Cabazon Elementary School Construction ScheduleActivity Description MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL
Off-Site Utilities & Street Work
On-Site Rough & Finish Grading
Building A, Classrooms
Building B, Administive Offices & Cafateria
Building C, Library
Relocatable Classrooms & Restroom Buildings
Parking Lot Lighting, Pavement & Signage
Landscape & Irrigation Work
SUB-TOTAL BASED ON ORIGINAL CONTRACT 243 DAYS
TIME EXTENTION DUE TO CHANGES IN SCOPE OF WORK 109 DAYS
TOTAL DURATION 352 DAYS
2000 2001