ced412 report_urban flooding analysis
TRANSCRIPT
Title of the Project
Urban Flooding Analysis using GIS
Submitted by
Suraj Kumar
2010CE10407
A report of CED 412 - Project Part II submitted
in partial fulfilment of the requirements of the degree of
Bachelor of Technology
Department of Civil Engineering
Indian Institute of Technology Delhi
May, 2014
2
STUDENT’S CERTIFICATE
I do certify that this report explains the work carried out by me in the Course CED 412: Project –
Part II under the overall supervision of Prof. A. K. Gosain and Prof. Dhanya C.T. The contents of
the report including text, figures, tables, computer programs, etc. have not been reproduced from
other sources such as books, journals, reports, manuals, websites, etc. Wherever limited
reproduction from another source had been made the source had been duly acknowledged at that
point and also listed in the References.
Suraj Kumar
2010CE10407
3
SUPERVISOR’S CERTIFICATE
This is to certify that the report submitted by Suraj Kumar (2010CE10407) describes the work
carried out by him/her in the Course CED 412 – Project – Part II under my overall supervision.
Prof. A. K. Gosain
Prof. Dhanya C. T.
4
ACKNOWLEDGEMENT
I am very grateful to Prof. A. K. Gosain and Dr. Dhanya C. T. for the guidance, encouragement
and co-operation received throughout the project work. I owe the timely completion of this project
work to their valuable advice, support and suggestions.
I would also like to thank to bentley.com for providing with a free Bentley CivilStorm as under
IIT Delhi student license (a completion certificate of which has been attached with this report) and
Mr. Satish Kumar, from GIS Lab, for their assistance, particularly in acquiring various
measurements, support material.
Suraj Kumar
2010CE10407
May, 2014
5
ABSTRACT
This thesis deals with simulation and analysis of urban storm water drainage. The thesis review
current methods and models used in urban storm water drainage e.g. SCS-CN, Rational Method,
SWAT and SWMM. It provide a methodology for simulation of urban storm water drainage. Its
studies 10 major storm drains in Barapullah catchment of Delhi. It takes cross-section data from
Delhi Drainage Master Plan-1976. It then analyse these sections for current loadings and check
whether they are sufficient or not. The analysis is based on rational method and EPA-SWMM
model. For rational method, rainfall with 5 year return period with 5 hour rainfall duration has
been taken. For SWMM Model, rainfall of cumulative depth of 135.6 mm over 24 hours durations
has been taken to provide worst case scenario. It finds out problematic nodes and links in network.
Its estimate quantity of water being flooded from which node. It estimate which link is
overflowing, for how much time. After analyses it proposes certain recommendations in design of
drains which can be taken up to stop local level flooding problems. It then list down certain
limitation of methodology and datasets.
The objectives of this part of B.Tech Project are:
Review of current storm water modeling methods and models
Storm water modeling of a Barapulla catchment of Delhi using Bentley CivilStorm and
ArcGIS
Use of SWMM Model to calculate runoff
Use of Rational Method to calculate peak runoff
6
CONTENTS
Student’s Certificate........................................................................................................................ 2
Supervisor’s Certificate .................................................................................................................. 3
Acknowledgement .......................................................................................................................... 4
ABSTRACT .................................................................................................................................... 5
Contents .......................................................................................................................................... 6
List of figures .................................................................................................................................. 9
List of tables .................................................................................................................................. 10
Chapter 1: Introduction ............................................................................................................. 11
1.1 Urban Drainage Problem ................................................................................................ 11
1.2 Scope of Work ................................................................................................................ 11
1.3 Objectives ....................................................................................................................... 12
1.4 Report Structure ............................................................................................................. 13
Chapter 2: DEscription of the Study Area ................................................................................ 14
2.1 Geography ...................................................................................................................... 14
2.2 Drains ............................................................................................................................. 15
2.3 Cross-Section Details ..................................................................................................... 22
2.4 Subbasin Details ............................................................................................................. 22
2.5 Channel Details .............................................................................................................. 22
2.6 Storm Data Details ......................................................................................................... 23
Chapter 3: Literature review ..................................................................................................... 25
3.1 Summary ........................................................................................................................ 25
3.2 Methods and Models Used ............................................................................................. 26
7
3.2.1 SWAT Model .......................................................................................................... 26
3.2.2 SCS-CN Method of estimating runoff volume ....................................................... 26
3.2.3 Rational Method...................................................................................................... 27
3.2.4 SWMM Surface Runoff .......................................................................................... 31
3.2.5 Manning Formula.................................................................................................... 33
Chapter 4: Methodology ........................................................................................................... 34
4.1 Brief Overview ............................................................................................................... 34
4.2 Storm Data Calculation .................................................................................................. 36
4.2.1 Intensity Calculation ............................................................................................... 36
4.2.2 Rainfall Depth Calculation ..................................................................................... 38
Chapter 5: Analysis and Results ............................................................................................... 39
5.1 Verification..................................................................................................................... 39
5.1.1 Catchment Area Validation..................................................................................... 39
5.2 SWMM Model Results................................................................................................... 40
5.2.1 General Results ....................................................................................................... 40
5.3 Rational Method Results ................................................................................................ 45
5.3.1 Analysis................................................................................................................... 48
5.4 Recommendation ............................................................................................................ 49
Chapter 6: Discussion ............................................................................................................... 50
6.1 Model Application.......................................................................................................... 50
6.2 Drawbacks and limitations of the Methodology ............................................................ 50
6.3 Advantages of SWMM Method over Rational Method ................................................. 51
Chapter 7: Conclusion and Future Work .................................................................................. 52
7.1 Conclusion ...................................................................................................................... 52
7.2 Future Work ................................................................................................................... 52
8
Appenddix – A .............................................................................................................................. 53
References ..................................................................................................................................... 61
9
LIST OF FIGURES
Figure 1.1 Barapullah Catchment Boundary ................................................................................ 12
Figure 2.1: Extent of Barapullah Catchment ................................................................................ 14
Figure 2.2 Bently CivilStorm Model ............................................................................................ 15
Figure 2.3 Barapulla Catchment ................................................................................................... 16
Figure 2.4 Time Vs Depth curve of 27 July, 2009........................................................................ 23
Figure 2.5 : IDF Curve for Delhi .................................................................................................. 24
Figure 3.1 Representation of the SWMM/RUNOFF algorithm ................................................... 31
Figure 4.1: ArcSWAT Watershed Delineator Window ................................................................ 34
Figure 4.2: Hydrological Model ................................................................................................... 35
Figure 4.3 : Hydraulic Model........................................................................................................ 36
Figure 5.1: SWMM Model of Barapullah Catchment .................................................................. 40
Figure 5.2: Precipitation and Runoff in Barapullah Catchment ................................................... 40
Figure 5.3: Flow in major drains of Barapullah Catchment ......................................................... 41
Figure 5.4: Node Flooding Graph ................................................................................................. 41
Figure 5.5: Node Flooding Summary ........................................................................................... 42
Figure 5.6: Link Flow Summary ................................................................................................... 43
Figure 5.7: Flooding Nodes (shown in red) at t = 12:15 ............................................................... 44
Figure 5.8: Depth/ Rise (%) and Flow (m3/s)............................................................................... 47
10
LIST OF TABLES
Table 2.1 Drains in Barapulla Catchment ..................................................................................... 15
Table 2.2 Cross-Section Details in Drains .................................................................................... 17
Table 2.3: Subbasin Details .......................................................................................................... 18
Table 2.4: Channel Details ............................................................................................................ 20
Table 2.5: Other SWMM parameter assumed for all subbasins ................................................... 22
Table 3.1: Project Plan .................................................................................................................. 25
Table 3.2: Runoff Coefficient ....................................................................................................... 28
Table 4.1: Intensity Calculation .................................................................................................... 37
Table 4.2: Maximum Rainfall Depth in a year ............................................................................. 38
Table 5.1 Catchment Area Comparison ........................................................................................ 39
Table 5.2: Channel Flow Summary .............................................................................................. 45
Table 5.3: Catchment flow Summary ........................................................................................... 46
Table 5.4: Comparison of Discharge from Rational Method and DMP -1976 ............................. 48
11
CHAPTER 1: INTRODUCTION
1.1 Urban Drainage Problem
Urban flooding problems range from minors ones where water enters the basements of a few house
to major incidents, where large parts of cities are inundated for several days. Most modern cities
in the industrialized part of world usually experience small scale local problems mainly due to
insufficient capacity in their sewer systems during heavy rainstorms (Schmitt et al, 2004). Cities
in other regions, including those in South/South-East Asia, often have more severe problems
because of much heavier local rainfall and lower drainage standards. This situation continues to
get worse because many cities in the developing countries are growing rapidly, but without the
funds to extend and rehabilitate their existing drainage systems. Moreover New Delhi, capital of
India due to fast urbanization and rapid migration with not simultaneous progress in drainage
condition is suffering from serious waterlogging issues which result in loss to public infrastructure
and severe traffic jams. For example, population of New Delhi has grown from 4 million in 1971
to about 17 million in 2012.
1.2 Scope of Work
This project deals with analysis and simulation of storm water drainage in Barapulla catchment of
New Delhi. It studies 10 major storm drains which form the drainage network of Delhi. Delhi area
is 1484 km2 out which Barapulla catchment constitute around 140 km2 which is around one-tenth
of New Delhi. The project studies main tributaries of Kushak-Barapulla Nallah. It takes cross-
section data from 1976 Master Drainage Plan. It then analyse these sections (which were proposed
in 1976) for current loading and check whether they are sufficient or not. The analysis is based on
rational method and EPA – SWMM Model. After analyses it proposes certain recommendations
in design of drains which can be taken up to stop local level flooding problems.
12
Figure 1.1 Barapullah Catchment Boundary
1.3 Objectives
The objectives of this part of project is as follows
Review of storm water modeling methods and models
Storm water modeling of a Barapulla catchment of Delhi using Bentley CivilStorm and
ArcGIS
Use of SWMM Model to calculate runoff
Use of Rational Method to calculate peak runoff
13
1.4 Report Structure
Chapter 1: Introduction: This chapter provides the brief introduction about the problems,
objectives and scope of work for CED412- Major Project Part 2
Chapter 2: Description of study area: This chapter explains in detail about geography of
barapullah catchment and its network elements. It provides input data which is being used
for modelling.
Chapter 3: Literature Review: It begins with plan of B.tech Project Part-2 and list out
sources of literature which author has gone through. It then explain in details about methods
and model used in thesis
Chapter 4: Methodology: It provides brief overview of methodology and rainfall
calculation summary
Chapter 5: Analysis and Results: It provide results of SWMM Model and rational method.
