camput 2015 energy regulation course transmission issues m. dale mcmaster evp, transmission and...
TRANSCRIPT
CAMPUT2015 Energy Regulation CourseTransmission Issues
M. Dale McMasterEVP, Transmission and Distribution Services
Donald Gordon Conference Centre Queen’s University, Kingston, Ontario
June 24, 2014
2
Transmission is difficult
It can be bigIt can be expensiveIt is viewed as intrusiveIt can be viewed by some as a health threatIt can have an environmental impactIt doesn’t produce energy -- it just delivers itIt is complex and difficult to understandBottom-line – it’s controversial
…..and it is in need of reinforcement/rebuilding across Canada
3
Overview
New TransmissionDrivers of “need”Regulatory approval processRights of WayConsultationCost Prudency
Utility financial performancePerformance Based (Incentive) Regulation
Merchant TransmissionCompetition for Transmission
Project Process
Fundamental process:Identify that something “needs” to be builtDetermine what the best solution is to meet that “need”
Technically bestEconomically bestAcceptable to society
Engineer/design how to best to implement the best solutionAchieve regulatory approvalBuild it
The challenges along the way include:Convincing the public, rate payer and regulator of the needLandownersSpecial interest groupsPolitical challenges
4
5
What drives the “need” for new transmission?
Customer needsCentrally planned (backbone) system needsCompetitive market needsSystem performance: reliability and efficiency
NERC Reliability Standards (or facsimile)
6
Customer Needs
Typically driven by local load growthLoad growth on the distribution system
Focuses on substation reinforcement/capacity increases
Service to customers at transmission system voltage Can involve new transmission lines
Substations can be controversial – even existing substationsConstruction noise – disruptions to residentsOperating noise (60 Hz hum)Not a thing a beauty
Transmission linesTend to be shorter and in areas that are less contentious
7
System Needs: Centrally Planned Jurisdictions
The “least cost” PlanTransmission and generation planning are coordinatedThe combined cost of generation and transmission are “optimized”
These plans have historically been driven by generationLocated close to the energy source and/or source of cooling (thermal)Need transmission to reliably and economically deliver generator output
Timing is driven by system load growth and performance needsGeneration can be used to solve a transmission system problemThe challenge for the Regulator is to ensure the correct integrated option(s) is selected, the timing is correct, the costs are appropriate and “in the public interest”
8
Market Needs: Competitive Energy Market Jurisdictions
There is no centralized planning for generation but……generation and transmission development still need to be coordinated Several big questions:
Which comes first generation or transmission?How do you deal with the uncertainty of investment in generation?
A complex problem in that it takes much longer to build transmission than it does to build generationIn Alberta legislation directs transmission to be built in advance of generation
Build transmission to the fuel source because that’s where the generating station will beWorks for coal and hydro, and to a certain extent for windStill faced with the question of how much transmission and when
9
Market Needs: Competitive Market Jurisdictions (2)
The cost and locational flexibility of gas fired generation has introduced some added complexity
Generation can be built closer to load centresIt is easier to move the fuel via pipeline than it is to build transmission linesAdvanced technologies in combined cycle and/or cogeneration make it more competitiveCooling water needs are less demanding
Decentralizing generation development may result in reduced investment in transmission
Dependent on the location/size of the generating station and the strength of the transmission system
Locational signals can be used to encourage generation to locate strategicallylocational market prices and/or loss factorshaving generation contribute to the cost of building transmission
This can be driven by government policy or it may be left to the Regulator to decide or some combination thereof
10
System Reliability and Performance
Notwithstanding the preceding drivers, the transmission system must be reliable and efficientTo ensure reliability and efficiency additional investment in new transmission may be necessaryHow much is enough when it comes to transmission?
How do you measure reliability and efficiency?
NERC Reliability standards or a derivative thereof sets the minimum level of reliability
All jurisdictions in Canada have adopted some form of compliance with these standards
MeasurandsActual system performanceExtensive technical studies required to prove compliance
Efficiency – typically determined by technical losses (I2R losses)Cost benefit analysis to evaluate need for new investment
11
Transmission Project Approvals
Projects fundamentally need two approvals Approval of the need and the recommended option to meet the needApproval of the proposed facilities (including the line routing) of the option to be implemented
The “need” application demonstrates the need to reinforce the systemUsually identifies several options that will meet the needIdentifies one of those options as a preferred optionFundamentally defines “what” needs to be done/built
The application will include Extensive technical analysis in the form of system studies Financial and economic analysisEnvironmental analysisPreliminary line routing and cost estimates -- If done separately from a facility application Details of the public consultation undertaken
12
Facility Application
The “need” application defines the “what”The facility application defines the “how”Detailed design/engineering of the facilities, including
Tower designsSubstation layoutsTechnical specifications
Line routingTypically several options are identifiedOne of the options is recommended as preferredDetailed line routing on the preferred option
Details of the public consultation carried outMany challenges but two of the biggest are:
Right of WayCost control/prudency
13
Right of Way
Land owner rights and compensationObjective -- settle as many issues and access agreements as possible Land owner interface – transparency, trust, historical relationship, consultationCompensation
Public concerns/objectionsPreviously reserved utility corridor vs. “my green space”Health issues – emf, schools, health facilities, etc.
Environmental GroupsFirst Nations
Access to First Nation landTraditional use of the land
14
Public Consultation
Regulator sets the rules for consultation Objective – to address/resolve as many of the issues that can be dealt with before a hearing – ultimate objective is no interventionsWho has to be consulted?
