cesmm
TRANSCRIPT
SEMINAR on
Standardising and Enhancing Bills of Quantities
forCivil Engineering Works
usingMalaysian Standard Method of
Measurement (CESMM)
31st MARCH 2010
EQUATORIAL BANGI
KAMALALDIN ABD. LATIF
JKR. MALAYSIA
CONTENT
• OVERVIEW
• CLASS E – EARTHWORK
• CLASS P – ENVIRONMENTAL PROTECTION
• CLASS G – ROADWORKS
O1- CLIENT – CONSULTANT - CONTRACTOR
OVERVIEW – CESMM_________________________________________________________________________________________________
CLIENT
CONTRACTORCONSULTANT
Idea, concept
Functional, size, material
Estimated cost (range)
Time
confirmation
- conceptual design
- detailed design
- Specification (work & material)
- Bill of Quantities
- Estimated Cost
COST & TIME
O2 - PRINCIPLE OF BILL of QUANTITIES
OVERVIEW – CESMM_________________________________________________________________________________________________
ENGINEER(DESIGNER)
CONTRACTORWORK
What ? - Item Ref. / Description
Quantity ?
Coverage Rules ?
Size (dimension) ?
Where ?
When/Duration/Interval ?
Material Specification ?
Additional Descripion Rule
O3 - PRINCIPLE OF BILL of QUANTITIES
OVERVIEW – CESMM_________________________________________________________________________________________________
WHAT? - Q 3
- Carry out routine maintenance
WHERE? - on existing road
SIZE / DIMENSION - within the limit of work
DURATION - for the duration of the contract period
O4 – BILL of QUANTITIES
OVERVIEW – CESMM_________________________________________________________________________________________________
Item Description- Describes briefly the work to be executed by the Contractor(the details of work will be described in the Tender Drawing and coverage rule in the Preamble to BQ and the MoM)
e.g: ‘Excavate unsuitable material below embankment or belowFormation in cuttings as shown in the drawing or as perspecification to disposal areas within the R.O.W asapproved by the S.O.’
Quantities- BQ quantity as a basis for estimating the rate - Final quantity to be remeasured
O5 – PREAMBLE to BQ
OVERVIEW – CESMM_________________________________________________________________________________________________
- Describes briefly the work to be executed by the Contractor(the details of work will be described in the Tender Drawing and items coverage in the Pramble to BQ and the MoM)
e.g: ‘Excavate unsuitable material below embankment or belowFormation in cuttings as shown in the drawing or as perspecification to disposal areas within the R.O.W asapproved by the S.O.’
Quantities- BQ quantity as a basis for estimating the rate - Final quantity to be remeasured
O6 – ITEM DESCRIPTION
OVERVIEW – CESMM_________________________________________________________________________________________________
- Describes briefly the WORK component (not the TASK i.e. howthe Work should be done) to be executed by the Contractor
- (the details of work will be described in the TenderDrawing and coverage rule in the Preamble to BQ and the MoM)
e.g: - ‘Excavate unsuitable material below embankment orbelow Formation in cuttings as shown in the drawing or as per specification to disposal areas outside the R.O.W asapproved by the S.O.’
- ‘Mild steel bar of nominal diameter 20mm’
not as: ‘Supply, deliver, cut, bent and fix mild steel bar of diameter 20mm’
O7 – MEASUREMENT RULE
OVERVIEW – CESMM_________________________________________________________________________________________________
Sets out the CONDITION under which the Work will be measured
and
the METHOD by which the Quantities shall be computed in accordance with paragraph 5.17
Section 5: Preparation of the Bill of Quantities5.17 : ‘All measurement shall be taken nett otherwise stated in the
measurement rules of the CESMM. No allowance shall bemade for bulking, shrinkages or wastages. Quantities can be rounded where appropriate but common sense must be applied. The total quantity and the effect on its rounding offmust be considered. Where unavoidable, fractional quantities should be given to one decimal place only’.
