change management guide
TRANSCRIPT
© 2008, Coles Myer Ltd.
CHANGE MANAGEMENT PROCESS GUIDE
Coles Group Ltd Information Technology IS&O - Service Delivery
© 2007, Coles Group Limited Change Management Guide Page 2 of 33 Coles Group Ltd. Information Technology IS&O - Service Delivery
Record of Changes to this Document Version Date Change Author Reviewed By
2.0 15/11/07 Major re-write, and merge from previous documents
Paul Cosgrave Ross Halford
Karen Hardman
2.1 23/06/08 Rewrite completed Revised for ServiceCenter 6
Ross Halford Ross Halford Paul Cosgrave
Document Stakeholders Name Position Interest
Robyn Freeman Service Delivery Manager Document Owner
Ross Halford Incident & Change Coordination Team Lead Approver
Paul Cosgrave Unix Manager Reviewer
Debbie Browning IS&O Platform Support Manager Reviewer
IT CAB Members Change Advisory Board Members Reviewers
Distribution List This document has been distributed to the following personnel:
Name Title & Department DATE
All updates to be communicated to all of IT via IT News announcements.
Details of significant changes, or process/policy changes to be noted in the version control above, for easy reference
© 2007, Coles Group Limited Change Management Guide Page 3 of 33 Coles Group Ltd. Information Technology IS&O - Service Delivery
CONTENTS
1. INTRODUCTION.............................................................................................................................................. 5 1.1 OBJECTIVE................................................................................................................................................... 5 1.2 INTENDED AUDIENCE .................................................................................................................................. 5
2. CHANGE MANAGEMENT OVERVIEW...................................................................................................... 6 2.1 WHEN TO USE CHANGE MANAGEMENT....................................................................................................... 6 2.2 CHANGE MANAGEMENT & PROBLEM / INCIDENT RESOLUTION................................................................... 6 2.3 CHANGE MANAGEMENT – EXEMPTIONS...................................................................................................... 7
3. ROLES AND RESPONSIBILITIES ................................................................................................................ 8 3.1 CHANGE REQUESTOR .................................................................................................................................. 8 3.2 CHANGE OWNER ......................................................................................................................................... 8 3.3 LINE MANAGER ........................................................................................................................................... 8 3.4 CHANGE COORDINATOR .............................................................................................................................. 9 3.5 SERVICE COORDINATOR ............................................................................................................................ 10 3.6 BRAND REPRESENTATIVE .......................................................................................................................... 10 3.7 SECONDARY SUPPORT TEAM REVIEW & APPROVAL ................................................................................. 11
3.7.1 Reviewing Another Teams Change Request......................................................................................... 11 3.7.2 Approving Another Teams Change Request ........................................................................................ 11
4. CHANGE ADVISORY BOARD (CAB) ........................................................................................................ 12 4.1 CAB – OVERVIEW..................................................................................................................................... 12 4.2 CAB MEMBERS......................................................................................................................................... 12 4.3 CAB MEETINGS ........................................................................................................................................ 12
5. CHANGE CONCEPTS.................................................................................................................................... 14 5.1 CHANGE CLASSIFICATION ......................................................................................................................... 14
5.1.1 Planned Changes ................................................................................................................................. 14 5.1.2 Urgent Changes ................................................................................................................................... 14 5.1.3 Retrospective Change Requests ........................................................................................................... 15 5.1.4 CAB Pre-Approved Changes ............................................................................................................... 15 5.1.5 CAB Exempt Changes .......................................................................................................................... 16 5.1.6 Change Templates................................................................................................................................ 16
5.2 REASON FOR CHANGE ............................................................................................................................... 16 5.2.1 Problem Resolution.............................................................................................................................. 17 5.2.2 Incident Resolution .............................................................................................................................. 17 5.2.3 Preventative Maintenance.................................................................................................................... 17 5.2.4 Company / Project Request.................................................................................................................. 17 5.2.5 Hardware Maintenance ....................................................................................................................... 17 5.2.6 Software Maintenance ......................................................................................................................... 17 5.2.7 Infrastructure Improvement ................................................................................................................. 18 5.2.8 Pre-Approved....................................................................................................................................... 18 5.2.9 Disaster Recovery Test......................................................................................................................... 18
5.3 LEAD TIMES .............................................................................................................................................. 19 5.3.1 Urgent Changes ................................................................................................................................... 19 5.3.2 CAB Pre-Approved Changes ............................................................................................................... 19 5.3.3 Planned Changes ................................................................................................................................. 19