It then verify the model using data from Drainage Master Plan for Delhi – 1976
Chapter 6: Discussion: It talks about the application of model. This chapter provides some
limitation and advantages of model.
Chapter 7: Conclusion: This chapter in brief provides the summary of thesis
14
CHAPTER 2: DESCRIPTION OF THE STUDY AREA
2.1 Geography
This project studies barapullah catchment of Delhi. Barapullah constitute around 140 km2 of area
which roughly around one-tenth of Delhi. It covers areas from Connaught place in North (Look at
Figure) to Mehrauli, Sangam Vihar in South, in east it covers till Nizamudin and in west it covers
portion of Vasant Vihar and RK Puram. It mostly consist of alluvial soil (Hydrologic Class D &
FAO Classification No. 3876).
Figure 2.1: Extent of Barapullah Catchment
15
2.2 Drains
The drains modelled in this study are presented in Table
Table 2.1 Drains in Barapulla Catchment
S.No Drain Name Length
Catchment
Area(in hectares)
1 AIIMs Drain 2289.50988 1799.17
2 Andrews Gunj Drain 3708.015119 398.5175
3 Barapullah Nallah 3681.066054 14083.945
4 Chirag Delhi Drain 9188.034697 5799.165
5 Greater Kailash Drain 1424.718489 434.64
6 Kushak Nallah 7858.408153 4879.5125
7 Lajpat Nagar Drain 4303.854535 442.8325
8 Malviya Nagar Drain 4944.39992 1112.78
9 Nauroji Nagar Drain 6859.92319 1591.65
10 Sunehri Pullah Nallah 1799 2533.3525
NOTE: Catchment Area values have been derived from watershed delineation using ArcSWAT
Figure 2.2 Bently CivilStorm Model
17
Table 2.2 Cross-Section Details in Drains
Drain Name Label
Elevation (Ground) (m)
Elevation (Invert) (m)
Bottom Width (m)
Height (m)
Slope (Left Side) (H:V)
Slope (Right Side) (H:V) Manning's n
AIIMs Drain CS-17 216.1 213.6 15.00 2.50 1.00 1.00 0.025
AIIMs Drain CS-30 211.3 208.8 15.00 2.50 1.00 1.00 0.025
Andrews Gunj Drain CS-20 221.52 218.72 3.00 2.80 0.00 0.00 0.025
Barapulla Nallah CS-26 201.87 198.37 50.00 3.50 1.50 1.50 0.025
Barapulla Nallah CS-32 202 198.5 50.00 3.50 1.50 1.50 0.025
Chirag Delhi Drain CS-3 205.1 202.8 24.00 2.30 1.25 1.25 0.025
Chirag Delhi Drain CS-14 213.55 211.2 20.00 2.35 1.25 1.25 0.025
Chirag Delhi Drain CS-16 206.01 203.71 24.00 2.30 1.25 1.25 0.025
Chirag Delhi Drain CS-21 209.06 206.71 20.00 2.35 1.25 1.25 0.025
Chirag Delhi Drain CS-24 221.12 218.92 17.00 2.20 1.25 1.25 0.025
Chirag Delhi Drain CS-27 227 224.8 17.00 2.20 1.25 1.25 0.025
Chirag Delhi Drain CS-29 224.56 222.36 17.00 2.20 1.25 1.25 0.025
Chirag Delhi Drain CS-34 208 205.7 24.00 2.30 1.25 1.25 0.025
Greater Kailash Drain CS-13 222.14 220.24 6.50 1.90 1.00 1.00 0.025
Kushak Nallah CS-9 216.01 214.81 20.00 1.20 1.00 1.00 0.025
Kushak Nallah CS-10 215 213.5 30.00 1.50 1.00 1.00 0.025
Kushak Nallah CS-15 208 205.5 40.00 2.50 1.00 1.00 0.025
Kushak Nallah CS-22 222.4 221.2 20.00 1.20 1.00 1.00 0.025
Lajpat Nagar Drain CS-7 211.37 210.37 5.00 1.00 0.70 0.70 0.025
Lajpat Nagar Drain CS-8 212.85 211.85 5.00 1.00 0.70 0.70 0.025
Lajpat Nagar Drain CS-11 210.1 209.1 10.00 1.00 1.23 1.23 0.025
Lajpat Nagar Drain CS-12 214.82 213.82 5.00 1.00 0.70 0.70 0.025
Malviya Nagar Drain CS-1 238.55 236.55 3.00 2.00 1.00 1.00 0.025
18
Drain Name Label
Elevation (Ground) (m)
Elevation (Invert) (m)
Bottom Width (m)
Height (m)
Slope (Left Side) (H:V)
Slope (Right Side) (H:V) Manning's n
Malviya Nagar Drain CS-2 234 232 3.00 2.00 1.00 1.00 0.025
Malviya Nagar Drain CS-23 238.29 236.29 3.00 2.00 1.00 1.00 0.025
Nauroji Nagar Drain CS-5 225.15 222.95 10.00 2.20 1.25 1.25 0.025
Nauroji Nagar Drain CS-6 223 220.8 10.00 2.20 1.25 1.25 0.025
Nauroji Nagar Drain CS-19 235.15 231.95 5.00 3.20 1.25 1.25 0.025
Nauroji Nagar Drain CS-33 218.2 216 15.00 2.20 1.25 1.25 0.025
Sunehri Pullah Nallah CS-4 203 199.5 50.00 3.50 1.50 1.50 0.025
Sunehri Pullah Nallah CS-18 203 199.5 50.00 3.50 1.50 1.50 0.025
Sunehri Pullah Nallah CS-25 208.77 205.27 30.00 3.50 2.50 2.50 0.025
Sunehri Pullah Nallah CS-31 204 200.5 30.00 3.50 2.50 2.50 0.025
Table 2.3: Subbasin Details
Subbasin Area (hectares)
Slope (%)
Longest flow path length (m)
C CN Characteristic Width (m)
Time of Concentration (min)
Time of Concentration (Progressive) ( min)
Imperviousness (%)
Roughness Coefficient (n)
Depression Storage ( in mm)
1 827.77 3.56 7415.18 0.50 84.09 1116.31 67.12 146.99 54.92 0.018 2.99
2 470.95 1.28 4220.67 0.51 85.11 1115.82 64.60 144.47 57.61 0.018 2.89
3 693.63 1.84 6684.56 0.55 88.66 1037.66 79.87 79.87 66.95 0.016 2.53
4 88.21 3.99 1690.13 0.56 89.26 521.90 20.58 20.58 68.71 0.016 2.46
5 0.08 5.23 54.32 0.70 95.00 13.81 1.31 1.31 100.00 0.012 1.27
6 429.08 3.16 5399.28 0.63 93.16 794.70 55.09 55.09 83.26 0.014 1.91
7 452.72 1.80 5673.73 0.55 89.46 797.93 71.05 71.05 65.30 0.017 2.59
8 14.47 6.44 1425.27 0.47 81.56 101.54 15.01 15.01 48.82 0.019 3.22
9 442.83 2.13 5481.14 0.67 93.85 807.92 64.87 64.87 93.43 0.013 1.52
10 89.21 3.31 3371.37 0.66 93.12 264.61 37.63 37.63 89.86 0.013 1.66
19
Subbasin Area (hectares)
Slope (%)
Longest flow path length (m)
C CN Characteristic Width (m)
Time of Concentration (min)
Time of Concentration (Progressive) ( min)
Imperviousness (%)
Roughness Coefficient (n)
Depression Storage ( in mm)
11 1215.45 4.91 8889.56 0.48 83.77 1367.28 68.21 68.21 49.27 0.019 3.20
12 184.03 2.41 3184.39 0.64 92.55 577.92 40.67 40.67 84.57 0.014 1.86
13 346.21 3.07 3348.06 0.62 92.45 1034.07 38.54 38.54 79.63 0.015 2.05
14 462.51 2.19 5662.75 0.63 92.37 816.76 65.73 65.73 81.13 0.014 1.99
15 270.11 1.53 4223.66 0.65 92.63 639.52 60.29 60.29 88.83 0.013 1.70
16 398.52 1.96 5983.84 0.51 87.85 665.99 71.63 71.63 55.26 0.018 2.97
17 420.77 2.33 6409.20 0.57 89.22 656.51 70.69 70.69 70.45 0.016 2.40
18 76.45 2.20 2069.59 0.45 85.31 369.40 30.25 30.25 41.84 0.020 3.49
19 782.93 7.43 7104.23 0.52 89.23 1102.06 48.94 48.94 51.84 0.018 3.10
20 133.35 2.78 3443.97 0.60 90.85 387.19 40.92 40.92 75.87 0.015 2.19
21 434.64 2.89 4992.24 0.60 91.12 870.63 53.68 53.68 74.79 0.015 2.23
22 533.09 5.95 6465.77 0.35 78.85 824.48 49.57 79.82 20.25 0.022 4.31
23 377.52 3.94 6943.40 0.35 80.04 543.71 61.38 61.38 21.66 0.022 4.25
24 391.35 6.23 7051.34 0.36 79.24 554.99 52.07 82.32 21.43 0.022 4.26
25 529.48 2.74 7160.44 0.51 88.36 739.45 72.30 72.30 56.22 0.018 2.94
26 263.43 2.72 3297.68 0.49 86.08 798.83 39.92 39.92 48.45 0.019 3.23
27 0.51 4.89 116.75 0.57 88.17 43.68 2.43 2.43 67.16 0.016 2.52
28 315.77 5.20 7015.15 0.58 88.31 450.12 55.60 55.60 71.09 0.016 2.37
29 1112.78 4.35 9267.11 0.42 85.89 1200.78 73.79 73.79 35.92 0.020 3.71
30 865.14 4.44 7913.64 0.60 90.88 1093.23 64.87 64.87 74.31 0.015 2.25
31 556.53 3.55 6678.57 0.52 88.32 833.30 62.05 62.05 56.12 0.018 2.94
32 319.59 9.54 3708.92 0.32 74.32 861.67 26.95 88.99 10.83 0.024 4.67
33 451.52 8.09 5528.59 0.32 72.34 816.70 39.06 101.10 14.39 0.023 4.53
20
Table 2.4: Channel Details
S.NO. Label Start Node Invert (Start) (m) Stop Node Invert (Stop) (m) Length (m) Slope (Calculated) (%)
1 AIIMs Drain_1 CS-17 213.6 CS-30 208.8 519.4 0.924
2 AIIMs Drain_2 CS-30 208.8 CS-15 205.5 1756.5 0.188
3 Andrews Gunj Drain CS-20 218.72 CS-21 206.71 3707.4 0.324
4 Barapullah Nallah_1 CS-18 199.5 CS-32 198.5 1210 0.083
5 Barapullah Nallah_2 CS-32 198.5 CS-26 198.37 2335 0.006
6 Chirag Delhi Drain_1 CS-27 224.8 CS-29 222.36 724.3 0.337
7 Chirag Delhi Drain_2 CS-29 222.36 CS-24 218.92 1279.3 0.269
8 Chirag Delhi Drain_3 CS-24 218.92 CS-14 211.2 1990.4 0.388
9 Chirag Delhi Drain_4 CS-14 211.2 CS-21 206.71 1647.7 0.273
10 Chirag Delhi Drain_5 CS-21 206.71 CS-34 205.7 1063.2 0.095
11 Chirag Delhi Drain_6 CS-34 205.7 CS-16 203.71 777.1 0.256
12 Chirag Delhi Drain_7 CS-16 203.71 CS-3 202.8 1096.8 0.083
13 Chirag Delhi Drain_8 CS-3 202.8 CS-4 199.5 184.2 1.791
14 Greater Kailash Drain CS-13 220.24 CS-14 211.2 1423.9 0.635
15 Kushak Nallah_1 CS-22 221.2 CS-9 214.81 3726.3 0.171
16 Kushak Nallah_2 CS-9 214.81 CS-10 213.5 627.5 0.209
17 Kushak Nallah_3 CS-10 213.5 CS-15 205.5 1519 0.527
18 Kushak Nallah_4 CS-15 205.5 CS-16 203.71 1977 0.091
19 Lajpat Nagar Drain_1 CS-8 211.85 CS-7 210.37 603.3 0.245
20 Lajpat Nagar Drain_2 CS-12 213.82 CS-7 210.37 613.3 0.563
21 Lajpat Nagar Drain_3 CS-7 210.37 CS-11 209.1 211 0.602
22 Lajpat Nagar Drain_4 CS-11 209.1 CS-18 199.5 2442.3 0.393
23 Malviya Nagar Drain_1 CS-23 236.29 CS-2 232 590 0.727
24 Malviya Nagar Drain_2 CS-2 232 CS-24 218.92 3411.5 0.383
25 Malviya Nagar Drain_3 CS-1 236.55 CS-2 232 146.6 3.104
