carey group scotland projects

Upload: chris-findlay

Post on 07-Jul-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/19/2019 Carey Group Scotland Projects

    1/15

    DEMOLITION | CIVIL ENGINEERING | CONCRETE STRUCTURES | BUILDING | ENVIRONMENTAL SOLUTIONSDEMOLITION | CIVIL ENGINEERING | CONCRETE STRUCTURES | BUILDING | ENVIRONMENTAL SOLUTIONS

    Scotland Case Studies

  • 8/19/2019 Carey Group Scotland Projects

    2/15

    More Information

    Sector

    Project

    Project Overview

    Gallery

    Services

    Project Details

    Client

    Location

    Principal Contractor

    Engineer / Consultant / PQS

    Case Studies

     A complex support system of hydraulic props was required to support the contiguous pile

    wall that retained the railway tracks. On two of the other excavations, ground anchors

    were used to tie back the contiguous pile walls. Above the 2 levels of parking are the new

    ofces for the City of Edinburgh Council.

    This is a 5 storey high quality nish concrete frame. The ceilings are formed with a series

    of drop beams spanning 14m with the slab spanning between. To add to the aesthetic

    appearance the concrete was curved from the bottom of the beam to the underside of

    the slab.

    Careys was awarded a complex substructure and superstructure contract adjacent to

    Waverly Station, Edinburgh. The building is seven storeys high and covers the entire

    footprint of the site, which has been overlaid on a series of brick arch vaults. These

    vaults had to be demolished and a further 2m depth of spoil was removed to make way

    for the 2 levels of underground car parking. Some 4,000m³ of foam concrete was used to

    stabilise the vaults left.City of Edinburgh Council

    Edinburgh, Scotland

    Miller Construction

    Beattie Watkinson

    Commercial / Ofce Development

    City of Edinburgh Council HQ

  • 8/19/2019 Carey Group Scotland Projects

    3/15

    More Information

    Project Overview

    Gallery

    Services

    Project Details

    Client

    Location

    Principal Contractor

    Engineer / Consultant / PQS

    Case Studies

    Sector

    Project

    The substructure works included construction of piles caps, ground beams and under-slab

    drainage including an RC basement and RC service tunnels.

    The 4 RC cores were constructed using a crane assisted jump-form system in advance

    of the oor construction. The frame includes both in-situ and precast concrete columns

    erected as the PT oorslab construction proceeds on a oor by oor cycle.

    Careys expertise was drawn on by the principal contractor to convince the client that a

    concrete design using PT slabs would provide signicant benets compared to a structural

    steel frame when constructing the new Emergency Care Centre in Aberdeen. Benets

    discussed with NHS Grampian included: reduced build programme (4 weeks), increased

    insulation and re resistance properties and a reduced number of support columns

    providing oor areas with exibility of use. The client accepted the advice and Careys was

    employed to build the substructure and superstructure works for the 8 storey building

    and to provide the design of the PT oor-slabs.

    Ramsey & Chalmers

    Robertson Construction Group

     Aberdeen, Scotland

    NHS Grampian

    Aberdeen Emergency Care

    Public / Health

  • 8/19/2019 Carey Group Scotland Projects

    4/15

    More Information

    Sector

    Project

    Project Overview

    Gallery

    Services

    Project Details

    Client

    Location

    Principal Contractor

    Engineer / Consultant / PQS

    Case Studies

    Hammerson Plc

    Aberdeen, Scotland

    Millers

    Fairhurst

    The contract was split into 2 phases, the first to provide a 5,500 m² car park to replace

    the existing station car park which was incorporated into the development and the

    construction of the new bus station with the structure for the cinema.

    During phase 1 works, Network Rail moved from the goods yard, next to the station, to a

    new facility at Dyce close to the airport. Once the move was completed work on phase 2;

    the retail space commenced.

    The retail space is a steel framed building founded on piles with a ground level carpark

    and a multi-storey carpark above the units. Access to the parking levels was via areinforced concrete elongated ‘U’ shaped ramp for the cars and a 3 story RC stair and lift

    tower for pedestrians.

    This development is situated next to the Railway Station and incorporated a new bus

    station and 55,000 m² of retail space. Careys was contracted to carry out all earthworks,

    piling mats, foundations, underground services, drainage, ground oor slabs, service

    and bus station brushed nished concrete slabs, upper oors on metal decking, hard

    landscaping and major highway works for the access and egress into the development.

