help local population to enjoy the fruit of better facilities in
nearby. BSP also will undertake various community welfare measures for up-
liftment of plant surrounding villages. These measures include:
• Encouraging female education
• Encouraging entrepreneurship among locals Vocational training
• Upgrading one/ two primary school buildings and play grounds.
• Adoption of few villages for infrastructure development (Sanitation, water
supply, education, primary health)
• Construction of bus shelters.
• Health camps and eye camps.
• Improvement of road network in the nearby villages
• Traffic islands, wherever required in Bellary / project surroundings. CHAPTER VIII ENVIRONMENTAL IMPACT STATEMENT
After collection of base line data, subsequent identification, prediction and
evaluation of impacts, EIS has been delineated for five basic environmental
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-80
components that are likely to be affected or benefited due to the proposed
project and its allied activities. For proper assessment of environmental changes
in the coming years, impacts predicted due to proposed project are presented for
each environmental parameter in Table 8.1.
EIS has been furnished for the following;
I. Air Environment
II. Water Environment
III. Noise Environment
IV. Land and Biological Environment
V. Socio Economic Environment
TABLE 8.1 COMPARATIVE CHART OF VARIOUS IMPACTS
Component Impact Due to Plant
I. Air Environment
1. Air Quality Impact scenario of air component due to the
proposed project is insignificant.
2. Meteorology The meteorological data collected confirmed that
the climatic status of the study area is consistent
with regional meteorology. The project activity
that is coming up has very negligible influence on
the meteorology of the region. As such, the same
pattern may continue.
II. Water Environment
3. Water There is no perennial water stream within or
outside the mine lease area and hence there is no
impact on surface water quality. The potential
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-81
impact of mining would have negligible impact on
the ground water, as the site and its adjoining
areas are, located at an elevated topography
coupled with mine run-off management planning
and regional geology. The likely chances of the
contaminants reaching the groundwater are very
rare. In general, no significant on ground water
quality in the study area.
4. Water Supply The impact on the water resources in and around
the mine is significant. Water conservation
practices, especially storage of Rainwater in mine
pits would likely fulfill the water requirements to
the project.
III. Noise Environment
5. Noise There may be slight increase in noise levels due to
the proposed project such as Dumper, Blasting,
vehicular movement etc,. Proper Noise
attenuation such as enclosures, green belt
development will minimize the noise impact to
the surrounding environment.
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-82
IV. Land and Biological Environment
6. Flora and Fauna Greenbelt has a positive impact on flora.
7. Land use No adverse impacts are anticipated on land use of
buffer zone due to the proposed mining
operations, as all the mining activities will be
confined to core zone only, except mine site.
8. Landscape Rich plantation improve the visual effect.
9. Livestock Positive impact due to demand for milk, eggs and
meat.
10. Solid waste The OB generated will be disposed off in ear
marked dumpsite.
V. Socio Economic Environment
11. Educational Facilities No significant impact is anticipated immediately.
12. Medical The proponent will provide medical facilities in
the study area
13. Occupational Facilities Some of the employees will find direct
employment and many others indirect
employment.
14. Transportation Slight impact due to increase in vehicular traffic.
15. Economic aspects Local economy may improve through employment
and rise in commercial activity.
CHAPTER – IX
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-83
ENVIRONMENTAL MANAGEMENT PLAN
9.1 General
This chapter discusses the environmental management plan (EMP) to minimize
the identified adverse impacts of the proposed 1.46MT enhanced capacity of
Mahamaya Iron ore mine. This section discusses the management plan for
mitigation/abatement of adverse environmental impacts and enhancement of
beneficial impacts due to mining. The EMP has been designed within the
framework of various Indian legislative and regulatory requirements on
environmental and socio-economic aspects. The implementation and monitoring
of pollution control measures and for overall environmental management,
environmental cell at the area and corporate level will take all necessary care.
It will look after the following aspects of environmental management.
• Generation of environmental data bank.
• Evolving micro environmental management plan for the project in
collaboration with other agencies and consultants.
• Monitoring project implementation along with environmental control
measures.
• Co-ordinate with other project activities to ensure timely implementation
of the project.
• Co-ordination with Ministry of Environment & Forests, Central / State
Pollution Control Board for prevention and control of water and air
pollution.
This organization will be responsible for:
• Implementation of environmental control and protection measures and
• Monitoring of the implementation system.
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-84
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-85
9.2 Objectives of EMP
The objectives of the proposed EMP are aimed for meeting five basic
requirements, namely,
i) To integrate comprehensive monitoring and control of impacts.
ii) To comply with the environment protection regulations.
iii) To ensure that adverse environmental impacts on the baseline are
minimized,
and
iv) To plan for ecologically sustainable development (ESD) within the frame
work of existing legislation and environmental management policies.
9.3 Applicable regulations
Following regulations on environment protection have been considered in
formulating this EMP:
• Section 21 of the Air (prevention and Control of Pollution) Act, 1981
• Section 25 and 26 of the Water (Prevention and Control of Pollution) Act,
1974
• The Manufacture, Storage and Import of Hazardous Chemicals Rules, 1989
• The Hazardous Wastes Management Handling Rules and Transboundary
Management Rule 2000
• The Noise Pollution (Regulations and Control) Rules, 2000
• The Environment (protection) Rules, 1986.
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-86
9.4 Implementation Organization
The responsible for implementing management plan would rest with the project
officer of the project, who would be properly assisted by team of qualified and
trained personnel. The existing environmental lab at Dalli - Rajhara will carry
out the task and responsibility connected therewith.
• Pollution Control Measures
• Plantation / Greenbelt Development
9.5 Environment Management Plan
9.5.1 Ambient Air quality Management
Mitigative measures suggested for air pollution controls are based on the
baseline ambient air quality of the area. From the point of view of maintenance
of an acceptable ambient air quality in the region, it is desirable that air quality
is monitored on a regular basis to check compliance of standards as prescribed
by CPCB. In case of non-compliance, appropriate mitigative measures need to be
checked. The proposed mining operations and related activities are expected to
add to the levels of air borne particulate mainly during daytime. The addition of
gaseous pollutants due to the proposed mining activities is expected to be
relatively low.
Controlling dust level
Dust would be generated during blasting, mining, crushing operations, and also
during handling and transportation of the material. An amount of Rs.50 Lakh is
allotted for capital investment and Rs.15 Lakhs is allotted for recurring cost.
The suggested control measures are:
Mines
Dust suppression systems (water spraying) shall be adopted at:
• faces/sites before and after blasting, • faces/sites while loading; and • use of sharp teeth for shovels. • Dust extraction systems to be used in drill machines; and
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-87
• use of sharp drill bits for drilling holes and drills with water flushing systems (wet drilling) to reduce dust generation.
Stock-piles
• Mist sprays to be provided at appropriate places for preventing dust
pollution during handling
• OB waste dumps shall be sprayed with water, as they are the major
source of air borne particulate matter/dust.
Haulage
• regular water spraying on haulage roads during transportation of ore and
waste by water sprinklers;
• transfer points to be provided with appropriate hoods/chutes to prevent
dust emissions; and
• Overloading of trucks is strictly prohibited
Controlling of CO level
Expected increase in the CO concentration is very low as CO emissions from the
proposed mining operations are less as compared to other pollutants. Heavy and
light vehicles are the major sources of CO in the mine. All vehicles and their
exhausts would be well maintained and regularly tested for pollutants
concentration.