21
S.NO. Label Start Node Invert (Start) (m) Stop Node Invert (Stop) (m) Length (m) Slope (Calculated) (%)
26 Nauroji Nagar Drain_1 CS-5 222.95 CS-6 220.8 409.8 0.525
27 Nauroji Nagar Drain_2 CS-19 231.95 CS-6 220.8 3635.8 0.307
28 Nauroji Nagar Drain_3 CS-6 220.8 CS-33 216 1132 0.424
29 Nauroji Nagar Drain_4 CS-33 216 CS-10 213.5 1670 0.15
30 Outfall Drain CS-26 198.37 O-1 190 637.7 1.313
31 Sunehri Pullah Nallah_1 CS-25 205.27 CS-31 200.5 1122.7 0.425
32 Sunehri Pullah Nallah_2 CS-31 200.5 CS-4 199.5 627.1 0.159
33 Sunehri Pullah Nallah_3 CS-4 199.5 CS-18 199.5 32.1 0
22
2.3 Cross-Section Details
The cross-section used in modelling have been taken from proposed recommendation of storm
water drainage master plan 1976. Each drain or Nallah has been assumed to have trapezoidal cross-
section with varying width and height. Different cross-sections have been assumed at different
intervals along drain to simulate real-life conditions. (See Table 2.2).
2.4 Subbasin Details
Sub basin details (see table 2.3) have been derived from analysis carried in ArcSWAT and MS
Excel. Watershed parameters for example slope, longest flow path length, etc. have been derived
from watershed delineation carried out in ArcSWAT. For parameters such as C or CN, analysis
done on the basis of soil cover and land use to determine their value for each subbasin using HRU
(generated from SWAT) report in MS Excel. For Other parameter required in SWMM model
following values have been assumed for each catchment. (See table 2.5) (EPA, 2009)
Table 2.5: Other SWMM parameter assumed for all subbasins
Parameter Value
Percent of impervious area without depression
storage
25
Storage (Impervious Depression) (mm) 1.27
Storage (Pervious Depression) (mm) 5.08
Drying Time (days) 10
2.5 Channel Details
Channel details have been shown in table 2.4. It has been derived from cross-section details and
catchment detail. Note that while modelling one should look at its slope column to check whether
any link has slope close to 0 slope or negative values as it may leads to errors in modelling.
23
2.6 Storm Data Details
This thesis uses two models for simulation of storm water. One is rational method is used which
is used with rainfall of 5 hours duration with return period of 5 years. (See Figure 2.5 : IDF Curve
for Delhi). For second model i.e. SWMM, 24 hours rainfall duration with cumulative depth of
135.6 mm has been used (It occurred on 27 July, 2009). It has been chosen because it has the
highest cumulative depth in daily rainfall data available with user (for more information see 0).
Figure 2.4 Time Vs Depth curve of 27 July, 2009
0.0
2.0
4.0
6.0
8.0
10.0
12.0
14.0
16.0
18.0
20.0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Rai
nfa
ll D
pet
h In
crem
enta
l (in
mm
)
Time (in Hrs)
Rainfall of 24 Hours Duration (27 July, 2009)
25
CHAPTER 3: LITERATURE REVIEW
3.1 Summary
For the purpose of collecting information about current practices and methodologies in storm water
simulation, author has referred to four research papers (details have been mentioned in References
section). For information on cross-section details about drains and their respective parameters,
author has referred to “Master Plan for drainage of storm water – 1976” by Flood Control Wing,
Delhi Administration. (FCW, 1976) For more information about methods used in modeling and
calculation e.g. rational method, author has repeatedly used “Engineering Hydrology” by K
Subramanya. Since this project requires to use ArcSWAT, SWMM and Bentley Civil Storm author
has referred their respective manuals (details have been mentioned in references section.).
Table 3.1: Project Plan
S. No. Steps Jan Feb March April
1 Literature Review
2
Basic Model of surface runoff and routing
via natural drains in Barapulla catchment
of Delhi
3
Building a more realistic storm water
model of a Barapulla using natural and
stormwater drains
4 Analysis (Hydrological and Hydraulic
Modeling using CivilStorm or SWMM)
5 Flood Inundation Mapping and Design
recommendations
6 Report writing
26
3.2 Methods and Models Used
From literature review, methods and models which are being used in simulation and analysis have
been described below.
3.2.1 SWAT Model
The Soil and Water Assessment Tool (SWAT) is a physically-based continuous-event hydrologic
model developed to predict the impact of land management practices on water, sediment, and
agricultural chemical yields in large, complex watersheds with varying soils, land use, and
management conditions over long periods of time.
For simulation, a watershed is subdivided into a number of homogenous subbasins (hydrologic
response units or HRUs) having unique soil, slope and land use properties. (Winchell et al. , 2013)
The input information for each subbasin is grouped into categories of weather; unique areas of
land cover, soil, and management within the subbasin; ponds/reservoirs; groundwater; and the
main channel or reach, draining the subbasin. The loading and movement of runoff, sediment,
nutrient and pesticide loadings to the main channel in each subbasin is simulated considering the
effect of several physical processes that influence the hydrology. (Chen et al. , 2009). This thesis
uses SWAT for identifying watershed boundaries, slope, longest flow path length, land use and
soil composition of each subbasin in the catchment.
3.2.2 SCS-CN Method of estimating runoff volume
1.1.1.1 Modelling equation and theory
SCS-CN method, developed by soil conservation services (SCS) of USA in 1969. It relies on only
one parameter, CN (Curve Number). The runoff curve number (also called a curve number or
simply CN) is an empirical parameter used in hydrology for predicting direct runoff or infiltration
from rainfall excess (Subramanya, 2008). The runoff curve number is based on the area's
hydrologic soil group, land use, treatment and hydrologic condition. The SCS-CN method is based
on the water balance equation of the rainfall in a known interval of time ∆t, which can be expressed
as
27
𝑃 = 𝐼𝑎 + 𝐹 + 𝑄 (water balance equation) Eq: 3.1
The runoff equation is:
𝑄 =(𝑃 − 𝐼𝑎)
2
𝑃 − 𝐼𝑎+𝑆 𝑃 > 𝐼𝑎 Eq: 3.2
𝑄 = 0 𝑃 < 𝐼𝑎 Eq: 3.3
𝑆 (𝑚𝑚) = 254(100
𝐶𝑁− 1) Eq: 3.4
Where
CN has a range from 30 to 100; lower numbers indicate low runoff potential while larger numbers
are for increasing runoff potential. The lower the curve number, the more permeable the soil is. As
can be seen in the curve number equation, runoff cannot begin until the initial abstraction has been
met.
3.2.3 Rational Method
Assumptions and Model
The most widely used method for estimating peak storm-water runoff is called the rational-formula
method. This formula assumes (a) that the rate of storm-water run-off from an area is a direct
function of the average rainfall rate during the time that it takes the runoff to travel from the most
remote point of the tributary area to the inlet or drain, (b) that the average frequency of occurrence
of the peak runoff equals the average frequency of occurrence of the rainfall rate, and (c) that the
quantity of storm water lost due to evaporation, infiltration, and surface depressions remains
constant throughout the rainfall.
P = Total precipitation
𝐼𝑎= Initial abstraction = 0.2 S or 0.05 S
F = cumulative infiltration excluding 𝐼𝑎
Q = direct surface runoff
S = Potential maximum retention
CN = Curve number
28
The coefficient of runoff is a coefficient which accounts for storm-water losses attributed to
evaporation, infiltration, and surface depressions. The peak value of the flow rate Q of storm-water
runoff is estimated using the following equations:
Q = CIA ft3/s Eq: 3.5
Q = /h Eq: 3.6
Where C = coefficient of runoff
I = rainfall rate for a specified rainfall duration and average frequency of
occurrence, in/h (cm/h)
A = tributary area to the inlet or drain, acres (m2)
Table 3.2: Runoff Coefficient
CHARACTER OF SURFACE COEFFICIENT OF RUNOFF
Pavement:
Asphaltic and concrete 0.70 – 0.95
Brick 0.70 – 0.85
Roofs 0.75 – 0.95
Lawns And Sandy Soil:
Flat, 2 percent 0.05 – 0.10
Average, 2 to 7 percent 0.10 – 0.15
Steep, 7 percent 0.15 – 0.20
Lawns, heavy soil:
Flat, 2 percent 0.13 – 0.17
Average, 2 to 7 percent 0.18 – 0.22
Steep, 7 percent 0.25 – 0.35
A given site may have areas with different coefficients of runoff all draining to a common point.
