capacity building of banks and financial institutions for energy efficiency project financing

35
Page 1 July 2014 Page 1 July 2014 Capacity Building of Banks/FIs For EE Project Financing Capacity Building of Banks and Financial Institutions for Energy Efficiency Project Financing Module 2 Energy Efficiency Project Characteristics Partnership to Advance Clean Energy-Deployment (PACE-D) Technical Assistance Program September 2014

Upload: axel-meadows

Post on 03-Jan-2016

45 views

Category:

Documents


2 download

DESCRIPTION

Capacity Building of Banks and Financial Institutions for Energy Efficiency Project Financing Module 2 Energy Efficiency Project Characteristics Partnership to Advance Clean Energy-Deployment (PACE-D) Technical Assistance Program. Presentation Outline. Energy Efficiency Projects - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Capacity Building of Banks and Financial Institutions for Energy Efficiency Project Financing

Page 1 July 2014 Page 1 July 2014Capacity Building of Banks/FIs For EE Project Financing

Capacity Building of Banks and Financial Institutionsfor Energy Efficiency Project Financing

Module 2 Energy Efficiency Project Characteristics

Partnership to Advance Clean Energy-Deployment (PACE-D)Technical Assistance Program

September 2014

Page 2: Capacity Building of Banks and Financial Institutions for Energy Efficiency Project Financing

Page 2 July 2014 Page 2 July 2014Capacity Building of Banks/FIs For EE Project Financing

• Energy Efficiency Projects

• Energy User Motivations

• EE Projects in Different Sectors

• EE Project Characteristics

• Typical Energy Efficiency Project

• Illustrative Project Examples

Presentation Outline

Page 3: Capacity Building of Banks and Financial Institutions for Energy Efficiency Project Financing

Page 3 July 2014 Page 3 July 2014Capacity Building of Banks/FIs For EE Project Financing

• In all major consuming sectors Large Industries

SMEs

Commercial Buildings (offices, hotels, hospitals, shopping malls, etc.)

Government Buildings

Municipalities (street lighting, water pumping)

Agriculture

Energy Efficiency Projects

Page 4: Capacity Building of Banks and Financial Institutions for Energy Efficiency Project Financing

Page 4 July 2014 Page 4 July 2014Capacity Building of Banks/FIs For EE Project Financing

• Achieve efficiency • Capture energy cost savings; • Improve productivity and enterprise competitiveness• Improve product quality • Address necessary system upgrades, equipment replacement, &

deferred maintenance requirements• Improve level of energy services in facilities• Improve living conditions • Improve energy system reliability• Comply with environmental regulations

Energy User Motivations

4

Page 5: Capacity Building of Banks and Financial Institutions for Energy Efficiency Project Financing

Page 5 July 2014 Page 5 July 2014Capacity Building of Banks/FIs For EE Project Financing

• Specific Energy Consumption (SEC) reduction targets for the energy-intensive units which are designated consumers under the Energy Conservation Act Targets would be % reduction of current SEC Percentage reduction requirement based on:

Sectoral targets to achieve the national goal Current SEC as a ratio of the best in the sector / groups within a sector Unit specific diversities

Target setting for the power generation and fertilizer sectors through the existing tariff-setting processes

SEC measurement and verification by BEE through designated verifiers

Perform, Achieve and Trade Scheme

Ramasamy, Sujata
5th slide in old presentation is list of major industries here pat. PAT not there in old slidelist of industries for pat in next slide presented.
Page 6: Capacity Building of Banks and Financial Institutions for Energy Efficiency Project Financing

Page 6 July 2014

• Cement

• Chlor alkali

• Aluminum

• Pulp & paper

• Textile

• Power Plants

• Iron & steel

• Fertilizer

List of sectors for PAT

Capacity Building of Banks/FIs For EE Project Financing

Page 7: Capacity Building of Banks and Financial Institutions for Energy Efficiency Project Financing

Page 7 July 2014 Page 7 July 2014Capacity Building of Banks/FIs For EE Project Financing

• Replacement of inefficient industrial technologies with energy saving technologies and equipment, such as more efficient industrial boilers, kilns, and heat exchange systems

• Recovery and utilization of by-product gas, waste heat

• Installation of highly efficient mechanical and electrical equipment, including lighting, motors, Chillers, refrigeration units, pumps, heating and ventilation equipment, etc.