O8 – SPECIFICATION
OVERVIEW – CESMM_________________________________________________________________________________________________
Gives the requirement of the workwrt material use & method statement
“Unsuitable material shall be excavated to such depth and over sucharea as directed by the S.O”
O9 – CONSTRUCTION DRAWING
OVERVIEW – CESMM_________________________________________________________________________________________________
indicates shapes & dimension- length- breadth- depth
as a basis for the Tenderer to calculate the ratesfor construction
the final dimension will be determined base on actual requirement on site
CLASS E - EARTHWORK
Class E – Earthwork __________________________________________________________________________________
CESMM (UK) - excavation in stageseg. ‘excavate from 0m to 1.5m depth
from 1.5m to 3.0m depth a.s.o
CESMM (M) - let the Contractor choose the appropriate method of construction
- difficulties encountered and loss of productivityassociated with increasing depth of excavation to be reflect in the builtup rate
- measured ‘whole’- item description or drawing should indicate the depth of excavation to facilitate computation of rateby the contractor
CLASS E - EARTHWORK
Class E – Earthwork __________________________________________________________________________________
Rule M1
In accordance with Paragraph 5.17, the quantities of earthwork shall be computed nett using dimension from the Drawings with no allowancefor bulking, shrinkages or wastages.
Where boundaries between different materials are not shown in theDrawings, measurement shall be made on Site.
CLASS E - EARTHWORK
Class E – Earthwork __________________________________________________________________________________
IMPORTED FILL
Importing fill materials occur, when
CUT (effective) – FILL = -ve
DIPOSAL OF EXCAVATED EARTH
Disposing of excavated materials occur, when
CUT (effective) – FILL = +ve
RULE 1
CUT < FILL
4.04.0
2.0
4 units – 6 units = 2 units imported
Cut
Fill
Import
2.0
RULE 1
CUT > FILL
4.06.0
2.0
6 units – 4 units = 2 units disposed
Cut
Fill
Dispose
RULE 1
Filling – Shrinkage Factor
1.2
4.86.0
1.5
Balance Cut & Fill SituationTo Fill 6 units – require 7.5 units
Cut - 6.0 units (4.8 units)Imported - 1.5 units (1.2 units)
RULE 1
Imported Volume – covered in Filling rate
1.2
4.86.0
1.5
Computation of Filling Rate6.0 m3 @ RM5.00 – RM30.00 1.5 m3 @ RM10.00 – RM15.00
Fill = RM45.00/6 m3 = RM7.50/m3
CLASS E - EARTHWORK
BACK ISSUES:
Defination for ROCKJKR/SPJ/1988Specification for Roadworks published by Jabatan Kerja Raya, Malaysia
“Rock shall mean material found in ledges or masses in its original position which would normally have to be loosened either by blasting or pneumatic tools or, if excavated by hand, by wedges and sledge hammers. “
“ It shall NOT include material which can be loosened with a track-type tractor with mounted and drawn ripper of the following description:
Class E – Earthwork (CESMM)__________________________________________________________________________
DOZER & RIPPER UNIT
Tractor Unit:Equiptment with a minimum weight of 20 tonnes and nett horse power rating of 200 brake horse power or more. The tractor unit is to be in good condition and operated by experienced personnel skilled in the use of ripping equipment
Ripping Unit:The ripper to be attached to the tractor shall be the most efficient parallelogram type recommended by the tractor or ripper manufacturer. The ripper shall have single shank in good working condition with sharpened cutting point.