Controlling of NOx level
NOx emissions in the mine mainly occur during blasting operations. The main
reasons for NOx emissions are:
• poor quality of explosives having large oxygen imbalance. This may be
due to manufacturing defect; and · use of expired explosives in which
ingredients have disintegrated.
• Incomplete detonation, which may be due to low Primer to Column ratio.
• To ensure low NOx levels following control measures would be adopted:
• use of good quality explosives having proper oxygen balance with regular
monitoring;
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-88
• regular updating of the date of manufacture/expiry to avoid confusions. A
normal procedure should be formulated to check/visually inspect all
explosives, and if disintegrated ingredients are spotted, the explosives
won't be used, even if the date has not expired.
9.5.2 Control measures for Noise
The present noise levels are below the prescribed limits. If the impulsive noise
levels increase due to mining operation, suitable measures will be adopted to
maintain the noise level within permissible limits at working zone. Mine workers
are generally exposed to a higher risk of hearing impairment than most other
industrial workers.
The circular of Directorate General of Mines Safety (DGMS) prescribes a
permissible level of 90 dB(A) for exposure without any protection for a maximum
duration of 8 hours: DGMS has recommended 115 dB(A) as the noise level at
and above which appropriate ear protection device should be used and 140
dB(A) as the level where no worker should be allowed to enter even with ear
protection device. An amount of Rs.20 Lakh is allotted for capital investment
and Rs.5 Lakhs is allotted for recurring cost towards Noise control measures.
Noise control measures at the mine can be broadly classified into three types,
namely (i) administrative control, (ii) engineering control and (iii) personal
hearing protection (Ref.Prof.B.B.Dhar,Environmental Management of Mining Operation, Ashis Publishing House, 1990). A brief outline of each of the
control measures is outlined below:
Administrative control:
The staff roster should be so planned that none of the workers working in noisy
environment gets over-exposed to noise beyond the permissible duration. Other
administrative control techniques include providing proper noise· proof enclosure
for the workers separated from the noise source and noise prone equipment.
Engineering control:
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-89
The effective attenuation of noise can be achieved by source control measures
such as:
Ø Selection of quieter mining equipment and machineries
Ø Retrofitting additional noise control device as required
Ø Installation of anti-vibration devices in crushing and screening
equipment
Ø Housing of the crusher separately to contain noise
Ø Covering by casing of the crusher internal elements to reduce
transmission of impact noise.
Ø Carrying of blasting during day time. Blasting shall not be carried
out in stormy and rainy weather and during lighting.
Ø Provision of noise proof cabin for operators and exhaust silencers
for all mine transport equipment.
Personal hearing protection: Personal hearing protection can be considered
as an accepted method of minimizing the impacts in a noisy environment.
Personal hearing protection devices include earplugs with glycerine soaked
cotton and earmuffs.
Blasting Vibration Control Plan
The following factors will be given special attention to minimize effects of
blasting:
• Charge per delay
• Charge per round
• Over charging will be avoided
• Distance from the structures (Scaled distance)
• Type of initiation & sequence of delay
• Stemming material used will be moist.
• Blasting time (safety aspect)
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-90
The blasting will be done at a fixed time as far as possible. As per the mining
plan, in order to ensure slope stabilization, controlled production blasting shall be
adopted to avoid tension cracks and back breaks. Such cracks may get filled
with water, which reduces the stability of excavated slopes and the angle of
slopes.
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-91
9.5.3 Water quality Management
Management of surface water drainage
Garland drains will be made around the periphery of the mine. These garland
drains will be connected to the local nalla which is not likely to be disturbed by
mining operation. In the workings, heavy duty pumps will be deployed in rainy
season which will throw the accumulated water from the working face into these
garland drains. As the extraction of the quarry advances, the position of garland
drain will also advance. Thus these garland drains will drain of the rain water
away from the workings. An amount of Rs.41.5 Lakh is allotted for capital investment and Rs.10 Lakhs is allotted for recurring cost towards water
pollution control measures.
Mine Water Discharge
The mine water discharge which needs treatment before discharge to the
surface water drainage. The collected water at the floor of mine sump will be
pumped to the settling tank where suspended solids will get settled. The clear
water after sedimentation will be reused for water sprinkling, plantation etc.
Water Conservation
The waste water recycling after due treatment for the purpose mentioned above
will enable conservation of water. Storage of conserved water in mine pits will
be given due emphasis to provided water round the year and quality of water
will be maintained before and after storage.
Silt water control
During the monsoon period, run-offs from the overburden dump and top soil
dump would be checked at the check dam. The check dam would prevent
carryover of fine solids to the peripheral drain, which finally follows the natural
slopes down the hill. The check dams would be made from boulders by cement
pointing. In addition the overburden dump would have garland drains all around
for each terrace of adequate size so that velocity is appreciably reduced to
enhance the settling of the fine particulate. Rock lined wide mouthed drains with
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-92
catchpits or silting pond need to be constructed near the crushing plant and
R.O.M. stockpile for arresting the carryover of ore dust to the drainage channels
on the hill slopes.
Check Dams
Check dams are proposed to avoid flow of material during monsoon season so
that the natural water courses are not polluted.
The water so collected would be utilized for watering the mine area, roads, green
belt development etc. The drain should be regularly de-silted and maintained.
The garland drain (size, gradient and length) and sump capacity should be
designed keeping 50% safety margin over and above the peak sudden rainfall
and maximum discharge in the area adjoining the mine site. Sump capacity
should also provide adequate retention period to provide proper settling of silt
material.
Girdle walls:
Girdle walls are proposed in order to prevent the sliding of the dump materials
and protect the soil erosion with agave and grass plantation on dumps for
stabilization.
9.5.4 Management of Land Environment
Land management is required in the key areas like land use scheme within the
ML area, calendar plan, mine bench advancement to arrest indiscriminate
degradation of landform, top soil preservation, overburden management, soil
erosion control and the restoration of the mine pits. On each of these prime
areas of land management, the following schemes are proposed. An amount of Rs.25 Lakh is allotted for capital investment and Rs.7 Lakhs is allotted for recurring cost towards Management of Land environment.
Land use
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-93
The ML area is principally degraded land and has sporadic patches of very little
shrub vegetal cover in the hill slopes. The core zone landscape shall be
improved by tree plantation, scrub growth etc.
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-94
Calendar plan
The calendar plan for such surface mining operation depicts the excavation
planning of overburden as against rising of minerals in each year upto a specific
period of mining. It ensures the landform change in a planned manner, one of
the essential tools for land management. The development of iron ore mine
would be in phases spread over a period of about 4-5 years.
Mine bench planning
This is again required for planned way of changing the land form and safety
aspects for meeting the desired mine production level. Determination of bench
height for exploitation of mineral deposit depends largely on topography of the
land, geological characteristics, best practicable utilization of excavation
equipment and the scale of operation. It is regulated by the provisions of Mines
Act 1952 and the Metaliferrous Mines Regulations, 1961.
