cdr status information
DESCRIPTION
CDR Status information. Much good progress by the authors since last meeting Today’s ( 08-July 2011) state: 47 contributions needed 40 received- 23 as draft only - 17 as “final” submission http:// project-clic-cdr.web.cern.ch/project-CLIC-CDR - PowerPoint PPT PresentationTRANSCRIPT
CDR Status information
• Much good progress by the authors since last meeting• Today’s (08-July 2011) state:
47 contributions needed40 received - 23 as draft only
- 17 as “final” submission• http://project-clic-cdr.web.cern.ch/project-CLIC-CDR• Can reasonably expect 4 more (draft) contributions in July.• IEB (Internal Editorial board) relaunched.• Only “received” contributions are compiled into the draft CDR.
We wish to get 5...10 authors, who convert in July their draft into a submission.• Most things agreed for the front-page layout. All volumes will have similar
appearance. Details (=matter of taste) still to be discussed.• Collection of CDR “signatories” through a web-page will
be tested in August and will be active for the period September-November
• Expect final document in time for December 2011 Council.
News from CTC WGs
G. Riddone
-As defined: not complete; only from those who are there and were something exciting has happened...
- we have to take the workpackages exercise serious
- technical news on:Two beam test module(Pre)alignmentMDI
Two-beam test module project (1)New organization of B169. Test modules in a dedicated room
Installation of supporting/positioning system for first two modules completed – validation tests under way
G. Riddone
Two-beam test module project (2)
DB quad mock-up
Pre-assembly of AS mock-ups
Load mock-up
G. Riddone
Several component to handle: Logistics and database
First rf structure mock-ups ready by end of July
5
Test modules: status
OK OK
OK
Under progress
6
Test modules : last results
• Repeatibility in the installation of cWPS sensors on their interfaces: < 1 μm
• Repeatibility in the installation of inclinometers on their interfaces : < 2 μrad
Installation & validation of alignment systems
Validation of linear actuators on 1 DOF test bench (M. Sosin)
• Maximum backlash: 4 μm
• Repeatability < 1.5 μm
• Resolution < 0.2 μm
7
MB quad mock-up (with cam movers)
• Measurements concerning Eigen frequencies of the interface plate took place last Tuesday & Wednesday
• Pre-alignment sensors to be installed this Friday
• First tests concerning resolution over the whole range & 5DOF will take place next week
• Design under progress concerning a smaller cam mover (for module type 1)
Mock-up installed in 927
M. Anastaspoulos, R. Leuxe
8
Geodesy studies
In collaboration with ETHZ, a deflectometer was installed in 839 (12 m long)
Deflectometer: relative measurements of deflection of vertical in tunnel
First results show that inclinometer installed is not adapted and will be replaced
N. Chritin
MDI
• Good progress on 3 D anti-solenoid simulations• Progress on stabilization (CERN and SYMME)• Progress on muon background simulations• First parts of QD0 prototype are at CERN (next slide)
G. Riddone
Michele Modena 1021st MDI Meeting, 1 July 2011
Final Focus “QD0” prototype procurement: