bwrvip integrated surveillance program (isp) · 2018. 6. 14. · surveillance program (isp) to...

58
© 2018 Electric Power Research Institute, Inc. All rights reserved. Drew Odell, Exelon/BWRVIP Nathan Palm, EPRI Heather Jackson, Structural Integrity NRC Public Meeting June 13, 2018 BWRVIP Integrated Surveillance Program (ISP) Extension of Program to Address Second License Renewal (SLR)

Upload: others

Post on 10-Feb-2021

3 views

Category:

Documents


0 download

TRANSCRIPT

  • © 2018 Electric Power Research Institute, Inc. All rights reserved.

    Drew Odell, Exelon/BWRVIPNathan Palm, EPRI

    Heather Jackson, Structural Integrity

    NRC Public MeetingJune 13, 2018

    BWRVIP Integrated Surveillance Program (ISP)

    Extension of Program to Address Second License

    Renewal (SLR)

  • 2© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Agenda

    IntroductionMeeting Purpose and ObjectivesSummary of November 2016 MeetingReview of Proposed ISP for SLR ApproachData InvestigationsSpecimen PreparationNeutron Flux InvestigationsHost Plant SelectionConceptual SSLR Capsule DesignsProgrammatic AspectsFuture Actions

  • 3© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Introduction

    Since 2002, the U.S. BWR fleet has been using an integrated surveillance program (ISP) to provide reactor vessel (RV) surveillance data and satisfy 10 CFR 50 Appendix H requirements.The ISP was designed and is managed by the EPRI Boiling Water

    Reactor Vessel and Internals Project (BWRVIP).All U.S. BWRs have amended their operating licenses to

    implement the BWRVIP ISP.The ISP addresses 60 years of operation and was approved by

    the NRC in 2006.– Current program plan document is BWRVIP-86, Revision 1-A

    BWR owners have expressed an intention to pursue SLR.Since 2015, the BWRVIP, in coordination with the EPRI Long-

    Term Operation (LTO) program, has had a program to address limitations of the ISP for SLR.

  • 4© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Meeting Purpose and Objectives

    Update the NRC on progress made on the ISP for SLR project since the November 2016 meetingProvide the NRC staff with a preview of the content of the

    ISP for SLR program planProvide NRC an opportunity to provide any comments or

    concerns in advance of the ISP for SLR program plan being submitted for review and approval

  • 5© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Summary of November 2016 Meeting

  • 6© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Issues Related to Original BWR Plant-Specific Surveillance Programs In the early 1990s, issues were identified with BWR plant-

    specific surveillance programs:– Some surveillance materials do not match limiting vessel beltline

    materials because they were designed: To earlier versions of ASTM E-185 that specified that capsules

    should contain materials that represent materials from the vessel beltline region.Prior to Reg. Guide 1.99, Revision 1 (1977) when embrittling effects

    of copper were not yet known.– Some surveillance materials were missing baseline data (unirradiated

    Charpy data, chemistry data, and/or heat numbers).Missing or incomplete data limits the usefulness of surveillance

    capsule data for predicting RPV embrittlement of vessel beltline materials.

  • 7© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Why Did the BWRVIP Develop an Integrated Surveillance Program? Increase overall technical quality and make most effective

    use of existing BWR surveillance capsules and data– Include the BWRVIP Supplemental Surveillance Program (SSP)

    capsule data (next slide)

    Address regulatory concerns regarding some cases of inadequate or missing dataCollectively monitor and manage embrittlement in BWR

    vessels– Share data between all BWR utilities– Avoid surprises from BWR surveillance data– Avoid excess conservatism in pressure test temperatures

  • 8© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Supplemental Surveillance Program (SSP)

    Began in late 1980’s by the BWROG to supplement database of BWR embrittlement data9 capsules inserted into host reactors:

    – Cooper (Capsules A, B, and C)– Oyster Creek (Capsules D through I)

