CITY OF RAINER RAILROAD CROSSING’S

Upload: beverley-powell

Post on 18-Jan-2018

223 views

Category:

Documents


0 download

DESCRIPTION

Presentation Outline Introduction Existing Conditions Future Conditions Intersection Alternative design Conclusion

TRANSCRIPT

Page 1: C ITY OF R AINER R AILROAD C ROSSING ’ S. Project # 2 Group Matthew DeGeorge Josh Crain Robert Acevedo Chris Penka Jim Harvey Heather Wenstrand

CITY OF RAINER

RAILROAD CROSSING’S

Page 2: C ITY OF R AINER R AILROAD C ROSSING ’ S. Project # 2 Group Matthew DeGeorge Josh Crain Robert Acevedo Chris Penka Jim Harvey Heather Wenstrand

Project # 2 Group

• Matthew DeGeorge• Josh Crain• Robert Acevedo • Chris Penka • Jim Harvey • Heather Wenstrand 

Page 3: C ITY OF R AINER R AILROAD C ROSSING ’ S. Project # 2 Group Matthew DeGeorge Josh Crain Robert Acevedo Chris Penka Jim Harvey Heather Wenstrand

Presentation Outline

• Introduction• Existing Conditions• Future Conditions• Intersection Alternative design• Conclusion

Page 4: C ITY OF R AINER R AILROAD C ROSSING ’ S. Project # 2 Group Matthew DeGeorge Josh Crain Robert Acevedo Chris Penka Jim Harvey Heather Wenstrand

ScopeTo design safe railroad crossings that maximizesthe movement of people and goods

Design safe pedistrian crossing across the railroadtracks

To design effective intersection closures thatminimizes the impact on traffic and thecommunity

Page 5: C ITY OF R AINER R AILROAD C ROSSING ’ S. Project # 2 Group Matthew DeGeorge Josh Crain Robert Acevedo Chris Penka Jim Harvey Heather Wenstrand

BackgroundThe City of Rainier is on the south bank of the Columbia River across from Longview Wa.

Our project is part of The Rainier Waterfront Urban Renewal Plan

The closing of the Trojan plant set off a decline in the number ofbusinesses in the city. Currently the population is around 2000 people

Page 6: C ITY OF R AINER R AILROAD C ROSSING ’ S. Project # 2 Group Matthew DeGeorge Josh Crain Robert Acevedo Chris Penka Jim Harvey Heather Wenstrand

Our Project

No dedicated engineering staff. Our contactfor this project is Lars Gare – CityAdministrator

Our project will consist of closing 4 railroadcrossings and 3 closures

Page 7: C ITY OF R AINER R AILROAD C ROSSING ’ S. Project # 2 Group Matthew DeGeorge Josh Crain Robert Acevedo Chris Penka Jim Harvey Heather Wenstrand

Existing Conditions

Page 8: C ITY OF R AINER R AILROAD C ROSSING ’ S. Project # 2 Group Matthew DeGeorge Josh Crain Robert Acevedo Chris Penka Jim Harvey Heather Wenstrand

Future Conditions• Railroad’s Plans-

– The “A” Street Streetscape and Railroad Safety Project, is a commercial street reconstruction project aimed at improving rail functionality and providing safety to the surrounding community.

• Street Improvements include;– Separation of heavy rail from other street

network users. Rail curbs, crossing closures and restricted access to A Street.

Page 9: C ITY OF R AINER R AILROAD C ROSSING ’ S. Project # 2 Group Matthew DeGeorge Josh Crain Robert Acevedo Chris Penka Jim Harvey Heather Wenstrand

• ODOT’s 3/3/1 Offer to City– ODOT Rail has made an agreement with The City of

Rainer Stating that if 3 rail crossing are closed ODOT will pay for 3 to be upgraded. This leaves the fourth additional rail crossing to be upgraded under the responsibility of the City of Rainer to finance.

– Under this agreement The City of Rainer is required to provide all the engineering for the project and ODOT Rail will have final decision making authority on the plans and will be financially responsible for 3 of the crossing upgrades.

Page 10: C ITY OF R AINER R AILROAD C ROSSING ’ S. Project # 2 Group Matthew DeGeorge Josh Crain Robert Acevedo Chris Penka Jim Harvey Heather Wenstrand

• Future Closures– City decided due to usage and location that it would be beneficial to

close the following• East 2nd Street • East 4th Street • East 5th Street

• Future Gated/Controlled– City decided that it would be necessary to allow the following

intersection to remain open however to provide control measures for safety purposes.

• West 2nd Street• 1st Street• East 3rd Street• East 6th Street

Page 11: C ITY OF R AINER R AILROAD C ROSSING ’ S. Project # 2 Group Matthew DeGeorge Josh Crain Robert Acevedo Chris Penka Jim Harvey Heather Wenstrand
Page 12: C ITY OF R AINER R AILROAD C ROSSING ’ S. Project # 2 Group Matthew DeGeorge Josh Crain Robert Acevedo Chris Penka Jim Harvey Heather Wenstrand

Intersection Design Alternatives

Page 13: C ITY OF R AINER R AILROAD C ROSSING ’ S. Project # 2 Group Matthew DeGeorge Josh Crain Robert Acevedo Chris Penka Jim Harvey Heather Wenstrand
Page 14: C ITY OF R AINER R AILROAD C ROSSING ’ S. Project # 2 Group Matthew DeGeorge Josh Crain Robert Acevedo Chris Penka Jim Harvey Heather Wenstrand
Page 15: C ITY OF R AINER R AILROAD C ROSSING ’ S. Project # 2 Group Matthew DeGeorge Josh Crain Robert Acevedo Chris Penka Jim Harvey Heather Wenstrand

The Next Phase

• Week 1 - Design 3 intersection closures

• Week 2 & 3 - Design the general railroad crossings. Intersections 1st and 3rd St E

• Week 4 & 5 - Design 2nd St W (Post Office)

• Week 6 & 7 - Design 6th St E (Foss)

• Week 8 - Overall review and finalize designs

• Week 9 & 10 – Presentation preperation