case study redesign of vertical pump trebles mean time between vespel® bearing failure… · 2021....

2
CASE STUDY REDESIGN OF VERTICAL PUMP TREBLES MEAN TIME BETWEEN FAILURE • Redesign addressed origin of failure • MTBF improved for under 1 year to more than 3 years • Chemical leakage prevented, improving site safety CHALLENGE A post-installation modification to improve flow in a vertical chemical pump had weakened the discharge elbow. Subsequent cracking had been weld-repaired several times, but the pump was increasingly difficult to maintain. The customer asked ClydeUnion Pumps to undertake a redesign of the discharge elbow to prevent further deterioration. SOLUTION The modification that had caused the failure was undertaken originally because the gland ring outlets on the discharge elbow were not sufficient to evacuate the liquid passing around the head shaft. ClydeUnion Pumps therefore proposed a solution that would address this original issue as well as repairing the point of failure. The solution was to re-design the discharge elbow and separate it in two parts: the elbow itself, above the support surface, and a suction spool under. ClydeUnion Pumps redesigned the upper section with vanes to make it stiffer than before and incorporated a new salvage pipe in case of leakages. The lower, suction spool section has been made as a single piece part to increase its solidity. The former three gland ring outlets have been replaced by one, and the liquid pumped is passed by five holes that represent an area equivalent to the former version. To prevent corrosion, the bearings were also upgraded to a material with superior wear and abrasion characteristics, plus better chemical compatibility. OUTCOMES The pump has been operating well since the upgrade. The change of bearings material has eliminated abnormal wear and reduced the MTBF from less than one year to in excess of three years. Industry: Oil & Gas – chemicals Region: Europe Category: Site fault investigation API Type: VS6 ClydeUnion Pumps Aftermarket Technical Services team has experience across a range of services on critical rotating and reciprocating equipment to improve operational safety, reliability and e�ciency. The design upgrade of the VM32 for the oil and gas market is one of our success stories documented in our library of case studies. These case studies highlight the requirement from the customer, how we achieved the goal and the process we followed to deliver the improvements. Vespel® bearing 3rd additional outlet Failure area 2 gland ring outlets Head shaft place

Upload: others

Post on 03-Aug-2021

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CASE STUDY REDESIGN OF VERTICAL PUMP TREBLES MEAN TIME BETWEEN Vespel® bearing FAILURE… · 2021. 1. 6. · Failure area 3rd additional outlet 2 gland ring outlets Head shaft place

CASE STUDY

REDESIGN OF VERTICAL PUMP TREBLES MEAN TIME BETWEEN FAILURE

• Redesign addressed origin of failure

• MTBF improved for under 1 year to more than 3 years

• Chemical leakage prevented, improving site safety

CHALLENGEA post-installation modifi cation to improve fl ow in a vertical chemical

pump had weakened the discharge elbow. Subsequent cracking had been

weld-repaired several times, but the pump was increasingly diffi cult to

maintain. The customer asked ClydeUnion Pumps to undertake a redesign

of the discharge elbow to prevent further deterioration.

SOLUTIONThe modifi cation that had caused the failure was undertaken originally

because the gland ring outlets on the discharge elbow were not suffi cient

to evacuate the liquid passing around the head shaft. ClydeUnion Pumps

therefore proposed a solution that would address this original issue as

well as repairing the point of failure.

The solution was to re-design the discharge elbow and separate it in two

parts: the elbow itself, above the support surface, and a suction spool

under. ClydeUnion Pumps redesigned the upper section with vanes to

make it stiff er than before and incorporated a new salvage pipe in case of

leakages. The lower, suction spool section has been made as a single piece

part to increase its solidity. The former three gland ring outlets have been

replaced by one, and the liquid pumped is passed by fi ve holes that

represent an area equivalent to the former version. To prevent corrosion,

the bearings were also upgraded to a material with superior wear and

abrasion characteristics, plus better chemical compatibility.

OUTCOMESThe pump has been operating well since the upgrade. The change of

bearings material has eliminated abnormal wear and reduced the MTBF

from less than one year to in excess of three years.

Industry: Oil & Gas – chemicals

Region: Europe

Category: Site fault investigation

API Type: VS6

ClydeUnion Pumps Aftermarket Technical

Services team has experience across

a range of services on critical rotating

and reciprocating equipment to improve

operational safety, reliability and e� ciency.