5.4 OTHER CHANGE ATTRIBUTES.................................................................................................................... 20 5.4.1 Risk....................................................................................................................................................... 20 5.4.2 Impact .................................................................................................................................................. 20 5.4.3 Business ............................................................................................................................................... 20
5.4.3.1 Business - Coles Group .............................................................................................................................. 20 5.4.3.2 If the Business is Unknown ........................................................................................................................ 21
6. CHANGE MANAGEMENT – PROCESS FLOW........................................................................................ 22 6.1 CREATING THE CHANGE REQUEST............................................................................................................. 22
© 2007, Coles Group Limited Change Management Guide Page 4 of 33 Coles Group Ltd. Information Technology IS&O - Service Delivery
6.2 SERVICECENTER APPROVAL PROCESS ...................................................................................................... 22 6.3 CHANGE IMPLEMENTATION....................................................................................................................... 23
6.3.1 Problems or Incidents during Implementation .................................................................................... 23 6.3.2 Implementation Exceeding Change Window ....................................................................................... 23
6.4 CHANGE CLOSURE AND NOTIFICATION ..................................................................................................... 24 6.4.1 Change Requests Not Successfully Implemented................................................................................. 24
7. CHANGE FOCUS AND FREEZE PERIODS .............................................................................................. 25 7.1 OVERVIEW................................................................................................................................................. 25 7.2 CHANGE FOCUS......................................................................................................................................... 25
7.2.1 Focus Period Criteria.......................................................................................................................... 25 7.3 CHANGE FREEZE ....................................................................................................................................... 26
7.3.1 Freeze Period Criteria......................................................................................................................... 26 7.4 FOCUS AND FREEZE– APPROVAL PROCESS................................................................................................ 26 7.5 FOCUS AND FREEZE - APPROVERS............................................................................................................. 28
7.5.1 IT Leadership Team Members / Production Services Managers......................................................... 28 APPENDIX A: TABLE OF DEFINITIONS .................................................................................................... 29
APPENDIX B: EXTERNAL REFERENCES.................................................................................................. 31
APPENDIX C: FORMS AND TEMPLATES .................................................................................................. 32 C.1: CAB – CHANGE INCIDENT FORM.............................................................................................................. 32 C.2: CAB – CHANGE REVIEW FORM ................................................................................................................ 32 C.3: CAB – CHANGE PRE-APPROVAL FORM .................................................................................................... 32 C.4: CAB – CHANGE EXEMPTION FORM .......................................................................................................... 32
APPENDIX D: ADDITIONAL CONTACT DETAILS .................................................................................. 33 D.1: CHANGE COORDINATION........................................................................................................................... 33
© 2007, Coles Group Limited Change Management Guide Page 5 of 33 Coles Group Ltd. Information Technology IS&O - Service Delivery
1. INTRODUCTION
Change Management is the process used to review, approve and implement alterations to
the IT environment, with a view to minimising the risk of incidents and disruption to IT
services.
1.1 Objective
The objectives of the Change Management process are:
• To ensure that standard procedures and consistent methods of implementation and
approval are used across Coles IT
• To minimise the risk of unexpected incidents impacting IT services
• To ensure all Change Requests can be audited.
1.2 Intended Audience
This Change Management Guide is presented for all users of, and stakeholders, in the
Change Management Process.
© 2007, Coles Group Limited Change Management Guide Page 6 of 33 Coles Group Ltd. Information Technology IS&O - Service Delivery
2. CHANGE MANAGEMENT OVERVIEW
2.1 When to Use Change Management
The Change Management process is to be used for alterations to all IT components and
services within the production, and non-production environments.
Changes that do not require a Change Request to be raised include:
• Changes to data within a database via data entry
• Application changes in the non-production environments
2.2 Change Management & Problem / Incident Resolution
The Change Management process will commonly be used reactively to address problems
or incidents, however the need to use the process is dependent on the priority and impact
of a problem or incident.
Where an incident with significant business impact requires immediate action to restore
service, a Change Request is generally not required and the details should be recorded in
the incident record. This would usually be a Priority One or Two Incident. If however,
the incident is a priority one and requires an update to system configurations or code, a
Retrospective Change Request will be required within 24 hours of the implementation.
Where an incident does not require immediate action to resolve or restore service and the
resolution can be planned or scheduled, a Change Request should be raised. This would
usually be the case for Priority Three incidents.
For more information regarding the definitions of priorities, please view the ‘Incident
Management Process’ document, available through the following Connect site:
http://portal.cmlconnect.org/portal/wps/portal/retail_support/it/working_in_it/managing_i
t
© 2007, Coles Group Limited Change Management Guide Page 7 of 33 Coles Group Ltd. Information Technology IS&O - Service Delivery
2.3 Change Management – Exemptions
For routine changes that can be made without impacting infrastructure or application
services, it’s possible to apply for an Exemption from the Change Management Approval
Process, by seeking approval from the CAB.