It is desirable to use a single coefficient of runoff for the entire area. Such a dimensionless
coefficient (termed a weighted coefficient of runoff) Cw, can be calculated using
29
Cw = (𝐴1 𝑥 𝐶1) + (𝐴2 𝑥 𝐶2) +⋯. + (𝐴𝑛 𝑥 𝐶𝑛) 𝐴1+𝐴2+⋯+𝐴𝑛 Eq: 3.7
Where A1, A2, and An are the area in acres (m2), and C1, C2, and Cn are the corresponding
coefficients of runoff of the individual tributary areas to a common point. A weighted coefficient
of runoff must be calculated for each segment of the stormwater drainage system.
In the design of a storm-water drainage system, runoff must be transported as fast as it is received,
unless specific provisions are made for ponding of the excess runoff which the storm-water
drainage system cannot handle. Determination of the rainfall rate to be used for design purposes
involves an evaluation of the potential damage which could occur as a result of flooding. If the
potential damage from flooding is high, the selection of an average frequency of occurrence of 50
or 100 years may be warranted. If the potential damage from flooding is rather slight, the selection
of an average frequency of occurrence of 5, 10, or 25 years may be appropriate. In many cases, the
local authority having jurisdiction will determine the average frequency of occurrence to be used
in the design of storm-water drainage systems.
IDF equation for Indian region
Ram Babu in 1979 developed an equation analysing rainfall characteristics for the 42 self-
recording rain gauge stations all over India.
𝑖 = 𝐾𝑇𝑎
(𝑡+𝑏)𝑛 Eq: 3.8
Where
i is the rainfall intensity in cm/hr
T is the return period in years
t is the storm duration in hours, and
K, a, b and n are coefficients varying with location
For New Delhi region
K = 5.208, a = 0.157, b = 0.5, n = 1.107
30
Time of concentration calculation
Time of concentration has been defined as the time taken for a drop of water from the farthest part
of catchment to reach the outlet. To calculate time of concentration, Kirpich Equation (1940) have
been used. It relates time of concentration with length of travel and slope of catchment
𝑡𝑐 = 0.01947 𝐿0.77𝑆−0.385 Eq: 3.9
Where tc = time of concentration (minutes)
L = maximum length of travel of water (m), and
S = slope of catchment = ∆H/L in which
∆H = difference in elevation between the most remote point on the catchment and the outlet
See Table 2.3 for information about time of concentration for each sub-basin. Note that table 2.3
give two time of concentration. First one i.e time of concentration is the time taken by a drop of
water to outlet of catchment. Another is time of concentration (progressive) which give actual time
taken by drop of water to reach drain inlet node.
31
3.2.4 SWMM Surface Runoff
The United States Environmental Protection Agency (EPA) Storm Water Management Model
(SWMM) is a dynamic rainfall-runoff-subsurface runoff simulation model used for single-event
to long-term (continuous) simulation of the surface/subsurface hydrology quantity and quality
from primarily urban/suburban areas. (EPA, 2009) The hydrology component of SWMM operates
on a collection of subcatchment areas divided into impervious and pervious areas with and without
depression storage to predict runoff and pollutant loads from precipitation, evaporation and
infiltration losses from each of the subcatchment. (SWMM-Runoff-Algorithm, n.d.)
Figure 3.1 Representation of the SWMM/RUNOFF algorithm
The method employs the surface water budget approach and may be visualized as shown in Figure
3-1. The incident rainfall intensity is the input to the control volume on the surface of the plane;
the output is a combination of the runoff Q and the infiltration f. Considering a unit breadth of the
catchment the continuity and dynamic equations which have to be solved are as shown in equations
below
𝑄 = 𝐵𝐶𝑚
𝑛 𝑆1/2(𝑦 − 𝑦𝑑)5/3 (Dynamic equation) Eq: 3.10
32
𝑖𝐿 = (𝑓𝐿 +𝑄
𝐵) + 𝐿
∆𝑦
∆𝑡 (Continuity equation) Eq: 3.11
Where L = overland flow length
B = catchment breadth
𝐶𝑚 = 1.0 for metric units
1.49 for Imperial or US customary units
n = Manning roughness coefficient
yd = surface depression storage depth
f = infiltration
Modelling Parameters required in simulation (EPA, 2009)
Area: This the area bounded by the subcatchment boundary.
Width: The width can be defined as the subcatchment’s area divided by the length of the
longest overland flow path that water can travel.
Slope: This is slope of the land surface over which runoff flows.
Imperviousness: This is the percentage of the subcatchment area that is covered by
impervious surfaces, such as roofs and roadways, through which rainfall cannot infiltrate.
Roughness coefficient: The roughness coefficient reflects the amount of resistance that
overland flow encounters as it runs off the subcatchment surface.
Depression storage: Depression storage corresponds to a volume that must be filled prior
to the occurrence of any rainfall.
Percent of impervious area without depression storage: This parameter accounts for
immediate runoff that occurs at the beginning of rainfall before depression storage is
satisfied.
Infiltration Model: It’s the method used for computing infiltration loss on the pervious area
of subcatchment. For this project SCS-CN method has been used
Precipitation Input: Precipitation is the principal driving variable in rainfall-runoff-quantity
simulation. For this project, Time vs Depth curve of 24 hrs duration of 27 July, 2009 has
been used.
33
Drying Time (days): Its show evaporation rate and losses during period of analysis.
3.2.5 Manning Formula
The Manning formula is an empirical formula estimating the average flow of a liquid flowing in a
conduit that does not completely enclose the liquid, i.e., open channel flow. All flow in so-called
open channels is driven by gravity.
𝑄 =1
𝑛 𝐴 𝑅2/3𝑆1/2 Eq: 3.12
Where
The Manning formula is used to estimate the average velocity of water flowing in an open channel
in locations where it is not practical to construct a weir or flume to measure flow with greater
accuracy. The hydraulic radius is a measure of a channel flow efficiency. Flow speed along the
channel depends on its cross-sectional shape (among other factors), and the hydraulic radius is a
characterisation of the channel that intends to capture such efficiency. The Manning coefficient,
often denoted as n, is an empirically derived coefficient, which is dependent on many factors,
including surface roughness and sinuosity.
A = Area of cross-section
S = Slope
P = wetted parameter (the portion of cross-section’s perimeter that is “wet”)
R = Hydraulic radius = A/P
34
CHAPTER 4: METHODOLOGY
4.1 Brief Overview
The modelling exercise begins with importing digital elevation model of barapullah catchment and
drains network in ArcSWAT (see Figure 4.1). Then drain network is burned in DEM such that all
the water from points nearer to drains falls in it (Note that this exercise can be done without drain
network as well i.e. using only DEM but when we input drain network our accuracy of model
improves). (Mark et al. , 2004) Then model computes flow direction and accumulates flows to
generate stream network based upon threshold values given in hectares. For this thesis 300 hectares
has been used as threshold values. After stream network is generated, we need to select a point in
stream network for which we want to generate watersheds. After watershed is generated, model
calculates watershed parameters e.g. characteristic width, longest flow path, etc. Next soil data and
land use data need to be imported in model. For this project, Soil data has been taken from FAO
(Food and Agriculture Organization)
Figure 4.1: ArcSWAT Watershed Delineator Window
35
And land use data has been taken from National Remote Sensing Centre (NRSC). Soil data and
land use data are required to calculate runoff parameters e.g. curve number (SCS-CN) or runoff
coefficient (rational method) (Weng, 2001). Now after importing soil data and land use data, model
creates HRUs (Hydrologic Response Units) and generate watershed reports which give percentage
of different soil and land use types in each watershed which would then be used to input parameters
in hydraulic modelling. Refer to figure 4.2 for brief summary of hydrologic model steps.
Figure 4.2: Hydrological Model
Now after building watershed subbasin in hydrologic model, we need to import subbasin and drain
network in CivilStorm. Then we need to define runoff method as EPA-SWMM or rational method,
on the basis of which we have to input watershed parameters such as time of concentration or CN
value. This project has used Modelbuilder tool in CivilStorm to import drain network and TRex
tool to assign elevation values to nodes in network. After assigning values to network elements,
Storm events are defined. For this project two storm events such as IDF equation for Delhi and
rainfall hyetograph for 24 hours duration have been used (see 2.6 for more details). Next step is
define calculation option using solver method.
Input Digital Elevation Model
(DEM)
Input Drain Network
Flow direction and
accumulation
Stream network Definition
Outlet/Inlet definition
Watershed Delineation
Calculation of subbasin
parameters
Input Land use data
Input Soil data
Slope characterization
HRU Creation
36
Figure 4.3 : Hydraulic Model
CivilStorm offers three methods to compute which are mentioned below
Explicit –SWMM solver
GVF- Rational (StormCAD)
Implicit (SewerGEMS dynamic wave solver)
For SWMM model, explicit – SWMM solver has been used and for rational method implicit
method has been used. Next model is exported to SWMM format from Bentley CivilStorm
format. This has been done as SWMM provide much more flexibility in analysing results.
4.2 Storm Data Calculation
4.2.1 Intensity Calculation
The model uses rational method to calculate runoff from a catchment. For analyses, rainfall event
of 5-year return period with 5 hour duration has been taken. (See Table 4.1: Intensity Calculation).
Input Runoff modelInput natural drains
network
Define catchment runoff as an input to
a node in networkInput Storm data
Define Calculation options
Validation and Calibration of Model
Compute Analyse results
37
Table 4.1: Intensity Calculation
Intensity Calculation
K 5.208
n 1.107
a 0.157
b 0.5
Return Period T(Years)
Intensity(cm/hr) 1 2 5 10
Durations (Hours)
1 3.324589 3.706804 4.28032 4.772412
2 1.88865 2.10578 2.431586 2.711137
6 0.655807 0.731202 0.844334 0.941404
12 0.317974 0.35453 0.409383 0.456448
24 0.150961 0.168316 0.194358 0.216703
38
4.2.2 Rainfall Depth Calculation
For this project, worst possible case to check efficacy of drains has been taken. From table 4-2 it’s
clear that maximum rainfall occurred in 2009 with 135.75 mm as a cumulative depth. From record
this rainfall occurred on 27 July in 2009.
Table 4.2: Maximum Rainfall Depth in a year
Max Rainfall (in mm of 24 hrs duration)
IMD Rain gauge SFD Rain gauge
Years
1997 69.8
1998
1999
2000
2001
2002
2003 69.9
2004
2005
2006 22.77
2007
2008 70.14
2009 135.7597 41.02
2010 109.3
2011 78.7 38.34
2012 60.9 46.37
2013 54.8 9.35
NOTE:
Low values are due to non-availability of data for whole year
39
CHAPTER 5: ANALYSIS AND RESULTS
5.1 Verification
Verification is the process of checking the model against independent data to determine its
accuracy whilst calibration is the process of adjusting model parameters to make the model fit with
measured conditions.
