challenges in design and construction of deep … in design and...challenges in design and...
TRANSCRIPT
Challenges in Design and Construction of Deep Excavation With Case Studies - KVMRT in KL Limestone
Gue See SewG&P Professionals Sdn Bhd
www.gnpgroup.com.my
20 July 2016
CONTENTS
� INTRODUCTION� SOIL PARAMETERS� NUMERICAL ANALYSES� CASE HISTORIES
� 3 Underground Stations for KVMRT� Circular Shaft for Launching of TBM� Hydraulic Failure @ Penang
� CONCLUSIONS
INTRODUCTION
� Deep basement construction� Urban areas for parking space� Infrastructures, e.g. KVMRT
� Risk associated with deep basement construction high!
SOIL PARAMETERS
� Some important soil parameters related to retaining wall and support system design:�Shear strength parameters (su, φ’ & c’)�Soil permeability�Soil stiffness
SOIL PARAMETERS
� Soil stiffness� Important parameters for retaining wall design
BUT difficult to obtain reliably� In Malaysia, sometimes based on empirical
correlations�Laboratory tests unreliable and values
obtained significantly smaller than appropriate values for retaining wall design
�Designer should be aware of small-strainnature of retaining wall design
SOIL PARAMETERS
� Soil stiffness�Seismic tests or seismic piezocone appears
promising�Basis of empirical correlations should be
understood – e.g. local soil conditions, constitutive model used, etc.
�Example, correlations in Kenny Hill formation using hardening soil model of PLAXIS software
Soil Type Maximum small-strain shear modulus, G0 (kPa)
Soft clays 2,750 to 13,750
Firm clays 6,900 to 34,500
Silty sands 27,600 to 138,000
Dense sands and gravels 69,000 to 345,000
Typical values of maximum small-strain shear modulu s
FINITE ELEMENT ANALYSIS
� Some important considerations in FEM:�Locations of the boundaries of the problem�Details of mesh�Modelling of stages of construction�Modelling of interfaces�Use of suitable constitutive soil model�Use of appropriate soil parameters, especially
empirical parameters
CONSTITUTIVE SOIL MODELS
� Various constitutive soil models, e.g. Mohr-Coulomb, Cam Clay, Hardening Soil, Soft Soil, etc.�Proper understanding and limitations of
each model important!� Incorrect use of soil models in Nicoll Highway!
Berjaya Times Square
� Hardening Soil Model of PLAXIS able to model the problem sufficiently accurate
� From FEM back-analysis, the correlations between soil stiffness (E’) and SPT ‘N’ as follows:�E’ = 2000*SPT‘N’(kN/m 2)�E’ur = 3*E’ = 6000*SPT’N’(kN/m 2)
To be developed based on specific project/site requ irements depending on factors such as risk to public safety, nature of
the works, site control measures, etc.
MONITORING TRIGGER LEVELS� Example for inclinometer:
� Alert : 0.8*Maximum predicted lateral movement using moderately conservative parameters
� Action : 0.9*Maximum predicted lateral movement using moderately conservative parameters
� Alarm : 1.0*Maximum predicted lateral movement using moderately conservative parameters
Berjaya Times Square
� Excavated depth24.5m - 28.5m (6-level basement)
� Retaining wall1.2m thick diaphragm walls
� Support systemPrestressed Ground Anchors
-10 0 10 20 30 40Wall Relative Lateral Displacement (mm)
-50
-40
-30
-20
-10
0
Dep
th (m
)
Measured ProfileFEM Back Analysed
Excavate to R.L.35.0m
Stage 1
-10 0 10 20 30 40Wall Relative Lateral Displacement (mm)
-50
-40
-30
-20
-10
0
Dep
th (m
)
Excavate to R.L.31.0m
Stage 2
-10 0 10 20 30 40Wall Relative Lateral Displacement (mm)
-50
-40
-30
-20
-10
0
Dep
th (m
)
Stage 3
Excavate to R.L.27.0m
-10 0 10 20 30 40Wall Relative Lateral Displacement (mm)
-50
-40
-30
-20
-10
0
Dep
th (m
)
Stage 4
Excavate to R.L.22.5m
-10 0 10 20 30 40Wall Relative Lateral Displacement (mm)
-50
-40
-30
-20
-10
0
Dep
th (m
)
Stage 4
Excavate to R.L.18.5m
-10 0 10 20 30 40Wall Relative Lateral Displacement (mm)
-50
-40
-30
-20
-10
0
Dep
th (m
)
Stage 6
Excavate to R.L.16.7m
WALL A
Berjaya Times Square
� Hardening Soil Model of PLAXIS able to model the problem sufficiently accurate
� From FEM back-analysis, the correlations between soil stiffness (E’) and SPT ‘N’ as follows:�E’ = 2000*SPT‘N’(kN/m 2)�E’ur = 3*E’ = 6000*SPT’N’(kN/m 2)
Case History 1 :Deep Excavation for Three (3) Underground Stations for KVMRT
– Sungai Buloh to Kajang Line (Line 1)
Geology of Kuala Lumpur
All three underground stations in KL Limestone Formation (with Karstic Features)
Karstic Features of Kuala Lumpur Limestone Formation
Valley in the bedrock
Cavity in the Bedrock Highly fractured bedrock
Limestone Pinnacle
Typical Excavation Section for Underground Station
(Note: Rock slope strengthening indicated is provisional only. Actual locations and extent of rock slope strengthening are determined after geological mapping works and kinematic analysis).
