ccc status report 14/12/2004d.manglunki ab/op 1 status of the cern control centre d. manglunki ab/op
TRANSCRIPT
CCC status report 14/12/2004 D.Manglunki AB/OP 1
Status of the CERN Control Centre
D.Manglunki AB/OP
CCC status report 14/12/2004 D.Manglunki AB/OP 2
ACKNOWLEDGEMENTS:
R.Bailey, J.-L.Baldy, M.Bätz, B.Frammery,R.Saban, L.Serio
M.Delrieux, R.Giachino, S.Knoops, E.Liénard, L.Randot, L.Stewart
M.Clark, D.Hartley, J.Wood
René Ballet, A.Bland, P.Charrue, J.J.Cloye, C.Frisk, R.Hopkins
S.Anghelone, M.Poehler,P.Vachetta
L.Burguete-Oliete, M.Colin, R.Forrest, R.Lauckner
CCC status report 14/12/2004 D.Manglunki AB/OP 3
Outline
• Update on OP days 4-5/3/2004• Current plan:
– 874 extension– Control desks– Layout
• Staff• Schedule• Remaining issues
CCC status report 14/12/2004 D.Manglunki AB/OP 4
Current building extension plan
• No budget for original plan – No closing of ex-CCR and ex-PCR– Loss of > 200m2
– No visitors’gallery– Combine conference room/remote
MD/videoconference – No sacrifice on operators‘ facilities
CCC status report 14/12/2004 D.Manglunki AB/OP 5
Current building extension plan
CCC status report 14/12/2004 D.Manglunki AB/OP 6
Current building extension plan
CCC status report 14/12/2004 D.Manglunki AB/OP 7
Current building extension plan
CCC status report 14/12/2004 D.Manglunki AB/OP 8
Current building extension plan
CCC status report 14/12/2004 D.Manglunki AB/OP 9
Control system
• Standard consoles for all desks… • …But different OS
– 2006 start-up with existing 2004 applications
• 4 different Access systems– SPS & EA as is– PS panels emulated– LHC new system
CCC status report 14/12/2004 D.Manglunki AB/OP 10
Control Desks• 3 screens control display
• 3 screens fixed display (shared by 2)
• 1 administrative PC(shared by 2)
• 5.0 m radius
• 0.65 m deep (+0.65 m)
• 0.72 m high
CCC status report 14/12/2004 D.Manglunki AB/OP 11
Control Desks
CCC status report 14/12/2004 D.Manglunki AB/OP 12
Control Desks: 4 firms selected for tendering
CCC status report 14/12/2004 D.Manglunki AB/OP 13
Control Desks: 4 firms selected for tendering
CCC status report 14/12/2004 D.Manglunki AB/OP 14
Layouts• 1 GTD• 2 CCD
• 2 CCC-WG
• 1 IDOC• Workshop held on 5/11
CCC-WG, IDOC, CCD, S.Baird
CCC status report 14/12/2004 D.Manglunki AB/OP 15
Layout
• 35 control console modules
• 5 access console modules
• 4 Mail/etc PC tables
• 1 social area
• Storage furniture
Laura Stewart AT/ECR
CCC status report 14/12/2004 D.Manglunki AB/OP 16Laura Stewart AT/ECR
CCC status report 14/12/2004 D.Manglunki AB/OP 17
Room ergonomics• Lighting
– 7x11 direct/indirect (20%-80%) from ceiling provide background 200+ Lux
– task lighting at workstation level
• Acoustics– Ceiling, walls, floor & furniture acoustically treated– Acoustic screens behind consoles– RT<0.6s
• Interior decoration– 3 Harmonious colour scheme – 4th chosen by IDOC
CCC status report 14/12/2004 D.Manglunki AB/OP 18Mike Clark CCD
CCC status report 14/12/2004 D.Manglunki AB/OP 19Mike Clark CCD
CCC status report 14/12/2004 D.Manglunki AB/OP 20Mike Clark CCD
CCC status report 14/12/2004 D.Manglunki AB/OP 21Mike Clark CCD
CCC status report 14/12/2004 D.Manglunki AB/OP 22
Staff policy• Mandate: “Define the operating scenario of the
CCC and make recommendations about the management and possible harmonization of the various categories of personnel corresponding to the different CCC usages”
• WG recommendation: 1 single group as soon as possible– merging TCR + MCR teams in 2005
• Method: establish scenario for 2010+ (“LHC steady state”) then study transition
CCC status report 14/12/2004 D.Manglunki AB/OP 23
Staff policy: LHC steady state (2010+)• 10 shift workers:
– 6 senior operators: LHC, SPS, PS, PSB, TI, Cryo
– 3 junior operators SPS, PS, TI/Cryo– 1 LHC EiC
• Shift coordinator among senior operators– Experience of running accelerators– Good understanding of TI & Cryo– CP D
PSBooster
PS SPS LHCTech.