Class E – Earthwork (CESMM)__________________________________________________________________________
ROCK CLASSIFICATION
Class E – Earthwork (CESMM)____________________________________________________________________________
ROCK (Grade I & II)
EARTH (Grade V & VI)
ROCK (Grade III & IV)
Fresh, monolithic, no fractures or cracks
Cracks and fissures, partially weathered
Totally weathered
THE PROBLEM
Class E – Earthwork (CESMM)____________________________________________________________________________
ROCK (Grade I & II)
EARTH (Grade V & VI)
SEDIMENTARY– HARD MATERIAL
THE PROBLEM
On Site:In between the two extreme material on site (earth and rock) we have “ HARD MATERIAL”
which is not been clearly defined not included in the scope of specification which the Contractor has to excavate but not
priced accordingly the current practice, it is usually been paid
under normal excavation i.e. excavation in earth
Class E – Earthwork (CESMM)____________________________________________________________________________
Resulting in:
Claim by the Contractor due to low productivity for excavation in natural hard material (get paid for earth excavation instead of excavation in rock)
THE SOLUTION
REDEFINE “ROCK”
ROCK or ARTIFICIAL HARD MATERIAL shall be material that requires the use of either hydraulic rock breaker, pneumatic tools or explosives. …..(CESMM)
DEFINE “ NATURAL HARD MATERIAL”
NATURAL HARD MATERIAL shall be material other than ROCK and ARTIFICIAL HARD MATERIAL that requires ripping and other specialised equipment. ….(CESMM)
Class E – Earthwork (CESMM)__________________________________________________________________________
“The Contractor gets paid For what he Did”
POINT TO TAKE NOTE
JKR TECHNIAL DIRECTIVE (ARAHAN TEKNIK) has redefine the term COMMON EXCAVATION, HARD MATERIAL and ROCK EXCAVATION (Draft)
COMMON EXCAVATION Common Excavation shall mean excavation in any
material either than hard material/rock excavation
HARD MATERIAL/ROCK EXCAVATION Hard material/rock excavation shall mean excavation
in any material that cannot be loosened by an excavator with a minimum mass of 44 tons and a minimum rating of 321 BHP. The excavator shall be in good condition and operated by an experience personnel skilled in the use of excavator equipment.
Class E – Earthwork (CESMM)__________________________________________________________________________
POINT TO TAKE NOTE…….cont.
HARD MATERIAL/ROCK EXCAVATION shall required one or a combination of the following
methods:
Excavation using track excavator exceeding a mass of 44 tones and 321 BHP rating
Ripping using a tractor unit of minimum weight of 37 tones and 305 BHP rating and a ripper attached
Excavation using pneumatic tools Open blasting Controlled blasting
Class E – Earthwork (CESMM)__________________________________________________________________________
- Hard Material & Rock will have a common rate -
COMPROMISE
ADDITIONAL DESCRIPTION RULE
Item description for EXCAVATION IN NATURAL HARD MATERIAL and ROCK shall state the method of excavation where appropriate …… A4
This clause will cater for Designer’s requirement to dictate the method of construction where specific need prevails
Class E – Earthwork (CESMM)__________________________________________________________________________
CLASS P – ENVIRONMENTAL PROTECTION AND ENHANCEMENT
Is of great concern lately in road projects, especially those road alignments traversing through environmentally sensitive areas
Quality & adequacy the mitigating measures varies from project to project depending on amount allocated for Environmental and Enhancement method of construction adhererance to the specification by the
contractor during construction concise statement of Owner’s requirement in
the Bill
Class P – Environmental Protection & Enhancement (CESMM)____________________________________________________
Class P – Environmental Protection & Enhancement (CESMM)______________________________________________________________
EIA REPORT
(MITIGATION MEASURES)
DRAWING & SPECS & BILL of QUANTITIES
DESIGNER
CONTRACTOR
ENVIROMENTAL MANAGEMENT
PLAN
HOW?
WHO?
WHAT?
WHEN?
