ch2mhill study

Upload: william-mook

Post on 30-May-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/14/2019 CH2MHill Study

    1/71

  • 8/14/2019 CH2MHill Study

    2/71

    40111 i July 2, 2004

    TABLE OF CONTENTS

    Section Page

    1 Executive Summary................................................................ 1-1

    2 Project Goals and Scope of Work........................................... 2-1

    3 Product Description................................................................. 3-1

    4 Assumptions and Design Considerations................................ 4-1Capacity Requirements .................................................. 4-1Materials......................................................................... 4-1Process Alternatives Considered.................................... 4-1Location of Manufacturing Facility............................... 4-2

    Potential Locations for Panel Arrays ............................. 4-2Cost Basis....................................................................... 4-2

    5 Concept Design Review.......................................................... 5-1General........................................................................... 5-1Equipment Requirements............................................... 5-1Typical Cell.................................................................... 5-2Area Requirements......................................................... 5-3Facility Block Layout..................................................... 5-4Material Flow................................................................. 5-6Raw Materials Handling................................................. 5-6Finished Good Handling................................................. 5-6

    Receiving........................................................................ 5-7Shipping.......................................................................... 5-8Storage............................................................................ 5-8Utilities........................................................................... 5-9Building Shell................................................................ 5-17Office Area, Support Space, and Amenities ................. 5-17

    6 Production Ramp Up, Organization, and Manpower.............. 6-1Proof of Concept ............................................................ 6-1Product Design............................................................... 6-1Process Design............................................................... 6-1Production Rate.............................................................. 6-1Production Ramp Up...................................................... 6-2Organization Recommendations.................................... 6-3Staffing Ramp Up.......................................................... 6-11Training Recommendations .......................................... 6-13

    7 Milestone Schedule................................................................. 7-1

    Page 41 of 159

  • 8/14/2019 CH2MHill Study

    3/71

    40111 ii July 2, 2004

    8 ROM Cost Estimate................................................................ 8-1Facility............................................................................ 8-1Process Equipment ......................................................... 8-1Operating Costs.............................................................. 8-1

    Summary........................................................................ 8-29 Analysis and Preliminary Recommendations ......................... 9-1

    General........................................................................... 9-1Areas/Issues of Concern................................................. 9-1

    APPENDIX

    Appendix 1.0PV Circuit/Assembly ConceptBus Bar Screen Printing

    PV Application

    Appendix 2.0Production CapacityEquipmentUtilitiesOpen IssuesPlastics CostLabor Cost Estimate-Manufacturing OperationsSimple Cost Summary

    Appendix 3.0Sheet ModuleTypical CellBlock Layout BaselineBlock Layout Option

    Appendix 4.0Master Plan Building

    Appendix 5.0Estimating Accuracy Curve

    Appendix 6.0Materials Comparison

    Appendix 7.0Planning for Success in Transitioning New Technologies into Economical Full-ScaleProduction

    Page 42 of 159

  • 8/14/2019 CH2MHill Study

    4/71

    40111 1 - 1 July 2, 2004

    Section 1

    EXECUTIVE SUMMARY

    Mk Industries, Inc. is proposing to construct solar power plants that produce cleanelectricity at a cost lower than any other power generation method, using a series ofproprietary technology and process innovations. The key element of Mks low energycosts is extreme concentration of sunlight onto photovoltaic generators designed to operateat extraordinary light intensities. The generator panel is comprised of an array ofconcentrating solar optics, each housing an advanced PV cell. To put its technology intolarge scale production, Mk desires to complete the design of the manufacturing process andestablish the production tool set needed to produce the generator panel.

    Mk has commissioned IDC to assist in refining the conceptual product characteristics,determine manufacturing resources, and develop a facility concept to commercially producethe generator panels. To accomplish these objectives, IDC has teamed with its sister

    company, Lockwood Greene.

    This report identifies preliminary conceptual designs for the following:

    Product and manufacturing process.

    Manufacturing facility.

    Site plan, based on the Millennium Technology Park in Lawrence County,Pennsylvania.

    Organizational and manpower requirements.

    Milestone project implementation schedule.

    Rough order of magnitude (ROM) opinion of probable construction andmanufacturing equipment costs.

    The concept developed for the panel is a 4- by 8-foot module composed of three plasticsheets that when formed, are bonded together to form the optical concentrator containing thePV cell. The finished module will be self-supporting and stackable. Throughout thedevelopment of the module, multiple design considerations were evaluated and assumptionsmade. Decisions made are based on experience and engineering judgement with cost alwaysa primary influence.

    In order to establish the manufacturability of the conceptual product design, a work cell wasdeveloped to meet the production output targets. The work cell, consisting of a typicalequipment set, can then be duplicated to achieve full-scale high volume production of97GW/year. The space and utility requirements for the manufacturing equipment were usedto determine the overall area and utilities required for the facility. The arrangement of thefacility accounts for support areas as typically necessary for general manufacturing. A site

    Page 43 of 159

  • 8/14/2019 CH2MHill Study

    5/71

    40111 1 - 2 July 2, 2004

    plan and architectural rendering is included, as well as preliminary facility support systemschematics.

    The report addresses organizational staff, manpower, workforce training, transportation,

    permitting, and ramp-up issues. A conceptual schedule and rough order of magnitudeopinion of cost is also included for the purpose of establishing a realistic timeline and budgetfor the project. From an economic development viewpoint, in addition to the new jobscreated by Mk, this project will have a significant multiplier effect on job creation,including the possibility that the PV cell manufacturer would build a fab adjacent to the Mkplant.

    Key findings are summarized as follows:

    Product and manufacturing process: The conceptual process described in thisreport is feasible, yet challenges remain to prove the manufacturing processand achieve the ramp-up to meet the large production volumes targeted.

    Manufacturing facility: The building is relatively simple in comparison to theprocess challenges. A crucial and somewhat ironic discovery is very highpower consumption resulting from the quantity and characteristics of themanufacturing equipment.

    Organizational and manpower requirements: Staffing levels at fullproductions are projected to be 659. This includes a corporate staff of 105and manufacturing staff of 555 spread over three shifts. While the staff rampshould be achievable, establishing an effectual organizational structure,attracting a competent management team, and developing effective training

    programs for manufacturing staff are critical to the success of the enterprise.

    Milestone project implementation schedule: The conceptual schedule showsthe first work cell, as a pilot line, going into full scale productionapproximately 2 years after project initiation. This could be accelerated byphasing the building construction to allow an earlier start for installation ofthe pilot line.

    (ROM) opinion of probable construction and manufacturing equipment costs:Total project capital costs are projected at $1.24 billion. For construction of afacility capable of supporting the full-scale production volumes, cost isprojected at $416 million, with manufacturing equipment comprising the

    balance of $830 million.

    Page 44 of 159

  • 8/14/2019 CH2MHill Study

    6/71

    40111 2 - 1 July 2, 2004

    Section 2

    PROJECT GOALS AND SCOPE OF WORK

    Mk Industries LLC has developed solar energy conversion technology to cost effectivelyproduce electricity. Mk Industries has successfully tested this product concept and nowneeds to quickly refine product characteristics, determine manufacturing resources anddevelop a facility concept to commercially produce these products.

    As a first step in this process, IDC has undertaken the effort of developing a preliminaryconcept design to refine the following issues:

    Product and Manufacturing Process

    Manufacturing Facility

    Site Plan

    Organizational and Manpower Requirements

    Milestone Project Implementation Schedule

    Rough-Order-of-Magnitude (ROM) Cost Estimate

    In order to accomplish this, IDC has completed the following services:

    Analyzed product design for manufacturability.

    Developed a concept for the manufacturing process concept based onLockwood Greenes recommended product concept and forecasted capacityrequirements.

    Determined site requirements size, containment, road access, rail accessoptions, traffic management, and parking.

    Determined what support functions will be required, approximate laborrequirements, and developed a recommended organizational structure for thestartup operations.

    Developed a milestone implementation schedule, including production and

    manpower ramp up.

    Developed a ROM cost estimate and capital spending schedule.

    Estimated up-front equipment costs, ongoing labor cost, and transportationcosts for manufacturing operations.

    Page 45 of 159

  • 8/14/2019 CH2MHill Study

    7/71

    40111 3 - 1 July 2, 2004

    Section 3

    PRODUCT DESCRIPTION

    Mk Industries LLC has developed an environmentally friendly product that will providelow cost electricity through the conversion of solar energy. This process is achieved byfocusing sunlight through an optical concentrator using a water-filled vessel and a clear lensarrangement that provides optimum internal reflection. This Compound ParabolicConcentrator (CPC) configuration captures incident solar radiation over a wide angle andconcentrates the light onto a photovoltaic cell (PV). The PV cells, designed to absorbvirtually the entire spectral distribution of solar energy, converts the solar energy intoelectrical energy. The water-filled vessels will be incorporated into a series of panels thatare arrayed over a tract of land and wired to strategically placed batteries that will store theelectrical energy. This innovative approach for the conversion of solar energy will enablethe Mk product to produce electricity with significantly higher efficiency than haspreviously been made commercially available.

    The basic product concept is reflected in the following schematic (a larger illustration isincluded in Appendix):

    Sheet Module Concept

    3 Piece Approach

    TOP BOTTOMPV

    Wiring

    Sealer/weld

    Anchor Tab

    Legend

    General Process Steps(1) Hot Press Mold the top (better precision for lenses).

    (2) Hot Press Mold middle (punch hole) and bottom (add dimple).(3) PV install/wiring on bottom (screen print, filament wiring).

    (4) Ultrasonic weld top to middle.(5) Fill CPC assembly (upside-down, submersion).