Examples of Change Requests exempt from the Change Management Approval process
are available by selecting the ‘Exemptions & Preapproval Register’ from the connect site
below:
http://portal.cmlconnect.org/portal/wps/portal/retail_support/it/working_in_it/managing_i
t
For more details on how to apply for an Exemption to the Change Management Approval
process, see section, ‘5.1.4 CAB Exempt Changes’.
© 2007, Coles Group Limited Change Management Guide Page 8 of 33 Coles Group Ltd. Information Technology IS&O - Service Delivery
3. ROLES AND RESPONSIBILITIES
3.1 Change Requestor
A Change Requestor is the person requesting the change be performed. This may be a
Business representative or an IT Team Member.
3.2 Change Owner
The Change Owner is the Team Member performing the change, or performing most of
the change. The Change Owner is responsible for creating the Change Request. Where
the Change Owner and the Change Implementer differ, then both are jointly responsible
for ensuring the following:
• Creating the Change record, complete with appropriate details for
implementation, backout, timelines, and testing
• Allocating change tasks when the assistance of additional Support Teams are
required
• Ensuring all approvals are obtained prior to commencing the change
• Liaising with any System Owners or Customers to ensure the change window is
appropriate
• Escalating to the Change Coordinator and their Line Manager if any problems
occur during, or as a result of the change
• Once the Change is complete, closing the Change Request with a suitable
completion status and within 48 hours of its implementation
3.3 Line Manager
The Line Manager is the team member who has direct line management responsibility for
the Change Owner, or departmental responsibility for the IT skills area.
Line Managers are responsible for:
© 2007, Coles Group Limited Change Management Guide Page 9 of 33 Coles Group Ltd. Information Technology IS&O - Service Delivery
• Reviewing and approving all Change Requests from their team, ensuring they’re
presented clearly and accurately
• Reviewing Change Requests where a Support Team has allocated one or more
change tasks to his or her group
• Approving Change Requests where the service supported by his or her team will
be impacted by the activities of another Support Team
• Verifying all Change Requests have been tested appropriately
• Evaluating the back out plan and ensuring it is achievable and appropriate for the
scheduled window
• Ensuring any risks have been mitigated
The Line Manager may choose to delegate approval to other members of the Assignee
Group, by registering one or more Team Members as Change Approvers in
ServiceCenter.
3.4 Change Coordinator
The Change Coordinator is an IT Team Member responsible for completing quality
control of the Change Management process.
Responsibilities include:
• Confirming all fields of the Change Request are clearly stated and satisfactorily
completed
• Ensuring Change Requests meet the set criteria during Focus or Freeze periods
• Providing approval to Change Requests that meet the Change Management
guidelines
• Providing assistance to Change Owners in understanding the Change
Management process
• Coordinating the CAB approval of Change Request Templates
The Change Coordinator is also responsible for the circulation of the Change Reports.
© 2007, Coles Group Limited Change Management Guide Page 10 of 33 Coles Group Ltd. Information Technology IS&O - Service Delivery
3.5 Service Coordinator
The Service Coordinator is a Coles Group IT Team member responsible for representing
the interests of the Coles Group brands.
Responsibilities include:
• Reviewing changes and assessing the planned or potential impact to the business
functions for which they are responsible
• Working with Brand Representatives to ensure the schedule of a change is
satisfactory, and if not, work with the Brand and Change Owner to reschedule the
work
• Highlighting business concerns or issues to the Change Owner
• Communicating upcoming Change Requests to Brand Representatives to ensure
their awareness and approval
• Approve Changes Requests on behalf of the brand(s)
For a list of the Service Delivery Coordinators for each business, view, ‘IT Change
Approver Contacts’ from the following connect site:
http://portal.cmlconnect.org/portal/wps/portal/retail_support/it/working_in_it/managing_i
t
3.6 Brand Representative
A Brand Representative maybe engaged during the Change Management process to
ensure the Brand agrees to the work being performed, the schedule of activities, or
system outage if one is required.
If the Brand Representative has provided approval for a Change Request, this should be
included within the text of the Change Request, as it will streamline the approval.
The Service Coordinators can be contacted for further details about who are the relevant
Brand Representatives.
© 2007, Coles Group Limited Change Management Guide Page 11 of 33 Coles Group Ltd. Information Technology IS&O - Service Delivery
3.7 Secondary Support Team Review & Approval
In certain situations, a Change Owner will require the assistance of a Secondary Support
Team to review or approve a Change Request.
3.7.1 Reviewing Another Teams Change Request
When a Change Owner has allocated a Change Task to a secondary Support Team, the
Change Approvers within the secondary Support Team will be prompted to review the
Change Request.
