ccus projects at lafargeholcim focus on oxycombustion · the ccus projects at lafarge (2005-2015)...
TRANSCRIPT
© LafargeHolcim 2015
CCUS Projects at LafargeHolcimFocus on Oxycombustion
Michel GIMENEZ, ECRA/CEMCAP WorkshopDüsseldorf, 16 September 2015
© LafargeHolcim 2015ECRA - CO2 Capture 16 September 2015 2
Why Studying CO2 Capture into the Cement Plant?
• As one potential additional lever to mitigate CO2 emissions
• To ensure that the cement plant flue gas specifications are addressed within capture technologies development
• To understand how all this works and find technologies adapted to our process
• To better integrate capture process into the cement plant
• To make the proof of concept and technical-economic feasibility studies of selected technologies
© LafargeHolcim 2015Harnessing CO 2 September 21st, 2015 3
CO2 Capture into the Cement Plant
• CO2 capture is tricky• e.g., post-combustion amine scrubbing (MEA), is not integrated to the cement
plant and is very energy intensive (in terms of both kWh & GJ)
• CO2 capture appears to be technically feasible into the cement plant but there is no viable business model identified today; the more integrated to the cement process, the cheaper the capture
• Once captured, CO2 needs to be used or geologically stored
3
© LafargeHolcim 2015ECRA - CO2 Capture 16 September 2015
The Oxycombustion Project
A collaborative project between 3 major companies from Cement, OEM and Gas & Combustion Technologies Supplier
4
© LafargeHolcim 2015ECRA - CO2 Capture 16 September 2015
The Oxy-Combustion Project (2009-2014)
collaboration, lead by LAFARGE
• In 2009 Air Liquide, FLSmidth and LAFARGE decided t o cooperate and jointly study the calciner Oxy-Combustion technolog y, including performing pilot trials at FLSmidth R&D pilot plant in Dania, Denmark
• The project included several phases:
• Feasibility paper study (performed by LAFARGE & Air Liquide)• Pilot trials to prove the technical feasibility of the technology (LAFARGE,
FLSmidth, AL)• The study of the retrofit of Le Havre Cement Plant / France with cost
estimation for CO2 capture shipping and storage in the North Sea (LAFARGE, FLSmidth, Air Liquide)
• Possible application to the EC NER300 program
5
© LafargeHolcim 2015ECRA - CO2 Capture 16 September 2015
The Oxy-Combustion Project (2009-2014)
• The aim was to integrate the CO2 capture technology into the cement plant by implementing the oxy-combustion at calciner
• Air is replaced by oxygen injection at calciner while the combustion gases get partially recycled to the calciner
• We wanted to reach a better integration (process & energy) into the cement making process and thus a lower cost for the CO2 capture than the reference post-combustion amine scrubbing technology
6
© LafargeHolcim 2015ECRA - CO2 Capture 16 September 2015
The Pilot Trials
• 7 test campaigns have been performed over 2011 and 2012 with a raw meal feed rate of 2 t/h i.e. 1 t CO2/h
• The FLSmidth pilot plant in DANIA / Denmark has been modified to oxycombustion at precalciner
7
© LafargeHolcim 2015ECRA - CO2 Capture 16 September 2015
Main Results from the Pilot campaigns
• No safety issues regarding oxygen have been experienced during the trials
• Stable operation was achieved
• Measured CO 2 concentration in calciner was limited to 66 % vol. dry below target 78 % due to false air and limited raw feed rate
• Calcined raw meal showed no difference between air and oxy-combustion i.e., no expected impact on cement quality
• Results showed that an existing preheater or calciner cement kiln line can be retrofitted to oxycombustion
8
© LafargeHolcim 2015ECRA - CO2 Capture 16 September 2015
Why Converting Le Havre plant – Normandy –France?
9
• Eligible to the European NER300 funding program
• Adapted to the oxy-retrofit: no calciner, space for ASU & CPU
• It is on the seashore, liquid CO2 can be shipped to off shore storage or EOR sites
• Pooling opportunities with the 14 Mt/y CO2 emitted in the Le Havre harbor area
• Air Liquide has an existing O2 production plant that can deliver 300 t/d, located 300 m away from the cement plant
© LafargeHolcim 2015ECRA - CO2 Capture 16 September 2015
The Retrofitted Le Havre Plant
10
© LafargeHolcim 2015ECRA - CO2 Capture 16 September 2015
• CAPEX (M€) (8,5 % money discount rate, 15 years)
CAPEX and OPEX Evaluation of the Retrofitted Plant Le Havre
• OPEX (M€/y)
11
22 €/t CO2 Captured 40 €/t CO 2 Captured
Full Cost is 62 €/t CO 2 Captured i.e.