• Industrial system optimization to reduce energy use

Energy Efficiency Projects in Industry

Page 8: Capacity Building of Banks and Financial Institutions for Energy Efficiency Project Financing

Page 8 July 2014 Page 8 July 2014Capacity Building of Banks/FIs For EE Project Financing

• Improve kiln combustion efficiency by reducing the false air ingress at the Preheater section and reducing marginally the sintering level of Clinker

• Optimize the air flow to the grate cooler and reduce the vent air losses

• Utilize cooler vent air as primary air to the Kiln burner

• Improve insulation at preheaters ducts & Kiln internally

• Replace the air cooled Turbulators with Refractory lined Turbulators

• Generate electricity from the Waste heat of PH exhaust & Cooler Vent streams

• Install variable frequency drive for fans in the production processes

Examples of EE in Cement Industry

Ramasamy, Sujata
EE in glass industry given in old slide
Page 9: Capacity Building of Banks and Financial Institutions for Energy Efficiency Project Financing

Page 9 July 2014 Page 9 July 2014Capacity Building of Banks/FIs For EE Project Financing

• Key Characteristics of SMEs Very small in size (majority are MSE units) Majority of units are proprietorship / family owned concern Very limited professional management Obsolete technology/ production process Low capital investment & labor intensive High energy consumption in many sectors Lack of Knowledge about energy efficient production options and

available technologies

EE in SMEs

Page 10: Capacity Building of Banks and Financial Institutions for Energy Efficiency Project Financing

Page 10 July 2014

• Forging

• Limekilns

• Rolling

• Pottery

• Edible oils

• Glass

• Foundry

• Brick

• Rice

• Paper

• Brass

Energy Intensive SME Clusters

Page 11: Capacity Building of Banks and Financial Institutions for Energy Efficiency Project Financing

Page 11 July 2014 Page 11 July 2014Capacity Building of Banks/FIs For EE Project Financing

• Established Energy Efficiency Cell

• Developed guidelines for EE project financing

• JICA credit line for EE equipment – disbursed in 2010

• AfD credit line – initiated in 2010

• KfW credit line – requires carbon savings estimates and monitoring – initiated in 2010

• Developing tools for Project Assessment

Impact Monitoring

SIDBI Activities for EE in SMEs

Page 12: Capacity Building of Banks and Financial Institutions for Energy Efficiency Project Financing

Page 12 July 2014 Page 12 July 2014Capacity Building of Banks/FIs For EE Project Financing

• Energy efficiency in residential, commercial, and government buildings:

Lighting

HVAC (heating, ventilation, and air conditioning)

Building envelope (insulation for roof, walls, windows, doors)

Renewable energy in buildings (roof-top solar PV, solar water

heaters, and ground source heat pumps)

Energy Efficiency in Buildings

Ramasamy, Sujata
12 th slide extra ee in buildings
Page 13: Capacity Building of Banks and Financial Institutions for Energy Efficiency Project Financing

Page 13 July 2014 Page 13 July 2014Capacity Building of Banks/FIs For EE Project Financing

• Energy Conservation Building Code (ECBC) launched in May 2007.

The ECBC sets minimum energy standards for new commercial buildings having a connected load of 100 kW or contract demand of 120 kVA.

• BEE Star Labeling Scheme for Day Use Buildings BPO buildings Shopping malls

Buildings Rating Systems

Ramasamy, Sujata
13th slide is extra here bilding ratings
Page 14: Capacity Building of Banks and Financial Institutions for Energy Efficiency Project Financing

Page 14 July 2014 Page 14 July 2014Capacity Building of Banks/FIs For EE Project Financing

• Water Pumping Leak detection Efficient pumping systems Operational optimization

• Street Lighting Efficient lighting Controls Solar systems

EE in Municipalities

Page 15: Capacity Building of Banks and Financial Institutions for Energy Efficiency Project Financing

Page 15 July 2014 Page 15 July 2014Capacity Building of Banks/FIs For EE Project Financing

• Stations, platforms Lighting Space cooling Water pumping

• Rolling stock performance Two tier rolling stock Four berth coaches Managing fuel cost Kinetic energy storage systems Power and energy optimization systems

EE in Railways

Ramasamy, Sujata
EE in railways extra
Page 16: Capacity Building of Banks and Financial Institutions for Energy Efficiency Project Financing

Characteristics of EE Projects

Page 17: Capacity Building of Banks and Financial Institutions for Energy Efficiency Project Financing

Page 17 July 2014 Page 17 July 2014Capacity Building of Banks/FIs For EE Project Financing

• Wide range of technologies, most with substantial experience in successful implementation, internationally as well as in India

• Relatively small project size - many projects less than INR 1 crore

• Relatively short simple payback periods – generally one to five years

• High proportion of project development costs

• Range of implementation business models with increasing interest in performance based approaches

• Manageable risks

Characteristics of EE projects

Page 18: Capacity Building of Banks and Financial Institutions for Energy Efficiency Project Financing

Page 18 July 2014 Page 18 July 2014Capacity Building of Banks/FIs For EE Project Financing

IFC Experience with Project Size

Project Size DistributionNo. of Projects = 818

95% of projects were under INR 4.5 crores

Source: International Finance Corporation

Page 19: Capacity Building of Banks and Financial Institutions for Energy Efficiency Project Financing

Typical Energy Efficiency Project

Page 20: Capacity Building of Banks and Financial Institutions for Energy Efficiency Project Financing

Page 20 July 2014 Page 20 July 2014Capacity Building of Banks/FIs For EE Project Financing

EER provides approximate scopeof savings and cost potential and is used to screen potential projects

ERR begins process of establishingESCO credibility

Is Credit check

good??