ServiceCenter will generate an email notification to all Reviewers, however prior to this
the Change Owner is responsible for contacting any Support Teams assigned tasks. This
ensures any rostering issues are addressed effectively and a Team Member is allocated to
the task.
If a Change Reviewer has any concerns with the allocation of the change task, he or she
needs to raise this concern with the Change Owner.
3.7.2 Approving Another Teams Change Request
A Change Approver within a secondary Support Team will be required to approve
Change Requests, where the service supported by his or her team will be impacted by the
activities of another Support Team.
This mitigates the risk of Support Teams inadvertently impacting others, and ensures a
good understanding of the planned activities across the relevant groups.
If a Change Approver within a secondary Support Team has any concerns with the
suggested activities, he or she needs to raise this concern with the Change Owner.
© 2007, Coles Group Limited Change Management Guide Page 12 of 33 Coles Group Ltd. Information Technology IS&O - Service Delivery
4. CHANGE ADVISORY BOARD (CAB)
4.1 CAB – Overview
The role of the CAB is to ensure:
• The Change Management process is understood and consistently applied across
the Organisation
• Change Owners present their Medium and High Risk, or Medium and High
Impact Change Requests to the CAB for review and CAB approval
• Constantly question current work practices and assist with the introduction of
improved work practices
• Increase the number of successful Change Requests implemented
4.2 CAB Members
The Change Advisory Board consists of a group of Senior IT Managers.
For further details, check the members of the “IT CAB” distribution list.
4.3 CAB Meetings
The CAB has a number of fixed items on the agenda of its weekly meetings, including:
• Review breakdowns in the change process, for example unapproved Change
Requests being implemented
• Medium and High Risk, or Medium and High Impact Change Requests requiring
approval from the CAB
• Retrospective evaluation of changes implemented as a direct result of a Priority
One problem or incident
• Review urgent Change Requests that are driven by IT Projects
• Review requests for Pre-approval or Exemption to the Change Management
process
© 2007, Coles Group Limited Change Management Guide Page 13 of 33 Coles Group Ltd. Information Technology IS&O - Service Delivery
• Review requests from Support Teams for Change Request Templates.
If invited to attend the CAB meeting, to discuss the implementation of a Change Request
that resulted in an incident, it is necessary for the Change Owner to complete the ‘CAB –
Change Incident Form’, Appendix C.1.
If attending the CAB meeting to discuss the implementation of a Change Request, then
the Change Owner must complete the ‘CAB – Change Review Form’, Appendix C.2.
The Change Owner should distribute these Forms and any other relevant information
regarding the Change Request, to the distribution list, ‘IT CAB’, ahead of the meeting.
© 2007, Coles Group Limited Change Management Guide Page 14 of 33 Coles Group Ltd. Information Technology IS&O - Service Delivery
5. CHANGE CONCEPTS
5.1 Change Classification
The classification of a Change Request will be one of the following:
• Planned
• Urgent
• Retrospective
• CAB Pre-Approved
The relevant classification will be based upon the implementation timeframe, risk, the
date of Line Manager approval and whether CAB Pre-Approval has been sought.
5.1.1 Planned Changes
Planned Changes are those that do not need to be implemented urgently, and can be scheduled for implementation within the published Change Management lead times.
Change Lead times are outlined below in section 5.4.
5.1.2 Urgent Changes
Urgent Changes are those that have a clear business requirement for implementation in
the shortest possible time, and would usually have one of the following Reasons for
Change:
• Problem Resolution
• Incident Resolution
• Preventative Maintenance
• Company / Project Request
The CAB may invite a Change Requestor to the next CAB meeting to discuss why a
Change Request did not meet the standard lead times.
© 2007, Coles Group Limited Change Management Guide Page 15 of 33 Coles Group Ltd. Information Technology IS&O - Service Delivery
5.1.3 Retrospective Change Requests
If the time to schedule the implementation for a fix to a business critical incident isn’t
available, the change can be implemented without a Change Request, however a
retrospective Change Request is required where that change is:
• A system configuration
• A code change
Retrospective Change Requests must be raised no later than 24 hours following the
implementation. These types of Change Request only require Line Manager approval.
5.1.4 CAB Pre-Approved Changes
For regular changes of minimal risk that meet the criteria below, teams may request CAB
Pre-approval. CAB pre-approved changes still require a change record, but have only a
24-hour lead-time and line manager approval.
The CAB will decided on the appropriateness of Pre-Approval based on the following
criteria:
• Frequency of the Change Request, two to three times a month
• Simplicity the of Change Request
• Low or Negligible Risk
• If the implementation is, or can be automated
• If the implementation process is documented, proven and repeatable
To request CAB Pre-Approval, complete the ‘CAB - Change Pre-Approval Form’, Appendix C.4.