36 €/t Cement
© LafargeHolcim 2015ECRA - CO2 Capture 16 September 2015
Foot Print of the ASU & CPU + Power Station
12
Liquid CO 2 Storage
© LafargeHolcim 2015ECRA - CO2 Capture 16 September 2015
Improvement Levers to Reduce CO 2 Capture Cost
• Treat more CO2 at calciner � 627,450 t/y of liquid CO2 � - 5 €/t CO2 capture cost
• Reduce the false air ingress � 84% (vol. dry) CO2 concentration in flue gases � decreased CPU power consumption ���� - 5 €/t CO2
• Produce CO2 at supercritical state for pipeline transport � lower CPU power consumption ���� - 4 €/t CO2
Total CO2 capture cost cut down to around 50 €/t
13
© LafargeHolcim 2015ECRA - CO2 Capture 16 September 2015
Project Conclusions
• No safety issues have been identified/experienced on the pilot plant
• The technical feasibility of the Oxycombustion technology has been demonstrated on the FLSmidth R&D Centre Dania pilot plant
• The retrofit of a LAFARGE cement plant was shown possible
• A full cost of this technology made for Le Havre plant is 62 €/t CO2captured, incl. CO2 compression, liquefaction and liquid storage
• Optimization levers have been identified to cut the expected CO2capture cost down to 50 €/t for a new plant
• There is no viable business model today for CCS on cement plants
• This new technology is now ready for FEED study & demonstration
14
© LafargeHolcim 2015ECRA - CO2 Capture 16 September 2015
Other CCUS Projects
15
© LafargeHolcim 2015ECRA - CO2 Capture 16 September 2015 16
The CO2 Projects Partnerships (2005-2015)
© LafargeHolcim 2015ECRA - CO2 Capture 16 September 2015
The CCUS Projects at LAFARGE (2005-2015)
• CapCO2 Project , studying the MEA scrubbing of CO2 (2005-2008),
• ACACIA Project , studying breakthrough technologies like Enzymes, Ionic Liquids, Clathrates, Demixing Amines (2008-2012),
• Algae Pilot experimentation into a cement plant (France) with Salata Gmbh (2009)
• MANTRA CO2 electroreduction to produce formic acid (CANADA) (started 2009 – on going )
• Oxy-Combustion Project with Air Liquide and FLSmidth (2009-2014)
• France Nord Project to find a CO2 storage in a deep saline aquifer North of France (2009-2014)
• IPMC (in plant mineral carbonation), LAFARGE (2010)
• Separated Calcination Project with Chem. Eng. Dpt. (2010 – on going )
And now:
• SOLIDIA new low CO2 binder using mineral carbonation of industrial ecology (since 2013 )
17
© LafargeHolcim 2015
Summary Learning on Capture Technologies
18
% CO2 Captured
CO2 Capture Cost€/t CO2
DMX™ Solvent (99%vol)
MEA Solvent (99%vol)
Oxycombustion (80%-99%vol)
Separated calcination (80%-99%vol)
CO2 from Flue Gas (15%-25%vol)
[1] From the ACACIA project with IFPEN (2009-2012)
[2] From the ACACIA project with IFPEN (2009-2012)
[3] Estim. by LAFARGE-AL-FLS Oxycomb. Project (2013)
[4] Estim. by LAFARGE IPC-LEC (2013)
[5] Estim. LAFARGE IPC-LEC (2015)
[1][2]
[3]
[4]
[5]
The CO2 and the Cement Industry, July 21 st, 2015
© LafargeHolcim 2015
Which CO 2 for which Applications in the Cement Industry?
The CO2 and the Cement Industry, July 21st, 2015 19
Thank you for your attention
20
BACK UP SLIDE
21
BACK UP SLIDES
© LafargeHolcim 2015ECRA - CO2 Capture 16 September 2015 22
© LafargeHolcim 2015ECRA - CO2 Capture 16 September 2015
Which Levers to Mitigate the CO2 Emissions in the Cement Industry ?
23
LAFARGE has committed to – 33 % in 2020 (base 1990) using those levers
• The usual levers of the Cement Industry are the following:• Cement on clinker ratio (c/k) i.e., allows producing more cement in
using additions to clinker (Blast Furnace Slag, Fly Ash, limestone…) • Control of the specific heat consumption of the kiln, • Use of alternative fuels, especially from biomass
• Between 1990-2014, Lafarge has decreased its specific CO2emissions by 24 % (from 785 to 597 kg CO2/t cement) i.e. a reduction of ~23 Mt CO2/y
• We are studying many other levers to mitigate further our CO2emissions