    (6) Insert and chemically seal CPC assembly to bottom.(7) Flash test.(8) Stack to bundles and load to trailer.

    submersion fillGeneral Equipment Set(1) Hot Press Molders

    (2) Stringers (screen print? wiring?)

    (3) Ultrasonic Welders(4) Fillers(5) Chemcial Sealers

    (6) Flash Testers(7) Stackers

    (8) Conveyor and buffers(9) Fork Lifts (loading)

    MIDDLE

    COMPLETE

    Each solar module assembly is 4 feet wide by 8 feet long by approximately 2 inches thickand is comprised of 4,697 water vessels that are 1 inch in diameter and 1.5 inches tall. Eachwater vessel contains a lens that is able to capture sunlight from angles exceeding 60 degreesfrom the vertical. This design eliminates the need to incorporate a mechanical tracking

    Page 46 of 159

  • 8/14/2019 CH2MHill Study

    8/71

    40111 3 - 2 July 2, 2004

    device to follow the path of the sun for maximum energy production. The remainingcontour of the vessel is designed to direct and concentrate the light that enters the lens to thephotovoltaic cell positioned at the bottom of the vessel. The resulting concentration of solarradiation substantially reduces the required area of each PV cell. In this case, a PV cell of

    0.014-inch diameter produces 0.2 Wp. A typical terrestrial solar panel requires an area of 3to 4 in2 to provide this level of power. Each module assembly will hold a total of 3.99gallons or 33.3 pounds of water.

    The module will be assembled from three plastic panels that are first produced in sheet formand then contoured through a thermal forming process to form the vessels and supportsystem. The top and middle panels will be produced from clear PET (PolyethyleneTerephthalate) and, when thermally bonded together, will form the lenses and water vessels.This assembly will then be passed through a submersion tank where the vessels will be filledwith water.

    The bottom panel will be produced from an opaque plastic such as ABS or PVC. The wirecircuitry and photovoltaic cells will be applied to the bottom panel through a printingprocess. Once assembled, the bottom panel will be chemically bonded to the top/middlepanel assembly and provide the watertight seal for the vessels.

    The contour of the finished assembly will enable each module to be self-supporting and willallow the modules to be stacked for shipping. The module will also incorporate lugs forsecuring the assembly to the ground. These lugs will double as shipping aids to facilitatepanel nesting.

    Page 47 of 159

  • 8/14/2019 CH2MHill Study

    9/71

    40111 4 - 1 July 2, 2004

    Section 4

    ASSUMPTIONS AND DESIGN CONSIDERATIONS

    CAPACITY REQUIREMENTS

    A planning model was developed to capture product assumptions, including expected outputper module and production requirements to meet specific production targets. The appendixcontains the planning model in its entirety.

    To minimize the amount of water needed for each module assembly, a concentrator size of1-inch diameter and 1.5-inches tall was selected. This results in a water volume for eachmodule of 3.99 gallons or 33.3 pounds. With the photovoltaic cell area per concentratorfixed at 0.00016 inch2 and 4,697 concentrators per module, this results in a power output of952 watts per module peak. Obtaining the target production of 97 GW per year requires aproduction rate of 11,893 modules per hour as shown below.

    The following recaps the production rates required to meet the 3 output targets:

    Output Target >>> 5 GW/yr 30 GW/yr 97 GW/yr

    Production Rate(modules per hour)

    613 3,678 11,893

    MATERIALS

    Clear, UV stabilized, PET (Polyethylene Terephthalate) was chosen for the top and middle

    panel due to its clarity, formability, availability and relative low cost. The bottom panel willbe produced from PVC or ABS to add rigidity to the final module to support the weight ofthe water and enable stacking of the modules for shipping. Boeing will supply thephotovoltaic cells that are installed onto the lower panel of the module. At the final solarcollection site, the array of modules will be wired to batteries that will collect and store theelectrical energy. It is anticipated that these batteries will be shipped from the batterysupplier directly to the solar collection site.

    PROCESS ALTERNATIVES CONSIDERED

    Initial geometries for the light concentrator were in a range of 4 inches to 8 inches in height,resulting in a water weight of 70 pounds to 140 pounds per 4-foot by 8-foot module. This

    weight was deemed too great to allow economical shipment. The geometry of theconcentrator was reduced to a 1.5-inch height (and corresponding 1-inch diameter lens) toprovide a more reasonable water weight of 33 pounds per 4-foot by 8-foot module. Basedon the revised geometries, the following processes were considered:

    Page 48 of 159

  • 8/14/2019 CH2MHill Study

    10/71

    40111 4 - 2 July 2, 2004

    Blow Molding:

    The original product concept was based on blow molding PET bottles, utilizing a cap for thePV attachment and wiring, and another structure to support and contain the bottles. Bottle

    blow molding rates were calculated to meet the production target of 400,000 acres ofcoverage in 5 years. To meet this production rate, approximately 1.2 billion bottles(1.5-inch height, 1-inch diameter) are required per day. Based on initial feedback frompeople knowledgeable in mass production blow molding, this quantity of bottles is notrealistically achievable.

    Sheet Concept:

    Several sheet concepts were developed to meet the geometric requirements of the productand achieve a high throughput. The 3-piece approach outlined previously was selected asthe baseline approach for this study based on its adaptability to molding, ease of filling, andsurface on which to mount and wire the PV cells. Initially "traditional wiring" of the PVs

    was considered (such as used in the microelectronics industry for wire bonding die prior topackaging). An assessment of the sheer number of cells to be wired deemed this approachunpractical (4700 PV cells per module, or 56 million PV cells per hour to meet the 97GW/yr target output). A screen-printing and poly-soldering approach was assumed for thebaseline concept based on its potential to meet the required throughput. It is acknowledgedthat many technological hurdles need to be addressed in order to make the screen-printingapproach viable.

    LOCATION OF MANUFACTURING FACILITY

    The proposed location for the Mk Industries solar panel fabrication plant is on a site in

    Neshannock Township, Lawrence County, Pennsylvania. The site is called MillenniumTechnology Park and consists of about 530 acres that lies between US Route 60 and theShenango River. The development of this site is currently in the site design and permittingprocess. The Master Plan for this site showing the Mk Industries facility is included in theAppendix.

    POTENTIAL LOCATIONS FOR PANEL ARRAYS

    The product from this facility, solar panels, will be shipped initially to a few select locations.The first being some testing sites in Pennsylvania, and possible nearby areas. The purposeof this is to take advantage of the available water and coal to demonstrate the process ofusing solar power to fractionalize water to obtain hydrogen. The hydrogen would then be

    combined with coke (coal product) to produce synthetic oil. The other site these panels willbe shipped to is in northern Nevada and this will be the initial main site at which manysquare miles will be covered with these panels.

    COST BASIS

    The estimated costs presented in Section 8 have been broken down into two areas. The first,called Facility, is the building and site amenities (parking areas, etc.). The building

    Page 49 of 159

  • 8/14/2019 CH2MHill Study

    11/71

    40111 4 - 3 July 2, 2004

    estimate includes the steel framed, high bay building as well as the associated mechanical,electrical, etc. equipment for the building. The second, called Process, is themanufacturing and material handling equipment associated with producing the solar panels.

    Page 50 of 159

  • 8/14/2019 CH2MHill Study

    12/71

    40111 5 - 1 July 2, 2004

    Section 5

    CONCEPT DESIGN REVIEW

    GENERAL

    The concept design for the manufacturing facility is presented in the order in which it wasdeveloped, and is summarized as follows:

    Equipment set developed to support the product/process concept andproduction rates.

    Work cell developed based on equipment and flows.

    Facility block layout developed based on work cell arrangement and flows.

    Organizational structure, support functions, and site considerations to supportthe overall operation.

    The following sections summarize the concepts developed regarding each of the areas ofconsideration.

    EQUIPMENT REQUIREMENTS

    The planning model in the Appendix contains the calculations used to determine thequantities of equipment required to meet the output targets. A summary of the equipmentrequired for 1 work cell (roughly 10GW output) is as follows:

    Equipment Name Quantity/Work CellExtrusion, Calendar and Cutter 3

    Hot Press Molder - TOP & MIDDLE 1

    Hot Press Molder - BOTTOM 1

    Screen Print, PV Application, and Curing 30

    Thermal Welder - TOP/MIDDLE 1

    Chemical Sealer - BOTTOM 1

    Flash Tester (sample only) 1

    Material Handling- Water Fill- Vertical Buffer- Stacker- Stretch Wrap- Conveyor

    1611

    1 lot

    Page 51 of 159

  • 8/14/2019 CH2MHill Study

    13/71

    40111 5 - 2 July 2, 2004

    TYPICAL CELL

    Below is a typical Panel Fabrication & Test Cell (a larger illustration is included in theAppendix).