© 2007, Coles Group Limited Change Management Guide Page 16 of 33 Coles Group Ltd. Information Technology IS&O - Service Delivery
5.1.5 CAB Exempt Changes
For regular changes of minimal risk that meet the criteria below, teams may request CAB
Exemption. CAB exempt changes do not require a change record.
The CAB will decided on the appropriateness of CAB Exemption based on the following
criteria:
• Frequency of the Change Request, hourly or daily
• Simplicity of the Change Request, for example an administrative function within
a role
• Low or Negligible Risk
• If the implementation is, or can be automated
• If the implementation process is documented, proven and repeatable
To request CAB Exemption, complete the ‘CAB - Change Exemption Form’, Appendix
C.5.
5.1.6 Change Templates
For regularly occurring Change Requests that do not meet the requirements of a CAB
Pre-Approval or Exemption, a Change Template maybe requested.
When a Change Owner flags a Change Request as a potential Template, the Change
Owners Line Manager and CAB will review it.
If approved, the Change Owner can reuse the template for similar Change Requests in the
future.
5.2 Reason For Change
The Reason For Change is a simple explanation as to why the change is required and is
determined by the Change Owner when creating the Change Request.
© 2007, Coles Group Limited Change Management Guide Page 17 of 33 Coles Group Ltd. Information Technology IS&O - Service Delivery
5.2.1 Problem Resolution
The Problem Resolution Change Driver is to be used when a Change Request is made to
resolve an outstanding problem.
5.2.2 Incident Resolution
The Problem Resolution Change Driver is to be used when a Change Request is made to
resolve an outstanding incident.
5.2.3 Preventative Maintenance
The Preventative Maintenance Reason for Change is used for instances where action is
required to maintain the stability of an operational system or service.
It is to be used for Change Requests where the likelihood of a service interruption is
considered significant. This may include taking action to prevent the likely occurrence of
a Priority One or Two problem or incident.
5.2.4 Company / Project Request
The Project Request Reason for Change is to be utilised when a Change Request is made
at the request of a Project.
5.2.5 Hardware Maintenance
This Reason for Change is used for any scheduled hardware maintenance required to
keep hardware at Vendor supported levels.
This Reason for Change is not used to correct an immediate Hardware problem or
incident.
5.2.6 Software Maintenance
This Reason for Change is used for any scheduled software maintenance required to keep
software at Vendor supported levels.
© 2007, Coles Group Limited Change Management Guide Page 18 of 33 Coles Group Ltd. Information Technology IS&O - Service Delivery
This Reason for Change is not used to correct an immediate Software problem or
incident.
5.2.7 Infrastructure Improvement
This Reason for Change is used for Change Requests to improve service capabilities,
such as increasing bandwidth, capacity or performance.
5.2.8 Pre-Approved
This Reason for Change is to be used for regularly occurring Change Requests previously
approved by the CAB.
For more information on CAB Pre-Approved Change Requests please see section ‘5.1.4
CAB Pre-Approved Changes’
5.2.9 Disaster Recovery Test
This Reason for Change is to be used for testing of Disaster Recovery functionality and
fail over.
© 2007, Coles Group Limited Change Management Guide Page 19 of 33 Coles Group Ltd. Information Technology IS&O - Service Delivery
5.3 Lead Times
5.3.1 Urgent Changes
Urgent Change Requests do not require a lead-time. It is recommended however, that the
Change Owner allow some time to gather the relevant approvals before initiating the
Change Request.
5.3.2 CAB Pre-Approved Changes
CAB Pre-Approved Changes require one day lead time, however a pre-approved change
may require less than one day lead time, in which case it is an Urgent Pre-Approved
change.
5.3.3 Planned Changes
The following table provides a summary of the lead times required for both Planned
Impact and Non Impact Change Requests.
The Lead Time is calculated from the time the Change Owners Line Manager approves
the Change Request.
Planned Change Requests (Non Impact and Impact)
Risk Lead Time
Negligible 1 Days
Low 7 Days
Medium 14 Days
High 21 Days
Change Requests that do not meet these lead times will be considered urgent.
© 2007, Coles Group Limited Change Management Guide Page 20 of 33 Coles Group Ltd. Information Technology IS&O - Service Delivery
5.4 Other Change Attributes
5.4.1 Risk
The risk level for a Change Request indicates the potential of the Change failing or
causing an unexpected impact during its implementation. It will be categorised as
Negligible, Low, Medium or High.
The risk level is calculated automatically when creating the Change Request, by the
Change Owner’s responses to the risk analysis questions.
The risk level calculated for a change will determine the lead-time for planned changes.