5.1.1 Catchment Area Validation
To verify the watershed model built with ArcSWAT, author has used data from Master Plan for
Drainage of Storm Water, 1976. Catchment areas for each drain calculated using SWAT and
Master Plan 1976 have been presented in Table 5.1 for comparison.
Table 5.1 Catchment Area Comparison
S.No. Drain Name
Catchment Area(in hectares)
From SWAT Model
Catchment (in hectares)
From DMP 1976
1 AIIMs Drain 1799.17 2060
2 Andrews Gunj Drain 398.5175 503
3 Barapullah Nallah 14083.945 17227.5**
4 Chirag Delhi Drain 5799.165 5300
5 Greater Kailash Drain 434.64 482.5
6 Kushak Nallah 4879.5125 4804
7 Lajpat Nagar Drain 442.8325 460
8 Malviya Nagar Drain 1112.78 269*
9 Nauroji Nagar Drain 1591.65 1700
10 Sunehri Pullah Nallah 2533.3525 1918*
*Note large difference in some drain is due change in drain network i.e. addition of drain which
have somewhere reduced the catchment area of other drain or in catchment area is increased due
to extension of drain.
**Barapullah Nallah catchment is basically the whole Barapullah region. Area values have been
obtained by adding catchments areas of all other drains. That is why we have such large difference
in their values.
40
5.2 SWMM Model Results
The schematic diagram of SWMM model has been shown in figure 5-1. For detailed results see
Appendix - A
Figure 5.1: SWMM Model of Barapullah Catchment
5.2.1 General Results
From figure 5.2 we can see that from total precipitation depth of 135 mm, runoff of about 115.7
mm has been generated which results in runoff coefficient = 115.7/135.6 = 0.853. It means that
Figure 5.2: Precipitation and Runoff in Barapullah Catchment
41
more than 85% of rainfall is converted into runoff which is intuitive also as barapullah catchment
is highly urbanized as it covers posh areas of south Delhi and central Delhi.
Figure 5.3: Flow in major drains of Barapullah Catchment
Figure 5.3 show flow (m3/s) in major tributaries of Barapullah catchment. Here we can analyse
that Chirag Delhi is the major tributary followed by Kushak Nallah which is followed by Sunehri
Pullah Nallah.
Figure 5.4: Node Flooding Graph
42
Figure 5.4 shows a profile graph of CS-2, CS-9, CS-11, CS-14 and CS-15. From this graph we
can find out how much water is being flooded a particular instant of time from a node. For more
detailed study of about how much water is being flooded from each node, let’s look at figure 5.5.
Figure 5.5: Node Flooding Summary
From figure 5.5 we can get information about how much flood volume is being generated at
node and how much ponded depth (maximum depth) it has. For detailed outlook see Figure 5.7.
Figure 5.6 display link flow summary. We can get information about maximum flow in CMS
from the figure 5.6. And also by using parameter Max/Full Depth, we can see which link has
been surcharged as Max/Full Depth ration is ratio of Maximum Depth of water in channel with
Depth of Channel. Max/Full Depth ratio >= 1 implies that channel has been surcharged. Using
this parameter it’s clear that
Chirag Delhi Drain (its subsection 2, 3 and 4) is getting surcharged, thus insufficient
needs improvement. Note that these cross-section used are being are the proposed
sections from Storm Water Drainage Master Plan – 1976 and rainfall data is of 29 July,
2009 with consideration of change in land use pattern in last 30 years taken into account.
Lajpat Nagar Drain is inadequate
Malviya Nagar is inadequate
Andrews Gunj Drain is inadequate
Kushak Nallah (subsection 2 and 4) are inadequate.
43
Note that we are using rainfall depth of 135.6 mm for 24 hours duration which is worst case
scenario or highest loading from the data available with the author. From data (See section 4.2.2)
we can see that this amount of rainfall has return period of greater than 10 years. So although it
seems they are inadequate but in day-to-day scenario it may be adequate.
Figure 5.6: Link Flow Summary
45
5.3 Rational Method Results
Rational Method analysis has been carried out using rainfall with return period of 5 years with
duration equal to 5 hours. The results are shown in Table 5-2 and Table 5-3.
Table 5.2: Channel Flow Summary
Label
Time (Maximum Flow) (hours)
Flow (Maximum) (m³/s)
Velocity (Maximum Calculated) (m/s)
Hydraulic Grade (Maximum) (m)
Greater Kailash Drain 1.85 17.88 3.26 216.17
Outfall Drain 3.15 491.66 8.94 195.67
Chirag Delhi Drain_1 1.85 12.27 2.09 223.94
Chirag Delhi Drain_2 2.15 92.4 4.15 221.86
Chirag Delhi Drain_3 2.9 142.12 5.35 216.38
Chirag Delhi Drain_4 2.7 165.06 4.88 210.5
Chirag Delhi Drain_5 3.2 178.76 3.85 208.12
Chirag Delhi Drain_6 4 190.78 3.58 206.77
Chirag Delhi Drain_7 2.9 363.06 5.14 205.85
Chirag Delhi Drain_8 2.9 363.03 7.21 202.45
Lajpat Nagar Drain_1 0 0 0 211.13
Lajpat Nagar Drain_3 1.85 0.01 0.15 209.79
Lajpat Nagar Drain_4 1.85 20.13 2.16 204.61
Lajpat Nagar Drain_2 17.95 0 0.01 212.1
Malviya Nagar Drain_1 8.5 0 0.02 234.15
Malviya Nagar Drain_2 1.25 31.46 3.72 226.27
Andrews Gunj Drain 1.2 13.69 2.51 213.2
AIIMs Drain_1 1.4 49.89 5.13 211.82
AIIMs Drain_2 2.8 49.89 2.57 207.86
Nauroji Nagar Drain_1 2.45 14.53 3.07 222.32
Nauroji Nagar Drain_2 0.85 27.53 3.52 227.28
Nauroji Nagar Drain_3 2.8 42.06 4.01 219.18
Nauroji Nagar Drain_4 3.7 61.61 2.86 215.68
Kushak Nallah_1 0 0 0 218.01
Kushak Nallah_2 2.25 40.57 1.89 215.43
Kushak Nallah_3 2.5 111.13 4.37 210.25
Kushak Nallah_4 2.75 172.08 2.07 207.01
Sunehri Pullah Nallah_1 3.7 86.79 3.83 203.63
Sunehri Pullah Nallah_2 2.45 93.23 0.84 202.52
Sunehri Pullah Nallah_3 2.55 454.53 3.07 202.25
Barapullah Nallah_1 3.05 474.06 2.89 202.01
Barapullah Nallah_2 3.1 491.81 3.27 201.21
Malviya Nagar Drain_3 0 0 0 234.53
46
Table 5.3: Catchment flow Summary
Label Area (User Defined) (ha)
Volume (Total Runoff) (m³)
Flow (Maximum) (m³/s)
Time (Maximum Flow) (hours)
CM-1 827.765 5,01,823.80 27.88 2.45
CM-2 470.95 2,92,204.20 16.23 2.45
CM-3 693.633 4,66,075.80 25.89 1.35
CM-4 88.208 60,291.60 3.35 0.35
CM-5 0.075 63.8 0 0.05
CM-6 429.083 3,29,431.30 18.3 0.95
CM-7 452.723 3,02,077.00 16.78 1.2
CM-8 14.473 8,295.60 0.46 0.3
CM-9 442.833 3,62,201.00 20.12 1.1
CM-10 89.21 71,091.00 3.95 0.65
CM-11 1,215.45 7,02,474.20 39.03 1.15
CM-12 184.033 1,43,133.30 7.95 0.7
CM-13 346.213 2,61,453.70 14.53 0.65
CM-14 462.51 3,51,941.50 19.55 1.1
CM-15 270.11 2,13,923.30 11.88 1.05
CM-16 398.518 2,46,354.50 13.69 1.2
CM-17 420.77 2,93,571.20 16.31 1.2
CM-18 76.45 41,672.50 2.32 0.55
CM-19 782.928 4,95,618.00 27.53 0.85
CM-20 133.348 97,201.30 5.4 0.7
CM-21 434.64 3,15,706.60 17.54 0.9
CM-22 533.088 2,29,962.20 12.78 1.35
CM-23 377.518 1,62,145.00 9.01 1.05
CM-24 391.345 1,70,522.90 9.47 1.4
CM-25 529.478 3,28,593.90 18.26 1.25
CM-26 263.428 1,57,244.00 8.74 0.7
CM-27 0.51 352.9 0.02 0.05
CM-28 315.768 2,20,939.00 12.27 0.95
CM-29 1,112.78 5,66,302.60 31.46 1.25
CM-30 865.14 6,29,166.50 34.95 1.1
CM-31 556.525 3,54,725.80 19.71 1.05
CM-32 319.585 1,25,169.60 6.95 1.5
CM-33 451.518 1,75,677.20 9.76 1.7
48
5.3.1 Analysis
It’s clear from figure 5.8 that except Chirag Delhi Drain_7 and Kushak Nallah_2 all other drains
have sufficient capacity to carry runoff as all of them have value of Depth/Rise less than 100%.
Depth (Maximum Depth)/Rise (Height of channel) is greater than 100% only for Chirag Delhi
Drain_7 and Kushak Nallah_2.
Table 5.4: Comparison of Discharge from Rational Method and DMP -1976
S.No Drain Name
Maximum
Discharge (from
Rational Method)
Maximum
Discharge (from
DMP 1976)****
1 AIIMs Drain 49.89 66.0
2 Andrews Gunj Drain 13.69 16.41
3 Barapullah Nallah 491.81
4 Chirag Delhi Drain 190.78 NA*
5 Greater Kailash Drain 17.88 27.33
6 Kushak Nallah 172.08 256.74**
7 Lajpat Nagar Drain 20.3 16.15
8 Malviya Nagar Drain 31.46 12.3***
9 Nauroji Nagar Drain 61.61 59.5
10 Sunehri Pullah Nallah 93.23 67
NA* = Not Available
** = Many changes have occurred in Kushak Nallah catchment from 1976 due to addition of new
drains near Connaught place which has reduced catchment area thus discharge from it.
*** = Malviya Nagar drain has been extended after 1976 till Lado Sarai so now it has a bigger
catchment thus more discharge.
**** = Calculation for DMP-1976 have been based on storm event with 5-year return period with
intensity = 5.17 cm/hr
49
5.4 Recommendation
Now after analysis of SWMM Model (Worst case scenario) and Rational Method (Normal
Scenario), we can say provide following design recommendations.