Mine roads:
Roads for haulage and access to different locations would be laid as per the
statutory regulations stipulated in the Metaliferrous Mines Regulations, 1961.
Some of the basic features of laying the haul roads at the mine site as required
from environmental and safety angle should cover the following:
Ø The road layout would be generally followed as per scheme shown in
mine general layout. The main haul road and feeder roads would be
generally of 12 m wide keeping provisions for arboriculture.
Ø The corners and bends would be made in such a way as to offer the
vehicle operator, a clear visibility of at least 30 m along the road.
Ø Road gradient would be maintained at 1 in 16 except in cases of ramps,
where gradient of 1 in 10 may be provided.
The alignment of haul roads and feeder roads may require alteration with the
progress of mining work.
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-95
Dump Management
The mine would produce considerable quantities of waste. The major problems
with this waste are its storage or dumping at proper location, slope stability of the
dump and stabilization or disposal.
The overburden would be loaded on rear-dump truck by front-end loaders for
transportation to dump areas. Formation of stacking of the overburden would be
initiated by dumping of overburden materials on the ground all along the outer
periphery of the demarcated area.
For further stability of the dump and improved aesthetics, the slopes of the
overburden would be progressively revegetated with local or introduced trees,
shrubs and grasses. Top soil preserved would be spread over the slopes of the
dump for vegetation growth.
Soil erosion control:
Most of the soil cover on the hill slopes would be lost. due to spoiling of the
natural vegetation cover. It would, therefore, be necessary to check the soil
erosion by tree plantation. The overburden and topsoil dumps would be provided
with check dam/bund wall to prevent carryover of soil particles/silt to the
drainage channels on the slopes during monsoon period.
Land restoration:
During the course of mining, the original land form would get disturbed. In the
initial stages of the mining operation, concomitant reclamation of the land may
not be possible due to following operational reasons:
Ø Simultaneous opening of different benches at different levels for achieving
the desired tonnage and grade of R.O.M.
Ø Irregular and heterogeneous nature of mineralization.
Ø Unfavorable topography limiting the total backfilling of the pits with
overburden.
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-96
In consideration of the above constraints, it would be preferable to take up the
backfilling of the mined out block after exploitation of the iron ore. The restoration
of the degraded land would cover backfilling and terracing with the overburden /
wastes and surfacing the same with top soil. The fast growing native shrubs
would be planted to stabilize the reclaimed land and prevent wind erosion of
solid particles.
9.5.5 Green Belt Development
Apart from reclamation and rehabilitation of the active mined out area, project
proposes to develop the non mineralized area within the leasehold of mine as
green belt.
The area falls under natural forest area named as Dondi-Lohara reserve forest.
In the directions where natural forest does not exist, there is need for creating
green belt of adequate width as an effective dust and sight curtain in the
periphery of mining area. The trees planted in the green belt area shall act as
buffers and shock absorber against dusts, noise and stone flying. The trees in
the green belt will be tall, wind firm, broad leaved and evergreen. A green belt of
adequate width on either side of the haul road will be raised and the existing
vegetation will be protected. Along the roads other than the haul roads also, dust
resistant plants as mentioned in the chapter IV will be planted. An amount of
Rs.361.5 Lakh is allotted for capital investment and Rs.25 Lakhs is allotted for recurring cost towards Green belt development.
9.5.6 Flora & Fauna
Conservation Plan for Flora
The floral conservation plan is mainly focused to regenerate a good forest cover
to the scattered small patches of barren lands present at the project sites.
However the project zone was already covered by a good diversity of plant
species that comprised of herbs, shrubs and tree species. The small plants such
as herbs, medicinal herbs and commonly available weeds were found to be good
in number and these plants were having the potential of rapid regeneration and
spread. Due to self regenerative capacity of these plants, the propagation
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-97
strategy is not required. Except for a few plant species, all the plant species
found in this region were found to be commonly available flora of all the regions.
From the present study, it appears that there is no Endemic or endangered plant
species in the core zone and the buffer zone were present. Hence it is
considered that there is no specific conservation plan is required. To improve
the vegetation cover, it is suggested that the saplings of diverse tree species
such as Acacia catechu, Anogeissus latifolia, Butea monosperma, Diospyros
melanoxylon, Bassia latifolia, Lagerstroemia parviflora, Lannea coromandelica,
Shorea robusta, Terminalia bellirica, Boswellia serrata, Dendrocalamus strictus,
Cassia siamea, Eucalyptus globules, Acacia auriculiformis, Albicia lebok,
Azadirachta indica, Delbergia sisoo, Gmellina arborea, Phyllanthus emblica,
Pongamea glabora and Tectona grandis could be planted to fill the gaps at
aregular intervels.
Conservation Plan for Fauna
In the core zone, no wild animals reported in the Schedule I of the Wild life
protection Act 1972 were present. However in the buffer zone, few animals were
found in the buffer zone of the project. Hence the conservation plan for each
species reported in the Schedule I and schedule II of the Wild life protection Act
1972 is given as follows for ensuring the community enrichment in their localities.
Conservation of Python molurus (Animals of schedule I part I of the core and buffer zone)
Since Indian pythons (Python molurus) are under threatened/endangered
condition, a conservation measure should essentially be taken. These animals
live in a wide range of habitats including river valleys, woodlands, forests,
grasslands, swamps, marshes and rocky foothills. Except swamps and marshes,
all the above said habitats can be seen in and around the core zone, which could
be protected to ensure the protection of these animals. Arrival of diverse fauna
by means of aforestation in the barren lands could act as a direct conservation
measure. These snakes have often been killed for their fine skin and the meat is
eaten by locals as the fat is purported to have medicinal value. Very strict
prohibition of these activities will enrich Pythons in these regions.
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-98
Conservation of Felis chaus (Animals of schedule I part I of the buffer zone)
Jungle cat (Felis chaus) is often assessed as being in no danger and has
therefore been ignored as a rare species. As a measure of its conservation, fruit
and nut yielding plant species such as Artocarpus hirsute, Manigifera indica,
Terminalia bellarica and Anacardium occidentale could be planted in the
aforestation zones which will ensure the arrival of rodents and other animals,
being prey for these cats.
Conservation of Melursus ursinus (Animals of schedule I part I of the buffer zone)
Sloth beers (Melursus ursinus) are not an inhabitant of the core zone of Jampali
OCP and they are the occasional visitor to the regions during nights especially in
the flowering season of Bassia latifolia. Hence it is suggested to raise a massive
plantation such plants in the border areas of core zone. Sloth bears are generally
killed for their bile which is used in traditional medicines, however in this area, no
reports are available on their poaching and hunting. Making awareness among
the local community will regenerate the habitats for sloth beers in the buffer
zones.
Conservation of Geoclemys hamiltoni and Kachuga dhongoka (Animals of
schedule I part I of the buffer zone)
Tortoises, namely Geoclemys hamiltoni and Kachuga dhongoka mentioned in
the above schedule were noticed. The buffer zone is not directly disturbed by the
mining activities but affected by anthropogenic activities of the local people.
These animals are being hunted for the purpose of food and for their medicinal
importance by some community of local people. In order to conserve those
animals, this should be strictly prohibited.