Is Credit check

good??

Conduct Facility Walk-Through

Conduct Facility Walk-Through

Prepare Energy Efficiency Report

Prepare Energy Efficiency Report

Doesenergy savings

justify project??

Doesenergy savings

justify project??

Select NewClient

Select NewClient

Initial Meetingwith Client

Initial Meetingwith Client

No

Yes

Present EERto Prospect

Present EERto Prospect

Review Energy Usage Data

Review Energy Usage Data

ESCO capabilities explained;expectations outlined; approvalto proceed obtained

Use CustomerData Form

Collect energy useand cost (2-3 yrs); analyzefor anomalies

NoCredit analysis is completedby the bank providing the long-term financing

This meeting is predicated ongood client research

Typical Energy Efficiency Project

Ramasamy, Sujata
Ramasamy, Sujata
20th slide is coloured in present slide
Page 21: Capacity Building of Banks and Financial Institutions for Energy Efficiency Project Financing

Page 21 July 2014 Page 21 July 2014Capacity Building of Banks/FIs For EE Project Financing

No

DES Confirms

Preliminary Energy

Savings

DES Confirms

Preliminary Energy

Savings

No

Yes

Owner agrees to haveESCO complete a DetailedEnergy Study (DES)

Detailed Energy Study (DES)

Completed

Detailed Energy Study (DES)

Completed

Clientsigns the

LOI??

Clientsigns the

LOI??

Yes

Present DES to Customer

Present DES to Customer

DES reinforces ESCO credibility

Review ResultsIncluding ProjectScope and Plan

Review ResultsIncluding ProjectScope and Plan

Select New Facility or Client

Select New Facility or Client

Select new Facility or Client

Select new Facility or Client

Review builds motivationto undertake energy servicesproject

If DES results depart significantlyfrom EER, ESCO absorbs part or allof DES costs

ESCO develops a Letterof Intent (LOI) andpresents it to the clientfor signature

A DES takes four to eight weeksto complete; provides opportunityto get to know client staff

Typical Energy Efficiency Project

Page 22: Capacity Building of Banks and Financial Institutions for Energy Efficiency Project Financing

PACE-D Finance Team Presentation Page 22 April 29, 2013

Customer AcceptsResults

Customer AcceptsResults

No

Yes

Client pays for 100% of DES

Client pays for 100% of DES

Draft Energy Services Agreement

(ESA) is developed

Draft Energy Services Agreement

(ESA) is developed

Client and ESCO

Sign ESA

Client and ESCO

Sign ESA

No

ProjectImplementation

Yes

Final mix of measures selected;Financial modeling used to helpprice the ESA and optimize profitand cash flow for selected measures

Typical Energy Efficiency Project

Page 23: Capacity Building of Banks and Financial Institutions for Energy Efficiency Project Financing

Illustrative Project Examples

Page 24: Capacity Building of Banks and Financial Institutions for Energy Efficiency Project Financing

Page 24 July 2014 Page 24 July 2014Capacity Building of Banks/FIs For EE Project Financing

• Major industrial unit manufacturing copper

• Copper smelting exothermic process

• Hot flue gases with high heat content being wasted

• Waste heat recovery system installed

• Power generation ~ 10.4 MW

• Payback <1 year Total generation : 82.8 million units Cost of generation : Rs 1.10 per unit Cost of Grid Power : Rs 4.30 per unit Annual Savings : Rs 265 million

• Reduction of CO2emission: 47,500 tons/year

Industrial Waste Heat Recovery

Page 25: Capacity Building of Banks and Financial Institutions for Energy Efficiency Project Financing

Page 25 July 2014 Page 25 July 2014Capacity Building of Banks/FIs For EE Project Financing

• Edible oil refinery in Maharashtra

• Steam required for processes

• Co-generation (top end) using biomass (bagasse)

• Generation of power 550 KW

• Loan amount: Rs 20 million

• Annual savings: Rs 16 million

• Reduction of CO2emission: 4,350 tpa

Biomass Cogeneration

Page 26: Capacity Building of Banks and Financial Institutions for Energy Efficiency Project Financing