Chirag Delhi Drain_7 (from CS-16 to CS-3) needs to be widen up as it surcharged during
rational method simulation. It bottom width can be increased from 24 m to 30 m.
Kushak Nallah Drain_2 (from CS-9 to CS-10) needs to be widen up as it surcharged during
rational method simulation. Its bottom width should be increased from 20 m to 30 m.
50
CHAPTER 6: DISCUSSION
6.1 Model Application
The methodology described in this thesis simulate industry standard practise for storm water
drainage simulation. It uses SWMM Model (with rainfall duration of 24 hrs) and Rational Method
(with Return Period = 5 year with rainfall duration of 5 hours). It begins with watershed analysis
using ArcGIS SWAT component then import modelling parameters in Bentley CivilStorm. It uses
MS Excel to calculate CN (Curve Number) and C (Runoff Coefficient) for each catchment. Then
it refines and add modelling parameters in Civil Storm. It then uses SWMM method to calculate
runoff in worst case scenario and studies it’s routing in drains. It’s also uses rational method to
calculate runoff from normal intensity rainfall.
6.2 Drawbacks and limitations of the Methodology
Model uses longitudinal section designs which were being proposed in Master Plan for
Storm water drainage – 1976. Due to silting and illegal construction, present day cross-
section might be different.
Rainfall Data taken to simulate model in SWMM is not adequate as to get proper
understanding of capacity of drainage system, atleast past 30 year data should have been
used. This will provide proper understanding return period for which we are designing
drainage network.
This study assumes one time vs depth curve (29 July, 2009) for whole barapullah catchment
which is not correct of representation of real-life condition. In reality, thiessen polygons
method should have been used which gives weightage to each rain gauge. However due to
insufficient data, author cannot go for thiessen polygon method.
Land use data taken from NRSC has several classes not properly defined e.g. in NRSC one
class was labelled as “Double/Triple” with no explanation. So based upon author’s
understanding of land use patterns, author assumed them as agricultural area.
Soil data has been taken from FAO (Food and Agriculture Organization). Data was found
to be too coarse. If proper data set would have been available then it might would have
resulted in better results
51
This project thesis studies Barapullah catchment as a whole and routes subbasin runoff into
respective nodes. However Barapullah catchment is very big catchment and results got
from analysis can only provide us with some broad understanding of drainage network. For
e.g. thesis proposes some design recommendations in Chirag Delhi Drain 7 and Kushak
Nallah, however to actually propose what should be the width and cross-section detail,
modelling needs to be done focussing on either Chirag Delhi Catchment or Kushak Nallah
catchment.
6.3 Advantages of SWMM Method over Rational Method
The major difference between SWMM and the rational method is in SWMM's ability to
give much more than a peak runoff as a result.
SWMM uses a rainfall hyetograph(or tabular inflow data - e.g. from a flow meter) to
generate a whole runoff hydrograph and route it through a network of links and nodes -
which allows one to assess such things as volume of runoff drained, effects of detention,
etc. The rational method is a much "rougher" tool which, in turn, gives you much less in
terms of results upon which to base design decisions.
The runoff coefficient lumps in all the hydrologic characteristics (imperviousness,
infiltration, evapotranspiration, depression storage, etc...) of a watershed into one number.
Besides area, the only number in the rational method calculation with any real, observable,
physical basis is the time of concentration that you select to determine your rainfall
intensity from the IDF (rainfall intensity-duration-frequency) curve (OK, the IDF curves
are based on observed rainfall).
SWMM does allow one to explicitly select parameters to (hopefully) better match the
actual hydrology of the system (e.g. you can base your infiltration on specific known soil
characteristics, imperviousness can be scaled from aerial photographs or ground survey,
depression storage and roughness can be varied to match ground cover and topography,
catchment response to runoff can be varied using the "WIDTH" parameter, etc...) You can
also use actual rainfall data directly instead of relying on IDF curves for storm
intensity (although, in practice, we tend to still use IDF curves a great deal).
52
CHAPTER 7: CONCLUSION AND FUTURE WORK
7.1 Conclusion
In the preceding chapters, various aspects involved in the analysis and design of storm water
drainage network were looked into. This thesis provided reader with a methodology to simulate
storm drainage in urban areas. It uses present day industry tools e.g. ArcGIS SWAT, EPA-SWMM
and Bentley Civil Storm for model building and analysis. Its starts from importing digital elevation
model and drain network. It takes cross-section data from Delhi Drainage Master Plan-1976. It
then analyse these sections for current loadings and check whether they are sufficient or not. The
analysis is based on rational method and EPA-SWMM model. For rational method, rainfall with
5 year return period with 5 hour rainfall duration has been taken. For SWMM Model, rainfall of
cumulative depth of 135.6 mm over 24 hours durations has been taken to provide worst case
scenario. It finds out problematic nodes and links in network. Its estimate quantity of water being
flooded from which node. It estimate which link is overflowing, for how much time. After analyses
it proposes certain recommendations in design of drains which can be taken up to stop local level
flooding problems. It then list down certain limitation of methodology and datasets.
7.2 Future Work
Writing a research paper about this methodology
More detailed analysis of barapullah catchment using rainfall data of last 30 years
Design and analysis of Chirag Delhi Drain network and simulation for providing
recommendation
Design and analysis of Kushak Nallah network for providing recommendation.
Building a scenario to study runoff using present day cross-section with normal intensity
runoff
53
APPENDIX – A
This section consist of detailed report of SWMM Model
EPA STORM WATER MANAGEMENT MODEL - VERSION 5.0 (Build 5.0.022)
--------------------------------------------------------------
******************************************************
*** NOTE: The summary statistics displayed in this
report are based on results found at every
computational time step, not just on results from
each reporting time step.
******************************************************
***
****************
Analysis Options
****************
Flow Units ............... CMS
Process Models:
Rainfall/Runoff ........ YES
Snowmelt ............... NO
Groundwater ............ NO
Flow Routing ........... YES
Ponding Allowed ........ YES
Water Quality .......... NO
Infiltration Method ...... CURVE_NUMBER
Flow Routing Method ...... DYNWAVE
Starting Date ............ JUL-27-2009 00:00:00
Ending Date .............. JUL-28-2009 12:00:00
Antecedent Dry Days ...... 0.0
Report Time Step ......... 00:15:00
Wet Time Step ............ 00:15:00
Dry Time Step ............ 01:00:00
Routing Time Step ........
30.00 sec
WARNING 04: minimum elevation drop used for Conduit Sunehri_Pulla_Nallah_3
WARNING 02: maximum depth increased for Node CS-1
WARNING 02: maximum depth increased for Node CS-2
WARNING 02: maximum depth increased for Node CS-5
WARNING 02: maximum depth increased for Node CS-6
WARNING 02: maximum depth increased for Node CS-7
WARNING 02: maximum depth increased for Node CS-8
WARNING 02: maximum depth increased for Node
CS-9 WARNING 02: maximum depth increased for
Node CS-10
WARNING 02: maximum depth increased for Node CS-11
WARNING 02: maximum depth increased for Node CS-12
WARNING 02: maximum depth increased for Node CS-14
54
WARNING 02: maximum depth increased for Node CS-16
WARNING 02: maximum depth increased for Node CS-20
WARNING 02: maximum depth increased for Node CS-21
WARNING 02: maximum depth increased for Node CS-22
WARNING 02: maximum depth increased for Node CS-23
WARNING 02: maximum depth increased for Node CS-24
WARNING 02: maximum depth increased for Node CS-27
WARNING 02: maximum depth increased for Node CS-29
WARNING 02: maximum depth increased for Node CS-33
WARNING 02: maximum depth increased for Node CS-34 **************************
Volume Depth
Runoff Quantity Continuity hectare-m mm
************************** --------- -------
Total Precipitation ...... 1891.701 135.600
Evaporation Loss ......... 0.000 0.000
Infiltration Loss ........ 249.863 17.911
Surface Runoff ........... 1614.890 115.758
Final Surface Storage .... 38.869 2.786
Continuity Error (%) ..... -0.630
************************** Volume Volume
Flow Routing Continuity hectare-m 10^6 ltr
************************** --------- ---------
Dry Weather Inflow ....... 0.000 0.000
Wet Weather Inflow ....... 1614.759 16147.754
Groundwater Inflow ....... 0.000 0.000
RDII Inflow .............. 0.000 0.000
External Inflow .......... 0.000 0.000
External Outflow ......... 933.097 9331.066
Internal Outflow ......... 676.438 6764.449
Storage Losses ........... 0.000 0.000
Initial Stored Volume .... 0.002 0.024
Final Stored Volume ...... 5.564 55.640
Continuity Error (%) ..... -0.021
********************************
Highest Flow Instability Indexes
********************************
All links are stable.
