Page 1: CATIA V4 SOFTWARE DEPLOYMENT PROJECT PROPOSAL JOCELYN NICHOLSON ITMGMT 510 MANAGING THE TECHNOLOGY PROJECT MAY 5, 2010

CATIA V

4 SOFTWARE

DEPLOYMENT PROJE

CT

PROPOSAL

JO

CE

LY

N

NI

CH

OL

SO

N

IT

MG

MT

5

10

M

AN

AG

IN

G

TH

E

TE

CH

NO

LO

GY

P

RO

JE

CT

MA

Y

5,

2

01

0

Page 2: CATIA V4 SOFTWARE DEPLOYMENT PROJECT PROPOSAL JOCELYN NICHOLSON ITMGMT 510 MANAGING THE TECHNOLOGY PROJECT MAY 5, 2010

CATIA V4 SOFTWARE DEPLOYMENT ]PROJECT PROPOSAL

Background

Project Goals

Problem / Opportunity

Resolution Proposal

Recommendation and Summary

Page 3: CATIA V4 SOFTWARE DEPLOYMENT PROJECT PROPOSAL JOCELYN NICHOLSON ITMGMT 510 MANAGING THE TECHNOLOGY PROJECT MAY 5, 2010

BACKGROUND

Dassault Systems produces CATIA V4 software Code.

ABC Aircraft Manufacturing Company XXX Airplane Program is the next new airplane to be build .

XXX New Airplane Program requirement request - capability to release engineering CAD/CAM drawings with CATIA V4 Code.

Engineering release date May 3rd, 2011

Software Life Cycle Development and implementation target timeframe is approximately 9 – 12 months

Page 4: CATIA V4 SOFTWARE DEPLOYMENT PROJECT PROPOSAL JOCELYN NICHOLSON ITMGMT 510 MANAGING THE TECHNOLOGY PROJECT MAY 5, 2010

PROJECT GOALSDevelop rigorous risk assessment processes to gain understanding of

software known and unknown risk

Identify key software risk categories (i.e. change management, configuration management) early stages to reduce risk and impacts.

Reduce cost impacts associated with software risk.

Deliver software quality products to customers.

Avoid schedule delays and eliminate risk to timely delivery of CATIA V4 software product.

Page 5: CATIA V4 SOFTWARE DEPLOYMENT PROJECT PROPOSAL JOCELYN NICHOLSON ITMGMT 510 MANAGING THE TECHNOLOGY PROJECT MAY 5, 2010

PROBLEM / OPPORTUNITY

CATIA V4 Software (S/W) is a new product which has never been released into ABC infrastructure.

Potential Cost budget overruns

Schedule delays due to unknown risk and impacts. 

Decreased Software product quality

Delayed Airplane deliveries to Airline Customers

Page 6: CATIA V4 SOFTWARE DEPLOYMENT PROJECT PROPOSAL JOCELYN NICHOLSON ITMGMT 510 MANAGING THE TECHNOLOGY PROJECT MAY 5, 2010

PROPOSED SOLUTION

Successful CATIA V4 Software implementation

 

SEI Taxonomy Based Questionnaire (TBQ).

 

Software Life Cycle Development Best Practices are documented and followed.  

 

3D CAD/CAM parts, assemblies, and installations capability available on distributed workstations.

Increase airplane sales and revenue gains

Page 7: CATIA V4 SOFTWARE DEPLOYMENT PROJECT PROPOSAL JOCELYN NICHOLSON ITMGMT 510 MANAGING THE TECHNOLOGY PROJECT MAY 5, 2010

SCOPE

ABC Airplane Manufacturing Company increased sales and revenues

CATIA V4 software implemented in production for XXX New Airplane Program

Engineering and Manufacturing Engineers Planning on line 3D Drawings

3D (Dimensional Views) CAD/CAM Released Drawings using CATIA V4

Page 8: CATIA V4 SOFTWARE DEPLOYMENT PROJECT PROPOSAL JOCELYN NICHOLSON ITMGMT 510 MANAGING THE TECHNOLOGY PROJECT MAY 5, 2010