    Railway station alterations included the construction of new lift pits, corridor roof slabsand removal and lowering of existing oor slabs. Works were undertaken out of hours for

    minimal disruption to the station schedule.

    Retail / Shopping Centres 

    Union Square

  • 8/19/2019 Carey Group Scotland Projects

    5/15

    Sector

    Project

    Project Overview

    Services

    Project Details

    Client

    Location

    Principal Contractor

    Engineer / Consultant / PQS

    Case Studies

    More Information

    Gallery

    The demolition works involved the removal & disposal of 350 tonne of asbestos

    containing materials and on site processing (recycling) of 20,000 tonnes of arisings,whilst maintaining designed site specic environmental protection measures.

    Careys was then contracted as a lead groundworks contractor, constructing a substantial

    element of the new European Headquarters of the Royal Bank of Scotland under an

    earthworks and drainage package, which required approximately 120,000m3 of earth to

    be moved on to the site. This earth was required to create a basement for the new HQ.

    The development covered a 78 acre site and included 350,000 sq ft ofce accommodation

    with all the new access routes to site also being constructed including; pedestrian and

    cyclist routes and bridges. Associated street furniture included a bus stop, a water feature

    - clad with black granite from China, and granite benches.

    The scope of works included hard landscaping at the ofces to create a central area

    for staff. These works included laying granite set paving and Caithness (Scottish typegranite) stone paving, granite kerbed footpaths with resin bound nish, granite steps and

    granite cubes were laid to a Bogen pattern. An articial grass football pitch and basketball

    court was built as a leisure facility. Soft landscaping was carried out throughout the

    extensive site for the installation of trees, plants and turfed areas. Careys works involved

    the preparation and placing of substantial areas of the site including importing soil ready

    for planting. Close collaboration, coordination and planning were carried out between

    Careys and the specialist soft landscaping trade contractor.

    Careys was initially instructed to perform a small enabling package for a car park near to

    Gogarburn House which is part of the above site, following successful completion Scudder

    was then appointed to demolish the former Gogarburn Hospital. Demolition made way for

    the Royal Bank of Scotland’s new European headquarters. Scudder was also instructed

    to carry out removal and disposal of asbestos containing materials found on the site. A

    further contract was awarded to Careys as lead groundworks contractor.Royal Bank of Scotland

    Edinburgh, Scotland

    Mace

    Robert Bird Associates / Doig & Smith

    Commercial / Ofce Development

    RBS Eurpopean HQ

  • 8/19/2019 Carey Group Scotland Projects

    6/15

    More Information

    Sector

    Project

    Project Overview

    Gallery

    Services

    Project Details

    Client

    Location

    Case Studies

    Sainsbury’s Supermarkets Plc

    Various

    In 1989 we embarked on our 1st major project at London Colney, this external works

    package proved to be a shining example of Careys commitment to delivery, almosthalving the programme from 37 weeks to 20 weeks.

    As the hypermarket format became more mainstream, other stores were developedacross England, with Careys playing an ever larger role in each project. In 1995

    Careys received the first commission to carry out substructure and external

    works at a flagship store in Hamilton, Scotland. This was quickly followed by arollout programme of stores across the country with Careys undertaking various

    commissions.

    The larger store format has proliferated since the late 1990s, and Careys has

    completed in excess of 200 UK contracts, delivering infrastructure, drainage,

    landscaping, roadworks and the construction of superstructures.

    Careys are proud to have worked in partnership with Sainbury’s since 1989 oncommissions throughout the UK and Ireland. Our relationship initially developedthrough our demolition business; Scudder, which carried out projects to such a highstandard Careys were invited to tender for main works packages. The continuedsuccess of project delivery led to Careys being awarded the design and build/

    extension contract for Sainsbury petrol stations, and we have now become arst tier contractor on the nationwide capital car park and drainage maintenancepackage.

    Retail / Food & General 

    Sainsbury’s

    Principal Contractor

    Engineer / Consultant / PQS

    Various

    Various

  • 8/19/2019 Carey Group Scotland Projects

    7/15

    More Information

    Sector

    Project

    Project Overview

    Gallery

    Services

    Project Details

    Client

    Location

    Principal Contractor

    Engineer / Consultant / PQS

    Case Studies

    The 4.6m high columns in the atrium area were constructed kickerless and seamless, with

    no horizontal ply wood joints. The upstand beams around the atrium were formed with a

    ne smooth nish with a regular ply pattern. The total oor area of 32,500m² was spread

    over 5 main oors and a mezzanine, with around 500t of reinforcement and 2,000m³ of

    concrete per oor. The 450mm thick concrete oors were constructed using large table

    forms.

