capital improvement task force update 09.23.2012

35
Capital Improvement Task Force Update 09.23.2012

Upload: anna-bingham

Post on 31-Mar-2015

220 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Capital Improvement Task Force Update 09.23.2012

Capital Improvement Task Force Update

09.23.2012

Page 2: Capital Improvement Task Force Update 09.23.2012

Capital Improvement Task Force

• The Council established the Capital Improvement Task Force (CITF) at the Annual Meeting, held in February 2012.

• The charge of the CITF is to assess deferred maintenance and capital improvement needs of our facility and to prepare recommendations for consideration by the congregation.

Page 3: Capital Improvement Task Force Update 09.23.2012

Teaming With HGA

• At a special congregational meeting in June, the congregation voted to hire the engineering firm of Hammel,Green & Abrahamson (HGA) to help evaluate our issues and develop a long range plan for addressing them.

• Our work with HGA began in early June and is being completed this month.

• We held six meetings over the summer with HGA.

Page 4: Capital Improvement Task Force Update 09.23.2012

Our Goals

• At our first meeting with HGA we established our goal – create a “structurally sound, safe, comfortable and dry facility.”

• We want to meet this goal by being good stewards of our facility and making wise decisions for the future.

Page 5: Capital Improvement Task Force Update 09.23.2012

Our Priorities Defined

• Major issues were ranked in the following order:• Roof / Gutter System• Water Drainage / Building Leaks /

Erosion• Structural (Building Settlement)• Parking Lot• HVAC / Electrical & Plumbing

Page 6: Capital Improvement Task Force Update 09.23.2012

Timeline

June

Hired HGA

July

Discovery & Analysis

August

Range of Options

Sept. 23

Summary Findings

Page 7: Capital Improvement Task Force Update 09.23.2012

Summary FindingsRoof/ Gutter System

Findings • Roofing damaged due to hail and improper repairs over the years

• Gutters damaged due to ice dams• Interior finishes (ceiling and walls) damaged

due to ice dams. • Ice dams are a result of a too warm roof,

which is a result of lack of insulation or ventilation.

Options • Repair and replace damaged slates, flashing and gutters.

• Install roof insulation on 1963 addition.

Status • Request for Proposal (RFP) under review.• Sent to select contractors Sept. 28• Bids Due

Page 8: Capital Improvement Task Force Update 09.23.2012

Summary FindingsWater Drainage / Building Leaks / Erosion

Findings • Storm water from downspouts isn’t directed away from building

• Erosion from too much storm water directed to a specific location (at the stairs, at the north slope, and in the parking lot)

• Waterproofing systems (at the choir room) deteriorated over the years

Options • Repair and replace gutters and downspouts.

• Connect/direct downspouts to retention system (rain gardens)

• Install foundation drainage• Install waterproofing • Combination of rain gardens/ infiltration/ and

storm water management

Status • Concepts are estimated for price

Page 9: Capital Improvement Task Force Update 09.23.2012

Summary FindingsStructural

Findings • Masonry cracking on the exterior walls and plaster cracking on the interior walls of the chapel

• Floor slab settlement in the Colonial Room• Soil borings reveal a layer of clay under the

chapel foundation• Geotechnical consultant concluded that the

structural settlement is due to the clay consolidation, and that the consolidation is complete

Options • Add insulation under window wells to avoid frost expansion

• As insurance against future settlement, add structural stabilization for foundations

Status • Soil boring and geotechnical evaluation is completed

• Options for additional stabilization are estimated for price

Page 10: Capital Improvement Task Force Update 09.23.2012

Summary FindingsParking Lot

Findings • Sinkholes have developed due to amount and velocity of storm water running over the parking surface

• Soil settlement results in uneven parking surface

• Multiple entrances and exits creates a confusing parking circulation pattern

Options • Revised parking layout to provide streamlined vehicle circulation, mitigate run-off, and allow for improved and inviting landscaping.

Status • Revised parking lot concept is estimated for price

Page 11: Capital Improvement Task Force Update 09.23.2012

Summary FindingsHVAC and Electrical Systems

Findings • The heating systems consists of steam boilers that are past expected life but are in good shape and are not in danger of failing

• Ventilation system in sanctuary is undersized per current standards and noisy

• The original electrical service should be replaced due to age, although there is no imminent need of replacement

Options • Replace the steam boilers with higher efficiency hot water boilers

• Modify return air path to quiet the sanctuary ventilation system

• Replace the 400 amp electrical service and panel boards serving the 1950 and 1960’s addition.

Status • Replacement cost estimates have been priced.