5.4.2 Impact
Changes Requests are categorised as having an impact of either negligible, low, medium
or high. The category is automatically calculated while creating the Change Request,
based on the Change Owners response to questions regarding system availability.
If during the time of the Change Request a system or application would normally be
available, but due to the actions being taken it will be unavailable, even briefly, then the
responses to the relevant availability questions should be no.
5.4.3 Business
The Change Originator should include in the Change Request all businesses that will be,
or could be affected as part of the Change.
5.4.3.1 Business - Coles Group
The Coles Group business should be selected for Change Requests affecting any Shared
Service function provided across the organisation, such as Finance or Human Resources.
© 2007, Coles Group Limited Change Management Guide Page 21 of 33 Coles Group Ltd. Information Technology IS&O - Service Delivery
Change Requests may also be considered Coles Group, if a change is being made on an
IT system that doesn't have any Users. An example of this would be the installation of a
new server that isn't yet being used.
5.4.3.2 If the Business is Unknown
The Change Owner is responsible for ascertaining the businesses that may be affected by
their change. If the owner is unsure which businesses may be affected, they should seek
clarification from the Line Manager, the Change Coordinator, or Service Delivery team.
If it is unclear if a business may be affected by the change, then that business should be
included in the change.
This ensures businesses are aware of changes, and reduces the risk of a Change Request
unexpectedly impacting businesses, other than those listed in the Change Request.
© 2007, Coles Group Limited Change Management Guide Page 22 of 33 Coles Group Ltd. Information Technology IS&O - Service Delivery
6. CHANGE MANAGEMENT – PROCESS FLOW
6.1 Creating the Change Request
As some of the Approvers may not have a thorough Technical understanding of the
change, Change Owners should take care to clearly and concisely describe the change
without being unnecessarily technical.
6.2 ServiceCenter Approval Process
Approvals occur in the following order:
• Line Manager
• Secondary Support Team Leader
• Change Coordinator
• Service Coordinator
The need for any additional approvals is dependent on the Change Request classification,
as well as the risk and impact.
Change Requests that are considered to be Medium or High Impact will require the
approval of the CAB, while Change Requests during the Focus or Freeze periods are
subject to increased scrutiny and approval, as documented in section, ‘7.4 Focus and
Freeze – Approval Process’.
All approvals must be recorded within the change record. This can be performed by using
the ‘Approval’ function of ServiceCenter, or by forwarding an email to the ‘IT Change
Co-ordinator’ mailbox with the relevant approval.
Approvers may deny a change if they have concerns with the Change Request. When a
Change Request is denied an email will be sent to the Change Owner with an explanation
as to why it was disapproved. The Change Owner is then responsible to discuss the
concern with the approver that denied the Change Request, so that it may again be
reviewed and submitted for approval.
© 2007, Coles Group Limited Change Management Guide Page 23 of 33 Coles Group Ltd. Information Technology IS&O - Service Delivery
6.3 Change Implementation
Before implementing a Change Request it is the Change Owners responsibility to ensure
the Change Request is fully approved, and all due diligence has been taken to maximise
the success of the implementation.
If it’s identified that the system is unstable, being used, or Team Members performing the
implantation are unavailable, then the Change Request must be withdrawn and
rescheduled to a later date.
6.3.1 Problems or Incidents during Implementation
If an unexpected problem or incident occurs during implementation, the first course of
action should be to perform a backout.
If backout is not possible, then the mode of operation will alter from change management
to problem management, and a ServiceCenter problem record logged. At this point, the
Change Owner should escalate to their Line Manager and the Change Coordinator.
For the contact details of the Change Coordinator, see ‘Change Coordination’, Appendix
D.1.
6.3.2 Implementation Exceeding Change Window
If during the implementation of a Change Request it becomes apparent the scheduled
change window will be exceeded, then the Change Owner must:
• Confirm if any additional impact will occur if the implementation continues
• If a further impact may occur, take steps to commence a back out of the Change
Request
• Notify the Change Coordinator of the situation and the actions being taken
© 2007, Coles Group Limited Change Management Guide Page 24 of 33 Coles Group Ltd. Information Technology IS&O - Service Delivery
If the impact in extending the Change Window is minimal, then the Change Coordinator
will contact the relevant Service Coordinators and ensure their approval for continuing
the implementation of the Change Request.
For the contact details of the Change Coordinator, see ‘Change Coordination’, Appendix
D.1.
6.4 Change Closure and Notification
Once the implementation of a Change Request is complete, it is an audit requirement for
the Change Owner to update the status and close the Change Request within 48 hours of
its scheduled completion.