Conservation of Herpestes edwardsi and Presbytis entellus (Animals of schedule II part I & II of the buffer zone)
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-99
Indian mongoose (Herpestes edwardsi) and Grey langur (Presbytis entellus) are
the two wild animals that were mentioned in the Schedule II of the Wild life
protection Act (1972), which are also needed to pay special attention for the
protection. Gray langur and mongoose feed mainly on leaves, fruit, buds and
flowers of the plant species. These animals also supplement their diet with
insects (up to 25%), tree bark and gum. Developing a forest with diverse
population of fruit bearing trees such as Artocarpus hirsute, Bassia latifolia,
Diospyros melanoxylon, Ficus bengalensis, Ficus religiosa, Manigifera indica,
Phyllanthus emblica, Psidium guajava, Phoenix sylvestris, Syzigium jombolanum
and Terminalia bellarica in the core zone, where there are no mining activities,
could be a conservation measure for these animals. Indian mongooses were
found in buffer zone and the population of which is stabilized by the local fauna.
Conservation of Vulpes benghalensis (Animals of schedule II part II of the buffer zone)
Jackel and foxes (Vulpes benghalensis) are some of the common inhabitants of
the area which live in burrows of this area. Only thing required for the protection
is to provide places to escape from predators. It is suggested that the
aforestation area provides sufficient hideoutes to those animals which helps to
escape from the predators since these two species are generally not hunted by
the local people.
An amount of Rs.50 Lakh is allotted for capital investment and Rs.15 Lakhs is allotted for recurring cost towards implementation of conservation plan for Flora & Fauna.
9.5.7 Health and Safety
Health and safety aspects of the mine will be taken care off as per the statutory
guidelines on open pit mining for proper maintaining of Health and Safety issues.
The workers continuously exposed to dust will be provided with some protective
devices like dust mask to prevent respiratory disorders. The workers
continuously exposed to a high noise will be provided with ear muffs/ ear plugs.
Green belt in and around the mining area will be developed to attenuate noise
and dust impact. The blasting carried out in the mine area will be carefully
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-100
planned and executed under the supervision of a responsible officer, to avoid
any accidents. The protective devices will be provided to the employees handling
hazardous substances. Proper handling of the hazardous chemicals and the
maintenance of Material Safety Data Sheet (MSDS) will be followed to ensure
safety within the mine. Drinking water supply for the employees and to the
proposed colony will be provided by the project authority. Proper sanitary
facilities will be taken care by the project authority so that employees do not
suffer from any health ailments. The employees will be made aware of general
sanitary practices. Periodical training programme to inform the employees about
their task, associated risk, and safe working practices will be undertaken.
Training will also include information on accident prevention, proper control and
maintenance of equipment and safe material handling practices. A regular
monitoring of the Occupational Health and Safety will reduce the chances of
accidents in the mine. Records of job related accidents and illness should be
maintained per the requirements. These information’s will be reviewed and
evaluated to improve the effectiveness of Environmental Health and Safety
programme.
The OHS scheme exclusively for the proposed Project, which is as follows:
• SAIL shall provide safe drinking water facilities to the mine worker at the
mine site: The standard of the drinking water will be per WHO guidelines.
• Iron ore does not contain any toxic elements, the possibility of any health
hazards does not arise. The most significant occupational health threat is
Occupational Lung Disease due to inhalation of silica dust and fine iron
ore dust. Noise exposure also represents a risk to the people operating
large equipments. The workers continuously exposed to dust will be
provided with some protective devices like dust mask to prevent
respiratory disorders. The workers continuously exposed to a high noise
will be provided with ear muffs/ ear plugs.
• Proper sanitation facilities shall also be provided at the mine site for the
employees: The employees will be made aware of general sanitary
practices.
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-101
• Periodical health check up of employees
• Attending specific problems related to occupational health hazards
• Health educational training like modular first aid training, malaria
education, AIDS awareness programme, work place health hazards and
prevention
• Work physiology ergonomics
• Medical examinations of superannuating employees
• Rehabilitation of employees
• Occupational hazards monitoring and suggesting control measures
• Personal respirable dust and noise level monitoring
• Specific problem on occupational hazard is attended in the site
• PPE (safety appliances) are issued based on hazard surveys
• Modular 4 days first aid training programme : 3 programmes / year
• Aids awareness programme : 2 programmes / year
• 2 days programme for work place hazard and its prevention : 2
program/year
• Publication of health education material and its distribution
An amount of Rs.100 Lakh is allotted for capital investment and Rs.20 Lakhs is allotted for recurring cost towards implementation of Occupational Health programs.
9.5.8 Socio-Economic development
SAIL shall take major initiative in sustainable development of the area by raising
the living standards of the people. Taking into consideration the aspirations of
local and regional people about the employment due to proposed beneficiation
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-102
plant, SAIL/BSP will provide employment opportunities to the people of
Chhattisgarh by way of contract labour during various activities ancillary to
mining operations. Due to such activities local people from these villages would
be self employed and will gradually become entrepreneurs over a period of time.
The details of the activities which will be taken under each head are mentioned
below.
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-103
9.5.8.1 Infrastructure Support Programmes
1.Medical Camps
♦ Medical camp shall be organized in the villages where the population is
more than 1000. For villages with less population, one medical camp shall
cover 2-3 nearby villages at a time. Such medical camps shall consist of a
complete team of doctors and specialist etc. from Allopathic disciplines
♦ Free medicine shall be made available by the SAIL/BSP during the camp
♦ Post operation treatments of patients treated in medical camps shall be
covered by Rajhara Hospital run by SAIL/BSP
2. Awareness Programme
♦ People of the region shall be covered in Health education programmes
particularly on personal hygiene, sanitation, prevalent diseases and
prevention of malaria etc.
♦ Ten programs shall be conducted every year in a systematic manner in
association with Government agencies and local NGOs
3. Education
Following measures are proposed to improve and strengthen the basic
educational facilities in the nearby area.
♦ SAIL/ BSP will adopt at least one High School
♦ The infrastructure facilities will be enhanced in 5 Government Schools for
primary education
♦ Provide scholarship to one meritorious student every year from each
village of the buffer zone for higher education
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-104
4. Improving Water Supply
Local people still consider water from well as pure and safe for drinking and
cooking purpose. The water from the wells is also used for performing several
rituals and religious ceremonies. Therefore, the existing well in villages shall be
improved by constructing pucca boundary wall around the well, fixing angle iron
frame to facilitate the collection of water. For other household purposes, one
hand pumps in villages having more than 1000 population will be installed.The
existing ponds shall be improved and in case new ponds are required, same
shall be constructed in these villages to harness rain water, which can be used
for agriculture purposes, dairy, fisheries, etc.
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-105
5. Sanitation
Sanitation facilities are lacking in the villages. Most of the people defecate in
open areas. Lack of drainage is also responsible for higher prevalence of malaria
in the area. SAIL/BSP will develop a low cost standard design of sanitary latrine
complete with commode, water tank, soak pit etc.
6. Development of Permanent/Semi Permanent Market Sheds
Weekly markets play an important role in rural economy. The location and days
of these markets are fixed for all the villages. It was observed that weekly
markets were a regular feature especially for the large villages. The people from
smaller villages also visit the weekly markets of the nearest villages for the sale
or purchase of various items.
