case study hospital

1
BREEAM OUTSTANDING ACCREDITED HOSPITAL MISSION STATEMENT The building design and engineering strategy follows the needs of a 21st century healthcare facility providing a therapeutic environment that promotes health and well-being, is patient orientated, intuitive and flexible to future needs. The aim is to design a positive impact building that uses fewer resources, generates less waste, curbs CO 2 emissions and to save the NHS money over its life-cycle. All wash basins are sensor operated All surfaces, floors and walls have an easy clean, durable hygienic surface coating. MECHANICAL SERVICES 9 Air Handling Units have been selected to provide all occupied rooms with the option of mechanical ventilation. Ultra Clean Ventilation system used within the operating theatres for infection control. 10kW ground source heat pump used for under-floor heating in atrium. 10000L GRP Storage Tank stores sufficient water to supply 24 hour requirements. 460kW gas fired, condensing boiler selected as the primary method of heating water. External VIE has been sized to store 3927L of oxygen at -160°C. ELECTRICAL SERVICES: Calculated power requirement of 210kVA, supplied by LV DNO connection. Standby generator provides backup to the essential areas of the hospital. Solar shading system tracks the sun and collects electricity via PV technology. 62 PV panels installed on the roof. Fibre optic cables draw natural light down into corridors. ESTIMATED CAPITAL COST: £7.92M Cost per square metre: £1494 SUPERSTRUCTURE: Cast-in-situ reinforced concrete frame. C50/60 concrete mix with a 50% GGBS content specified. Flat slab design offers maximum flexibility in layout. Slabs designed using the yield-line method. The structure is braced by concrete shear walls incorporated into lift cores. Steel sections have been utilized in the atrium to provide long spans of column free space. SUBSTRUCTURE: CFA piles are to be utilized due to their low noise and vibration installation. 144 CFA piles (450mm diameter) are to be installed to a depth of 23 metres. Floor slabs are to be ground bearing. PROJECT COSTS: BREEAM Rating: 85.2%. ARCHITECTURAL CONCEPTS: The hospital layout is designed around clinical adjacencies to ensure it is highly functional. Patient orientated design that promotes health and wellbeing. Intuitive layout reduces the stresses of wayfinding within the hospital. Wherever possible natural daylight is introduced and views to the outside are provided. The facade design follows a modern, simple and efficient statement design. Each floor is divided into 3 main fire compartments. Each compartment has two independent escape routes 25% Green Space. INFECTION CONTROL: Inpatient and outpatient departments separated. Clean and dirty corridors provided for operating theatres. High ventilation rates throughout patient areas prevent airborne transmission. SUSTAINABILITY: Narrow plan design reduces energy costs. Rainwater harvesting for toilet flushing and irrigation. Locally sourced materials & labour specified. Extensive green roof. Building management system optimises the use of services. Flexible for future developments in medical science or management. R. Bayton, B. Drew, S. Godicke, T. Lawson & I. Smith Cardiff Bay Orthopaedic Hospital Group F 2011

Upload: yoga-lakshmi

Post on 03-Oct-2015

78 views

Category:

Documents


3 download

DESCRIPTION

orthopedic hospital case study presentation

TRANSCRIPT

  • BREEAM OUTSTANDING ACCREDITED HOSPITAL

    MISSION STATEMENT

    The building design and engineering strategy follows the needs of a 21st century healthcare facility

    providing a therapeutic environment that promotes health and well-being, is patient orientated,

    intuitive and flexible to future needs. The aim is to design a positive impact building that uses fewer

    resources, generates less waste, curbs CO2 emissions and to save the NHS money over its life-cycle.

    All wash basins are sensor operated

    All surfaces, floors and walls have an easy clean, durable

    hygienic surface coating.

    MECHANICAL SERVICES

    9 Air Handling Units have been selected to

    provide all occupied rooms with the option

    of mechanical ventilation.

    Ultra Clean Ventilation system used within

    the operating theatres for infection control.

    10kW ground source heat pump used for

    under-floor heating in atrium.

    10000L GRP Storage Tank stores sufficient

    water to supply 24 hour requirements.

    460kW gas fired, condensing boiler selected

    as the primary method of heating water.

    External VIE has been sized to store

    3927L of oxygen at -160C.

    ELECTRICAL SERVICES:

    Calculated power requirement of

    210kVA, supplied by LV DNO connection.

    Standby generator provides backup to the

    essential areas of the hospital.

    Solar shading system tracks the sun and

    collects electricity via PV technology.

    62 PV panels installed on the roof.

    Fibre optic cables draw natural light down

    into corridors.

    ESTIMATED CAPITAL COST: 7.92M Cost per square metre: 1494

    SUPERSTRUCTURE:

    Cast-in-situ reinforced concrete frame.

    C50/60 concrete mix with a 50% GGBS

    content specified.

    Flat slab design offers maximum flexibility in layout.

    Slabs designed using the yield-line method.

    The structure is braced by concrete shear walls incorporated into lift cores.

    Steel sections have been utilized in the atrium to provide long spans of column free space.

    SUBSTRUCTURE:

    CFA piles are to be utilized due to their low noise and vibration installation.

    144 CFA piles (450mm diameter) are to be installed to a depth of 23 metres.

    Floor slabs are to be ground bearing.

    PROJECT COSTS:

    BREEAM Rating: 85.2%.

    ARCHITECTURAL CONCEPTS:

    The hospital layout is designed around clinical adjacencies to ensure it is highly

    functional.

    Patient orientated design that promotes health and wellbeing.

    Intuitive layout reduces the stresses of wayfinding within the hospital.

    Wherever possible natural daylight is introduced and views to the outside are

    provided.

    The facade design follows a modern, simple and efficient statement design.

    Each floor is divided into 3 main fire compartments. Each compartment has

    two independent escape routes

    25% Green Space.

    INFECTION CONTROL:

    Inpatient and outpatient departments separated.

    Clean and dirty corridors provided for operating theatres.

    High ventilation rates throughout patient areas prevent airborne transmission.

    SUSTAINABILITY:

    Narrow plan design reduces energy costs.

    Rainwater harvesting for toilet flushing and irrigation.

    Locally sourced materials & labour specified.

    Extensive green roof.

    Building management system optimises the use of services.

    Flexible for future developments in medical science

    or management.

    R. Bayton, B. Drew, S. Godicke, T. Lawson & I. Smith

    Cardiff Bay Orthopaedic Hospital Group F

    20

    11