QUALITY

Total Quality Assurance (TQA)

Policy and Procedures

Continuous Process Improvements (CPI)

Software Engineering Institute Taxonomy Questionnaire and Survey Results

Lean Value Stream Mapping (VSM) to be used on all key processes

Page 9: CATIA V4 SOFTWARE DEPLOYMENT PROJECT PROPOSAL JOCELYN NICHOLSON ITMGMT 510 MANAGING THE TECHNOLOGY PROJECT MAY 5, 2010

Cost Categories Amount

Note: cost figures are estimates and not completely accurate.

Internal Labor hours 100 developer and system analyst support @ $65 = $6500

External costs  

Labor (consultants, contract labor) 50 @ $46 = $2300 - contract analyst support

Equipment, hardware or software 200 Distributed Workstations @ $1800 = $360,000

5 Software License @ $25000 annually = $125,000

BUDGET COST(ESTIMATE)

Page 10: CATIA V4 SOFTWARE DEPLOYMENT PROJECT PROPOSAL JOCELYN NICHOLSON ITMGMT 510 MANAGING THE TECHNOLOGY PROJECT MAY 5, 2010

Major Milestones Schedule

Opportunity Evaluation 03/30/10Build Requirement Plan 05/30/10Build Risk Management Plan 06/20/10Preliminary Analysis 06/30/10Preliminary Analysis Review 07/13/10Update Risk Management Plan 07/30/10CATIA Work Station Deployment 08/12/10Design and Code 09/30/10Test and Validation 12/30/10Production Implementation 03/20/11

MAJOR MILESTONE SCHEDULE(PRELIMINARY)

Page 11: CATIA V4 SOFTWARE DEPLOYMENT PROJECT PROPOSAL JOCELYN NICHOLSON ITMGMT 510 MANAGING THE TECHNOLOGY PROJECT MAY 5, 2010

MAJOR MILESTONE SCHEDULE(PRELIMINARY)

(CONT’D)

Page 12: CATIA V4 SOFTWARE DEPLOYMENT PROJECT PROPOSAL JOCELYN NICHOLSON ITMGMT 510 MANAGING THE TECHNOLOGY PROJECT MAY 5, 2010

RESOURCE AVAILABILITY

CATIA Usability Lab and Distributed workstations

Core Planning team

Application Developers

Systems Analyst

Project Manager

Software Licenses

Page 13: CATIA V4 SOFTWARE DEPLOYMENT PROJECT PROPOSAL JOCELYN NICHOLSON ITMGMT 510 MANAGING THE TECHNOLOGY PROJECT MAY 5, 2010

RECOMMENDATIONS

Core Planning Team Recommends

CATIA V4 Deployment Target date March 15, 2011

CATIA V4 Developer and System Analyst Training

Escalation boards established immediately

Management Committee buyoff and approval

Page 14: CATIA V4 SOFTWARE DEPLOYMENT PROJECT PROPOSAL JOCELYN NICHOLSON ITMGMT 510 MANAGING THE TECHNOLOGY PROJECT MAY 5, 2010

Q & A

Page 15: CATIA V4 SOFTWARE DEPLOYMENT PROJECT PROPOSAL JOCELYN NICHOLSON ITMGMT 510 MANAGING THE TECHNOLOGY PROJECT MAY 5, 2010

REFERENCES

Project Management Institute (2008). A guide to the project management body of knowledge

 

(PMBOK Guide)(4th ed). Chp. 4 - 12. Pennsylvania: Project Management Institute Inc.

 

Verzuh, E. (2008). The fast forward MBA in Project Management, 4th edition. Hoboken, NJ:

 

John Wiley and Sons. Retrieved April 12, 2010