SAIL will develop permanent/semi permanent structures in these markets by
involving the Village Development Committees of the concerned villages. This
will help the villagers in disposal of their produce.
9.5.8.2 Economic Upliftment Activities
1.Improving Agriculture Practices
Agriculture is the main occupation of over 90% population of the areas. The main
emphasis would be given to improve the current agricultural practices. Women
would be given proper representation in the process. Identification of the Self
Help Groups/ NGO as facilitator of programme will be made. The following
activities will be taken to improve the agricultural practices.
♦ Training of farmers on various agriculture practices including exposure
visits to agriculture institutions and the farms of progressive farmers
♦ Develop village ponds, check dams, canals and other soil and water
conservation measures for irrigation,
♦ Promote vegetable cultivation as cash crops,
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-106
2. Dairy Development
All people rear cows and buffalos to support agricultural activities and milk
production. Lack of proper mechanism for collection, distribution and marketing
of milk and milk products is mainly responsible for not converting these produces
into an economically viable opportunity for local people. Following activities will
be taken up for collection, distribution and marketing of milk and milk products in
the area.
♦ Organizing training programmes on dairy development including exposure
visits
♦ Establishment of facilities for treatment of animals
♦ Regular checkups and vaccination of the animals
3. Develop Forest based Income Generating Activities
The low economic status of local people is responsible for exploitation of forest
and its destruction. Sustainable harvesting will be ideal to improve the income of
local people and reduce their dependence on forest. Collection of mahua seeds,
sal seeds, lac (gum), tamarind (imli), honey, medicinal plants etc. and their value
addition and marketing through the Village Development Committees (VDCs)
shall be undertaken under this programme. Most of these are seasonal activities.
Women and children are mainly involved in the collection of mahua and sal
seeds whereas men are involved in collection of lac and honey. The collection
and marketing of various forest produce shall be channelized through the VDCs.
Value addition of products at local level will be done by cleaning, drying, grading,
making powder, packaging of medicinal plants/plant products, purification and
packaging of honey. Their publicity as quality organic products shall be carried
out to maximize the profit margin of local people. The modus operandi for
sustainable harvesting of various products and maximizing the profit margin of
local people are mentioned below:
♦ Identification of the Self Help Groups / NGO to develop the process and
products in the initial stages
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-107
♦ Providing training to the specific groups of the people for making value
added products by involving experts of related fields,
♦ Developing Women Self Help Groups for making specific products, and
♦ Organize publicity and marketing of different products through VDCs
4 . Women Empowerment
Women are hard working and share most of the family responsibilities such as
collection of drinking water, collection of fuel wood, fodder and other non timber
products from the forests, cooking of food and childcare. Rural women will be
involved in all decision making processes for developmental activities. The
economic upliftment of women folk is necessary for the development of society
as a whole. For this purpose, training in knitting, sewing, potteries, cottage
industries etc. shall be given and they will be motivated to form Self Help Group
(SHGs). Provision for adoption of schools and support to educational
infrastructure has already been provided which will also empower the girl child,
besides other students, through imparting proper education.
5. Cultural Development
Local culture is quite rich. There are many dances, rituals, prayers etc., which
are performed by the whole village or the group of villages to please the god for
getting the good harvest or for the protection of agriculture crops from damage
by wild animals and other natural calamities, etc. The culture gives an identity to
the people and they enjoy it during various festivals, ritual and ceremonies. It is
proposed to provide avenues to propagate their cultural activities among their
communities.
The panchayats shall be provided a Community Development Fund to carryout
cultural activities of tribal communities. A cultural troop shall be constituted in
each zone and they will be encouraged to participate in various festivals, fairs
and shows in and around the state depending upon the opportunity and scope.
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-108
Table 9.1 Activities and Cost of Infrastructure Support Programme
Sr.No. Activities Total
Rs. (lakh) 1. Health and Family Welfare. 25
2. Education 25
3. Improving water supply 20
4 Sanitation 20
5. Development of Weekly Market Infrastructure and maintenance 10
Total 100
Table 9.2 Details of Income Generating Activities along with Their Costs
Sr. No. Activities Total
Rs. (lakh)
1 Improving Agriculture Practices 20
2 Dairy Development 15
3 Women Empowerment 10
4 Forest based Income Generating Activities 20
5 Cultural Development 15
Grand Total 80
9.6 Cost of Environmental Control Measures
Statement showing the estimated capital requirement for environmental
protection measures is given in Table 9.3.
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-109
Table – 9.3 Budget for Environmental control measures
Sr. No. Activity Capital Cost
(Lakhs Rs.) Annual Recurring Cost
(Lakhs Rs./yr)
1 Dust control 50 15
2 Noise Control 20 5
3 Water Quality Management 41.5 10
4 Land Environment 25 7
5 Green Belt Development 361.5 25
6 Flora & Fauna Conservation
50 15
7 Health & Safety measures 100 20
8 Socio-economic development
180 20
9 Environmental Monitoring - 20
10 Others 30 10
Grand Total 858 147
CHAPTER X
SUMMARY AND CONCLUSION
10.1 Preamble
Steel Authority of India Limited (SAIL) is the leading steel-making company in
India. It is a fully integrated iron and steel maker, producing both basic and
special steels for domestic construction, engineering, power, railway, automotive
and defense industries and for sale in export markets. The company is ranked
amongst the top ten public sector companies in India in terms of turnover. SAIL
manufactures and sells a broad range of steel products, including hot and cold
rolled sheets and coils, galvanized sheets, electrical sheets, structural, railway
products, plates, bars and rods, stainless steel and other alloys. The growth of
mining / industry significantly contribute towards economic progress of the
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-110
country. However, any project progress brings along with it a number of
environmental problems. Many of these problems can be avoided, if adequate
environmental control considerations are thought of during conceptual stage of
the project. In accordance with Mission and Objectives of M/s. Steel Authority of
India Limited and National Steel Policy, SAIL proposes to develop/expand
Mahamaya – Dulki mine with a rated production capacity from 0.96 to 1.46
Million Tone Per Annum. The Mining lease area under is 1522.67 Ha.
10.2 Project Details
Location
BSP proposes expand Mahamaya - Dhulki Iron Ore Project, at Mahamaya and
Dhulki villages, Durg , Chhatisgarh state. The deposit is located in the Nos. 64
D/15 and 64 H/3 between longitude 80°57'02” to 81°00'53"E and between
latitude 20°26'06" to 20°30’21"N..The lease area is well connected by road lying
at a distance of 111 kms. South-West of Bhilai Steel Plant. The Iron ore
produced from this mine is being transported by road to Dalli-Rajhara Iron ore
Complex located at a distance of 23km.
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-111
Geological structure
The area under reference is Mahamaya-Dulki lease which lies partly in
Mahamaya and partly in Dulki hills. The rock types exposed in this area belong
to Dharwar group, similar to Dalli-Rajhara and Mahamaya deposits. The iron
ores traced here generally occupy the peaks and BHQ in intervening ridges.
Both upper and lower shale/ phyllites contacts with BHQ in hill sides. The
intrusive bodies like thin quartz veins of younger age also occur within the area.