The design upgrade of the VM32 for the oil

and gas market is one of our success stories

documented in our library of case studies.

These case studies highlight the requirement

from the customer, how we achieved the

goal and the process we followed to deliver

the improvements.

Vespel® bearing

3rd additional outletFailure area

2 gland ring outlets Head shaft place

Page 2: CASE STUDY REDESIGN OF VERTICAL PUMP TREBLES MEAN TIME BETWEEN Vespel® bearing FAILURE… · 2021. 1. 6. · Failure area 3rd additional outlet 2 gland ring outlets Head shaft place

For more information about our worldwide locations, approvals, certi� cations, and local representatives, please visit www.celeros� .com. Celeros Flow Technology reserves the right to incorporate our latest design and material changes without notice or obligation. Design features, materials of construction and dimensional data, as described in this bulletin, are provided for your information only and should not be relied upon unless con� rmed in writing.

Ref no: CUP_383_04_VS6-VTU_GB Version: 10/2020 COPYRIGHT © 2020 Celeros Flow Technology

• Re-design of the upper part of the discharge elbow This part is designed to be stiff er than the older version

It also integrates a salvage pipe for possible leaks.

• Re-design of the lower part of the discharge elbow

(suction spool) A step-by-step manufacturing process was developed due to

the necessity to alter dimensions for cladding after initial

testing. Finally, calculations were made to predict the likely

shrinkage of casing and cover fi ts after processing/cladding

at 1,900 °F.

• View of the assembly

• Assembly of Vespel® CR6100 bearings Due to the abrasive nature of the liquid pumped (water +

organic matter), the choice was made to change the former

PTFE based bearings to Vespel® CR6100 bearings.

OPERATIONAL IMPROVEMENTSSince the upgrade and the change of bearings material from

PTFE to Vespel® CR6100, there has been no abnormal wear of

bearings. Before the MTBF for the PTFE bearings was less than

one year. The pump is operating well with the new discharge

elbow.

FINANCIAL ILLUSTRATION

Analysis on 3 years

• Current version:

Expertise, overhaul of the entire pump + studies and supply

of new designed parts = 70K Euros

MTBF is currently more than 3 years.

• Former version:

Maintenance cost required for bearings change and expertise

of pump state = 20K /year

Cost for 3 years = 60K Euros + spare parts + weld repair of

discharge elbow > 70K Euros

Aberdeen Service Center P: +44 1224 756 100

Abu Dhabi Service CenterP: +971 02 4081900

Annecy Service CenterP: +49 405 220 2401

Baton Rouge Service CenterP: +1 225 778 3310

Battle Creek Service CenterP: +1 269 966 4782

Burlington Service CenterP: +1 905 315 3813

Calgary Service CenterP: +1 800 352 8294

Corpus Christi CenterP: +1 361 371 6519

Downey Service CenterP: +1 562 622 2371

Glasgow Service CenterP: +44 141 637 7141

Jenks Service CenterP: +1 281 217 6359

Odessa Service CenterP: +1 704 808 3780

Penistone Service CenterP: +44 1226 763 311

Singapore Service CenterP: +65 6513 9276

Zhengzhou Service CenterP: +86 371 8665 2391

E: [email protected]

AFTERMARKET CASE STUDY

DS.812035/1

ISSUE DATE: December 09

Industry: Chemistry Territory: France

Discharge elbow and bearings modifications on VM 32x28 9 stages

Category: Design upgrade API Type: VS6

These documents are CONTROLLED when viewed on-line only. Hard copies or local copies are UNCONTROLLED. © Clyde Pumps Ltd Page 2 of 4

DESCRIPTION OF WORK UNDERTAKEN

- Re-design of the upper part of the discharge elbow This part is design to be stiffer than the older version. It also integrates the salvage pipe for possible leaks.

- Re-design of the lower part of the discharge elbow (suction spool) The choice was made to have a single-piece part to increase its solidity. The former 3 gland ring outlets are replaced by one, and the liquid pumped pass by 5 holes that represent an area equivalent at the former version.

Outlet

5 Holes for liquidpassage

Head shaft place

Discharge elbow

Suction spool

Gland ring

Salvage pipe for leaks

Head shaft place

Gland ring outlet

Addition of 4 ribs to increase sti� ness

Salvage pipefor leaks