    25 materials (13 plate and 12 weld); 84 sets of weld and plate Charpy specimens, including EPRI-contributed materialsMaterial chemistries and target fluences chosen to span the

    range of BWR vessel beltline materialsExcellent characterization of baseline Charpy data and

    chemistryAll capsules have been tested and capsule reports have

    been published and transmitted to the NRC

  • 9© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Current ISP Structure

    Selected representative surveillance materials from the capsules of 13 host plants, plus selected materials from 9 SSP capsules, constitute the ISP– 15 representative plate heats and 15 representative weld heats

    provide data for the BWR fleet– 13 host plant capsules to be withdrawn and tested during the original

    plant license period– 13 host plant capsules to be withdrawn and tested during the first

    license renewal period – All 9 SSP capsules were tested

    The ISP Test Matrix links the representative materials to a “target” plate and weld material in each BWR RVTesting of remaining non-host BWR fleet capsules will be

    deferred or designated as contingencies

  • 10© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Considerations for Extending Current ISP to 80 Years

    GALL-SLR specifies that surveillance programs must be in place that meet 10CFR50 Appendix H, allowing for use of ISP for SLR.Extending the current ISP to address 80 years of operation

    presents challenges– Total number of plants and which plants will pursue SLR are uncertain Some of the current host plants may not pursue SLR Plants electing to pursue SLR may have surveillance materials that are

    not representative of other plants and are therefore not suitable as “host” plants

    – Current host plants will likely not have additional capsules available for testing in the 60 to 80 year period

    – Some representative surveillance materials were in the SSP capsules only– Many BWRs, as well as ISP host plants, have lag factors as opposed to

    lead factors (surveillance capsules are exposed to lower fluence than the inside surface of the RV)

    Effort initiated in 2015 to evaluate options and feasibility for providing BWR RV surveillance for 80 years

  • 11© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Feasibility Evaluation

    Task group of experts formed Options to extend or replace ISP identifiedFeasibility study performed assessing all optionsOptions ranked based on:

    – Technical merit– Ease of implementation– Cost– Regulatory acceptabilityTask group developed a recommended approach to be taken for ISP for SLR

  • 12© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Review of Proposed Approach for Addressing Surveillance Needs of BWR Fleet in SLR

  • 13© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Proposed Approach

    Maintain the critical elements of the ISP to the greatest extent possible, i.e., the ISP Test MatrixMake 80-year surveillance data available for the entire set of

    ISP materialsUtilize existing data to the extent possible

    – SSP capsules had lead factors higher than typical BWR capsules– For some materials, specimens from many capsules, exposed to a

    wide range of fluence levels, have been tested

    Reconstitute previously tested specimens to fill gaps in data– Specimen inserts will be irradiated prior to reconstitution (next slide)– Inserts will be placed in “Supplemental SLR Capsules”

    Extend the existing ISP versus replace

  • 14© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Reconstitution Approach

    Specimen inserts will be irradiated prior to reconstitution Inserts will be placed in

    specially designed “Supplemental SLR (SSLR) Capsules”All SSLR capsules can be

    irradiated in one host plantAfter irradiation is complete,

    reconstituted specimens will only be fabricated and tested for those materials that are needed by plants that actually pursue SLR

    Insert

    End Tab

    End Tab

  • 15© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Irradiation of Inserts Only

    Irradiation of inserts prior to welding of end tabs has several advantages for the ISP for SLR– Many materials can fit into a single capsule – Cost of completing specimen fabrication is deferred Irradiation may need to begin prior to plants’ decisions to pursue

    SLR being made If certain plants do not pursue SLR or shutdown early, fabrication of

    specimens for some materials may not need to be completed

    Although irradiating the inserts prior to specimen fabrication increases dose, it will still be less than typical PWR levels

  • 16© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Materials in the ISP for SLR Program

    The ISP Test Matrix will remain unchanged for the ISP for SLR– The program will still consist of 15 representative plate heats and 15

    representative weld heats– The limiting “target” materials for the BWR RVs will not be reevaluated