The soil, laterite capping and ferruginous shale etc. occurring above the ore body
normally contain low iron and high alumina percentages and are considered as
overburden. The iron ore body consists of lateritic ore, shaly ore, silicious ore,
laminated ore, compact ore and soft friable / powdery type of ores. Among these,
the laterite ore, shaly ore and silicious ore are generally low grade. The ore
containing less than 55% Fe content and these ores are not considered for
reserve calculation. The remaining three types of ores viz. Laminated, Pre-
Compact Laminated and friable contain 55% to 67% Fe. The laminated ore
constitute about 75% of the total available reserves. The average grade of ore
occurring in the area contains 62.17% Fe, 4.68% Si02 and 2.83% Al2O3.
Manpower requirement
The requirement of manpower at the rated capacity of 1.46 MTPA of ore has
been estimated as 50 numbers approximately.
10.3 Description of Environnent
Meteorology
Pre-monsoon`09: Predominant wind was from South-west quadrant. Wind velocity was ranging
from <1.0 to 18.0 Kmph. Temperature values were ranging from 24.5 °C to 46.0°C. The mean
relative humidity value was found to be ranging from 37.9 - 70.3 %.Sky was clear during the study
period. A total rainfall of 3.3 cm was recorded during the study period.
Monsoon`09 : A total rainfall of 80.2 cm was recorded during the study period.
Post-monsoon`09: Predominant wind was from North-east quadrant. Wind velocity was ranging
from <1.0 to 14.7 Kmph. Temperature values were ranging from 24.5 °C to 46.0°C. The mean
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-112
relative humidity value was found to be ranging from 37.9-70.3%.Sky was clear during the study
period. A total rainfall of 3.3 cm was recorded during the study period.
Winter`2010 : Predominant wind was from East Northeast quadrant. Wind velocity was ranging
from <1.0 to 17.7 Kmph. Temperature values were ranging from 10.0 °C to 39.0.0°C. The mean
relative humidity value was found to be ranging from 52.8-75.5 %.Sky was clear during the study
period. A total rainfall of 0.2 cm was recorded during the study period.
Pre-monsoon 2011 : Predominant wind was from South-west quadrant. Wind velocity was
ranging from <1.0 to 20.4 Kmph. Temperature values were ranging from 25.0 °C to 44.0°C. The
mean relative humidity value was found to be ranging from 35.4 – 68.4 %.Sky was clear during
the study period. No rainfall was recorded during the study period.
Post-monsoon (November 2012): Predominant wind was from NE/NNE. Wind velocity was
ranging from <1.0 to 12.7 Kmph. Temperature values were ranging from 16.5 °C to 30.5°C. The
mean relative humidity value was found to be ranging from 58 – 72 %. Sky was clear during the
study period. No rainfall was recorded during the study period.
Air Environment
Pre-monsoon season (Apr.09-Jun.09)
Corezone : SPM and RPM values were ranging between 200 and 321 µg/m3 and
83 and 128 µg/m3 respectively. The SO2 and NOx values ere ranging between 8.2
and 14.2 µg/m3 and 8.9 and 15.8 µg/m3 respectively.
Bufferzone : SPM and RPM values were ranging between 77 and 184 µg/m3 and
24 and 83 µg/m3 respectively. The SO2 and NOx values ere ranging between 5.5
and 9.7 µg/m3 and 6.8 and 11.2 µg/m3 respectively.
Post-monsoon Season (Oct-Dec.09)
Corezone : SPM and RPM values were ranging between 205 and 321 µg/m3 and
59 and 90 µg/m3 respectively. The SO2 and NOx values ere ranging between 8.7
and 10.8 µg/m3 and 10.6 and 12.9 µg/m3 respectively.
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-113
Bufferzone : SPM and RPM values were ranging between 90 and 172 µg/m3 and
34 and 74 µg/m3 respectively. The SO2 and NOx values were ranging between
5.2 and 9.2 µg/m3 and 6.3 and 11.5 µg/m3 respectively.
Winter season (Jan – Mar.10)
Core-zone : SPM and RPM values were ranging between 185 and 293 µg/m3 and
62 and 96 µg/m3 respectively. The SO2 and NOx values ere ranging between 7.1
and 9.7 µg/m3 and 9.0 and 11.5 µg/m3 respectively.
Buffer-zone : SPM and RPM values were ranging between 102 and 177 µg/m3
and 34 and 74 µg/m3 respectively. The SO2 and NOx values were ranging
between 5.6 and 9.9 µg/m3 and 6.9 and 12.3 µg/m3 respectively.
All CO & heavy metals values were found to be below the detectable limit.
Based on the above discussions, it may be concluded that air quality of the area
is less susceptible with respect to seasonal variations. The variation is mainly
contributed by active mining.
Pre- monsoon 2011 (March-May 2011)
Core zone : PM10 and PM2.5 values were ranging between 77 and 125 µg/m3
and 28 and 46 µg/m3 respectively. The SO2 and NOx values were ranging
between 8.8 and 14.8 µg/m3 and 9.3 and 16.7 µg/m3 respectively. The Ammonia
and Ozone values were ranging between 18 and 38 µg/m3 and 6 and 17 µg/m3
respectively.
Buffer zone : PM10 and PM2.5 values were ranging between 30 and 65 µg/m3 and 8
and 21 µg/m3 respectively. The SO2 and NOx values were ranging between 4.1 and
10.2 µg/m3 and 4.1 and 16.1 µg/m3 respectively. The Ammonia and Ozone values
were ranging between 10 and 40 µg/m3 and 4 and 14 µg/m3 respectively.
Postmonsoon (November 2012)
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-114
Core zone : PM10 and PM2.5 values were ranging between 58 and 82µg/m3 and
19 and 28 µg/m3 respectively. The SO2 and NOx values were ranging between 6.4
and 10.2 µg/m3 and 9.2 and 16.3 µg/m3 respectively. CO values were ranging
between 285 and 410 µg/m3. The heavy metals values are found to be
negligible.
Buffer zone : PM10 and PM2.5 values were ranging between 44 and 64 µg/m3
and 14 and 23 µg/m3 respectively. The SO2 and NOx values were ranging
between 5.8 and 9.1 µg/m3 and 9.1 and 15.6 µg/m3 respectively. CO values
were ranging between 210 and 355 µg/m3. The heavy metals values are found to
be negligible
Noise level
Pre-monsoon : The Day and night time Leq Noise levels were ranging from 39.6
dB(A) to 57.7 dB(A) and 30 dB(A) to 47.4 dB(A) respectively.
Post-monsoon: The Day and night time Leq Noise levels were ranging from 41.3
dB(A) to 55.3 dB(A) and 29.8 dB(A) to 46.6 dB(A) respectively
Winter: The Day and night time Leq Noise levels were ranging from 43.2 dB(A) to
56.9 dB(A) and 33.8 dB(A) to 49.3 dB(A) respectively
November 2012: The Day and night time Leq Noise levels were ranging from
42.3 dB(A) to 54.8 dB(A) and 32.3 dB(A) to 45.0 dB(A) respectively.
The Noise level values were found to be well within the CPCB limit prescribed by
CPCB.