    The BBC Scotland Headquarters is situated on the bank of the River Clyde. The

    substructure was heavily reinforced with pile caps and ground beams sitting on large

    diameter [up to 1200mm] piles. This involved the placing 900t of reinforcement and

    2,500m³ of concrete.

    The superstructure columns were set on a 9m grid and varied in height from 3.0m up to6.0m. All columns were constructed with a ne smooth nish with sharp arises.

    The central atrium was constructed in structural steelwork with metal decked concrete

    oors. It contained four lift and stair cores, with precast concrete stair ights.

    BBC

    Glasgow, Scotland

    Bovis Lend Lease

    Faber Maunsel / Gleeds

    Commercial / Ofce Development

    BBC Scotland HQ

  • 8/19/2019 Carey Group Scotland Projects

    8/15

    More Information

    Sector

    Project

    Project Overview

    Gallery

    Services

    Project Details

    Client

    Location

    Principal Contractor

    Engineer / Consultant / PQS

    Case Studies

    The contract works undertaken by Careys included; installation of all underground

    drainage and ducts; earthworks, off site and on site cut and ll; construction of pile caps;

    construction of 8 concrete stair and lift cores (constructed using rail climbing system) and

    ground oor slab.

    The substructure is 3 levels of underground concrete frame car park all with post

    tensioned slabs. The superstructure is a 7 storey concrete frame hotel and 6 storey

    concrete frame ofce block both with post tensioned slabs.

    The Carey team was appointed to provide sub and superstructure works on this Hotel

    and Ofce Block development in Aberdeen, including underground car park. The scope of

    works also included bulk excavation and all external hard landscaping of the site. A total

    of 13,000m3 of concrete was poured throughout the duration of this project.

    Hazeldene Ltd

     Aberdeen, Scotland

    Miller Construction

    Buro Happold

    Commercial / Mixed Use

     Justice Mill Lane

  • 8/19/2019 Carey Group Scotland Projects

    9/15

    More Information

    Project Overview

    Gallery

    Services

    Project Details

    Client

    Location

    Principal Contractor

    Engineer / Consultant / PQS

    Case Studies

    Sector

    Project

    The 15,500 square metres of oor-space will host over a quarter of a million books,

    maps and manuscripts, as well as 1,200 reader spaces in a variety of environments.

     Addit ionally, special libraries and archives of fer historical collections in connection to a

    secure rare books reading room. The new library will run by approximately 60 staff and

    serve a community of over 16,000 students.

    The historic nature of the site brought challenges to the project but Careys philosophy

    of approaching every project with care, planning and attention to detail ensured that the

    project ran smoothly.

    The University of Aberdeen, which was established in 1495 and is one of the oldest

    English language universities in the world and of real historical importance. Careys

    works included; ground oor slab, concrete cores, retaining walls and suspended slabs.

    The project was to carry out the construction of in-situ reinforced concrete basement

    walls, columns, podium deck and 2 no. large nine storey cores (both containing 9 cells)

    resulting in 3,000m3 of concrete being poured. The columns, soft and core concrete are

    all exposed faces.

    Public / Education

    University of Aberdeen - Library

     Arup

    Pihl UK Ltd.

     Aberdeen, Scotland

    University of Aberdeen

  • 8/19/2019 Carey Group Scotland Projects

    10/15

    More Information

    Sector

    Project

    Project Overview

    Gallery

    Services

    Project Details

    Client

    Location

    Principal Contractor

    Case Studies

    Aldi

    Scotland

    Mace, LM Construction and Chard Ltd.

    Woolgar Hunter and Stuart McTaggart /

    Doig & Smith

    The stores are steel framed and clad with pre-cast concrete panels, metal sheeting,

    curtain walling, or a mixture. Careys role was to construct the foundations and install

    pre-cast ground beams, retaining walls, and the floor slabs. The average size of a store

    is 1800m² comprising of power floated warehouse and office accommodation and the

    remainder sales floor which is usually tiled.