All persons whose rights may be directly and adversely affected by the proposed developmentUrban – all occupants, residents and landowners within the first row of houses facing the developmentRural – all occupants, residents and landowners within 800 meters of the proposed right of wayApplicant needs to decide if more than the minimum need to be consulted
How is the public to be consulted?Information packagesOpen housesRespond to questions and concernsDiscuss options, alternatives and mitigating measures
15
Public Consultation (2)
What are the challenges/issues?Increasing number of parties that feel their rights are directly and adversely affected by the proposed developmentIncreasing sophistication/organization of affected partiesIncreasing expectations of affected parties/the public at largeDifficulties in tracking down landownersScheduling of open housesNotifications of open houses
16
Cost Prudency
Project costs are evaluated during the Facility Application; however, there is considerable cost risk during construction
Material and labour escalationUnexpected challenges and the associated change orders
Project Costs are reviewed for prudency by the Regulator at completion of the projectSome stakeholders claim this is too late and that only rarely are costs denied
They want greater cost transparency and a role in cost control as the project progresses – difficult to achieve
In Alberta at the direction of the Government, a stakeholder Transmission Cost Review Committee has been established
Given greater access to project costs during constructionAbility to meet with the transmission developerNo authority
17
Regulatory Framework
Provincial RegulatorsGenerally stated transmission and distribution development falls under the purview of provincial regulatorsIncluding but not limited to approvals for new transmission and tariffs
National Energy BoardRarely get involved in transmission approvals unless they involve international borders – in particular if there is a merchant transmission developmentNEB approvals are required for the export of energy; hence, they are particularly interested in merchant transmission linesIf they do get involved they tend to focus on socio economic impacts, economic justification, financial viability, environment, heritage issues, engineering and line routing issues
18
Other Challenges
Utility financial performanceGeneric Cost of Capital/Return on EquityDebt/Equity for new investmentPerformance Based Regulation
Rate Impacts of transmission buildMerchant TransmissionCompetition versus service territory Government policy
19
Utility Financial Performance/Performance Based Regulation
Cost of Service RegulationOperating cost flow through – return on equity portion - no real incentive for efficiencyPerceived sandbagging of the cost of serviceToo frequent hearingsGeneric Cost of Capital (permitted return on Equity)Equity limitations
Performance Based Regulation“Going-in” ratesThere is an incentive for operational efficiency
Increased emphasis on safetyGrowing footprint
Earnings sharing – in AB this has been eliminated – a good thing Regulatory burden has not been reduced – has increasedCapital investment over the PBR period – “capital tracker”Volatility of transmission investment difficult to accommodateRisk/reward balance still to be found
20
Merchant Transmission
A new issue – currently only 1 in CanadaMontana – Alberta Transmission Line (MATL) – now operational
Issues/Challenges“need” issues are for the most part mute as the construction cost will be paid for by the developers and/or users of the line unless there is a significant impact on the system that requires new transmission investment“facility” issues remain including but not limited to:
EnvironmentalLandowner rights and Public Interest issuesInterconnection to and impact on the gridImport/export licenses for an international transmission lineFinancial viability of the project
“market” issues can be significant and may have to be addressed by the Regulator(s)
21
Transmission Competition
Most jurisdictions assign the right to build new transmission based on service territoryCompetition for new development
Tried and abandoned in Alberta in the early 2000sRe-initiated in 2011/12 in response to stakeholder concerns regarding the cost of very large investment in new transmission infrastructure
500-kV transmission between Edmonton and Fort McMurray
AESO charged with developing the competitive process (rules for competition)AUC charged with reviewing and approving the competitive processComplexity is significant
Risk/reward balanceBarriers to new entrants
That said, there was considerable interest from Alberta and international companies
22
Competitive Process:
Edmonton – Ft. McMurrayThe first of two 500 kV ac transmission lines and associated substations$1.8 billion (2013$) project – preliminary estimate
AESO filed the Competitive Process with the AUC – September 2011AUC approved the Competitive Process – May 2013AESO issued Request for Expressions of Interest – May 2013
20 companies/consortiums expressed interest5 were shortlisted by the AESO – 2 ultimately withdrew3 of the 4 incumbent transmission companies participated as part of a consortium
Competitors submitted proposals based on capital costs, O&M costs and project financing
23
Competitive Process (2):
AESO evaluated the proposals and declared the winner – December 2014
Evaluation based on technical, financial and environmental criteria
Contract execution is underwayATCO/Valard Consortium will file a Facility Application with AUC
Targeted filing by year-end 2015Targeted decision year-end 2016
Pending P&L approval there will be a debt funding competitionProjected in-service 2020After 35 years the transmission line will be turned over to a Transmission Facility Owner – to be determined
24
Emerging Issues
The need for infrastructure development – a massive build is ongoing and there is more to come
Expected to drive significant increases in rates
Move to “off the grid”We tend to think of this a distribution problem but the distribution customer also pays for the transmission system so if the distribution system is losing customers do is the transmission systemCo-generation development to avoid transmission costs
Energy EfficiencyFinancial implications for wire ownersRate design is very important
25
Summary
Transmission is difficult and controversial Transmission regulation is complex and evolvingThere are significant challenges for
transmission owners, system planners,consumers,landowners, the public, and Regulators!