Page 26 July 2014 Page 26 July 2014Capacity Building of Banks/FIs For EE Project Financing

EE Project – SME

Page 27: Capacity Building of Banks and Financial Institutions for Energy Efficiency Project Financing

Page 27 July 2014 Page 27 July 2014Capacity Building of Banks/FIs For EE Project Financing

• Project: Reduction in contract demand and savings through upgrades to the building’s reactive power controllers, lighting, air conditioning, raw water pumping and switching electric loads in geysers to solar water heating

EE Project – Major Health Center

Annual Energy Bill INR 182 million

Investment Cost – Equipment INR 85 million

Project Dev. Cost INR 32 million

Total Project Cost INR 117 million

Energy Cost Savings INR 40 million

Simple Payback ~ 3 years

Page 28: Capacity Building of Banks and Financial Institutions for Energy Efficiency Project Financing

Page 28 July 2014 Page 28 July 2014Capacity Building of Banks/FIs For EE Project Financing

• Installation by ESCO of 486 street light controllers covering 19,000 street lights of Nasik Municipal corporation

• Improvement in the existing electrical distribution network for : Reduction in cable losses Power factor optimization

• Savings were shared for five years

• Annual Energy bill prior to implementation - Rs 50.0 M

• Achieved annual savings - Rs 17.0 million on a capital investment of Rs 16.6 million

• Payback period ~1.5 years

Streetlighting Project

Page 29: Capacity Building of Banks and Financial Institutions for Energy Efficiency Project Financing

Page 29 July 2014 Page 29 July 2014Capacity Building of Banks/FIs For EE Project Financing

Energy Service Companies (ESCOs)• Initiated in mid-1990s

• Growth has been slow

• Many issues and challenges faced

• BEE has empanelment scheme

• Over 137 ESCOs have been empanelled

• ESCO capacity building program planned

Energy Services Market in India

Page 30: Capacity Building of Banks and Financial Institutions for Energy Efficiency Project Financing

Page 30 July 2014 Page 30 July 2014Capacity Building of Banks/FIs For EE Project Financing

Energy Service Companies:• Provide or arrange a complete package of services, including energy

analysis, design, installation, financing, and maintenance of the energy management (and other) technologies

• Offer business and financing models under which customers effectively pay for the energy services from a portion of actual energy savings achieved

• Payments to the ESCO are based on demonstrable results (that satisfy the performance guarantees provided by the ESCO)

• Most of the project risks are assumed by the ESCO.

Key Characteristics of ESCOs

Ramasamy, Sujata
energy service market in india is extra here this is esco in new one
Page 31: Capacity Building of Banks and Financial Institutions for Energy Efficiency Project Financing

Page 31 July 2014 Page 31 July 2014Capacity Building of Banks/FIs For EE Project Financing

Other energy service providers• Energy auditors – certified by BEE• Equipment manufacturers and vendors (Schneider, Siemens, Alstohm,

etc.)• Engineering firms – extending capabilities to provide performance

contracting services• Contract energy management companies (Dalkia, A to Z Power, etc.)

Energy Services Market in India

Page 32: Capacity Building of Banks and Financial Institutions for Energy Efficiency Project Financing

Page 32 July 2014 Page 32 July 2014Capacity Building of Banks/FIs For EE Project Financing

Energy Services Business Models

Guaranteed Savings

Guaranteed Savings

Shared SavingsShared Savings

OutsourcedEnergy

Management

OutsourcedEnergy

Management

Energy ServicesBusiness Models

Deemed EnergySavings

Deemed EnergySavings

Ramasamy, Sujata
from 32 to 35 extra from old slides
Page 33: Capacity Building of Banks and Financial Institutions for Energy Efficiency Project Financing

Page 33 July 2014 Page 33 July 2014Capacity Building of Banks/FIs For EE Project Financing

Example of Customer Benefit – Hotel Guaranteed Savings

Page 34: Capacity Building of Banks and Financial Institutions for Energy Efficiency Project Financing

Page 34 July 2014 Page 34 July 2014Capacity Building of Banks/FIs For EE Project Financing

• Based on target market and project characteristics and implementation business models credit characteristics typical deal size & project economics (cash flow, ROI, NPV, etc.) Ability to assemble acceptable collateral/security package

• Define loan offer(s) term, pricing required security structure, with guarantee(s) economic parameters: e.g., size, % own funds documentation requirements

• Prepare business plan, identify/implement initial deals, train branch staff network

Developing Financial Products for EE Projects

Page 35: Capacity Building of Banks and Financial Institutions for Energy Efficiency Project Financing

Thank you

Dilip R. LimayeFinance Team Leader

USAID PACE-D Technical Assistance Program

[email protected]