    New materials will not be added to the program to address:– Materials now considered as part of the extended beltline– Changes in limiting materials as a result of potential changes in

    embrittlement trend curves

    The intent is to trend the embrittlement behavior of the materials in the surveillance program– Adding a new material in the SLR period and obtaining one data point will

    not allow for trending of embrittlement– Several embrittlement trend curves have been considered/proposed

    since the publication of RG 1.99, R2 and it is not possible to know which trend curve may be selected for the next revision or when that will occur

  • 17© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Benefits of Proposed Approach

    Definitions of representative and target materials, as defined in approved ISP test matrix, will remain unchangedResponsibilities of utilities to implement ISP data will remain

    unchangedNo changes to existing ISP test scheduleSatisfies Appendix H requirements and GALL-SLR

    expectationsReduces uncertainty associated with not knowing which

    plants may implement SLROnly change to ISP is addition of 80-year data where

    such data does not currently exist

  • 18© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Data Investigations

  • 19© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Overview: Data Needs for SLR are Determined by Evaluating Available Data from BWRVIP ISP program80-year fluences are projected for vessel target materials.Target fluences are compared with fluences of tested

    surveillance capsule materials.Gaps and additional data requirements are identified to plan

    SSLR capsules.

    Target vessel materialRepresentative

    (surveillance) material Host plant

  • 20© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Methodology for Projecting BWR Target 80-year Fluences

    1/4T fluence values for ISP target plate and weld materials were taken from the latest docketed P-T curve reports, or from updated fluence evaluations for tested ISP capsules.Fluence was estimated by projecting linearly from the

    reference fluence (e.g. 32 or 54 EFPY) to 72 EFPY.The projected 72 EFPY fluences were compared with

    fluences of capsules that will be tested by the ISP prior to the end of the 60-year license renewal period.Where gaps exist, data needs were identified for extending

    the ISP for SLR to bound the fleet.

  • 21© 2018 Electric Power Research Institute, Inc. All rights reserved.

    72 EFPY 1/4T Fluence Projections for BWR Target Plates

    7 plates < 1x1018 n/cm2

    5 plates > 5x1018 n/cm2

    22 plates > 1x1018 n/cm2and < 5x1018 n/cm2

  • 22© 2018 Electric Power Research Institute, Inc. All rights reserved.

    72 EFPY 1/4T Fluence Projections for BWR Target Welds

    9 welds < 1x1018 n/cm2

    4 welds > 5x1018 n/cm2

    21 welds > 1x1018 n/cm2and < 5x1018 n/cm2

  • 23© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Target 80-year Fluences are Compared with Fluences for ISP Surveillance CapsulesData for 15 plate and 15 weld materials are available from

    25 existing capsules tested under the ISP and individual plant programs and 9 SSP capsules.Data not included for 6 ISP capsules tested in 2016-2025.Testing of 13 ISP(E) capsules is planned during the license

    renewal period.Fluences for tested ISP and SSP capsules are obtained from

    published capsule test reports.– All ISP and SSP capsules have been evaluated using the RAMA

    fluence methodologyProjected fluences for remaining ISP capsules and ISP(E)

    capsules are obtained from BWRVIP-86, Rev. 1-A.– Matching of projected vessel fluence and surveillance capsule fluence

    shows that some materials are already covered and the remaining materials can be grouped by fluence needed to catchup to the vessels

  • 24© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Fluences of Tested and Planned ISP Capsules Bound 13 Target Plates and 17 Target Welds for 80 years

    Tested Capsule Fluence as a % of Target SLR Fluence

    Number of Target Plates

    Number of Target Welds

    < 50% 16 1350-99% 10 12≥ 100% 8 9

    Projected ISP(E) Capsule Fluence as a % of Target

    SLR Fluence

    Number of Target Plates

    Number of Target Welds

    < 50% 5 150-99% 16 16≥ 100% 13 17

    When ISP(E) capsules are considered, an additional 5 plates and 8 welds are bounded

    Existing ISP data bounds 8 target plates and 9 target welds for 72 EFPY

  • 25© 2018 Electric Power Research Institute, Inc. All rights reserved.