    Flash Test

    Test

    Shipping

    Submerged Water Fill

    Station

    ChemicalWeldBottomPanel

    Feeders &Extruder

    Feeders &Extruder

    Die,Gear

    Pump,Screen

    Changer

    Die,Gear

    Pump,Screen

    Changer

    Roll Form, 3-RollStand

    with

    individualdrives

    Roll Form, 3-RollStand

    with

    individualdrives

    Accumulator,

    Preheat, Hot

    PressMold,Cut,

    Discharge,Thermal BondTop & Middle

    Sheet

    Vertical Buffer

    215Feet

    220Feet

    Feeder & ExtruderDie,GearPump,

    Screen Changer

    Roll Form, 3-Roll Stand with

    individualdrives

    Accumulator,Preheat,

    Hot Press Mold, Cut,Discharge

    Vertical Buffer

    Screen Print, PV Assembly, Cure

    Vertical Buffer

    Top Panel MiddlePanel

    BottomPanel

    Screen Print, PV Assembly, Cure

    Screen Print, PV Assembly, Cure

    Screen Print, PV Assembly, Cure

    Screen Print, PV Assembly, Cure

    Screen Print, PV Assembly, Cure

    Screen Print, PV Assembly, Cure

    Screen Print, PV Assembly, Cure

    Screen Print, PV Assembly, Cure

    Screen Print, PV Assembly, Cure

    Screen Print, PV Assembly, Cure Screen Print, PV Assembly, Cure

    Screen Print, PV Assembly, Cure Screen Print, PV Assembly, Cure

    Screen Print, PV Assembly, Cure Screen Print, PV Assembly, Cure

    Screen Print, PV Assembly, Cure Screen Print, PV Assembly, Cure

    Screen Print, PV Assembly, Cure Screen Print, PV Assembly, Cure

    Screen Print, PV Assembly, Cure Screen Print, PV Assembly, Cure

    Screen Print, PV Assembly, Cure

    Screen Print, PV Assembly, Cure

    Screen Print, PV Assembly, Cure

    Screen Print, PV Assembly, Cure

    Screen Print, PV Assembly, Cure

    Screen Print, PV Assembly, Cure

    Screen Print, PV Assembly, Cure

    Screen Print, PV Assembly, Cure

    Raw

    MaterialInput

    VerticalBuffer

    Vertical Buffer

    Vertical Buffer

    Page 52 of 159

  • 8/14/2019 CH2MHill Study

    14/71

    40111 5 - 3 July 2, 2004

    Raw plastic material enters the fabrication & test cell in bulk pellet form and is loaded intothe feeders for each sheet line. The bottom panel sheet enters an accumulator where it isheated, press formed, cut and discharged into a vertical buffer. The panels are then screenprinted with a wiring matrix, oven cured and the photovoltaic cells applied.

    The top and middle panel sheet lines are located side by side. The formed sheets enter anaccumulator where they are then preheated, press formed, cut and thermal bonded to formthe concentrator vessels. The top and middle panel assembly is then submerged in a watertank to fill the vessels and the bottom panel assembly is then chemically bonded to theassembly to complete the module. The module is then flash tested and moved to shipping.

    The size of each cell is 220 feet by 215 feet and is equipped to produce approximately 1200modules per hour.

    AREA REQUIREMENTS

    Area requirements are detailed in the planning model contained in the Appendix. A recap ofthe summary requirements is as follows:

    000 SF # of Work Cells >> 1 4 10

    Production Space 51.6 206.4 516

    Receiving, Shipping 5.2 20.6 51.6

    Stretch Wrap, Staging 5.2 20.6 51.6

    Support (prep, labs, R&D) 15 30 60

    Canteen/Break 2.3 4.5 10

    Office 6 6 12

    Central Utilities 17 57.6 140

    SUBTOTAL 102 346 841

    Contingency (15%) 15 52 126

    TOTAL 117 398 967

    Page 53 of 159

  • 8/14/2019 CH2MHill Study

    15/71

    40111 5 - 4 July 2, 2004

    FACILITY BLOCK LAYOUT

    Site Specific - A block layout was developed for the current building outline programmedon the Lawrence County site. The building outline was developed for the northern portion

    of the Millennium Technology Park site, allowing the center portion of the site to remainavailable for a semiconductor manufacturing facility or wafer fab. The shape of thebuilding is based on physical restriction of this part of the site such as wetlands, topography,and site vehicular circulation requirements.

    Block Layout - Baseline

    This layout arrangement provides for receiving at one end of the building and shipping at theother. Based on the output target, work cells would be installed starting at one end of thebuilding (say the northeast corner) and built-out away from the first work cell (a largerillustration is included in Appendix).

    Page 54 of 159

  • 8/14/2019 CH2MHill Study

    16/71

    40111 5 - 5 July 2, 2004

    Optimized Block Layout - An alternative layout arrangement was develop to show a moreoptimum process centric arrangement, without regard to permissible building footprintconstraints dictated by the present site considerations.

    Block Layout - Option

    This arrangement allows the receiving functions to be located closer to the work cells. It

    also allows the output from each work cell to be directed down a central aisle and routed tothe stacking/stretch wrap area (a larger illustration is included in Appendix). Consequently,if there is an opportunity to utilize an alternate site, there are several points to consider forthe Optional layout:

    Improved site and facility logistics by placement of receiving locations closerto process lines.

    - Pneumatic conveying systems are shorter allowing more economicfirst cost and reduced operating cost due to smaller motor/blowersrequirements.

    - Reduced truck traffic density for receiving once abandoning a centralreceiving operation.

    Reduced internal material handling distances minimize material handlingequipment and reduces non-value added material handling.

    - Fewer lift trucks.

    Page 55 of 159

  • 8/14/2019 CH2MHill Study

    17/71

    40111 5 - 6 July 2, 2004

    - Shorter lengths of pallet conveyor.

    Increased utility runs will require more expensive first cost for distribution.

    MATERIAL FLOW

    Due to the extremely high production rate requirement of this project, the facility concepthas been designed with a high degree of priority placed on the flow of material. Each PanelFabrication & Test Cell is designed for the entry of bulk plastic pellets at a single point andindividual sheets and panel assemblies moving in simple, continuous flow paths through thecell with no cross-over or switch-back paths. Final product exits the cell at the opposite endfrom the raw material entry point.

    The cells are arranged in the facility so that raw material entry points are easily accessedalong the exterior walls and final product can flow out of the cells, down central aisles toshipping.

    RAW MATERIALS HANDLING

    Other than PETand PVCpellets, lift trucks are planned for the delivery of most materialfrom Receiving to the work cells. Five lift trucks, separate from those dedicated to Shippingand Receiving, will be needed once full production is achieved. They will deliver the itemslisted in the palletized materials paragraph of the Storage section. These materials includerolls of stretch wrap. A lift truck roll handling attachment is provided for in the costestimate.

    FINISHED GOODS HANDLING

    A conveyor system was selected for finished panel transport from the individual work cellsto Shipping. Three modes of transport were considered: conveyors, transfer cars, andautomatic guided vehicles (AGV). Two of these, conveyors and AGV Systems, canachieve the needed throughput. The conveyor needed to transport these unit loads with a 4-by 8-foot footprint is not particularly economical; however, the conveyor system will still bemore economical than an AGV System to accomplish the same transport volume. Transportcars were initially considered because of their relatively low cost; however, for thisapplication they are too slow to achieve the needed throughput.

    The Conveyor system for the Baseline Layout is expected to have approximately 2,575 feetof conveyor. At an estimated $400 per foot installed, including all diverts, merges, and the

    control system; the conveyor system will require a $1 million investment. In contrast, anAGV system will require approximately 24 single deck or 14 double deck vehicles toachieve the needed throughput. Based upon budgetary information obtained from Jervis B.Webb, an AGV System would require approximately a $1.8 million investment.

    Page 56 of 159

  • 8/14/2019 CH2MHill Study

    18/71

    40111 5 - 7 July 2, 2004

    RECEIVING

    Receiving will be required primarily for PET pellets; however, a comparatively smallamount of discrete raw materials will be received in palletized form. The receiving area will

    be composed of docks, unloading stations for trucks of PET and PVC pellets, silos forbackup PET pellet storage, and a small amount of rack storage.

    PET Pellets The large quantity of PET and PVC consumed dictates bulk quantity delivery.Bulk delivery will be via truck. There is no rail service available on the preferred site.However, if an alternate site were considered in the future, rail service would be provide formore economical PET delivery and should be considered.

    Truck delivery for PET and PVC pellets will require unloading stations. A pneumaticsystem will be utilized to directly feed each extruder from the bulk truck. These stations arebest located as close to the extruder serviced as practical to minimize blower sizes andsystem expense. Motors and blowers for the PET pellet pneumatic delivery system will be

    located adjacent to the unloading stations. A 6- by 6-foot pad should be adequate for ablower and motor; there will be three motor/ blowers per work cell. Motors and blowers forthe pellet pneumatic delivery systems will be located adjacent to the unloading stations. Anexternally located 6- by 6-foot pad, located adjacent to the unloading station, should beadequate for a blower and motor; there will be three motor/ blowers per work cell.

    At peak production the weight of PET and PVC consumption will be somewhat in excess offour truckloads in an hour. However, since two types of resins (clear PET for the top twolayers and an opaque PVC resin for the base layer) additional unloading stations are needed.For planning purposes, two stations are priced for clear PET and four stations for the opaquematerial. This will allow one truck to be staging for both clear PET and the opaque resin

    while the other stations are in operation. Two suppliers, Eastman Chemical and M&Gindicated that the unloading stations would probably be provided without cost due to thehigh projected consumption rate of PET and PVC.

    Palletized Materials Lift trucks will be used to unload palletized loads from trailers. Forthe most part, these materials will be delivered directly to the work cells. However, thesematerials will be stored as necessary to maintain a small safety stock. Storage will be inracks located adjacent to Receiving and is more thoroughly discussed in the Storage section.For the Baseline Layout it is felt that approximately 20 docks in a centralized Receiving willbe adequate for palletized materials.

    The large number of docks is required to assure the smooth operation of a JIT delivery

    philosophy. This will allow for a trailer of each high volume raw material to remain parkedat the dock for the lift trucks to work out of, while simultaneously providing docks for theyard tractor to stage the next trailer of materials and to have the needed buffer to allow anempty trailer to sit at the docks for some time.

