CERN Single Phase PrototypeInitial Discussion on Power/Space Requirements

Terri Shaw

Neutrino Platform

July 30, 2015

Page 2: CERN Single Phase Prototype Initial Discussion on Power/Space Requirements Terri Shaw Neutrino Platform July 30, 2015

Outline

• 35T Power

• “Simple” scale of power to CERN single phase prototype (may be room for optimization)

7/30/2015 T. Shaw | Neutrino Platform Meeting2

Page 3: CERN Single Phase Prototype Initial Discussion on Power/Space Requirements Terri Shaw Neutrino Platform July 30, 2015

Early Block Diagram of 35T – slightly out of date

7/30/2015 T. Shaw | Neutrino Platform Meeting3

Purity Monitor

Drift HV

Camera

Trig_Scint

TPC_PD

DAQ(2)

Page 4: CERN Single Phase Prototype Initial Discussion on Power/Space Requirements Terri Shaw Neutrino Platform July 30, 2015

35T test lab at Fermilab

7/30/2015 T. Shaw | Neutrino Platform Meeting4

35T Test lab at Fermilab

Page 5: CERN Single Phase Prototype Initial Discussion on Power/Space Requirements Terri Shaw Neutrino Platform July 30, 2015

Present Rack Configuration (excludes Drift HV)

7/30/2015 T. Shaw | Neutrino Platform Meeting5

Page 6: CERN Single Phase Prototype Initial Discussion on Power/Space Requirements Terri Shaw Neutrino Platform July 30, 2015

Rack Services – Rack Protection System (D. Huffman)

Consists of two parts—chassis and smoke sensor (SS 2W-B)

•Economical solution (~$650)

•Design includes:

–System Sensor photoelectric smoke sensor.

–EPO (Emergency Power Off for UPS).

–+12V Voltage output interlock.

–Two sets of NO/NC interlock contacts, AUX1 and AUX2.

–Audible alarm.

–Front panel reset button.

–Status bit to Slow Controls.

T. Shaw | Neutrino Platform Meeting6

Page 7: CERN Single Phase Prototype Initial Discussion on Power/Space Requirements Terri Shaw Neutrino Platform July 30, 2015

Rack Services: AC Distribution Options used at 35T

• SurgeX: SX-1120-RT• 120V/20A• 6 switched outlets• 2 un-switched outlets• 1 FP courtesy outlet• Interlock

• Eaton: PW309BA0U409• 208/3f/30A • Requires AC Switch Box• L21-30P, 5-20R

D. Huffman

T. Shaw | Neutrino Platform Meeting7

Page 8: CERN Single Phase Prototype Initial Discussion on Power/Space Requirements Terri Shaw Neutrino Platform July 30, 2015

35T HV Drift Rack

7/30/2015 T. Shaw | Neutrino Platform Meeting8

RACK Powered from one 120V/20A SurgeX: SX-1120-RT

Same equipment can be used for CERN Prototype Installation

Page 9: CERN Single Phase Prototype Initial Discussion on Power/Space Requirements Terri Shaw Neutrino Platform July 30, 2015

35T Trig_Scint Rack

7/30/2015 T. Shaw | Neutrino Platform Meeting9

RACK Powered from one 120V/20A SurgeX: SX-1120-RT

Questions: Do we have sufficient coverage with present 35T counters for CERN prototype?Will present equipment be reliable for CERN Proto and do we have spares?

Page 10: CERN Single Phase Prototype Initial Discussion on Power/Space Requirements Terri Shaw Neutrino Platform July 30, 2015

35T TPC_PD Rack

7/30/2015 T. Shaw | Neutrino Platform Meeting10

RACK Powered from two 120V/20A SurgeX: SX-1120-RT

For CERN Prototype we anticipate upgrades:Photon Detectors plan will gang SiPM readout (groups of 3) and require:

qty(15) 16-channel SSP (Silicon Photo-multiplier Signal Processor) Readout Modules (present SSPs are 12-channel)

Required Pulser/Calibration units for CERN Prototype:qty (2) Pulsers for Photon Detectors – similar to SSP unitsqty (8) Pulsers for FE modules

Weiner MPOD Crate for HV Wire Bias Will be very similar to 35T

Weiner MPOD Crate for FE LVRight now a full 10 slot MPOD crate is being used to supply 5

independent voltage channels to each FE card. If we stay with this design, we will need 9 MPOD crates to supply LV for 6 APA’s FE modules.

Page 11: CERN Single Phase Prototype Initial Discussion on Power/Space Requirements Terri Shaw Neutrino Platform July 30, 2015

35T Purity Monitor Rack

7/30/2015 T. Shaw | Neutrino Platform Meeting11

RACK Powered from two 120V/20A SurgeX: SX-1120-RT

For CERN Prototype, some type of purity monitor will be required.In the process of checking with cryostat team.

Page 12: CERN Single Phase Prototype Initial Discussion on Power/Space Requirements Terri Shaw Neutrino Platform July 30, 2015

35T Camera Rack

7/30/2015 T. Shaw | Neutrino Platform Meeting12

RACK Powered from one 120V/20A SurgeX: SX-1120-RT

35T has a set of 9 Cameras inside cryostat.

Page 13: CERN Single Phase Prototype Initial Discussion on Power/Space Requirements Terri Shaw Neutrino Platform July 30, 2015

35T DAQ Racks (2)

Each rack powered by one Eaton:PW309BA0U409 208/3φ/30Aand one 120V/20A SurgeX: SX-1120-RT

Mostly similar equipment list, but we will need to have two ATCA shelves to support a quantity of 15 COB readout boards.

DAQ racks to be enclosed air conditioned racks.

7/30/2015 T. Shaw | Neutrino Platform Meeting13

Page 14: CERN Single Phase Prototype Initial Discussion on Power/Space Requirements Terri Shaw Neutrino Platform July 30, 2015

Summary Table - Draft

7/30/2015 T. Shaw | Neutrino Platform Meeting14