Water Environment
Ground water : While comparing with IS: 10500 – 1991 norms, all values except
total coliforms were found to be well within the limits.
Surface Water: Low BOD/COD values and good D.O. content at these locations
indicate that the natural restoration of water quality is maintained. While
comparing with IS 2296 all values were found to be well within the norms for
Surface water quality.
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-115
Hydrogeology
The Hydrogeology study reveals that the pre-monsoon water levels vary from
3.20 m to 9.45 m with an average of 5.73m and the post-monsoon water levels
vary from 1.15 m to 4.50 m with an average of 3.09 m. The average water
fluctuation in the area was found to be 2.62 m. As per, CGWA norms, the trends
reveal that the groundwater exploitation in the study area is well within the
acceptable limits.
Land-use Pattern
Remote sensing satellite Imageries were collected and interpreted for the 10 Km
radius study area with project site as center. Based on the satellite data land -
use / land cover maps have been prepared delineated in chapter III of EIA/EMP
report .
Flora & Fauna
The environment has not supported foreign visitor birds since the entire zone
(core and buffer) is devoid of large water bodies. There are no ecologically
sensitive/fragile areas such as Wild life Sanctuaries, National Parks, and
adjoining National Monuments, areas of cultural heritage, ecologically fragile
areas, areas rich in biological diversity, gene pool, etc located on the proposed
stretch. There are no known rare, endangered or ecologically significant animal
and plant species. Except for a few wild species of plants and grasses and a few
animals that are very commonly spotted in any rural environment, the study area
does not have any endangered or endemic species of animals and plants. The
conservation plan for Fauna is explained in Chapter – IX.
Socio economic
As per 2001 census, the study area consisted of 17538 persons inhabited in 37
villages. The configuration of male and females indicates that the males constitute
to about 49.37% and females to about 50.63% of the study area population. The
study area at an average has 1025.64 females per 1000 males. Majority of the
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-116
people in the study area belong to Hindu religion. The study area also contains
Scheduled Castes (SC) and Scheduled Tribes (ST).
In the study area 2.78% of the population belongs to Scheduled Castes (SC) while
77.55% to Scheduled Tribes (ST), thus indicating that about 80.33% of the
population is formed by SC and ST population. Scheduled Caste and Scheduled
Tribe sections are predominant in this area. The study area experiences a
moderate literacy rate of 61.57%. The male literacy i.e. the percentage of literate
males to the total males of the study area is observed as 70.07% while female
literacy rate, which is an important indicator for social change, is observed as
53.29% in the study area.
10.4 Anticipated Environmental Impacts And Mitigation Measures
Impact on Land use
The topography within the mining area will have marked changes in the quarry
area, the dump area and the mining equipment area. No appreciable change in
the topography is anticipated out side mining area. Total scenario of landscape
and land use pattern will undergoes a stark change within the mining area. There
will be a stark change in surface drainage and new pattern drainage will be
developed within the mining area.
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-117
Impact on Air Quality
The major source of air pollution into the atmospheric environment are:
1. Removal and dumping of over burden
2. Drilling and blasting operations
3. Extraction of ore by machinery.
4. Loading of ore into trucks.
5. Dump yard waste material.
Predicted Ambient Air Quality
Post Monsoon season ( Nov.2012)- Post project Scenario (PM10) (µg/m3) S.
No. Location name Baseline scenario (max)
Predicted values
Post Project scenario
1 Corezone (Mine Pit 3) 73 8.8 81.8 2 Corezone (Canteen) 82 7.1 89.1 3 Tuedand 56 0.2 56.2 4 Dupkatola 52 0.2 52.2 5 Dulki 56 6.2 62.2 6 Markamtola 56 5.4 61.4 7 Kalangpur 64 0.5 64.5
8 Rasuli 56 0.8 56.8
9 Bodra 56 1.8 57.8 10 Kalwar 64 1.1 65.1 11 Dorba 62 0 62.0 12 Nagbur 52 0 52.0
Impact on Noise Level
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-118
Once the mine becomes operational, there would be various sources of noise in
the area. These sources would be Drilling,Blasting,Operation of HEMM, Crusher
and Workshop,Vehicular Movement and Belt Conveyor. Mining operations and
the ore crusher would be the main sources of noise pollution. Noise due to
vehicular movement will be intermittent, but will also add to the background
noise level. It is being observed that at the mine site where heavy earth moving
machinery is in operation, noise level is more than the stipulated 90 dB (A) per
DGMS Circular, No 18 (Tech) of 1975. The noise level is within the tolerance
limit at a distance of 15 to 20 m or so. The sound pressure level generated by a
noise source decreases with increasing distance from the source due to wave
divergence.
Socio economical impacts and infrastructural developments
In terms of the major socio-economic impacts, the project will provide more
direct and indirect job opportunities and better economic standards to the
people and others, through improved infrastructural, community facilities etc.
Development of residential colony, creation of civic and welfare amenities like
primary health care, communications, educational institutes, recreational
facilities, etc, that will develop along with the project will ensure better quality
of life for the local population. The increase in income opportunities and -
employment potentialities in this sector is anticipated as the mining activities
increase, the other economic sectors starts gaining in momentum. With added
educational, medical and communication facilities developed in the areas, the
standard of living has improved. With ongoing of mining activities additional
facilities for local population by way of better communication, postal services,
educational facilities, advanced medical services etc. are on in the area. There
is a marked change in social status of the area with opening of the project.
State Government is benefited through financial revenues in crores of rupees by
way of royalty, sales tax etc. from the -direct and indirect operations in the
project area. Central exchequer is also getting financial revenues by way of
Income tax, Central Sales Tax etc.
Impact on flora and fauna
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-119
There will be positive impact on flora and fauna due to the proposed plantation
activities and the conservation plan proposed for the forest and wild life. The
negative impacts are mainly due to Mining activities such as excavation for
quarry, erection & development of plants, service & allied structures, colony,
roads, drains, culverts, etc. These activities will guide to forest degradation,
lost of vegetation cover and ecological changes.
Mitigative measures
Secondary Employment opportunities
There will be spontaneous economic stimulus in the area with the
commencement of opencast mine. Traders and private enterprises will grow in
the area with this economic growth. Besides, the State exchequer will derive
financial revenues through levy of royalty, sales tax etc. and Central Government
will also be, benefited by way of Central Sales Tax, Income Tax, Cess's etc.
Medical Facilities
The project authorities have adopted following measures to prevent occupational
diseases and health hazards.
• Pre-employment, pre-placement and periodic medical examination of
employees.
• Regular monitoring of working environment and implementation of safety
and control measures, to prevent hazards.
• Use of protective equipments, clothing, helmets, Gas mask, shoes, etc.
• Periodical medical examination-of every worker is done once in five years
to detect preventable and curable diseases at an early stage.
• Cases suspected having Pneumoconiosis is examined by a Special Board
constituted by the Chief Medical Officer. Established cases are suitably
compensated and their job is changed if required.
Literacy Drive
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-120
An action plan for achieving 100% literacy among workers to be implemented by
establishing Educational Institutions / adoption with modern facilities.
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-121
Control measures for air pollution
Following air pollution control measures are being done and will be practiced
within the mining area and at ore handling plants.