    To Bound all Target Heats for 80 years, Additional Surveillance Data is Needed for 13 Representative Plates and 10 Representative Welds

    Needs additional surveillance data?

    Number of Representative

    Plates

    Number of Representative

    WeldsYes 13 10No 2 5

    Total 15 15

  • 26© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Methodology for Planning Proposed Supplemental SLR CapsulesFor each representative plate and weld material for which

    additional surveillance data is needed:– The tested capsule having the highest fluence is identified.– Some representative heats represent multiple target vessels. The

    corresponding target heat with the bounding projected 72 EFPY 1/4T fluence is identified.

    – The needed “catchup” fluence is determined by:

    Catchup fluence for each

    representative heat

    Bounding 1/4T fluence projected for 72 EFPY for corresponding target vessels

    Highest fluencetested capsule–=

  • 27© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Representative Materials Needing Additional Data are Grouped Based on the Range of Additional Fluence Needed

    GroupCatchup Fluence Needed

    (n/cm2, E > 1 MeV) Number of Materials

    1 < 1x1018 72 > 1x1018 n/cm2 and < 5x1018 n/cm2 83 > 5x1018 n/cm2 8

    Groupings show fluence targets for selection of materials and design of Supplemental SLR capsules.

    Three Supplemental SLR capsules are proposed with catchup fluences that bound all target plates and welds for 80 years.

    This approach is a natural extension of the existing ISP program to fill in needed data.

  • 28© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Conclusions of Data Investigations

    80-year fluence needs can be met with a small number of SSLR capsules, with materials grouped based on “catchup” fluence8 of 34 target plates and 9 of 34 target welds are bounded

    for 80 years by existing ISP data13 of 34 target plates and 17 of 34 target welds will be

    bounded for 80 years by ISP capsules tested during the license renewal periodAdditional data is needed for 13 of 15 representative plates

    and 10 of 15 representative welds to meet projected fluence needs for 80 years

  • 29© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Specimen Preparation

  • 30© 2018 Electric Power Research Institute, Inc. All rights reserved.

    ISP Repository

    All specimens tested under the ISP and SSP are maintained in a single repository Specimens are stored in a highly organized manner

    – Each capsule has a unique storage container– Broken Charpy halves from an individual specimen are stored

    together in their own labeled container– An ISP repository inventory report is maintained and updated on a

    yearly basis

    Previously tested specimens are readily retrievable to support the ISP for SLR effort

  • 31© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Specimen Etching – Background and Objectives

    Etching of broken ISP weld and HAZ specimens performed to determine if enough weld material is available in Charpy specimens halves to support fabrication of inserts for reconstitution– Original weld surveillance specimens contain a varying amount of weld and plate

    material– Original HAZ specimens are roughly one half base metal and one half weld metal

    For reconstitution, ASTM E1253 specifies an insert width of 18 mm, but this requirement may be relaxed if:– It can be experimentally or analytically shown that the plastic deformation zone in

    subsequent testing will not extend into the heat affected zones produced by reconstitution and,

    – Heat input during welding shall be controlled such that no part of the volume of the central 10-mm portion of the reconstituted Charpy-sized specimen exceeds the prior metal irradiation temperature at any time during welding

    Target for SSLR capsules is to have14 inserts of each weld material– 12 per ASTM E-185-82– 2 Spare

  • 32© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Specimen Etching – Results

    Etching completed on 9 of 10 weld heats (one heat to be used will come from Peach Bottom Unit 2 capsule to be withdrawn in fall 2018)– 3 heats have more than adequate material to obtain 14 inserts of an

    18mm width– 3 heats will require the use of smaller insert sizes to obtain 14 inserts Some specimens with an insert width of 15mm, which will be tested in the

    transition region or lower shelf As many as 3 specimens with an insert size of 12mm that will be tested on

    the lower shelf and lower portion of transition curve only– 3 heats will require the use of smaller insert sizes and as few as 10

    specimensTechnical bases and procedures for using smaller insert

    sizes and specimen quantities will be provided in the ISP for SLR program plan

  • 33© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Basis for Use of Smaller Specimen Insert Sizes