    Page 57 of 159

  • 8/14/2019 CH2MHill Study

    19/71

    40111 5 - 8 July 2, 2004

    SHIPPING

    Finished goods will be palletized in the work cells and subsequently stretch wrapped tofacilitate handling and security. Palletized panels will be delivered to Shipping where they

    will be stretch wrapped. These unit loads will be automatically delivered to the stretchwrappers. Unit loads will be fed into the stretch wrapper on an automatic conveyor. Nocorner posts are required; the panel design will have strengthened corners that nest so as toprovide a robust package once stretch wrapped. The wrapped load will be discharged onto aconveyor to await pickup by a lift truck. Lift trucks will load trailers at the docks.Approximately 30 docks are provided.

    STORAGE

    As with the dock areas, a just-in-time philosophy affects the storage area design. Storagequantities are based upon JIT deliveries. As such, only the smallest of safety stock isconsidered.

    Raw Materials The primary raw material will be PET and PVC pellets. While delivery isstraight from the trucks to the extruders, with the trucks parked in the unloading station forthe duration, silo storage is also recommended by resin suppliers as a backup to guardagainst delivery disruptions. The suppliers interviewed indicate that the cost of the silos willbe borne by them as a service due to the anticipated large volume of PET and PVCconsumption. To preclude mixing PET types, separate silos will be maintained for clearPET and opaque PVC. A 2-hour backup supply of PET and PVC is recommended. Atpeak production, this will be approximately 104,000 pounds of clear PET pellets and312,000 pounds of opaque resin. This can be accomplished with a relatively small silolocated adjacent to each of the bulk unloading stations. For the clear PET, 2 silos of

    approximately 8-foot diameter and for the opaque resin four silos of 10-foot diameter shouldbe adequate.

    Palletized Materials As with PET and PVC pellet storage, the philosophy of design is thatJIT deliveries will keep stored palletized materials at a minimum. For the most part, storageis a 2-hour buffer. It has been calculated that 62 pallet rack positions and 12 drive-in rackpositions will hold the necessary materials. This amount of rack is small and will beinstalled adjacent to Receiving. The rack will provide three high pallet storage and willhave a footprint of 915 square feet (425 square feet for pallet rack and 490 square feet fordrive-in rack). The materials to be stored are:

    PVs photovoltaic cells will be received in tubes for insertion, these will be

    in cartons and on pallets. Due to the extremely small size of the PVs, a lot ofstorage space will not be required. With just in time delivery, material flowwill be primarily from the dock to the production floor. Storage space for 12pallet loads of photovoltaic cells will be provided.

    Empty pallets the finished panels will be placed on pallets for securehandling; therefore, an ample supply of pallets will be required. Emptypallets will require more storage space than any other material placed in

    Page 58 of 159

  • 8/14/2019 CH2MHill Study

    20/71

    40111 5 - 9 July 2, 2004

    racks. These pallets will be a specialized 4- by 8-foot size. Where storage isnecessary pallets will be stored in drive-in racks. The equivalent of twohours of pallets will be stored; otherwise, pallets will go directly from trailersat Receiving to the work cell stackers where pallet loads are formed. Space

    for storing 400 empty pallets will be provided; this will requireapproximately 12 drive-in storage slots.

    Stretch wrap a considerable quantity of stretch wrap will be used topackage the completed panels for shipping. The wrap will be received inrolls, the rolls are palletized, and the rolls weight no more than 1000 pounds.A roll handling attachment will be provided on one of the lift trucks thatoperate in Receiving. Twenty pallet loads of stretch wrap will be stored forbackup.

    Cement the final assembly operation for the panels requires chemicalbonding of layers. The glue utilized will be in liquid form, received in 55gallon barrels, filled barrels will weigh approximately 450 pounds, the barrelswill be palletized, and potentially with have hazardous storage requirements.Space for the storage of 10 barrels of cement will be provided.

    Miscellaneous numerous other unidentified materials in small quantitieswill be received that require storage. Twenty storage positions will beprovided for miscellaneous items.

    WIP The only work-in-process envisioned at this time will be due to exception conditions.Primarily this is thought to be units that need repair. Otherwise, there is no intermediatehandling or accumulation planned for panels or panel components beyond that supplied

    internally by the process equipment and its interconnection conveyor system.

    Finished Goods (surge only) Completed product is shipped as soon as possible.Therefore, Shipping will only have a staging area for product. This will primarily be in theform of a conveyor queue of several unit loads at the output of each stretch wrapper.

    Research and Development The facility will have a Research and Design Laboratoryequipped with essential prototyping equipment such as a drill press, mill, lathe, hydraulicand electrical test benches, microscopes and various hand tools. Basic shop lighting andutilities will be provided to this area.

    UTILITIES

    The following paragraphs describe the key utilities that will be required for themanufacturing facility and describe projected facilities equipment requirements.

    Electrical Each 51,000 square-foot manufacturing cell is projected to have an electricaldemand of 13.4 MVA, which includes manufacturing equipment and associated facilitiessupport equipment. See the attached Tool Utility Matrix Estimates for Typical Work Cellfor demand and connected load numbers. This demand load represents a high density

    Page 59 of 159

  • 8/14/2019 CH2MHill Study

    21/71

    40111 5 - 10 July 2, 2004

    electrical load of 260 watts per square foot of manufacturing space. At ten manufacturingcells, the corresponding projected electrical load is 134 MVA, a significant number whichrequires multiple dedicated high voltage substations and transmission planning at theelectrical utility level.

    A large portion of the electrical load is made up of electrical furnaces and heating equipmentwhich are part of the manufacturing process. IDC has contacted equipment manufacturersto discuss the possibility of changing these furnaces to natural gas. The manufacturersresponded indicating that some of the equipment components are not available in natural gasat this time and that some processes are better served with electrical heating components.

    First Energy has received connected and demand load forecasts along with a projected loadtimeline. First Energys previous study an alternate use for this site, which wascommissioned in 2003, indicated that the 138 kV line can support 80 MW of additional load.60 MW of this capacity was to be allocated for the Millennium Park industrial site and 20MW was to be allocated to supporting regional businesses and residential uses. Becausedemand figures for a ten module factory presently indicate a demand of 130 MVA, FirstEnergy has indicated that utilizing the existing 345 kV transmission line, located four milesfrom the proposed site, may be preferable. First Energy has an existing easement for the138 kV line extension to Millennium Park, but does not have a similar easement for the 345kV line. Utilizing the 345 kV transmission would require land to be purchased verypreliminary estimates indicate purchasing the land and constructing the four-mile 345 kVextension would cost $3-$5 million. First Energy has indicated that it would need to becommissioned to execute a three to four month duration electrical study to confirm the useof the 345 kV transmission line. One possible solution is to utilize the 138 kV transmissionto provide power for the first five modules of the factory and, if necessary, utilize the 345kV transmission line for the remaining five factory modules.

    Load projections are based upon demand figures gathered by IDC and Lockwood Greeneacross several different industrial plant types. Demand factors for industrial facilities ofdifferent types vary widely. As this facility is the first of kind, the actual loads seen after thefirst module is operational will be valuable in assessing the actual demand for the followingmodules. The actual demand factor for the first production module will be criticaldetermining the size and cost of electrical substations and distribution equipment necessaryfor the following nine modules.

    See the Electrical Concept Drawing included in this report for a single line diagramindicating possible utility substation quantity/configuration and plant 15kV, 5kV, and 480Vdistribution. Electrical system design and cost is based upon N+1 redundancy.

    Page 60 of 159

  • 8/14/2019 CH2MHill Study

    22/71

    40111 5 - 11 July 2, 2004

    DI Water IDC believes that DI water would be required for filling the PV lenses. Thisrequirement is based upon no bacteria or algae growth within the lenses for a period ofseven years where the lenses are installed in an outside ambient condition. Calculationsindicate that the flow for one production module is 95 gpm, with a corresponding flow rate

    for the ten module factory at 950 gpm.

    This flow would require a DI water production facility within the manufacturing facilitywith prefiltration, RO, continuous DI (CDI), filtration, UV sterilization, and degas. Watersource will be municipal potable water - assume groundwater at 10 grams of hardness,100 ppm calcium. Water quality will be low TOC (>50 ppb), 17 Megohm resistivity, gascontent (all N2 and o2) less than 50 ppb. Membrane degas preferred in pilot system.Production level could use vacuum tower degas. Both w/o N2 purge.

    HVAC, Mechanical, & Exhaust HVAC, mechanical, and exhaust systems are required forremoval of heat from production cells and space conditioning for operator comfort. Each51,000 square foot cell has a heat load of 4,198 kW. That is a demand load of 80 watts persquare foot of manufacturing space. The mechanical systems are designed to keeptemperature at the plant floor between 75 and 80 degrees Fahrenheit. This requires a greatamount of airflow to be induced and removed from the space. Mechanical system designand cost is based upon N+1 redundancy. See attached Mechanical Equipment Summarydocument for a list of projected mechanical components and their corresponding ratings.See attached Mechanical Equipment Sizing document for calculations performed todetermine equipment quantities and ratings.

    Mechanical Equipment Summary

    FOR 1 CELL ONLY

    # of Units Capacity HP- kW / each

    AHU 14 50000 cfm 60 hp

    Chillers 3 1280 tons 535.4 kW

    Boilers 2 15876 MBTU 500 hp

    Cooling Tower 2 143500 cfm 40 hp

    CHW Pumps 2 1590 gpm 60 hp

    HW Pumps 2 815 gpm 30 hp

    CW Pumps 2 1990 gpm 40 hp

    Solvent EF 3 36000 cfm 40 hp

    Page 61 of 159

  • 8/14/2019 CH2MHill Study

    23/71

    40111 5 - 12 July 2, 2004

    # of Units Capacity HP- kW / each

    General EF 3 72000 cfm 50 hp

    Assumptions

    AHUs

    - AHUs will maintain the work space between 75 F and 80 F.