    The external drainage works can be constructed around a SUDS system where required;

    this usually involved the installation of a large Stormcell attenuation tank, backed up with

    stone filled filter trenches to discharge the water back to ground. The external areas

    have tarmac circulation routes with block paved parking bays and concrete service yards/ delivery bays. The block paving is laid on no fines aggregate to allow draining back to

    filter drains.

    Careys was contracted to provide the civil engineering works on sites across Scotland.

    Careys undertook the concrete and external works on 14 stores, and have additionally

    completed resurfacing work for the car park at Dumfries and minor works on the Stirling

    store. The stores are generally built on inner city brown eld sites which give rise to their

    own problems of access, underground obstructions and existing site features.

    Retail / Food & General 

    Aldi

    Engineer / Consultant / PQS

  • 8/19/2019 Carey Group Scotland Projects

    11/15

    Sector

    Project

    Project Overview

    Services

    Project Details

    Client

    Location

    Principal Contractor

    Engineer / Consultant / PQS

    Case Studies

    More Information

    Gallery

    The enabling works involved the construction of; a 50m long retaining wall, 150m of6m deep drainage diversion, the exposure and protection of transatlantic bre optic

    cables and the placing of 12,000m3 of piling mat. Careys remit for the substructure and

    superstructure packages for the commercial building involved the construction of three

    32m high reinforced concrete (RC) cores, drainage, pile caps, ground beams (concrete

    works consisting of 6200m3 of concrete) and a seven storey steel structure.

    The scope of works for the residential building consisted of two number RC cores. The

    cores were constructed ahead of the RC oors and columns which consisted of twenty-

    one storeys covering 645m2 with twenty-three RC columns. Two tower cranes had been

    erected at 72m high and 76m high using a 500t mobile crane with an extended y jib to

    assist with this phase of works. In order to minimise the crane usage, the structure was

    constructed with the use of a 66m high static pump to place the concrete. A mixture of

    sky decking and tables were used for the formwork.

    Programme targets of the construction of one storey per week were all achieved. The site

    itself created a challenge due to the conned space and inner city location, bordering the

    14 storey Marriot Hotel, two 20 storey blocks of council ats and Argyle Street in the city

    centre of Glasgow. Working in a sensitive inner city location, health and safety for the

    site workers and the public was our greatest concern and trafc management, logistical

    planning and restricted site access were a priority.

    The initial project undertaken by Careys was to carry out the enabling works. After

    the successful completion a further project was awarded for the substructure and

    superstructure packages of the development which included construction of a 7 storey

    commercial and 21 storey residential building. An added challenge to the project was

    that works were carried out in a complex inner city environment with the site bordering a

    major hotel, residential property and one of the busiest streets in Glasgow City Centre.Taylor Woodrow Ltd

    Glasgow, Scotland

     Vinci Construction

    Halcrow Yolles

    Commercial / Mixed Use

    Anderson Regeneration

  • 8/19/2019 Carey Group Scotland Projects

    12/15

    More Information

    Sector

    Project

    Project Overview

    Gallery

    Services

    Project Details

    Client

    Location

    Principal Contractor

    Engineer / Consultant / PQS

    Case Studies

    The contract began with the construction of the tower crane base, core bases and car

    pit. Core construction progressed while the ground oor slab was constructed followed

    by the suspended concrete slabs. A panel system that was used to form the softs of the

    suspended slabs with a framed perimeter providing a safe working platform for our PT

    contractor; cycle times of between 8 -10 days were typically achieved between oors.

    The construction of the suspended slabs was broken down into three pours per level due

    to the restrictions caused by PT construction, with a total oor area of 880m2.

    Freyssinet were awarded the subcontract for the PT works on site. Cables weretensioned up to 25% after 1 day, and to 100% after 3-4 days depending on cube

    results. With PT slabs the concrete is put into compression which means the amount of

    reinforcement required can be reduced. It also allows greater spans between columns

    giving a greater uninterrupted oor area. PT slabs also allow the thickness of concrete

    slabs to be reduced allowing for a greater height between oors.

    Careys was awarded the contract to construct this 10 storey Post Tension Concrete

    Frame in the centre of Glasgow. The scope of works included the following; supply and

    install groundworks, pile caps, drainage, ground slab, concrete frame and core including

    associated works. Design, supply and installation of suspended concrete slabs including

    post tensioning were also carried out by Careys.

    This post tension (PT) concrete frame consisted of a 10 storey concrete superstructure, 2

    no. concrete cores, (one with 3 no. lift shafts), a car pit to hold 9 no. cars below ground

    level and all foundations and below ground drainage.