Infrastr.Cryo
JuniorSPS
JuniorPS
JuniorTI/Cryo
CCC status report 14/12/2004 D.Manglunki AB/OP 24
Staff policy: PS/SPS shutdown (2005)
PSBooster
Tech.Infrastr.
JuniorPSB
AB/OP CRYO/OP
Senior
Junior
CryoACR
CryoACR
CryoECR
MCR Local control rooms
3x8 shift also during SD (minimum 2 TI in MCR)
3x8 shift1x8
On-call2x8Shift
legend
CCC status report 14/12/2004 D.Manglunki AB/OP 25
Staff policy: LHC Hardware commissioning (2006-2007)
PSBooster
PS SPSTech.
Infrastr.
JuniorSPS
JuniorPS
AB/OP CRYO/OP
Senior
Junior
CryoACR
CryoACR
CryoECR
CCC Local control rooms
HC LHC
Field CR Field CR
3x8 shift also during SD (minimum 2 TI in MCR)
3x8 shift1x8
On-call2x8Shift
legend
CCC status report 14/12/2004 D.Manglunki AB/OP 26
Staff policy: LHC start-up (2007-2008)
PSBooster
PS SPS LHCTech.
Infrastr.
JuniorSPS
JuniorPS
JuniorTI
CryoECR
CryoACR
AB/OP CRYO/OP
Senior
Junior
CryoACR
CryoECR
CCC
3x8 shift1x8
On-call2x8Shift
legend
CCC status report 14/12/2004 D.Manglunki AB/OP 27
Staff policy: LHC steady state (2010+)
PSBooster
PS SPS LHCTech.
Infrastr.
JuniorSPS
JuniorPS
JuniorTI/Cryo
AB/OP
Senior
Junior
SeniorCryo
CRYO/OP
CryoAcceler.
CryoExper.
CCC
3x8 shift1x8
On-call2x8Shift
legend
CCC status report 14/12/2004 D.Manglunki AB/OP 28
The (very tight) Planning: 59 weeks to go
• 31/12/2004: CE Studies completed, call for tenders out, preparatory works completed; start of civil engineering
• 1/11/2005: building ready; installation begins, followed by commissioning
• 1/2/2006: CCC commissioned, ready for OP
CCC status report 14/12/2004 D.Manglunki AB/OP 29
Planning: 59 weeks to go
CCC status report 14/12/2004 D.Manglunki AB/OP 30
Status of the work• Concrete slab poured• PCR empty• Servers in BA3• IT for consoles going
out• … so far so good!
CCC status report 14/12/2004 D.Manglunki AB/OP 31
Remaining issues
• Operators chairs
• Access systems
• Control system: when to converge?
• Communications
• Fast analog signals
• Parking / Office space
CCC status report 14/12/2004 D.Manglunki AB/OP 32
Conclusions• The CCC project is now well on its way• Tight schedule but respected so far