Subsoil Bedrock
Material type Silty Sand Limestone
Averagedepth
5m 5m below
Unit weight 18 kN/m3 24 kN/m3
SPT N 2 - 4 -RQD - 0 – 100%AverageUCS
- 50 MPa
Effectiveshearstrength
c’= 1 kPaɸ’= 29º
c’= 400 kPaɸ’= 32º
ElasticModulus,E' (kPa)
4000 -12000
1.0E6 –1.0E7
Hydraulicconductivity,k
1.0E-5 m/s
0 – 31 Lugeon
Conchrane Underground Station
Description PropertiesWorking loads (kN) 212; 424; 636; 848No. of strand 2; 4; 6; 8Strand diameter 15.24mmBreaking load 260.7 kNFactor of safety 1.6Strand U-turn radius 47.5mmReduction factor 0.65Drill hole diameter 175mmAllowable bond stress
400 kPa (limestone)
Free length Varies (until bedrock)
Bond length (m) 3; 3; 4.5; 6
Temporary Ground Anchor Support System
Original Retaining Wall (Insufficient Depth)
Thickness of Clay insufficient to resist Water Uplift Pressure
Water Uplift Pressure
Original Retaining Wall (Insufficient Depth)
Water flowed through cracks in the Silty Clay
layer
Water Uplift Pressure
Original Retaining Wall (Insufficient Depth)
Water Ponding in the Pit
Water Uplift Pressure
Lowering of ground water level � Causing settlement to surrounding ground
Groundwater Changes
0 5 10 15 20 25
Distance from Excavation / Depth of Excavation
-6
-4
-2
0
2
4
Red
uce
d L
eve
l (m
CD
)
Ground water level from Piezometer(Days from the date of investigation)
(28 days)
(49 days)
(84 days)
Ground Level
0 50 100 150 200 250 300
Distance from Excavation (m)
PZ 4PZ 5
PZ 1PZ 2
PZ 3
PZ 8
PZ 7
Estimated Original Groundwater Table
Ground level
Additional SettlementExcavation
Side Retained Side
Earlier settlement before investigation not available.
0 2 4 6 8 10 12
Distance from Excavation / Depth of Excavation
-30
-25
-20
-15
-10
-5
0
Additi
onal S
ettle
ment (m
m)
Settlement ProfileLine no. (Days from the date of investigation)
Line 3 (27 days)
Line 3 (62 days)
Line 4 (27 days)
Line 4 (62 days)
Line 5 (27 days)
Line 5 (62 days)
0 20 40 60 80 100 120 140
Distance from Excavation (m)
HYDRAULIC FAILURE
� Base instability caused by piping�Seepage due to high groundwater level
� Available methods�Terzaghi’s method�Critical hydraulic gradient method
HYDRAULIC FAILURE
� Terzaghi’s method recommended�Based on latest research by Tanaka &
Verruijt (1999)�Factor of safety required – 1.2 to 1.5
HYDRAULIC FAILURE
� Heaving due to artesian pressure
�Factor of safety – 1.0 to 1.2�Smaller FOS sufficient as it did not
consider shear strength or adhesion strength of the ground and retaining wall
CONCLUSIONS
� Parameters & calibrations� Constitutive models� Impact of lowering water table & Mitigation
measures
Successful deep excavation depends on:
ACKNOWLEDGEMENTThe input from the following team members for KVMRT and in this presentation are very much appreciated:-
- Ir. TAN Yean Chin- Ir. CHOW Chee Meng- Ir. KOO Kuan Seng- TIONG Chiong Ngu- Ir. Dr. GUE Chang Shin
G&P Professionals Sdn Bhd