    - Sensible cooling only at the cooling coils.

    - AHUs configured to operate in full economizer.

    - 13 units are required, one extra for shutdown purposes.

    Chillers

    - There is 1300 tons of cooling for each cell. One chiller will operate.

    - One redundant chiller for shutdown purposes.

    - The chillers will operate at 55 F leaving water temperature.

    Boilers

    - During the winter months the space will go to minimum OSA and recirculateairflow back through the unit.

    - The boilers will only operate during the winter months.

    - One redundant boiler for shutdown purposes.

    Solvent Exhaust

    - Two Exhaust fans will operate at 18,000 cfm.

    - One redundant fan for shutdown purpose.

    - Assume high static for VOC abatement.

    General Exhaust

    - The two fans are operating at 36,000 cfm.

    - One redundant fan for shutdown purposes.- Assuming the general exhaust is not connected to any tools or static removal

    Page 62 of 159

  • 8/14/2019 CH2MHill Study

    24/71

    40111 5 - 13 July 2, 2004

    MECHANICAL EQUIPMENT SIZING

    Cooling Load calculations for Airflow & Chillers

    Givens:

    Room Temperature 75 F - 80 F

    OSA Summer Temp 85 F DB / 70 F WB

    OSA Winter Temp 11 DB

    1 Cell Heat Load 14,336, 170 BTU

    Air Handler Calculations

    CFM = 14,336,170 / 4.5 (34-29) = 637,163 CFM

    Q = 50,000 * 1.08 (85 - 64) =1,134,000 BTU/H

    GPM = 1,134,000 / 500 (75-55) = 114 GPM

    14 Air Handling Unit @ 50,000 CFM

    Total GPM = 1590 GPM

    Chiller Calculations

    1 Cell Requires 1304 Tons ( cell calculations attached)

    For Sensible cooling the operating Temperatures:

    Entering Water Temp 75F

    Leaving Water Temp 55 F

    1 - 1280 Tons Chiller @ 535.4 kW / 1 Chiller for redundant

    2 - Primary Pumps 1590 gpm @ 110 ft w/ 60 HP

    2 - Condensing Pumps 1990 gpm @ 60 ft w/ 40 HP

    2 - Cooling Towers

    Heating load calculations for Airflow & Boilers

    OSA = 20% @ 11 F

    Page 63 of 159

  • 8/14/2019 CH2MHill Study

    25/71

    40111 5 - 14 July 2, 2004

    RA = 80% @ 75 F

    MA = 100% @ 62 F

    Q = 1.08*50,000 ( 83 - 62) = 1,134,000 BTU

    GPM = 1,134,000 / 500 (160-120) = 57 GPM

    Total GPM = 800 GPM

    Total BTU/hr = 15,876,000 BTU

    Operating Temperatures:

    Entreating Water Temp = 120 F

    Leaving Water Temp = 160 F

    1- 500 HP Boilers Required Plus One redundant Boiler

    2 Primary Pumps 800 gpm @ 80 ft w/ 25 HP

    Solvent Exhaust Fan Sizing

    4.5 inches of static consider for scrubber

    2.5 inches of static consider for operation

    2 fans operate at 18,000 cfm @ 7 inches of static plus 1 for redundancy

    General Exhaust Fan Sizing

    Assuming no tool connection.

    2 fans operate at 36,000 cfm @ 3.5 inches of static plus 1 for redundancy

    Cooling Load Calcs for 1- Cell

    1 - Cell kW BTU Tons

    Load 4193 14306516 1192

    Support Bldg

    Area People BTU Assumption

    People 15000 20 5000 250 Btu / Person

    Space 15000 20 450000 30 Btu / Sq Ft

    Page 64 of 159

  • 8/14/2019 CH2MHill Study

    26/71

    40111 5 - 15 July 2, 2004

    Lighting 15000 20 4396.248535 1 Watt / Sq Ft

    Office Bldg

    Area People BTU Assumption

    Office Space 6000 40 10000 250 Btu / Person

    Break Rm 2250 25 6250 250 Btu / Person

    Office Bldg 8250 65 247500 30 Btu / Sq Ft

    Lighting 8250 65 2417.936694 1 Watt / Sq Ft

    CUB

    Area People BTU Assumption

    Space 20440 2 613200 30 Btu / Sq Ft

    Lighting 20440 2 5990.621336 1 Watt / Sq Ft

    Total Tons 1304

    Cooling Load Calcs for 4- Cells

    4 - Cells kW BTU Tons

    Load 16793 57297716 4775

    Support Bldg

    Area People BTU Assumption

    People 30000 40 10000 250 Btu / Person

    Space 30000 40 900000 30 Btu / Sq Ft

    Lighting 30000 40 8792.497069 1 Watt / Sq Ft

    Office Bldg

    Area People BTU Assumption

    Office Space 6000 40 10000 250 Btu / Person

    Break Rm 4500 80 20000 250 Btu / Person

    Office Bldg 10500 120 315000 30 Btu / Sq Ft

    Lighting 10500 120 3077.373974 1 Watt / Sq Ft

    Page 65 of 159

  • 8/14/2019 CH2MHill Study

    27/71

  • 8/14/2019 CH2MHill Study

    28/71

  • 8/14/2019 CH2MHill Study

    29/71

    40111 5 - 18 July 2, 2004

    Maintenance 2,200 sq. ft.

    Safety/Medical Supplies 1,300 sq. ft.

    Office Mechanical 3,200 sq. ft.

    Circulation/Egress 17,500 sq. ft.

    TOTAL 80,000 sq. ft.

    Page 68 of 159

  • 8/14/2019 CH2MHill Study

    30/71

    40111 6 - 1 July 2, 2004

    Section 6

    PRODUCTION RAMP UP, ORGANIZATION AND MANPOWER

    PROOF OF CONCEPT

    Proving that the design of the product and the manufacturing process used to produce thepanel is the first critical step to gain confidence that the panel functions as desired and canbe manufactured as designed. This is the time to tweak design elements and manufacturingsteps so that pilot production can be focused on fine tuning the units of operation inpreparation of full scale production ramp-up. Appendix 7.0 contains a technical paper, co-authored by David Causey, who participated in the production of this report. This paperoutlines the challenges in transitioning from R&D (Proof of Concept) to pilot production,then to full-scale production.

    PRODUCT DESIGN

    To prove the design concept, it is recommended to complete detail design drawings of theCPC module components and assemblies and to produce prototypes on temporary tooling.All three panels of the module assembly could be produced on vacuum-forming equipment.This will enable the resolution of design issues such as the interface of the bottom panelwith the top/middle panel assembly to completing the vessel seal without incurring the costof hot press forming equipment and dies. Screen-printing and PV placement sensitivityshould also be verified.

    PROCESS DESIGN

    Once the product design concept has been tested and proven, the processing equipment and

    tooling can be designed and the first prototype cell installed. It is recommended that thisfirst cell contain the minimum equipment necessary to prove the manufacturing process.The prototype cell should contain one line of sheet forming equipment and the necessarydies to produce all three panels of the completed module. Again, vacuum-formingequipment would be suitable and, in fact, could be outsourced to save the cost of theequipment at this stage in product development. The screen print, PV, and cure processequipment should also be limited to one line in the prototype cell. The prototype cell willalso need to include all equipment necessary for water submersion, thermal, and chemicalbonding, as well as material handling of the panels and finished modules. The estimatedprice of this prototype cell could be up to $15,000,000 if all the process equipment ispurchased. This value includes approximately $10,400,000 for one of each primary unit

    process equipment, plus an allowance for material handling equipment, storage racks, leasedspace, and other miscellaneous costs. For prototyping, a leased space of 10,000 to 15,000square feet should be adequate.

    PRODUCTION RATE

    Once the process design has been verified, it is recommended to install one completemanufacturing cell to verify the production rate of the facility.

    Page 69 of 159

  • 8/14/2019 CH2MHill Study

    31/71

    40111 6 - 2 July 2, 2004

    PRODUCTION RAMP UP

    Building ready will be achieved in Project Month 21. Equipment procurement, productionstart up. Ramp up to Production Capacity Target #1 (5 GW per year) will take

    approximately six months from the start of pilot line installation and will be achieved inProject Month Number 27, and will proceed in the following Phases:

    Product Line Install

    Pilot Line Startup & Test

    Manpower Training & Ramp Up

    Production Ramp to Target #1 5 GW per year rate (5,252,649, 4- by 8-footpanels per year)

    After successful Pilot Line testing and commissioning, it is feasible to install approximately

    1 additional cell per month. This will allow capacity increases to meet Target #2 and Target#3, as follows:

    Production Ramp to Target # 2 30 GW per year rate (31,515,892, 4- by8-foot panels per year) projected to be achieved Month 31.

    Production Ramp to Target #3 97 GW per year rate (101,901,384, 4- by8-foot panels per year) projected to be achieved Month 47.

    Ramp up from Production Capacity Target #1 to Production Capacity Target #2 will take anadditional four months and will be achieved in project week number 31. Interim ProductionTarget #2 will be achieved in approximately 22 months. This is the optimal ramp up period

    that can be reasonably anticipated due to equipment procurement lead times, installation andtesting, manpower hiring, and training requirements.

    0.0

    10.020.0

    30.0

    40.0

    50.0

    60.0

    Units per Year

    (Millions)

    25 26 27 28 29 30 31 32 33 34 35 36

    Product Life Cycle Month

    Production Ramp Up

    Page 70 of 159

  • 8/14/2019 CH2MHill Study

    32/71

    40111 6 - 3 July 2, 2004

    These production capacity projections assume the following:

    3 shift per day operations, 52 week per year.

    Installation of 1 cell per month.

    Availability of trained labor.

