case study - usa - connecticut - moses wheeler bridge
TRANSCRIPT
CASE STUDYUSA - Connecticut
Moses Wheeler Bridge
#CHALLENGES
1) Keep the bridge fully operational during the replacing and widening process
2) Safely run on variable curved runway rails, at different levels and slopes.
#SOLUTION
Supply of 3 "Special Gantries" equipped with a 70 US ton capacity winches and custom engineered, able to run on two rails installed in two snakeline bands and to perform all the necessary material handling.
#OUTCOME
A smart technology, high productivity, safe working conditions and 135,000 cars and trucks passing every day, as usual, also during replacement and widening operations.
Via Buttrio, 3633050, Cargnacco (UD)- ITALYTelephone: +39 0432 607900
Fax: +39 0432 [email protected]