CDM 2015 & information a view from HSE. Louise Brearey Head of Operations HSE London & South-East. Review of CDM 2007. Key points from research aims of CDM 2007 largely met, but 3 concerns: application and interpretation coordination not working Had not tackled bureaucracy - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: CDM 2015 & information a view from HSE

Health and Safety Executive

Health and Safety Executive

CDM 2015 & information

a view from HSE

Louise Brearey

Head of Operations

HSE London & South-East

Page 2: CDM 2015 & information a view from HSE

Review of CDM 2007

• Key points from research– aims of CDM 2007 largely met, but– 3 concerns:

• application and interpretation• coordination not working• Had not tackled bureaucracy

– ACoP – how effective?

Page 3: CDM 2015 & information a view from HSE
Page 4: CDM 2015 & information a view from HSE

Main proposed changes to CDM on which we are consulting

• Simplification of the Regulations

• Applies to projects for domestic clients (Implements the TMCS directive)

• Strengthens role of the client

• Removes corporate competence requirements & concentrate on site competence

• Removal of CDM Coorinator role

• Makes designers responsible for coordination in the pre-construction phase

• Removal of ACOP (replace with HSE & industry guidance)

• Change to thresholds for notification (500 person days or 30 days with 20 contractors)

Page 5: CDM 2015 & information a view from HSE

Our message remains the same:

•The right information

•To the right people

•At the right timeAND

Tackling bureaucracy

Page 6: CDM 2015 & information a view from HSE

Golden Rule

EFFORT ≈ RISK (UNFAMILIARITY)

Page 7: CDM 2015 & information a view from HSE

The right information

What information does CDM require (& IS LIKELY TO CONTINUE TO)?

1. Preconstruction information

2. Information about the design that others need to manage risks

3. Information needed to produce the construction phase plan plan

4. Information for the health and safety file

Page 8: CDM 2015 & information a view from HSE

But there are other H&S information requirements:

Risk assessments (method statements),

H&S policies,

COSHH data / assessments/asbestos survey

Training records

Inspections

Lifting plans

Transport management / logistics

Fire / emergency / evacuation

Page 9: CDM 2015 & information a view from HSE

Preconstruction

• “The site contains no unusual hazards that would be unfamiliar to a competent contractor” – a reasonable concept?

Page 10: CDM 2015 & information a view from HSE

Providing design information

• Designers need to provide information about aspects of the design….– not likely to be obvious to a competent contractor– unusual– likely to be difficult to manageIf in doubt, ask those who will use the

information

Page 11: CDM 2015 & information a view from HSE
Page 12: CDM 2015 & information a view from HSE

BIM

Page 13: CDM 2015 & information a view from HSE

Construction phase plan

• A manual?

• “How health and safety will be managed on this site”

• Live document not shelf dweller

• More than somewhere to file generic risk assessments

• How will I monitor? What are the KPIs?

• Appendix 2 of current ACoP

Page 14: CDM 2015 & information a view from HSE

Health & Safety File

• Description: What will future designers / construction or demolition contractors need to know to MANAGE THE RISKS?

• What goes in?

• What stays out!

• Relevant

• Anticipate what users will need?

Page 15: CDM 2015 & information a view from HSE

Golden Rule

EFFORT ≈ RISK (UNFAMILIARITY)

Page 16: CDM 2015 & information a view from HSE
Page 17: CDM 2015 & information a view from HSE

Summary

• Aim is to manage and control the risks

• Paperwork is of value if it contributes to this aim

• Remember the user and purpose of the paperwork

• CDM Revision an opportunity for change