    Availability of production equipment.

    ORGANIZATION RECOMMENDATIONS

    The challenge for the Mk organization will be to meet changing needs as the businessrapidly evolves from the present stage of the business, the Initiation Stage, through theDevelopmental, Organizational and Expansion stages of the business. This will create a needfor an organization that can quickly make decisions in response to a changing companyenvironment as illustrated in the chart below.

    0.0

    20.0

    40.0

    60.0

    80.0

    100.0

    120.0

    Panels per

    Year (Millions)

    37 38 39 40 41 42 43 44 45 46 47

    Project Life Cycle Month

    Production Ramp Up

    Page 71 of 159

  • 8/14/2019 CH2MHill Study

    33/71

    40111 6 - 4 July 2, 2004

    Early Stages of a Business

    Stage Activity Characteristics Culture

    Initiation

    Great ideas

    Selling it

    Gaining commitment

    Hands on leadership

    Forming

    Dependent

    Gathering

    New Venture

    Entrepreneur (visionary)

    Performer (task oriented)

    Administrator (TOS, OAS)

    Person-to-person contact

    Product development &market development

    Developmental Making it work

    Testing it

    Pressure to produce results

    Moving from task to task

    Produce & distribute

    Short term orientation

    Every opportunity a priority

    Highly centralized

    Informal

    Leadership involved ineverything

    Storming

    Counter-dependent

    Repeating

    Expansion

    Growing pains

    Must develop infrastructure

    Turmoil creates counter-dependence among withinthe organization

    Start & stop of objectives

    Operational systems

    Page 72 of 159

  • 8/14/2019 CH2MHill Study

    34/71

    40111 6 - 5 July 2, 2004

    Early Stages of a Business

    Stage Activity Characteristics Culture

    Organizational Organization takes on

    identity

    Time previously spentdoing & selling now spentplanning & coordinating

    Administration rises inimportance

    Functional structuredevelops

    Policies and procedures areestablished

    Salary systems

    Accounting systems

    Tension betweenentrepreneurs andadministrators

    Management essential

    Norming

    Independence

    Sharing

    Professionalization

    More formal planning

    Develop a strategicplanning & managementsystem

    Defined roles &responsibilities

    Sensitivity and orientationto people

    Management systems

    Expansion Moving into prime

    More focus on out there

    Growing reputation

    Need to determine level ofaspiration

    Restructuring(decentralizing)

    Mgt. Information Systemsfor expanded &decentralized structure

    Manager/strategist(innovator)

    Performing

    Interdependent

    Transforming

    Consolidation

    Maintain growth &development

    Organizational culture

    Acknowledgeorganizations Missionimplementation strategies

    Culture system

    Page 73 of 159

  • 8/14/2019 CH2MHill Study

    35/71

    40111 6 - 6 July 2, 2004

    Our proposed organization creates an important group of Corporate level managers withinoperations, consisting of a Corporate Supply Chain Manager, Corporate ManufacturingManager and Corporate Engineering Manager to assist the Director of Operations in thedevelopment and implementation of an integrated Strategic Plan and make timely decisions

    to support the growth of the business.

    Major functions in the recommended organization are as follows:

    Operations

    Administration and Finance

    Sales

    Marketing

    Human Resources

    Information Systems

    Overall, the purpose of IDCs recommendations is to help Mk Industries to initiate a lean,simple, efficient organization in alignment with the Lean Enterprise philosophy. Mostcompanies tend to concentrate their efforts to become lean on the process at the plant floorlevel. Lean is a human system driven by and focused on the customer. Therefore, theorganization and the culture must focus upon serving internal and external customers with aminimum of waste. When this is done successfully, it creates a pull system throughout theorganization. For these reasons, implementing as flat an organization as possible with theminimum number of sub-layers is recommended.

    We also recommend organizing along functional lines. Combined with standardized

    processes and organizations, a functionally aligned organization also promotes theconcentration of appropriate resources on the execution of strategic and tactical initiatives.The Mk organization should have the following general responsibilities at the Corporateand Plant levels:

    Page 74 of 159

  • 8/14/2019 CH2MHill Study

    36/71

    40111 6 - 7 July 2, 2004

    Corporate PlantManufacturing Strategy RegulationAsset Utilization Production Engineering

    Supply Management 1st Line MaintenancePlanning/Estimating Liaison & Quality AssuranceManagement Accounts Cell SchedulingFleet Management WarehousingScheduling Reconciliation DistributionCapacity Planning/Forward PlanningFacilities & Specialized MaintenanceQuality AssuranceInventory ControlCost Control

    In order to cope with the complexities of establishing and rapidly growing the business, thecorporate organization plan proposed is based on the following five specific objectives:

    Focus the entire organization towards an internal and external client serviceapproach.

    Clearly define the roles and interaction procedures between corporatemanagement and operations.

    Standardize systems, methods, procedures, objectives, and strategies for thewhole group.

    Minimize the levels of hierarchy within the organization.

    Minimize the number of personnel.

    IDCs recommendations are intended to divide responsibilities among managementfunctions to maximize coordination and control of the operational network, humanresources, and capital assets as described below:

    Corporate Administration and Finance Director

    Corporate Marketing Director

    Corporate Sales Corporate Human Resource Director

    Corporate Systems Management Director

    Corporate Operations Director

    The resources required to undertake a supply chain optimization for Mk Industries includestrategic planning analysis, engineering analysis, material flow analysis, cost justification,

    Page 75 of 159

  • 8/14/2019 CH2MHill Study

    37/71

    40111 6 - 8 July 2, 2004

    project management, and system implementation. In the recommended organization, theseresources are controlled by Operations. Further, day-to-day operations of a distributioncenter are also the responsibility of operations. The Operations Director assumes direct lineresponsibility for Operations and the largest portion of the supply chain. Specifically, this

    applies to the entire supply chain, except the portion of the supply chain from the plant anddistribution center (DC) out to the panel array site(s). The purpose for centralizing allactivities related to Operations is to standardize systems and procedures across theorganization and optimize the entire supply chain network.

    For the Director of Operations to assume the added responsibilities described above,resources with specialized skill sets will have to be included in the corporate organization.Care has been taken in development of the proposed Operations organization to assure thatthe number of direct reports to any individual is in line with responsibilities and the verticalfunctionality required of the new organization. Direct reports to the Director of Operationsin the proposed organization include:

    Corporate Supply Chain Manager

    Plant Manager

    Corporate Engineering Manager

    A brief description of the responsibilities each of the corporate operations managers follows.Each of these managers will have a vertical functional responsibility down through the plant.

    Corporate Supply Chain Manager will be responsible for fleet management andcorporate purchasing support functions. At the corporate level, the Corporate SupplyChain Manager will have under him, a Corporate Purchasing Manager and a

    Corporate Fleet Manager. Fleet Management (transportation management) will beespecially important given the projected number of truck shipments.

    Plant Manager will be responsible for day-to-day manufacturing and distributioncenter operations. System standardization, utilization of assets, and meetingproduction requirements will be the critical drivers for this manager. Theseresponsibilities will be overseen through a functional vertical organization. Thisincludes day-to-day panel manufacturing operations.

    Corporate Engineering Manager. We recommended that a corporate sheet formingtechnical services group be reorganized under the Corporate Engineering Manager.This group will still be responsible for technical services support plant. The

    Corporate Engineering Manager will have two ways of supplying technical servicessupport to the plant. First is a corporate engineering bench comprised of engineerswith specialized skill sets. The second method is through outsource engineeringresources brought in on an as-needed basis.

    Page 76 of 159

  • 8/14/2019 CH2MHill Study

    38/71

    40111 6 - 9 July 2, 2004

    To support the Director of Operations in both annual operations plans and strategic plans,IDC recommends that a strategic planning team will be formed at the corporate level. Fromthe operations side, the team will be comprised of Corporate Supply Chain Manager,Corporate Manufacturing and DC Manager, and Corporate Engineering Manager. Thiswould be a most effective group for planning purposes since from an operational perspectivethey are the ones ultimately responsible for system wide operations.

    The organization at the plant level must be aligned to properly execute its tactical functions

    and take advantage of the corporate and regional support structures. This alignment requiresa degree of standardization throughout the Mk manufacturing plant(s).

    The IDC team has developed a 4-Dimensional approach to cellular manufacturing thataddresses the integration of four major elements:

    Logistics & Control

    Organization & People

    Production Flow

    Performance Metrics

    IDCs recommended Plant Level organization is aligned to take advantage of the matrix ofsupport to value-adding operations.

    The Manufacturing Support Manager will be responsible for making sure processes are setup to enable workers within the plant to do their jobs, motivating plant personnel,coordinating production support, and coaching.

    ChairmanWilliam Mook

    Vice Chairman

    Sales DirectorMarketing

    DirectorOperations Director

    Human

    ResourcesDirector

    Info. Systems

    ManagementDirector

    Corp. SupplyChain Mgr.

    Corp. Engr.Manager

    Corp.

    TrainingManager

    Admin & Finance

    Director

    Corp. Fleet

    Manager

    Corp. Purchasing

    Manager

    Engineering BenchOutsource

    Engineering

    Plant Level

    Page 77 of 159

  • 8/14/2019 CH2MHill Study

    39/71

    40111 6 - 10 July 2, 2004

    The organizational practices of lean operations, which include the transition to cellularteams at the plant level, are an essential element of IDCs recommendations. To besuccessful, however, team-based processing will also need to include all four dimensions ofcellular processing.

    IDCs proposed organizations for cells are based on start-up requirements. Theserequirements will be reduced as improvements are made to the cell. For example, the CellLeader is a temporary position and will be phased out as the cell teams gain experience.

