cea myanmar - bottle blower installation

2
BOTTLE BLOWER INSTALLATION BOTTLE BLOWER INSTALLATION Location Yangon, My. Duration 5 Days Project value 25,000 USD Weights Bottle blower 12 Tonnes Oven 4.9 Tonnes Compressor 4 Tonnes Conveyor & feed unit 2 Tonnes Chiller unit 2 Tonnes Air handling unit x2 1.5 Tonnes Equipment Used 10t City crane 3.7t Telehandler 5t Forklift 30t Toejacks x6 12t Skates x6 8 Inch steel form work 4 Axle low bed trailer 6 Man installation team SCOPE CEA Project Logistics Myanmar were employed for the transportation, customs process and installation of a pre-formed bottle blowing machine and it’s auxiliary parts at the Loi Hein soft drinks factory in Yangon, Myanmar. This was the completion of a three-part project that CEA had been conducting. CASE STUDY CS020 Bottle Blower Installation 1/2 MAIN BLOWER MACHINE LOWERED ON TO 12T SKATES READY TO MOVE INTO THE FACTORY

Upload: cea-project-logistics

Post on 25-Jul-2016

226 views

Category:

Documents


0 download

DESCRIPTION

CEA Project Logistics Myanmar recently completed the final part of a three-part project in Yangon. The whole project consisted of the moving of an entire soft drinks factory from its old location to the new site some 20kms away. The final part of the project involved the transportation and installation of a new Bottle Blower Machine and other auxiliary parts, the total value of the cargo was in excess of 500,000 USD. CEA Myanmar was responsible for the unloading at the port, customs process, transportation and eventual installation. Due to the complex layout of the factory several modifications were made to the walls to facilitate the installation process. The project was completed in under five days ahead of schedule and within operational budget.

TRANSCRIPT

Page 1: CEA Myanmar - Bottle Blower Installation

BOTTLE BLOWER INSTALLATIONBO

TTLE BLOW

ER INSTA

LLATIONLocation

Yangon, My.

Duration 5 Days

Project value 25,000 USD

Weights Bottle blower 12 Tonnes Oven 4.9 Tonnes Compressor 4 Tonnes Conveyor & feed unit 2 Tonnes Chiller unit 2 Tonnes Air handling unit x2 1.5 Tonnes

Equipment Used 10t City crane 3.7t Telehandler 5t Forklift 30t Toejacks x6 12t Skates x6 8 Inch steel form work 4 Axle low bed trailer 6 Man installation team

SCOPECEA Project Logistics Myanmar were employed for the transportation, customs process and installation of a pre-formed bottle blowing machine and it’s auxiliary parts at the Loi Hein soft drinks factory in Yangon, Myanmar. This was the completion of a three-part project that CEA had been conducting.

CASE STUDY CS020Bottle Blower Installation 1/2

MAIN BLOWER MACHINE LOWERED ON TO 12T SKATES READY TO MOVE INTO THE FACTORY

Page 2: CEA Myanmar - Bottle Blower Installation

BOTT

LE B

LOW

ER IN

STA

LLAT

ION

CEA PROJECT LOGISTICS

G-18 PEARL CONDO

KABAR AYE PAGODA ROAD

BAHAN TOWNSHIP

YANGON

MYANMAR

+959 421 031 286

www.ceaprojects.com

CEA service teams took charge of the cargo as it arrived at the port and used escort vehicles throughout the transportation of the oversized cargo to the factory site. The equipment with a value of over 500,000 USD was carefully unloaded and unpacked and lifted on to 15 tonne multi-wheel skates to ease the manoeuvring through and across the factory to the installation site.

Due to the complexity of the factory layout, a 10-Tonne city crane was used inside to facilitate the movement of some of the machinery, modifications to several of the factory’s walls were also made. When all the bottle blower machinery parts were in place, each one was jacked down from its skates and final levelling commenced. The whole project was completed within the five-day time frame and under budget.

CASE STUDY CS020Bottle Blower Installation 2/2

STANDARDIZED CARGO AWAITS UNOADING

TELEHANDLER UNLOADING CONTAINERS

OVERSIZED CARGO ARRIVAL AT FACTORY

CEA TEAMS UNPACK THE CARGO

MAIN PARTS ASSEMBLED IN OPERATIONAL LOCATION AND AWAITING FINAL INSTALLATION

BLOWER BEING SKATED ACROSS FACTORY5T FORKLIFT ASSISTS IN SKATING

BLOWER AND OTHER MACHINERY IN PLACEAUXILIARY MACHINERY IN PLACE