6.4.1 Change Requests Not Successfully Implemented
If the Change Request was not successfully implemented, then the Change Owner must
close the Change Request by choosing the relevant ‘Closure Status’, and provide a
description of why the Change Request did not go ahead as planned, including a brief
comment on what action is to now be taken.
© 2007, Coles Group Limited Change Management Guide Page 25 of 33 Coles Group Ltd. Information Technology IS&O - Service Delivery
7. CHANGE FOCUS AND FREEZE PERIODS
7.1 Overview
Change Focus and Change Freeze Periods are scheduled to increase the stability of IT
environments and maintain service levels during critical trading periods.
For the dates of the Focus and Freeze periods, select ‘Focus & Freeze Dates & Approvals
08/09’ from the following Connect site:
http://portal.cmlconnect.org/portal/wps/portal/retail_support/it/working_in_it/managing_i
t
7.2 Change Focus
Change Focus periods are scheduled for busy trading periods and business sensitive
times.
7.2.1 Focus Period Criteria
Only changes that meet the following criteria will be approved during Focus Periods:
• Single Business: Where the Change Request has been initiated and approved by
a business and the Change risk is isolated to that business (excluding IT)
• Incident Resolution: Change Requests that are required to resolve an open
priority one or two incident
• Problem Resolution: Change Requests that are required to resolve a known error
• Preventative Maintenance: Change Requests required to prevent potential
problems, or to ensure that the integrity of services is maintained throughout the
Focus Period
• Change Requests to Non-Production environments, including Test and
Development systems
• CAB Pre-Approved Change Requests
© 2007, Coles Group Limited Change Management Guide Page 26 of 33 Coles Group Ltd. Information Technology IS&O - Service Delivery
7.3 Change Freeze
Change Freeze periods are scheduled for critical trading periods and business critical
times.
Changes that do not meet the specified criteria are actively discouraged during Freeze
periods.
7.3.1 Freeze Period Criteria
During the Change Freeze Period, Change Requests that meet the following criteria are
permitted to proceed:
• Incident Resolution: Change Requests that are required to resolve an open
priority one or two incident
• Problem Resolution: Change Requests that are required to resolve a known error
• Preventative Maintenance: Change Requests required to prevent potential
problems, or to ensure that the integrity of services is maintained throughout the
Freeze Period
• Change Requests to Non-Production environments, including Test and
Development systems
7.4 Focus and Freeze– Approval Process
Change Requests that do not meet the above criteria will need extra approvals in order to
proceed, these include:
• A member of the IT Leadership team, or their delegate, within the Change
Owners line of reporting structure
• The Production Services Manager for the affected Business(es), or a delegate of
the Production Services Manager
© 2007, Coles Group Limited Change Management Guide Page 27 of 33 Coles Group Ltd. Information Technology IS&O - Service Delivery
The Change Owner should either ‘paste’ these approvals into the Change Request, or
forward an email to the ‘IT Change Co-ordinator’ mailbox displaying the Change
Request Number, and its approval.
If the Change Owners Line Manager provides approval of the Change Request prior to
approval being given by the relevant IT Leadership Team Member (or delegate) or
Production Services Manager (or delegate), then the Change Coordinator will deny the
Change Request.
Once the additional approvals have been received, the normal approval process is
followed.
For more information on the approval process, see section, ‘6.2, ServiceCenter Approval
Process’.
© 2007, Coles Group Limited Change Management Guide Page 28 of 33 Coles Group Ltd. Information Technology IS&O - Service Delivery
7.5 Focus and Freeze - Approvers
7.5.1 IT Leadership Team Members / Production Services Managers
A list of members of the IT Leadership Team and the Production Services Managers is contained below:
Coles Liquor IT Manager Phil Fisher
Merchandise Systems IT Manager John Kelvie
General Manager Infrastructure
Services and Operations
Ken
Harmsworth
Coles Express IT Manager Mark Freeman
Logistics Systems Manager Paolo Azzali
IT Manager Shared Services Terry Court
Program Delivery Manager Helen Brunt
PMO Manager Sally Duncan
IT Leadership Team
IT Manager Carole Ackland
Supermarkets & Coles Liquor Group David Hooley Production Services Managers
Supply Chain, Coles Express &
Retail Support
Lindsay Watson
For a Change Owner to locate the name of the relevant IT Leadership Team Member, Production Services Manager, or any of their delegates, please view the Organisation Chart from the following Connect site:
http://portal.cmlconnect.org/portal/wps/portal/HRonline/content?WCM_GLOBAL_CONTEXT=/CML+Connect/HR+online/Indexes/Organisational+Charts/Organisational+Charts
If still unsure, please speak to your Line Manager.