    The use of cell teams for demand-pull processing will have a substantial effect upon theworking culture and the management organization. Traditional hierarchical chains ofcommand are replaced by task oriented teams working in a matrix style organization.Leadership within each cell must replace the current emphasis placed on extra-cell control.Tasks and skills including such functions as production engineering, production control andmanagement services will, be the responsibility of cell team members.

    Cell support personnel will consist of a Process Engineer, Scheduler, Logistics Planner,Quality Engineer, and Maintenance Technician. Representatives from each of these will be

    ShiftLeader

    Facilitator

    Operators

    CellLeader

    Fab & Test Cell

    HumanResourcesManager

    Administration

    Manager

    Manufacturing

    SupportManager

    Logistics/

    WarehouseFleetSupervisor

    Procurement

    SupervisorQualityControl

    PlantManager

    ProcessEngineering

    Manager

    Maintenance

    Scheduler

    Cell Support Team

    DirectorofOperations

    Typical Cell

    (10 required)

    ShiftLeader

    Facilitator

    Operators

    CellLeader

    Fab & Test Cell

    PLANT LEVELORGANIZATION CHART

    Page 78 of 159

  • 8/14/2019 CH2MHill Study

    40/71

    40111 6 - 11 July 2, 2004

    allocated responsibility for specific cells and individual resources will be shared amongmultiple cells. These functions will play a more consultative or advisory role in the futurethan at startup, eventually becoming centers of excellence where cell teams can go toobtain skills and information that they will apply on their own initiative.

    STAFFING RAMP UP

    Corporate Staffing at full production, 3-shift operations will equal approximately 104people. It is advisable to begin assembling the corporate staff as soon as possible afterinitiation of facility design in order to ensure the ability to acquire manufacturingequipment, hire personnel, develop and administer training programs, handle financialmatters, install and test equipment, and complete other key activities required formanufacturing startup as soon as the facility is ready.

    THE CELL CONCEPTSpecialist Support People

    Centers ofExcellence

    Prod. Engineering

    Quality Maintenance Information Services

    The Cell Leader

    Trained as a

    leader Has most skills Understands

    cell logistics

    Multi - SkilledProduction Team

    Cell contained

    within well definedboundary

    All processes

    owned by the cell Cell team

    accountable for its

    own performance

    inputs :

    Fit for purpose materials

    tools information

    Outputs

    products on time rapid response performance

    data

    Page 79 of 159

  • 8/14/2019 CH2MHill Study

    41/71

    40111 6 - 12 July 2, 2004

    The hiring and training of manufacturing personnel should begin approximately 3 monthsprior to initial pilot production and equipment commissioning. The followingmanufacturing manpower ramp up chart assumes that corporate staff is already on board.

    Manufacturing staffing at full production, 3-shift operations will equal approximately 555

    people.

    Recommended Corporate Staffing

    Headcount 3-Shift Operation

    Pre-Start Start Full Prod

    Chairman 1 1 1

    Vice-Chairman 1 1 1

    Administration & Finance Director 1 1 1

    Accounting Department Staff 3 5 10

    Administration Staff 16 18 20

    Sales Director 1 1 1

    Staff 1 1 1

    Marketing Director 1 1 1

    Staff 1 2 2

    Operations Director 3 3 3

    Information Systems Director 1 1 1

    Staff 2 5 8

    Human Resources Director 1 1 1

    HR Asst. 2 3 5R&D Director 1 1 1

    R&D Staff 3 3 3

    Corporate Supply Chain Manager 1 1 1

    Purchasing Manager 1 1 1

    Staff 2 2 4

    Fleet Manager 1 1 1

    Staff 2 3 6

    Corporate Engineering Manager 1 1 1

    Outsource Engineering Manager 1 2 2

    Engineering Bench Staff 7 14 21

    Corporate Training Manager 1 1 1

    Staff 2 3 6

    Total Corporate Staff 58 77 104

    Page 80 of 159

  • 8/14/2019 CH2MHill Study

    42/71

    40111 6 - 13 July 2, 2004

    TRAINING RECOMMENDATIONS

    At a minimum, training programs must be established for start up operations as follows:

    Indoctrination, company policy internal training

    Safety Training internal training

    Machine operator training for cell team members vendor supplied

    Lean Manufacturing training for all employees outside supplier short term,internal training long term

    Work team dynamics training for all cell team and cell support teampersonnel - internal

    Routine maintenance training for cell team members vendor supplied shortterm, internal long term

    Equipment Maintenance training for maintenance personnel vendorsupplied

    Information systems training for administrative and support personnel systems supplier short term, internal long term

    These training programs must be developed prior to the hiring of plant staff andimplemented/expanded in alignment with manpower and operations ramp up. Werecommend that the development and implementation of internal training programs shouldbe the responsibility of the Human Resources manager and developed with the assistance ofoutside resources as needed.

    Manufacturing Manpower Ramp Up

    0

    100

    200

    300

    400

    500600

    21 23 25 27 29 31 33 35 37 39 41 43 45

    Project Life Cycle Month

    Headcount

    Page 81 of 159

  • 8/14/2019 CH2MHill Study

    43/71

    40111 7 - 1 July 2, 2004

    Section 7

    MILESTONE SCHEDULE

    The following schedule is conceptual in nature and incorporates progress already maderegarding the development of the Millennium Park site.

    Page 82 of 159

  • 8/14/2019 CH2MHill Study

    44/71

    40111 8 - 1 July 2, 2004

    Section 8

    ROM COST ESTIMATE

    FACILITY

    The estimate for the facility and site infrastructure is budgetary in nature based on theconceptual information developed for this report. The ROM cost estimate accuracy can beexpected to be plus 50 percent or minus 30 percent of the actual cost. A high level breakoutof the estimate is included in the Appendix as well as an Estimating Accuracy Curve asdefined by the Association for the Advancement of Cost Engineers (AACE).

    Any resulting conclusions on project financial, economic feasibility, or fundingrequirements should be made with this in mind. The final costs of the project and resultingfeasibility will depend on actual labor and material costs, competitive market conditions,actual site conditions, final project scope, implementation schedule, continuity of personnel

    and engineering and other variable factors. The recent increases in material pricing mayalso have a significant impact that is not predictable. Careful review or consideration mustbe used in evaluation of material prices.

    Total cost of Work includes general conditions, overhead, and profit. Not included areescalation and contingency. The following table presents the cost for the facility.

    PROCESS EQUIPMENT

    The estimate detail for manufacturing equipment is also included in the Appendix. Valuesassigned are based on conversations with vendors. For example, CDL Technology providedinput for the panel sheet and forming equipment. All values include installation. The

    process equipment cost is presented in Appendix 2.0.

    OPERATING COSTS

    While not specifically part of the scope of this report, it is important to consider operatingcosts to help determine overall project economic feasibility. Therefore, IDC identifiedmajor variable operating costs, including raw material, labor, utility, and transportation.Appendix 2.0 includes a simple summary of these costs as well as fixed costs of the facilityand process equipment. The pie chart below graphically shows the proportional costs on aper module basis assuming the plant operates for 7 years at peak production. For a shorterperiod, the fixed cost proportion increases.

    Page 83 of 159

  • 8/14/2019 CH2MHill Study

    45/71

    40111 8 - 2 July 2, 2004

    It is worthy to note, based on the peak production rate and the process that this report hasdefined, the electrical demand is huge, and the natural gas demand is very high as well. Theenergy demand is being driven primarily by the heat needed to form the plastic layers of thepanel using hot press molders. At full production, this plant would be one of the highestpower consumers in the country. And while the utility costs account for only 3% of the costper module in the pie chart above, it may be worthwhile to research other plastic materialcomposites with properties suitable for forming the panels at lower temperatures and therebyrequiring less energy. Appendix 6.0 gives a material comparison of the three materialsunder consideration for the bottom panel: ABS, PET UV, and CPVC. The pie chart belowshows the proportional utility costs for electricity, natural gas, and water. Telecom andsewage costs should be relatively minor in comparison.

    Cost Breakdown per Module

    Facility Cost

    Equipment Cost

    PV Cost

    Resin Cost

    Circuitry Cost

    Labor Cost

    Utilities

    Transportation Cost

    Page 84 of 159

  • 8/14/2019 CH2MHill Study

    46/71

  • 8/14/2019 CH2MHill Study

    47/71

  • 8/14/2019 CH2MHill Study

    48/71

  • 8/14/2019 CH2MHill Study

    49/71

    40111 9 - 3 July 2, 2004

    DI Water Usage/Substrate Cleaning- In addition to its use in filling the CPC, DI/RO waterwill be required for several rinsing operations. Welding, forming, chemical sealing, andscreen print are processes that will contaminate the sheets with particulate and organicimpurities. As discussed in Sec 3, particulate or other impurities will degrade the optical

    properties of the CPC, lowering the efficiency of the module. IDCs intent is to minimizewater consumption, and achieve optimum sheet cleaning. This may be addressed by acascading counterflow wet bench. This equipment is commonly used in semiconductor andPV manufacturing, and may provide a workable solution.

    Transportation Costs- A cursory analysis was performed to assess the cost impact fromtransportation. The basis of the analysis is contained in the Production Capacity planningmodel located in the Appendix. Based on this analysis, the transportation cost per module isapproximately $3.40. Based on a target finished product cost of $25 per module, thistransportation cost represents almost 14 percent. Many factors will need to be considered insite selecting, including raw materials supplier locations, labor availability and cost, waterand other utilities availability and cost, as well as others.

    An alternative to minimize the impact of transportation cost would be to locate the pilot lineand initial production at the Pennsylvania site, and subsequently locate the mass-productionline adjacent to the installation site.