*************************
Routing Time Step Summary
*************************
Minimum Time Step : 30.00 sec
Average Time Step : 30.00 sec
Maximum Time Step : 30.00 sec
Percent in Steady State : 0.00
Average Iterations per Step : 2.05
***************************
Subcatchment Runoff Summary
***************************
55
-----------------------------------------------------------------------------------------------
---------
Total Total Total Total Total Total
Peak Runoff
Precip Runon Evap Infil Runoff Runoff
Runoff Coeff
Subcatchment mm mm mm mm mm 10^6 ltr
CMS
-----------------------------------------------------------------------------------------------
---------
CM-1 135.60 0.00 0.00 18.45 114.66 949.14
109.53 0.846
CM-2 135.60 0.00 0.00 16.46 116.86 550.33
64.54 0.862
CM-3 135.60 0.00 0.00 10.74 122.64 850.64
90.80 0.904
CM-4 135.60 0.00 0.00 9.11 126.37 111.47
17.45 0.932
CM-5 135.60 0.00 0.00 0.00 135.76 0.10
0.02 1.001
CM-6 135.60 0.00 0.00 3.12 131.38 563.75
64.18 0.969
CM-7 135.60 0.00 0.00 10.38 123.10 557.31
62.41 0.908
CM-8 135.60 0.00 0.00 23.38 113.64 16.45
2.90 0.838
CM-9 135.60 0.00 0.00 1.09 133.42 590.83
60.02 0.984
CM-10 135.60 0.00 0.00 1.90 133.38 118.99
14.46 0.984
CM-11 135.60 0.00 0.00 21.06 111.72 1357.93
154.54 0.824
CM-12 135.60 0.00 0.00 3.15 131.86 242.66
29.65 0.972
CM-13 135.60 0.00 0.00 4.23 130.69 452.48
57.82 0.964
CM-14 135.60 0.00 0.00 3.96 130.21 602.24
65.84 0.960
CM-15 135.60 0.00 0.00 2.26 132.28 357.31
38.48 0.976
CM-16 135.60 0.00 0.00 15.71 117.31 467.49
52.31 0.865
CM-17 135.60 0.00 0.00 9.07 124.64 524.45
58.39 0.919
CM-18 135.60 0.00 0.00 21.68 111.95 85.59
12.42 0.826
CM-19 135.60 0.00 0.00 14.77 118.66 929.06
117.47 0.875
CM-20 135.60 0.00 0.00 6.17 128.54 171.41
21.81 0.948
CM-21 135.60 0.00 0.00 6.24 128.03 556.45
66.42 0.944
CM-22 135.60 0.00 0.00 43.80 91.54 487.99
60.12 0.675
CM-23 135.60 0.00 0.00 34.23 96.99 366.15
38.60 0.715
CM-24 135.60 0.00 0.00 42.69 92.65 362.58
43.62 0.683
CM-25 135.60 0.00 0.00 14.65 118.40 626.89
69.94 0.873 CM-26 135.60 0.00 0.00 18.94 114.64
302.01 40.45 0.845
CM-27 135.60 0.00 0.00 10.26 127.90 0.65
0.11 0.943
CM-28 135.60 0.00 0.00 9.72 124.38 392.76
47.33 0.917
56
CM-29 135.60 0.00 0.00 25.78 106.03 1179.94
123.50 0.782
CM-30 135.60 0.00 0.00 6.55 127.42 1102.33
124.74 0.940
CM-31 135.60 0.00 0.00 14.74 118.55 659.79
77.98 0.874
CM-32 135.60 0.00 0.00 54.82 80.70 257.91
38.90 0.595
CM-33 135.60 0.00 0.00 57.07 78.39 353.93
46.28 0.578
******************
Node Depth Summary
******************
---------------------------------------------------------------------
Average Maximum Maximum Time of Max
Depth Depth HGL Occurrence
Node Type Meters Meters Meters days hr:min
---------------------------------------------------------------------
CS-1 JUNCTION 0.00 0.00 236.55 0 00:00
CS-2 JUNCTION 0.44 2.00 234.00 0 12:02
CS-3 JUNCTION 0.24 0.86 203.66 0 09:29
CS-4 JUNCTION 0.56 2.94 202.44 0 12:27
CS-5 JUNCTION 0.10 1.02 223.97 0 12:15
CS-6 JUNCTION 0.22 2.04 222.84 0 12:31
CS-7 JUNCTION 0.00 0.00 210.37 0 00:00
CS-8 JUNCTION 0.00 0.00 211.85 0 00:00
CS-9 JUNCTION 0.19 1.20 216.01 0 12:10
CS-10 JUNCTION 0.19 1.23 214.73 0 12:24
CS-11 JUNCTION 0.15 1.00 210.10 0 12:12
CS-12 JUNCTION 0.00 0.00 213.82 0 00:00
CS-13 JUNCTION 0.15 1.35 221.59 0 12:30
CS-14 JUNCTION 0.39 2.35 213.55 0 12:07
CS-15 JUNCTION 0.37 2.50 208.00 0 12:17
CS-16 JUNCTION 0.69 2.50 206.21 0 08:44
CS-17 JUNCTION 0.17 1.48 215.08 0 12:30
CS-18 JUNCTION 0.54 2.91 202.41 0 12:27
CS-19 JUNCTION 0.30 2.65 234.60 0 12:30
CS-20 JUNCTION 0.35 2.80 221.52 0 12:13
CS-21 JUNCTION 0.56 2.80 209.51 0 12:06
CS-22 JUNCTION 0.00 0.00 221.20 0 00:00
CS-23 JUNCTION 0.00 0.00 236.29 0 00:00
CS-24 JUNCTION 0.35 2.20 221.12 0 12:05
CS-25 JUNCTION 0.19 1.55 206.82 0 12:30
CS-26 JUNCTION 0.23 1.11 199.48 0 13:00
CS-27 JUNCTION 0.08 0.75 225.55 0 12:30
CS-29 JUNCTION 0.30 2.20 224.56 0 12:06
CS-30 JUNCTION 0.28 2.37 211.17 0 12:31
CS-31 JUNCTION 0.27 2.11 202.61 0 12:32
CS-32 JUNCTION 0.91 3.50 202.00 0 12:18
CS-33 JUNCTION 0.32 2.20 218.20 0 12:09
CS-34 JUNCTION 0.36 1.85 207.55 0 12:30
O-1 OUTFALL 0.23 1.11 191.11 0 13:00
*******************
Node Inflow Summary
*******************
-------------------------------------------------------------------------------------
Maximum Maximum Lateral Total
Lateral Total Time of Max Inflow Inflow
Inflow Inflow Occurrence Volume Volume
57
Node Type CMS CMS days hr:min 10^6 ltr 10^6 ltr
-------------------------------------------------------------------------------------
CS-1 JUNCTION 0.000 0.000 0 00:00 0.000 0.000
CS-2 JUNCTION 123.502 123.502 0 12:30 1179.719 1179.716
CS-3 JUNCTION 0.000 192.320 0 09:27 0.000 5405.280
CS-4 JUNCTION 0.000 530.526 0 12:32 0.000 8422.725
CS-5 JUNCTION 57.818 57.818 0 12:15 452.463 452.463
CS-6 JUNCTION 0.000 172.490 0 12:30 0.000 1381.246
CS-7 JUNCTION 0.000 0.000 0 00:00 0.000 0.000
CS-8 JUNCTION 0.000 0.000 0 00:00 0.000 0.000
CS-9 JUNCTION 154.542 154.542 0 12:30 1357.779 1357.778
CS-10 JUNCTION 0.000 236.503 0 12:14 0.000 3000.043
CS-11 JUNCTION 60.024 60.024 0 12:30 590.771 590.770
CS-12 JUNCTION 0.000 0.000 0 00:00 0.000 0.000
CS-13 JUNCTION 66.421 66.421 0 12:30 556.427 556.427
CS-14 JUNCTION 21.813 393.601 0 12:30 171.406 4865.133
CS-15 JUNCTION 44.110 488.784 0 12:31 361.638 5187.185
CS-16 JUNCTION 2.903 686.212 0 12:31 16.447 9581.123
CS-17 JUNCTION 212.786 212.786 0 12:30 1826.628 1826.626
CS-18 JUNCTION 0.016 576.391 0 12:32 0.102 8985.488
CS-19 JUNCTION 117.472 117.472 0 12:30 929.013 929.012
CS-20 JUNCTION 52.308 52.308 0 12:30 467.442 467.442
CS-21 JUNCTION 0.000 357.650 0 12:59 0.000 5034.602
CS-22 JUNCTION 0.000 0.000 0 00:00 0.000 0.000
CS-23 JUNCTION 0.000 0.000 0 00:00 0.000 0.000
CS-24 JUNCTION 69.943 379.163 0 12:30 626.825 4380.734
CS-25 JUNCTION 327.280 327.280 0 12:30 2907.154 2907.150
CS-26 JUNCTION 0.000 524.527 0 13:00 0.000 9333.276
CS-27 JUNCTION 47.326 47.326 0 12:30 392.735 392.735
CS-29 JUNCTION 328.422 375.519 0 12:30 2676.483 3069.074
CS-30 JUNCTION 0.000 212.476 0 12:30 0.000 1826.131
CS-31 JUNCTION 17.453 340.556 0 12:30 111.466 3017.808
CS-32 JUNCTION 64.183 645.909 0 12:33 563.720 9545.832
CS-33 JUNCTION 65.838 236.811 0 12:30 602.196 1982.692
CS-34 JUNCTION 38.483 262.087 0 12:30 357.283 4493.460
O-1 OUTFALL 0.000 524.527 0 13:00 0.000 9331.024
**********************
Node Surcharge Summary
**********************
Surcharging occurs when water rises above the top of the highest conduit.
---------------------------------------------------------------------
Max. Height Min. Depth
Hours Above Crown Below Rim
Node Type Surcharged Meters Meters
---------------------------------------------------------------------
CS-2 JUNCTION 2.01 0.000 0.000
CS-9 JUNCTION 1.41 0.000 0.000
CS-11 JUNCTION 0.73 0.000 0.000
CS-14 JUNCTION 1.59 0.000 0.000
CS-15 JUNCTION 0.67 0.000 0.000
CS-16 JUNCTION 4.58 0.000 0.000
CS-20 JUNCTION 0.78 0.000 0.000
CS-21 JUNCTION 2.08 0.000 0.000
CS-24 JUNCTION 1.51 0.000 0.000
CS-29 JUNCTION 0.82 0.000 0.000
CS-32 JUNCTION 0.71 0.000 0.000
CS-33 JUNCTION 0.97 0.000 0.000
*********************
Node Flooding Summary
*********************
58
Flooding refers to all water that overflows a node, whether it ponds or not.