    Although ASTM E1253 identifies an insert size of 18mm, use of smaller inserts is permitted, as discussed on slide 31.– ASTM E1253 further provides reference to test programs have shown

    acceptable Charpy results using shorter inserts– The multi-lab RESQUE program (ASTM STP 1418) concluded: 12mm inserts can be tested in the transition region 15mm inserts can be tested at any energy

    – Other studies (ASTM STP 1204) have also shown acceptability of using 15mm inserts on the upper shelf

  • 34© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Basis for Use of Smaller Specimen Quantities

    Although it is desirable to be in compliance with ASTM E185-82 by having 12 specimens, current BWR capsules often contain only 8 specimens– Capsules were designed to earlier versions of E185– The BWRVIP has had no issues developing high quality Charpy

    curves with only 8 specimens

    For all materials tested under the ISP for SLR Program, at least 2 capsules will have been previously tested– Embrittlement behavior of materials has been characterized– Previous test results can be used to inform selection of appropriate

    test temperatures

  • 35© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Material Identification and Reconstitution

    Positive identification of the inserts will be maintained during the irradiation period by only including one material per packet.Arc stud welding will be performed for all of the SLR weld

    inserts in accordance with ASTM E1253 proceduresEnd-tabs will be oversized so that they can be EDM

    machined in plane with the irradiated insert

  • 36© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Neutron Flux Investigations

  • 37© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Fluence vs. Flux and Lead Factor Considerations

    The primary objective for obtaining additional surveillance data is to achieve a fluence exposure that is equal to or greater than 80-year RV fluenceCatchup fluences cannot be achieved prior to the end of 80

    years of operation using typical BWR surveillance capsule flux rates– Catchup fluences must be reached in a reasonable timeframe - ~10

    years or less– An accelerated flux rate is needed

    Concerns were identified at the November 2016 public meeting regarding flux embrittlement effects and ASTM E185 lead factor recommendationsA balanced perspective is needed concerning fluence, flux,

    and lead factor – some compromise is needed

  • 38© 2018 Electric Power Research Institute, Inc. All rights reserved.

    ASTM E185 Lead Factor Recommendations

    ASTM E185-82 recommends that surveillance capsule lead factors be in the range between 1 and 3ASTM E185 is written for the development of a plant-specific

    surveillance program– The ASTM E10.02 committee is currently considering an annex to the

    standard for integrated surveillance programs

    Lead factor is not a meaningful consideration for integrated surveillance programs– The data from one surveillance capsule is representative of materials

    in multiple reactor vessels and a different lead factor exists for each

    For planning of the ISP for SLR, lead factor will not be considered. Target flux and fluence will be the primary considerations.

  • 39© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Selection of Target Flux

    In order to obtain the needed catchup fluences of the ISP for SLR program in 10 years, a flux of at least 2.4E+10 n/cm2-s is neededThe embrittlement trend curve in the Alternate PTS Rule,

    10CFR50.61a, contains a breakpoint value for flux of 4.39E+10 n/cm2-s for consideration of flux effects– 4.39E+10 n/cm2-s will be used as an upper limit on flux for the SSLR

    capsules

    2.4E+10 n/cm2-s < TARGET FLUX < 4.39E+10 n/cm2-s

  • 40© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Neutron Flux Investigations

    Project initiated to investigate neutron flux values for SSLR capsules– Provide data for use in selection of potential host plants– Determine possible positions for placement of capsules

    Candidate host plants selected for evaluation based on similarity to other BWR designs– Increase potential for capsule transferability, if needed– Parameters evaluated for similarity included shroud inner diameter

    (ID), shroud thickness, annulus width, core size– Four BWR/4 units selected for evaluation

    Flux values calculated at varying azimuthal, axial, and radial positions within the reactor annulus

  • 41© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Neutron Flux Investigation Conclusions