• Saplings planted on OB dump, road side and colony to arrest dust.
• Mobile water sprinklers deployed in mine.
• Stationary sprinkler installed in the mine haul road from mine entry.
• Overloading of trucks is strictly prohibited.
• Ore transportation through covered trucks
• Optimum blast hole geometry will be followed to reduce the dust during
blasting.
• Regular monitoring of ambient air quality of the project area & its
surroundings villages
Management of surface water drainage
Garland drains will be made around the periphery of the quarry. These garland
drains will be connected to the local nalla which is not likely to be disturbed by
mining operation. In the workings, heavy duty pumps will be deployed in rainy
season which will throw the accumulated water from the working face into
these garland drains. As the extraction of the quarry advances, the position of
garland drain will also advance. Thus these garland drains will drain of the rain
water away from the workings. There are 14 nos. of Check dams were already
constructed and10 nos. are proposed.
Control measures for Noise
• Innovative approaches of using improvised plant and machinery designs,
with in-built mechanism to reduce sound emissions like improved
silencers, mufflers and closed noise generating parts
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-122
• procurement of drill, loaders and dumpers and other equipment with noise
proof system in operator's cabin
• confining the equipment with heavy noise emissions in soundproof cabins,
so that noise is not transmitted to other areas
• regular and proper maintenance of noise generating machinery including
the transport vehicles and belt conveyors, to maintain the noise levels
• blasting operations to be carried out only during daytime so as to avoid
high noise intensity in night time
• siting of mine colony, buildings and other infrastructure away from the
noise sources with the probability of sound waves being directed towards
them being least
• provision should be made for noise absorbing pads at foundations of
vibrating equipment to reduce noise emissions
• thick green belt should be provided at the mine periphery, within the mine
lease area along the roads and all around the working areas, to screen
the noise.
Blasting Vibration Control Plan
• Peak particle velocity or ground vibrations for safety of nearby structures
and residential buildings should be well within 12.5 mm/sec
• to contain fly rocks, stemming column should be 1/3 the depth of hole
• detonating fuse, if used, should be covered at least with 150 mm thick
cover of sand or drill cuttings
• blasting should be carried out in the daytime, as during the night time the
sound intensity becomes higher
• blasting should not be carried out when strong winds are blowing towards
the inhabited areas
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-123
• each blast should be carefully planned, checked, and executed under the
supervision of a responsible officer. Blasting data/observations should be
recorded
Green Belt Development
Green Belt around Mine
In the directions where natural forest does not exist, there is need for creating
green belt of adequate width as an effective dust and sight curtain in the
periphery of mining area. The trees planted in the green belt area shall act as
buffers and shock absorber against dusts, noise and stone flying. The trees in
the green belt will be tall, wind firm, broad leaved and evergreen.
A green belt of adequate width on either side of the haul road will be raised and the
existing vegetation will be protected. The plants will be raised at spacing of 2.0x2.0
metre. Along the roads other than the haul roads also, dust resistant plants as
mentioned above will be planted.
Mine closure plan
The extent of impacts due to mine closure and mitigation measures to prevent or
minimize them are classified under the following heads Viz Environmental
Aspects,Technical Aspects,Social Aspects and ,Safety Aspects which is explained
in Chapter IV.
10.5 Environmental Monitoring Program
The Environment Management Department (EMD) at Dalli – Rajhara of BSP will
be entrusted with this responsibility. The officers of EMD will assess the progress
and analyze the data periodically. It will look after the following aspects of
environmental management.
• Generation of environmental data bank.
• Evolving micro environmental management plan for the project in
collaboration with other agencies and consultants. Monitoring project
implementation along with environmental control measures.
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-124
• Co-ordinate with other project activities to ensure timely implementation of
the project.
• Co-ordination with Ministry of Environment & Forest, Central/State
Pollution Control Board for prevention and control of water and air
pollution.
10.6 Risk Assessment
Risk assessment were carried out by considering the following aspects
• To identify the potential hazardous areas so that necessary design safety
measures can be adopted to minimize the probability of accidental events.
• To identify the potential areas of environmental disaster which can be
prevented by proper design of the installations and its controlled
operation.
• To manage the emergency situation or a disastrous event, if any, from the
plant operation.
10.7 Project benefits
The BSP authorities have adopted following measures to prevent occupational
diseases and. health hazards.
• Pre-employment, pre-placement and periodic, medical examination of
employees.
• Regular monitoring of working environment and implementation of safety
and control measures, to prevent hazards.
• Use of protective equipments, clothing, helmets, Gas mask, shoes, etc.
• Periodical medical examination of every worker is done once in five years
to detect preventable and curable diseases at an early stage.
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-125
• Cases suspected having Pneumoconiosis are examined by a Special
Board constituted by the Chief Medical Officer. Established cases are
suitably compensated and their job is changed if required.
There will be infrastructure development in the near by village which are as
follows.
• Construction of Pond/Deepening of existing pond.
• Construction of School Building
• Construction of Bore Wells for drinking water supply
• Construction of Dispensary Building/Panchayat Bhawan
• Construction of Children Park.
• Construction of Road, culverts and drains
The requirement of manpower at the rated capacity of 1.46 MTPA of ore has
been estimated as 50 numbers and secondary employment opportunities also
expected.
10.8 Environmental Management plan
The objectives of the proposed EMP are aimed for meeting five basic
requirements
• To integrate comprehensive monitoring and control of impacts.
• To comply with the environment protection regulations.
• To ensure that adverse environmental impacts on the baseline are
minimized
• To plan for ecologically sustainable development (ESD) within the frame
work of existing legislation and environmental management policies.
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-126
The Statement showing the estimated capital requirement for environmental
protection measures is given as follows
Sr. No. Activity Capital Cost (Lakhs Rs.)
Annual Recurring Cost (Lakhs Rs./yr)
1 Dust control 50 15
2 Noise Control 20 5
3 Water Quality Management 41.5 10
4 Land Environment 25 7
5 Green Belt Development 361.5 25
6 Flora & Fauna Conservation
50 15
7 Health & Safety measures 100 20
8 Socio-economic development
180 20
9 Environmental Monitoring - 20
10 Others 30 10
Grand Total 858 147
The detailed EMP is delineated in chapter IX.
10.9 Consultant Credentials
Environment Impact Assessment Study is carried by Richardson & Cruddas
(1972) Ltd., Chennai, A Govt. of India undertaking under Ministry of Heavy
Industry, one of the pioneers in the field of Environmental Engineering for the past
three decades. R&C Laboratory is recognized as Environmental Laboratory by the
Central Pollution Control Board (CPCB), Ministry of Environment & Forests
(MoEF) under the Environmental Protection Act, 1986 and is, also, recognized by
Tamil Nadu Pollution Control Board for carrying out air and waste water emissions
monitoring as per Air (Prevention and Control of pollution) Act, 1981 and Water
(Prevention and Control of Pollution) Act, 1974. We are also recognized by
various other State Pollution Control Boards as Environmental Consultants for
such studies.
Comprehensive EIA / EMP studies for Mahamaya -Dulki Iron Ore mine of M/s. Bhilai Steel Plant
I-127