    Equipment Lead Times- In general, the equipment lead time issue will be driven by (1)extrusion and press equipment, and (2) screen print/PV assembly equipment. Discussionswith vendors indicate the following:

    Design(assuming proven

    concepts)

    InitialLead Time

    Follow-onLead Times

    Extrusion and PressEquipment

    6 ~ 8 weeks 8 ~ 10 months 1 year forbalance

    Screen Print and PVAssembly Equipment

    10 ~12 weeks 8 ~ 12 months 4 ~ 6 monthsper work cell

    Much of the equipment set will be standard and require minimal, if any, modification by themanufacturer. In other cases, most notably screen print and some items of test andmeasurement, the tools will likely be custom fabricated to some extent. The most cost-

    effective methodology here is a close coordination between Mk and the respective vendorsto adapt standard equipment in an attempt to minimize the cost of modifications required tomeet the Mk specifications. The equipment set will come from a variety of industries suchas Flat Panel Display, Silicon PV, Printed Circuits, and Optical Electronics. Fortunately,equipment manufacturers in these areas are generally flexible and are accustomed to a rangeof needs. This approach generally results in significant cost savings to the user, but willextend the procurement phase of the schedule.

    Page 88 of 159

  • 8/14/2019 CH2MHill Study

    50/71

    40111 9 - 4 July 2, 2004

    Typically, a pre-qualified equipment vendor will be given a Performance Specification bythe user, Mk Industries, and asked to provide submittals, with exceptions noted, within areasonable date. Mk reviews the submittals, and exceptions are taken into consideration.In most cases, a test run can be made at the vendor site, with any needed modifications

    agreed upon at that time. Mk Industries and the vendor(s) will agree upon the generalrequirements and Mk will follow-up with an Equipment Specification and a Data Sheetsent to the vendor. The equipment can be competitively bid or awarded on the basis of bestqualified. In any case, final acceptance of the equipment should be conducted at the vendorsite, when possible, with acceptance criteria having been stipulated in the specification.

    The follow-on lead times assume firm orders issued to fabricators for equipment that isidentical. In the case of the Screen Print/PV Assembly equipment, a group of fabricatorsmay need to be contracted in order to meet the projected delivery schedule.

    Critical Path Items- Startup, process verification - In order for the process startup toproceed as smoothly as possible, several prerequisites are in order. First of all, a productspecification must be developed with some level of detail. This specification will naturallyaddress module power output and lifetime performance, but will also require some level ofprecision required for the physical characteristics of the module itself, e.g.,dimensionalstability, dimensional tolerances, Voc and Isc, and temperature limits. The productinformation can then be deconstructed to develop the requirements for the parameters ateach individual process step. For instance, the optimum power output is achieved when thePV cells are within +/- 5 m placement. These parameters may be specified initially basedon theoretical data, but empirical results are necessary to validate the initial assumptions.This step is normally a part of a pilot phase, but may be accomplished in a researchenvironment if the tool set is appropriately similar to that used in the final process.Achievement of this phase is measured by statistical analysis to some level of certainty.

    Historically, validation of the process steps to comply with product specification is timeconsuming and requires many iterations, usually with slight adjustments of the processparameters. Interaction between the individual process steps, if present, is also detected atthis time. Controlled experiments are often required to quantify and address the interactiveeffects. Consequently, the time required in the overall schedule is often underestimated.Open Issues in Appendix 2.0 addresses the challenges normally seen in this stage, and howthey may best be surmounted. In the ideal case, process verification is accomplished with aone-off tool set that closely replicates the planned tool set.

    Permitting Issues- All of the permits associated with site development will have beenobtained prior to site construction activities. Applicable permits associated with the buildingsuch as air quality, discharges, material storage, etc. will have to be obtained. These,however, would require more detailed process information than that currently available.This information would be available after preliminary design.

    Page 89 of 159

  • 8/14/2019 CH2MHill Study

    51/71

    1.0 - Process Concept Sketches

    - PV Circuit/Assembly Concept

    - Bus Bar Screen Printing

    - PV Application

    Page 90 of 159

  • 8/14/2019 CH2MHill Study

    52/71

    PV Circuit/Assembly Concept

    PV Circuit/Assembly Concept

    Dry and Fire FurnaceBusBar ScreenPrint PV Applicat ionPigtail

    Connect

    16 60 4

    X

    Rolled

    ScreenPrintPV Feeder and

    Applicator

    Pigtail Applicator

    and SolderDry and Fire Furnace

    PLAN VIEW

    ELEVATION

    Y

    Page 91 of 159

  • 8/14/2019 CH2MHill Study

    53/71

    Bus Bar Screen Printing

    BusBar Screen Print

    Cross

    Bus BarLength-wise

    Bus Bar

    Page 92 of 159

  • 8/14/2019 CH2MHill Study

    54/71

    PV Application

    PV Application

    Initial Row

    PV Applicator

    Off-set Row

    PV Applicator

    PVFeed

    PVFeed

    PV

    Feed

    PV

    Feed

    Page 93 of 159

  • 8/14/2019 CH2MHill Study

    55/71

    2.0 - Planning Data

    - Production Capacity

    - Equipment

    - Utilities

    - Open Issues- Plastics Cost- Labor Cost Estimate Manufacturing Operations- Simple Cost Summary

    Page 94 of 159

  • 8/14/2019 CH2MHill Study

    56/71

    Mok Industires insert values in these cells

    Production Planning - 4' X 8' MODULE

    Item Value Notes

    Concentrator H/D Ratio 1.5Module Area Add Factor 1.27 Square and support ( lense area times factor for module area)Distance Add Factor 1.01 Assumption of 1/100

    Panel Size width 48 Incheslength 96 Inches

    Sun Power 0.1 W/cm2 (full sun)Sun Power 0.6452 W/in2 (full sun)Water Estimate 0.17 1/6th times cylinder volumeCircle "Nesting" Factor 0.93 Factor t imes 2 diameters for length of 2 rows of cirlces nestedProduction Rate #1 5 GW per year 0.0078125

    Baseline Scenario

    Page 95 of 159

  • 8/14/2019 CH2MHill Study

    57/71

  • 8/14/2019 CH2MHill Study

    58/71

  • 8/14/2019 CH2MHill Study

    59/71

    MokIndustries

    OPENISSUES

    Description

    Impact

    MitigationApproach

    Comment

    Wateruseperday(>1milliongallons)

    -

    Notunusualforindustrialplants.

    Shouldnotbeissue.

    Poweruseatsite(>100MVA)

    -

    Availableatsite?

    -Equipmentinstallisphasedu

    tilityproviderto

    planforpeakrequirements3~5yearsout.

    Volumeofbottles/day(~1.2billion)

    -

    Estimateof400+blowmolders.

    -

    Deliveryscheduleofblowmolderquantity.

    -

    Capacityofblowmoldersuppliers.

    -

    Resinsupply(limited#ofsuppliers).

    -Multipleplants?

    -Higherthru-putdesign?

    -Useof"pre-forms"?

    -Alternateapproach?

    MaterialeffectivenessofPET

    -

    PETmaynotperformwelltosunlightandheat.

    -

    Resistancetoimpact(hail,dust).

    -

    Swellinginwater.

    -

    Surfacegettingdirtyovertime(lossinefficiency).

    -Alternatematerials(polycarbonate,other).

    -Furtherresearchrequired.

    Numberofconnectionstobemade

    (functionofconcentrators)

    -

    Reliability.

    -

    Efficiencylossofconnectors.

    -Reduceconnectionrequirements(larger

    bottles)?

    -Furtherresearchrequired.

    "Wiring"ofPV's,insulation?

    -

    Conductivityofwaters

    hortconnectionwires?

    Shipping(Penn->NV)

    ~350trucksperdayat$340million/year

    -

    Costoftransporttosite.

    -

    #oftrucks/trailers(deadheading).

    -Locateplantnexttosite("batchplant"

    approach).

    -InstallpilotlineinPenn.,otherlinesnearsite.

    PVCellsupply

    -

    Limitoutput.

    -Seecomment.

    PerBillMook,SpectraLabscanramp

    capacity(possiblyonsite)tomeet

    demand.

    Z-fold/hinge

    -

    Complexitytoincludehingespriral.

    -Ifneeded,usethinplasticconnection.

    CDmeasurements

    -

    Repeatabilityinprocess.

    -

    Efficiencyreduction.

    -Furtherresearchrequired.

    DryandFiretemperaturesforscreenprinted

    circuit?

    -

    Effectof120degCtoplasticback.

    -Furtherresearchrequired.

    Page

    98

    of159

  • 8/14/2019 CH2MHill Study

    60/71

    MokIndustries

    OPENISSUES

    Description

    Impact

    MitigationApproach

    Comment

    Onlybulkshippingoffinishedpanels

    addressed

    -

    Retailbusinesscouldbealargepartofthesales

    g

    enerated;however,anadditionalpackagingoperation

    a

    ndspacededicatedtopackagingisneededifindividual

    p

    anelsaretobepackagedforresale.

    -Buildingadditiontohouseadditionalpackaging

    operationorutilizea3rdpartytopackage.

    PricingofPETandotherresins

    -

    Veryvolatilerecentlyduetooilpriceincreases.

    -Usemoreeconomicalopaqueresin,possibly

    notPET,forthebaselayerofthepanel&

    minimizetheuseofallresinsconsistentwith

    requiredpanelstrength.

    Plasticresinavailability

    -

    Regardlessoftypeselected,volumemayexceedwhat

    isreadilyavailableinthemarket.

    -Mayneedtoworkwithsupplier(s)toincrease

    capacity.

    Equipmentleadtimes

    -

    Delayinoutputscheduleand/oroutputcapacity.

    -Workwithvendorstounderstandinglimitin