    Target flux values for SSLR capsulescan be obtained by a combinationof the following:– Locating the capsules at a core “flat”

    (0°, 90°, 180°, and 270° positions)– Offsetting the capsules from the

    shroud by several inches– Positioning the capsule lower in the core

    (although the flux profile is less uniformacross the capsule in this region)

    Optimal location:– Several inches radially from the core shroud toward the reactor vessel– Within +/- 5° of the 0° and 180° positions Low flux locations Free from jet pump obstructions

    – Between 60” and 100” from the bottom of the active fuel Flux profile will be relatively uniform over height of capsule

  • 42© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Flux Investigation Results - Azimuthal

  • 43© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Flux Investigation Results - Axial

  • 44© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Neutron Flux Investigation Methods

    The 4 candidate SLR plants are current ISP host plants and have been previously evaluated using the RAMA fluence methodologyTo evaluate the potential flux of the SSLR capsules:

    – Previously developed RAMA transport solutions for the most recent available operating cycle (actual or projected) were used as a starting point

    – RAMA models were modified to include representative capsules in the annulus region where the SSLR capsules may be placed

    – 3D interpolation was performed to produce axial, aziumthal, and radial flux profiles

    To evaluate the flux spectrum, RAMA inputs were modified to analyze flux on a group-by-group basis

  • 45© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Neutron Flux Spectrum Comparison

    Evaluation performed to compare neutron spectrum at potential SSLR capsule location and that at position of typical BWR capsulesSSLR capsule positioned at:

    – 0° azimuthal position– Axial position where flux profile is “flat”– Radial position corresponding to a flux of 4.39E10 n/cm2-s

    Comparisons made for energy groupings between 1Mev and 17MeVFlux normalized for each grouping by dividing by total fluxFour candidate SLR host plants evaluatedMaximum difference in flux between SSLR capsule and a typical

    BWR capsule for all energy groupings is less than 2.5%Small difference in neutron flux spectrum between typical

    BWR capsule and SSLR capsules

  • 46© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Neutron Flux Spectrum Comparison - Example

  • 47© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Host Plant Selection

  • 48© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Candidate Host Plant Selection

    Intent is to identify multiple plants in the ISP for SLR program plan as candidate host plants for the SSLR capsules– Addresses the contingency planning requirements of 10 CFR 50

    Appendix H for cases of plant shutdown– Provides flexibility for changes that may occur between time of program

    plan development and capsule insertion (~3 to 4 years from today)Several plants selected for consideration based on the following:

    – Similarity to other plant designs In case relocation of SSLR capsules and holder becomes necessary

    – End of 60-year license dates Provides enough time for SSLR capsules to be installed and obtain

    needed fluence levels– Existing quality fluence model Needed in order to determine potential flux values for SSLR capsules

    – Existing ISP host plant Familiar with existing ISP host plant responsibilities

  • 49© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Conceptual SSLR Capsule Designs

  • 50© 2018 Electric Power Research Institute, Inc. All rights reserved.

    SSLR Capsule Design

    Each SSLR capsule will contain 8 packets– Each packet will contain the inserts for one material– One capsule containing only 7 materials will include a “filler” packet so

    that all capsules can have the same dimensions

    Dosimetry– Flux wires of high-purity iron, nickel, copper, and niobium will be

    included in each packet– Wire length in the horizontal direction is sufficient to overlap each

    weld insert in the packet, so that any azimuthal variation in flux can be measured if required

  • 51© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Packet Design

    (14x)

  • 52© 2018 Electric Power Research Institute, Inc. All rights reserved.