--------------------------------------------------------------------------
Total Maximum
Maximum Time of Max Flood Ponded
Hours Rate Occurrence Volume Depth
Node Flooded CMS days hr:min 10^6 ltr Meters
--------------------------------------------------------------------------
CS-2 2.01 71.200 0 12:30 279.170 2.00
CS-9 1.41 60.842 0 12:30 138.194 1.20
CS-11 0.73 16.319 0 12:30 26.362 1.00
CS-14 1.59 72.112 0 12:30 269.238 2.35
CS-15 0.67 86.165 0 12:17 113.666 2.50
CS-16 4.57 493.887 0 12:32 4165.884 2.50
CS-20 0.78 15.993 0 12:30 27.559 2.80
CS-21 2.07 136.778 0 13:01 895.317 2.80
CS-24 1.51 73.167 0 12:30 242.608 2.20
CS-29 0.82 117.935 0 12:30 215.196 2.20
CS-32 0.71 121.761 0 12:33 190.456 3.50
CS-33 0.97 94.239 0 12:30 200.769 2.20
***********************
Outfall Loading Summary
***********************
-----------------------------------------------------------
Flow Avg. Max. Total
Freq. Flow Flow Volume
Outfall Node Pcnt. CMS CMS 10^6 ltr
-----------------------------------------------------------
O-1 77.90 92.415 524.527 9331.024
-----------------------------------------------------------
System 77.90 92.415 524.527 9331.024
********************
Link Flow Summary
********************
-----------------------------------------------------------------------------
Maximum Time of Max Maximum Max/ Max/
|Flow| Occurrence |Veloc| Full Full
Link Type CMS days hr:min m/sec Flow Depth
-----------------------------------------------------------------------------
Greater_Kailash_Drain CONDUIT 66.201 0 12:30 5.01 0.56 0.86
Outfall_Drain CONDUIT 524.527 0 13:00 9.16 0.15 0.32
Chirag_Delhi_Drain_1 CONDUIT 47.158 0 12:30 1.70 0.16 0.67
Chirag_Delhi_Drain_2 CONDUIT 257.177 0 12:55 5.92 1.00 1.00
Chirag_Delhi_Drain_3 CONDUIT 305.858 0 12:55 7.04 0.99 1.00
Chirag_Delhi_Drain_4 CONDUIT 321.440 0 13:16 5.96 0.95 1.00
Chirag_Delhi_Drain_5_ CONDUIT 223.611 0 12:30 4.77 1.12 0.89
Chirag_Delhi_Drain_6 CONDUIT 261.826 0 12:31 4.75 0.69 0.90
Chirag_Delhi_Drain_7 CONDUIT 192.320 0 09:27 4.69 0.89 0.69
Chirag_Delhi_Drain_8 CONDUIT 192.320 0 09:15 5.82 0.19 0.69
Lajpat_Nagar_Drain_1 CONDUIT 0.000 0 00:00 0.00 0.00 0.00
Lajpat_Nagar_Drain_3 CONDUIT 0.000 0 00:00 0.00 0.00 0.50
Lajpat_Nagar_Drain_4 CONDUIT 44.580 0 12:14 3.97 0.92 1.00
Lajpat_Nagar_Drain_2 CONDUIT 0.000 0 00:00 0.00 0.00 0.00
Malviya_Nagar_Drain_1 CONDUIT 0.000 0 00:00 0.00 0.00 0.50
Malviya_Nagar_Drain_2 CONDUIT 52.376 0 13:46 5.50 1.00 1.00
Andrews_Gunj_Drain CONDUIT 36.210 0 12:52 4.31 1.00 1.00
AIIMs_Drain_1 CONDUIT 212.476 0 12:30 6.53 0.42 0.77
AIIMs_Drain_2 CONDUIT 210.291 0 12:32 4.95 0.91 0.97
Nauroji_Nagar_Drain_1 CONDUIT 57.815 0 12:16 3.42 0.27 0.69
59
Nauroji_Nagar_Drain_2 CONDUIT 116.235 0 12:31 6.25 0.62 0.73
Nauroji_Nagar_Drain_3 CONDUIT 171.515 0 12:32 6.40 0.88 0.96
Nauroji_Nagar_Drain_4 CONDUIT 142.520 0 12:19 4.88 0.84 0.78
Kushak_Nallah_1 CONDUIT 0.000 0 00:00 0.00 0.00 0.50
Kushak_Nallah_2 CONDUIT 94.469 0 13:29 3.71 1.00 1.00
Kushak_Nallah_3 CONDUIT 235.892 0 12:24 5.50 0.72 0.91
Kushak_Nallah_4 CONDUIT 423.247 0 12:56 3.98 1.00 1.00
Sunehri_Pulla_Nallah_1 CONDUIT 325.813 0 12:31 5.15 0.24 0.52
Sunehri_Pulla_Nallah_2 CONDUIT 338.206 0 12:32 3.72 0.41 0.72
Sunehri_Pulla_Nallah_3 CONDUIT 532.721 0 12:32 3.40 5.48 0.83
Barapullah_Nallah_1 CONDUIT 584.678 0 12:34 3.36 0.64 0.92
Barapullah_Nallah_2 CONDUIT 524.527 0 13:00 4.26 2.23 0.66
Malviya_Nagar_Drain_3 CONDUIT 0.000 0 00:00 0.00 0.00 0.50
***************************
Flow Classification Summary
***************************
----------------------------------------------------------------------------------------
Adjusted --- Fraction of Time in Flow Class ---- Avg. Avg.
/Actual Up Down Sub Sup Up Down Froude Flow
Conduit Length Dry Dry Dry Crit Crit Crit Crit Number Change
-----------------------------------------------------------------------------------------
Greater_Kailash_Drain 1.00 0.19 0.00 0.00 0.74 0.07 0.00 0.00 0.38 0.0004
Outfall_Drain 1.00 0.22 0.00 0.00 0.01 0.77 0.00 0.00 1.63 0.0001
Chirag_Delhi_Drain_1 1.00 0.19 0.00 0.00 0.81 0.00 0.00 0.00 0.19 0.0001
Chirag_Delhi_Drain_2 1.00 0.19 0.00 0.00 0.66 0.14 0.00 0.00 0.56 0.0008
Chirag_Delhi_Drain_3 1.00 0.19 0.00 0.00 0.38 0.43 0.00 0.00 0.87 0.0008
Chirag_Delhi_Drain_4 1.00 0.19 0.00 0.00 0.71 0.09 0.00 0.00 0.54 0.0007
Chirag_Delhi_Drain_5_ 1.00 0.19 0.02 0.00 0.67 0.11 0.00 0.00 0.56 0.0010
Chirag_Delhi_Drain_6 1.00 0.19 0.00 0.00 0.72 0.08 0.00 0.00 0.39 0.0006
Chirag_Delhi_Drain_7 1.00 0.19 0.00 0.00 0.50 0.31 0.00 0.00 0.68 0.0007
Chirag_Delhi_Drain_8 1.00 0.21 0.01 0.00 0.20 0.58 0.00 0.00 0.94 0.0002
Lajpat_Nagar_Drain_1 1.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.0000
Lajpat_Nagar_Drain_3 1.00 0.19 0.81 0.00 0.00 0.00 0.00 0.00 0.00 0.0000
Lajpat_Nagar_Drain_4 1.00 0.19 0.00 0.00 0.73 0.07 0.00 0.00 0.30 0.0007
Lajpat_Nagar_Drain_2 1.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.0000
Malviya_Nagar_Drain_1 1.00 0.19 0.81 0.00 0.00 0.00 0.00 0.00 0.00 0.0000
Malviya_Nagar_Drain_2 1.00 0.19 0.00 0.00 0.02 0.79 0.00 0.00 1.14 0.0008
Andrews_Gunj_Drain 1.00 0.19 0.00 0.00 0.78 0.02 0.00 0.00 0.38 0.0007
AIIMs_Drain_1 1.00 0.19 0.00 0.00 0.43 0.38 0.00 0.00 0.86 0.0003
AIIMs_Drain_2 1.00 0.19 0.00 0.00 0.76 0.05 0.00 0.00 0.46 0.0006
Nauroji_Nagar_Drain_1 1.00 0.19 0.00 0.00 0.75 0.05 0.00 0.00 0.38 0.0002
Nauroji_Nagar_Drain_2 1.00 0.19 0.00 0.00 0.30 0.50 0.00 0.00 0.89 0.0004
Nauroji_Nagar_Drain_3 1.00 0.19 0.01 0.00 0.65 0.14 0.00 0.00 0.58 0.0006
Nauroji_Nagar_Drain_4 1.00 0.19 0.00 0.00 0.59 0.22 0.00 0.00 0.63 0.0006
Kushak_Nallah_1 1.00 0.19 0.81 0.00 0.00 0.00 0.00 0.00 0.00 0.0000
Kushak_Nallah_2 1.00 0.19 0.00 0.00 0.68 0.12 0.00 0.00 0.64 0.0007
Kushak_Nallah_3 1.00 0.19 0.02 0.00 0.70 0.09 0.00 0.00 0.56 0.0005
Kushak_Nallah_4 1.00 0.19 0.00 0.00 0.81 0.00 0.00 0.00 0.21 0.0007
Sunehri_Pulla_Nallah_1 1.00 0.19 0.00 0.00 0.66 0.15 0.00 0.00 0.68 0.0002
Sunehri_Pulla_Nallah_2 1.00 0.19 0.00 0.00 0.80 0.00 0.00 0.00 0.24 0.0003
Sunehri_Pulla_Nallah_3 1.00 0.21 0.00 0.00 0.79 0.00 0.00 0.00 0.40 0.0038
Barapullah_Nallah_1 1.00 0.19 0.02 0.00 0.79 0.00 0.00 0.00 0.23 0.0004
Barapullah_Nallah_2 1.00 0.19 0.00 0.00 0.81 0.00 0.00 0.00 0.34 0.0015
Malviya_Nagar_Drain_3 1.00 0.19 0.81 0.00 0.00 0.00 0.00 0.00 0.00 0.0000
*************************
Conduit Surcharge Summary
*************************
----------------------------------------------------------------------------
Hours Hours
60
--------- Hours Full -------- Above Full Capacity
Conduit Both Ends Upstream Dnstream Normal Flow Limited
----------------------------------------------------------------------------
Chirag_Delhi_Drain_5_ 0.01 0.01 0.01 2.29 0.01
Lajpat_Nagar_Drain_4 0.73 0.73 0.74 0.01 0.01
Kushak_Nallah_2 1.37 1.37 1.38 0.01 0.01
Sunehri_Pulla_Nallah_3 0.01 0.01 0.01 7.53 0.01
Barapullah_Nallah_2 0.01 0.01 0.01 5.08 0.01
Analysis begun on: Wed Apr 30 21:53:51 2014
Analysis ended on: Wed Apr 30 21:53:51 2014
Total elapsed time: < 1 sec
61
REFERENCES
Chen, J., Hill, A. A., & Urbano, L. D. (2009). A GIS-based Model for urban flood inundation.
Journal of Hydrology, 184-192.
EPA. (2009). Storm Water Managment Model: Applicatons Manual . Cincinati: United States
Environmental Protection Agency.
FCW(Flood Control Wing). (1976). Master Plan for Storm Water Drainage in Union Territory of
Delhi (MCD, DDA, NDMC & Cantonment). Delhi: Delhi Adminstration.
Mannings n Tables. (n.d.). Retrieved from
http://www.fsl.orst.edu/geowater/FX3/help/8_Hydraulic_Reference/Mannings_n_Tables.
htm
Mark, O., Weesakul, S., Apirumanekul, C., Aroonnet, S. B., & Djordjevic, S. (2004). Potential
and limitations of 1D modelling of urban flooding. Journal of Hydrology, 284-299.
Schmitt, T. G., Thomas, M., & Ettrich, N. (2004). Analysis and modeling of flooding in urban
drainage systems. Journal of Hydrology, 300-311.
Subramanya, K. (2008). Engineering Hydrology. New Delhi: Tata McGraw-Hill.
SWMM-Runoff-Algorithm. (n.d.). Retrieved from http://www.alanasmith.com/theory-Calculating-
Runoff-SWMM-RUNOFF-Algorithm.htm
Weng, Q. (2001). Modeling Urban Growth Effects on surface runoff with the integration of remote
sensing and GIS. Environmental Management Vol. 28, No. 6, 737-748.
Winchell, M., Srinivasan, R., DiLuzio, M., & Arnold, J. (2013). ArcSWAT Interface for SWAT2012
User's Guide. Texas -76502: Blackland Research and Extenstion Center.