OLD PRACTICE
itemised under Preliminaries description of Bill too general, up to the Contractor’s imagination in determining
the coverage required for the Environmental Protection & Enhancement
no indication as to what the work items included under this Class
allocated sum is Lump Sum (no detailed breakdown of work given)
e.g. ‘To carry out environmental protection works according to the existing laws and regulations’
Class P – Environmental Protection & Enhancement (CESMM)______________________________________________________________
CURRENT PRACTICE
separate Bill for Environmental Protection & Enhancement
work items to be indicated
item description has to be clear and concise
allocated as Provisional Sum or can be subjected to re-measurement of quantities at the end of contract
Class P – Environmental Protection & Enhancement (CESMM)______________________________________________________________
ITEMS COVERAGE
7 items coverage:
Appointment of Environmental Officer Preparation of Environmental Management Plan
(EMP) Pollution Control Measures Preservation of Flora Preservation of Fauna Environmental Monitoring Programme Environmental Audit
Class P – Environmental Protection & Enhancement (CESMM)______________________________________________________________
SAMPLE BQ
- CLASS P -
ENVIRONMENTAL PROTECTION AND
ENHANCEMENT
Code DESCRIPTION Unit Qty. Rate Amt.
P1 0 0
P 2 0 0
P 3 0 0P 3 1 1
P 3 1 2
P 3 1 3
P 3 1 4
CLASS P: ENVIRONMENTAL PROTECTION AND ENHANCEMENT
APPOINTMENT OF ENVIRONMENTAL OFFICERAppoint an Environmental Officer for the duration of the contract period.
PREPERATION OF ENVIRONMENTAL MANAGEMENT PLAN (EMP)To prepare the Environmental Management Plan (EMP) according to the guideline produced by the Department of Environment (DOE).
POLLUTION CONTROL MEASURESWater Quality Control, Silt FenceSupply and install 1.0m height silt fence including non-woven geo-textile and wooden post with dimension as shown in the drawing or as directed by the S.O.
Gabion WallTo construct gabion earth retaining wall of dimension as shown in the drawing using block stones of size 150mm
Sediment BasinTo construct sediment basin of the dimension:7m x 4m x 2m15m x 4m x 2m
Silt TrapTo construct Silt Trap of the following dimensions:2m x 3m4m x 6m
manmonth
sum
m2
m3
nrnr
nrnr
Code DESCRIPTION Unit Qty. Rate Amt.
P 3 2 1
P 3 2 2
P 3 2 3
P 3 3 1
P 3 4 0
Air Quality Control,Tyre Washing FacilitiesSupply portable water jet including operators, water tank and other necessary equipment needed to carry out the cleaning tyres of vehicles at the exits of the worksite
Water Browser TruckSupply Browser Truck to carryout water spraying 3 times a day along existing road and near settlement as directed by S.O
Lorry Wash TroughTo construct Lorry Wash Trough of dimension: 2m x 5m x 250mm deep
Noise Control, Noise BarrierSupply and install 1.0m height concrete reflective type noise barrier with dimension as shown in the drawing or as directed by the S.O
Vibration ControlTo carryout vibration control at the following locations:a. Hospital Besar Kuala Terengganu
nr
nr
nr
m2
sum
Code DESCRIPTION Unit Qty. Rate Amt.
P 4 1 1
P 4 1 2
P 4 1 3
CONSERVATION / PRESERVATIONPreservation of Flora,Floral Survey ReportConduct Flora Survey and prepare 30 copies of Floral Survey Report according to the format as set in Appendix
Floral Conservation PlanPrepare Floral Conservation Plan according to the format as set in the Appendix
Relocation of Treesa) To relocate the following flora species to the approved location within the construction site:1. Tongkat Awang2. Tualang Salak
b) To relocate the following flora species to the Arboretum at Pusat Penyelidekan Tumbuhan Hutan di Kuala Berang, Terengganu1. Kemuning Minyak2. Kemuning Kuning
sum
sum
nrnr
nrnr
Code DESCRIPTION Unit Qty. Rate Amt.
P 4 2P 4 2 1
P 4 2 2
P 4 2 3
Preservation of FaunaFauna Survey ReportConduct Fauna Survey and prepare 30 copies of Fauna Survey Reportaccording the format as set in Appendix
Relocation of FaunaTo relocate the following fauna species to Taman Negara Belum, Ulu Perak, Darul Redzuan:1. Gajah2. Harimau
Conservation of Archeological / Heritage
sum
nrnr