Page 12: Capital Improvement Task Force Update 09.23.2012

Existing Roof / Gutter Issues

Damaged GuttersDamaged Dormers and Flashing

Damaged/Missing Tiles

Page 13: Capital Improvement Task Force Update 09.23.2012

Roof / Gutter Improvements

Roof Repairs Insulate Roof

Repair damaged areas

Install insulation & replace roof

Page 14: Capital Improvement Task Force Update 09.23.2012

Existing Drainage / Leaks / Erosion –Issues

Damaged SiteWet BuildingPoor Downspout Function

Page 15: Capital Improvement Task Force Update 09.23.2012

Existing Drainage / Leaks / Erosion –Issues

Downspout Locations

Page 16: Capital Improvement Task Force Update 09.23.2012

Drainage / Leaks / Erosion –Improvements

At Grade Discharge: slope away from building

Below Grade Collection: gather and route

Downspout Solutions

Page 17: Capital Improvement Task Force Update 09.23.2012

Drainage / Leaks / Erosion –Improvements

Foundation Drainage

Rain Garden

Waterproof Choir Room

Gather Downspouts and direct to Raingarden

Downspout & Drainage System

Page 18: Capital Improvement Task Force Update 09.23.2012

Landscape at the Choir Room

Page 19: Capital Improvement Task Force Update 09.23.2012

Rain GardenWaterproofed Choir Room

Foundation Drainage

Accessible Patio(pedestal pavers)

Ornamental Plantings

Downspout and Drainage System

Page 20: Capital Improvement Task Force Update 09.23.2012

Patio above Choir Room

Page 21: Capital Improvement Task Force Update 09.23.2012

Memorial Garden Option

Page 22: Capital Improvement Task Force Update 09.23.2012

Interior CracksChapel Settlement – Exterior Cracks

Existing Structural Issues

Page 23: Capital Improvement Task Force Update 09.23.2012

Soil Borings

Results- Did discover a clay layer under the chapel, didn’t discover a high water table, did discover sandy soil under parking lot

Page 24: Capital Improvement Task Force Update 09.23.2012

Survey Elevations at Colonial Room

0.01’

-0.18’

-0.08’

Page 25: Capital Improvement Task Force Update 09.23.2012

Structural Improvements

Page 26: Capital Improvement Task Force Update 09.23.2012

Parking Lot

Page 27: Capital Improvement Task Force Update 09.23.2012

Parking and LandscapingConcept Site Plan

Page 28: Capital Improvement Task Force Update 09.23.2012

Parking and Landscaping Improvements

Rain Gardens

Improved Parking Lot TreesPlay Areas

Page 29: Capital Improvement Task Force Update 09.23.2012

Storm Water Management

Infiltrate and retain as much as possible, slowly discharge the rest

Rain garden

Underground storm piping

Storm water detentionCistern

Page 30: Capital Improvement Task Force Update 09.23.2012

Storm Water Management

Page 31: Capital Improvement Task Force Update 09.23.2012

Mechanical and Electrical Existing Issues

Old, but still in workable condition

Page 32: Capital Improvement Task Force Update 09.23.2012

Preliminary Cost EstimatesGloria Dei Lutheran Church

Building Repair Cost Study Date: 23-Sep-12

Low Mid High

1. Existing Roof Repair / Replacement $286,000 - $313,500 - $360,800

2. Foundation Drainage / Waterproofing $429,000 - $473,000 - $544,500

3. Colonial Room Slab on Grade Replacement $18,700 - $20,900 - $24,200

4. Chapel Foundation Stabilization - Helical Anchors $75,900 - $83,600 - $96,800

5. Surface Parking $770,000 - $847,000 - $973,500

6. Landscaping $275,000 - $302,500 - $347,600

7. Boiler Replacement - $220,000 -

8. Electrical service and Panelboard Replacement - ? -

Page 33: Capital Improvement Task Force Update 09.23.2012

Preliminary Cost EstimatesGloria Dei Lutheran Church

Building Repair Cost Study Date: 23-Sep-12

Alternate Adds

1A. Replace roofing at 1950 / 1963 bldgs. and repair roof at 2002 bldg. $859,1002A. Foundation Drainage / Waterprooofing rest of bldgs. excluding the Courtyard. $903,1002B. New entry at Mold Room. $80,3002C. Memorial Garden Master Plan $129,8003A. Colonial room slab on grade; replace entire slab. $9,0204A. Chapel foundation stabilization; segmental underpinning. $49,5007A. Add 20 tons of geothermal while parking is redone $220,000

Cost Estimates based on HGA’s concept documents

Page 34: Capital Improvement Task Force Update 09.23.2012

Next Steps - Project 1: Roof and Gutter Repairs

• Wednesday, September 26, 6:30 p.m. Informational meeting in the Gathering Space

• September 28: Send out RFPs• October 18,19: Interview contractors• November 4: Congregation votes on

recommended plan and contractor

Page 35: Capital Improvement Task Force Update 09.23.2012

Long Range Plan- Project 2: Waterproofing and Stabilization

• January 20th, Adult Education: Long range plan presentation and Project #2 Informational Meeting regarding Waterproofing and Stabilization

• Spring Building Improvement Campaign