    SSLR Capsule Holder Design

    Specialized holder design is needed for SSLR capsules– One holder capable of containing three capsules for the three catchup

    fluence groupings– Allow for the removal of capsules from the holder independently– Attach to core shroud to obtain needed flux– Allow for transfer to an alternate host plant, if needed

    Conceptual capsule holder designs are being developed for the candidate host plantsPrimary intent of conceptual design effort is to ensure that

    capsules can be installed in locations that provide needed fluxDetailed capsule holder design effort will occur after NRC

    approval of ISP for SLR program plan

  • 53© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Conceptual SSLR Capsule Holder Design

  • 54© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Conceptual SSLR Capsule Holder - Installed

  • 55© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Programmatic Aspects

  • 56© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Project Administration and Implementation

    The ISP for SLR program plan will maintain the following elements of the current NRC approved ISP (exceptions as noted):– Project Management Responsibilities– Capsule Data EvaluationDeviation from 10CFR50 Appendix H timeliness requirements will

    be requested – materials will be reconstituted and tested once it is known that a plant will be pursuing SLR and data will be needed

    – Fluence and Dosimetry– Plan for Ongoing Vessel Dosimetry Three options are currently provided for dosimetry for those plants

    not withdrawing and testing capsules– Data Sharing– Data Utilization

  • 57© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Future Actions

    Completion of ISP for SLR program plan in late 2018Submittal of ISP for SLR program plan in early 2019 for NRC

    review and approvalRespond to NRC requests for additional informationPost NRC approval activities

    – Final host plant selection– Capsule holder design finalization and fabrication– Capsule insertion and irradiation– Capsule withdrawal, specimen reconstitution, and testing– Use of data by BWRVIP members

  • 58© 2018 Electric Power Research Institute, Inc. All rights reserved.

    Together…Shaping the Future of Electricity

    BWRVIP Integrated Surveillance Program (ISP)�Extension of Program to Address Second License Renewal (SLR)AgendaIntroductionMeeting Purpose and ObjectivesSummary of November 2016 MeetingIssues Related to Original BWR Plant-Specific Surveillance ProgramsWhy Did the BWRVIP Develop an Integrated Surveillance Program?Supplemental Surveillance Program (SSP)Current ISP StructureConsiderations for Extending Current ISP to 80 YearsFeasibility EvaluationReview of Proposed Approach for Addressing Surveillance Needs of BWR Fleet in SLRProposed ApproachReconstitution ApproachIrradiation of Inserts Only Materials in the ISP for SLR ProgramBenefits of Proposed ApproachData InvestigationsOverview: Data Needs for SLR are Determined by Evaluating Available Data from BWRVIP ISP programMethodology for Projecting BWR Target 80-year Fluences72 EFPY 1/4T Fluence Projections for BWR Target Plates72 EFPY 1/4T Fluence Projections for BWR Target WeldsTarget 80-year Fluences are Compared with Fluences for ISP Surveillance CapsulesFluences of Tested and Planned ISP Capsules Bound 13 Target Plates and 17 Target Welds for 80 yearsTo Bound all Target Heats for 80 years, Additional Surveillance Data is Needed for 13 Representative Plates and 10 Representative WeldsMethodology for Planning Proposed Supplemental SLR CapsulesRepresentative Materials Needing Additional Data are Grouped Based on the Range of Additional Fluence NeededConclusions of Data InvestigationsSpecimen PreparationISP RepositorySpecimen Etching – Background and ObjectivesSpecimen Etching – ResultsBasis for Use of Smaller Specimen Insert Sizes Basis for Use of Smaller Specimen QuantitiesMaterial Identification and ReconstitutionNeutron Flux InvestigationsFluence vs. Flux and Lead Factor ConsiderationsASTM E185 Lead Factor RecommendationsSelection of Target FluxNeutron Flux InvestigationsNeutron Flux Investigation Conclusions Flux Investigation Results - AzimuthalFlux Investigation Results - AxialNeutron Flux Investigation MethodsNeutron Flux Spectrum ComparisonNeutron Flux Spectrum Comparison - ExampleHost Plant SelectionCandidate Host Plant SelectionConceptual SSLR Capsule Designs�SSLR Capsule DesignPacket DesignSSLR Capsule Holder DesignConceptual SSLR Capsule Holder DesignConceptual SSLR Capsule Holder - InstalledProgrammatic Aspects�Project Administration and ImplementationFuture ActionsSlide Number 58