    CSE (West Regent Street) Ltd.

    Glasgow, Scotland

     VINCI Construction UK Limited

    Hodgins Smith / VINCI

    Commercial / Ofce Development

    West Regent Street

  • 8/19/2019 Carey Group Scotland Projects

    13/15

    Project Overview

    Services

    Project Details

    Client

    Location

    Case Studies

    Sector

    Project

    More Information

    Gallery

    The Aquatics Centre project is the next phase of the Aberdeen Sports Village

    development, and will include a 50m pool, allowing international level swimming events

    to be hosted in Aberdeen. Careys provided a reinforced concrete structure; constructed

    centrally between both the main pool and the diving pool structures. This will house the

    various water treatment processing plant, electrical & drainage services. This structure

    will be fully enclosed at low level and will allow for the construction of the changing

    area and various facilities which will be located on top of the structural suspended slab

    covering the plant room area.

    60 ground bearing pad foundations will be constructed around the extent of the

    construction area. These will support the steel portal frame for the main pool, diving pool

    and aquatic centre envelopes. A ground bearing slab will also be constructed between the

    main pool, dive pool and plant room areas in a crescent shape to all of the facilities in the

    same footprint.

    In addition to the construction Careys will undertake the complete drainage package to

    provide the foul, surface and treated water networks, some of which will be constructed

    at up to 6m in depth in saturated sands and gravels. Included within the drainage

    package will be the construction of a concrete surrounded GRP backwash tank, pumping

    station and 60m3 surface water attenuation tank.

    The pool comprises a 50m long by 25m wide tank to provide ten swimming lanes. To

    comply with current Olympic standards the tolerances between each of the end walls will

    be within +/- 3mm to ensure accurate timing of competitive events. The pool will also

    contain a state-of-the-art oating oor system (situated at the deep end) which will allow

    the pool oor level to be adjusted specically for individual activities.

     Aberdeen, Scotland

    John Graham (Dromore) Ltd

    Hotel, Art & Leisure / Leisure

    Aberdeen Aquatic Centre

  • 8/19/2019 Carey Group Scotland Projects

    14/15

    More Information

    Project Overview

    Gallery

    Services

    Project Details

    Client

    Location

    Principal Contractor

    Engineer / Consultant / PQS

    Case Studies

    Sector

    Project

    Glasgow Harbour is a residential development that has been built in several phases on

    the site of the old grain dock on the North bank of the river Clyde, opposite the Govan

    shipyards.

    Careys was contracted to construct a substructure of pile caps and ground beams and

    a superstructure of 5 stair and lift cores, along with a 3.0m deep basement car park.

    The cores varied in height from 7 up to 14 storeys. The basement retaining walls were

    constructed using traditional plywood on aluminium walers and steel soldiers tied with

    through bolts. Traditional decking was used to build the landings. The stairs were precast

    and installed using the tower cranes. The works involved Careys xing 450 tonne of

    reinforcement and pouring 3500m³ of concrete into 12,000m² of formwork.

    Hodgins Smith

    Dawn Construction Ltd

    Glasgow, Scotland

    Dawn Construction Ltd

    Glasgow Harbour

    Residential & Regeneration /Residential Apartments

  • 8/19/2019 Carey Group Scotland Projects

    15/15

    Milton Keynes

    CAREY GROUP PLC

    Chesney Wold , Bleak HallBuckinghamshire MK6 1NJ

    T 01908 668383

    Bristol

    CAREY GROUP PLC

    2440 The Quadrant, Aztec West

    Bristol BS32 4AQ

    T 01454 877674

    Ireland

    CAREY GROUP PLC

    Carey House

    Dardistown, Cloghran

    Co. Dublin

    T 00353 1 842 7300

    Scotland

    CAREY GROUP PLC

    Carey House

    21 Shairps Business Park 

    Houstoun Road, Livingston

    West Lothian EH54 5FD

    T 01506 444 448

    Headquarters

    CAREY GROUP PLC

    Carey House

    Great Central Way

    Wembley

    Middlesex HA9 0HR 

    T 020 8900 0221

    [email protected] 

    Operating throughout the UK & Ireland, the Carey Group’s Head Ofce is located in Wembleywith further regional ofces in Milton Keynes, Scotland and the Republic of Ireland.

    www.careysplc.co.uk