© 2007, Coles Group Limited Change Management Guide Page 29 of 33 Coles Group Ltd. Information Technology IS&O - Service Delivery
APPENDIX A: TABLE OF DEFINITIONS
The following terms, acronyms and abbreviations are referred to in this document.
Table 1 - Table of Definitions
Term Definition
CGL Coles Group Ltd
Production A critical IT environment required for the delivery of Business and IT
Operations, including redundancy
Non-Production A non-critical IT environment typically used for Development and
Testing. These systems are isolated from Production and provide no
operational functionality to the Business or IT
Assignee Group Specialized skill groups that work on incidents, problems and raise
Changes Requests
Incident An event that isn’t part of the standard system operation
Problems An unknown underlying cause of one or more incidents
ServiceCenter The tool used for the recording of all incidents, problems and Change
Requests
Change Request A documented account of planned changes within, or affecting an IT
environment.
Retrospective Change
Request Raised within 24 hours of implementing a fix for a business critical
incident. Retrospective Change Requests are only required for fixes
that involved updates to system configurations or code
Change Tasks Change Tasks are allocated to additional Support Teams when their
assistance is required
CAB Change Advisory Board, made up of senior IT Managers who provide
review and approval of certain Change Requests
Approval Acceptance of a Change Request
Pre-Approval Granted by the CAB for recurring Change Requests that meet a set
criteria. Pre-Approved changes require a Change Request, but have
a reduced lead time
Exemption Granted by the CAB for regularly occurring Change Requests that
meet a set criteria. A ServiceCenter Change Request is not required
when Exemption is received
© 2007, Coles Group Limited Change Management Guide Page 30 of 33 Coles Group Ltd. Information Technology IS&O - Service Delivery
Term Definition
Change Template Change Templates can be requested to make the process of raising
Change Requests for regularly occurring work more efficient
Change Classification The urgency of the Change Request, planned, urgent or Pre-
Approved
Reason for Change The reason for the Change Request, for example Problem
Resolution, Business Request, Project Request etc.
Lead Times The period of time required for a Change Request to be reviewed
and approved before being implemented
Impact A description of the effect the implementation will have on the
environment
Urgent An urgent Change Request that must be implemented as soon as
possible typically to resolve a high priority incident or problem
Planned A non urgent Change Request that can be implemented based on
the published lead times
Back Out The action taken to return a system to its pre-implementation state
Change Window The period of time allocated for the Change Request to be
implemented
Focus Period Change Focus periods are scheduled for busy trading periods and
business sensitive times. During Focus periods certain Change
Requests are actively discouraged while others require additional
review and approval
Freeze Period Change Freeze periods are scheduled for busy trading periods and
business sensitive times. During Freeze periods certain Change
Requests are actively discouraged while others require additional
review and approval
Risk Level An indication of the potential risk in implementing the Change
Deny The action taken when an Approver disapproves a Change Request
© 2007, Coles Group Limited Change Management Guide Page 31 of 33 Coles Group Ltd. Information Technology IS&O - Service Delivery
APPENDIX B: EXTERNAL REFERENCES
Document Title Source Location
IT Service Delivery – Connect Home Page Home > Retail Support > IT > Managing IT
Focus Calendar Home > Retail Support > IT > Managing IT
Incident / Problem Management Guide Home > Retail Support > IT > Managing IT
Urgent Change Procedures Home > Retail Support > IT > Managing IT
Change Management Risk Assessment Table \\Goanna\Grpdata\Service Delivery\Change Co-
ordination\New Change Process\New Change
Process\Risk Assessment
Change Approval Contacts \\Goanna\Grpdata\IT IS&O Change co-
ordination\Change Approval Contacts.htm
© 2007, Coles Group Limited Change Management Guide Page 32 of 33 Coles Group Ltd. Information Technology IS&O - Service Delivery
APPENDIX C: FORMS AND TEMPLATES
C.1: CAB – Change Incident Form
CAB - Change Incident Form
C.2: CAB – Change Review Form
CAB Change Review
Form
C.3: CAB – Change Pre-Approval Form
C.4: CAB – Change Exemption Form
CAB - Change Exemption Form
The CAB Form’s are available via the following page of the Portal:
http://portal.cmlconnect.org/portal/wps/portal/retail_support/it/working_in_it/managing_it
CAB Change Pre Approval Form
© 2007, Coles Group Limited Change Management Guide Page 33 of 33 Coles Group Ltd. Information Technology IS&O - Service Delivery
APPENDIX D: ADDITIONAL CONTACT DETAILS
D.1: Change Coordination
The on site hours of coverage for the Change Coordinor is 08:00 to 16:30, Monday to Friday.
The Change Coordination contact details are:
• Email: IT Change Co-ordinator
• Business Hours: 8544 7461
• After Hours: 0408 569 194