Business UpdateAnalyst Site Visit

October 2013

Page 2: Business Update - Ferrexpo

High quality and diversecustomer base

Integrated logistical solution

Strong governance andexperienced management team

Premium product producer

Strong cash flow and competitive cost position

Vast resource base with established production facilities

1

2

3

– 100% of production is in the form of iron ore pellets…

– 50% of which c. half contain 65% Fe– No production major outages

experienced

– One of the lowest pelletizing costs in the industry on an FOB basis

– Globally competitive on iron ore concentrate cost curve

– 2.1 Bnt of JORC M&I resources– ca.27 years of reserve life1

– Opportunities for further brownfield development of production facilities– Investment largely completed for 12mtpa of pellets & increase in quality

– Focus on customers producing high value added steel products who are “crisis resistant”

– Sales split between Europe & Asia

– Stake in Yuzhny port terminal – New top-off vessel in harbor– Own railcar (2,200 units) & river barge

fleet

– Governance in line with the requirements of LSE Premium Listing

– Management combining international expertise & detailed local knowledge

4

5

6

Ferrexpo Poltava Mining (FPM) a World Class Pellet Producer

1

1 Estimate based on total reserves of 824 Mt and average ore mining rate of 30Mtpa

Page 3: Business Update - Ferrexpo

FPM Key Objectives

― Continue to increase production to 12mtpa

― Improve product mix: increase average pellet content to 65% Fe

― Maintain disciplined cost management, costs to benefit from past investments

― Continue to improve health & safety performance, fundamental to operational success

― Maintain strong focus on CSR & the community

― Minimise environmental impact

2

Page 4: Business Update - Ferrexpo

OperationsProduction, Costs & Investments

Page 5: Business Update - Ferrexpo

Historic Volume Growth of Largest Pellet Producers

CAGR growth 2010 to 2013F

Source: CRU 2Q 2013

4

Pellet exports by company (Mt)

2010 2011 2012 2013 CAGR

Metalloinvest 13.2 13.6 14.3 15.0 4%

Ferrexpo 10.0 9.8 9.7 10.7 2%

Samarco 21.4 21.7 21.1 21.9 1%

LKAB 20.4 20.5 21.0 19.6 (1)%

QCM / ArcelorMittal

6.8 5.5 6.3 6.5 (1)%

Vale 30.7 34.4 30.8 26.5 (5)%

Cliffs 12.3 11.5 11.1 10.4 (5)%

IOC 11.5 9.0 9.0 9.0 (8)%

Page 6: Business Update - Ferrexpo

5

– Forecast FY 2013 production of 10.7 to 11mt, double digit increase

– Volume of high grade pellets to continue to increase

‘000 t

onne

s

62

63

64

65

4,000

7,000

10,000

13,000

2009 2010 2011 2012 2013F

Production from FPM Production from FYM ore

Third party concentrate Average Fe content

% F

e pell

et co

ntent

+11%

FPM Consistent Production History, now Positioned for Growth

2012 2013F

TOTAL 9,690 10,700 – 11,000High-grade pellets 4,173 4,800 – 5,000Low-grade pellets 5,517 5,600 – 5,800

Page 7: Business Update - Ferrexpo

6

Continuous Quality Improvement

5.3

5.4

5.5

5.6

5.7

5.8

5.9

6

6.1

January February March April May June

2012 2013

230

235

240

245

250

255

January February March April May June

2012 2013

Cold Compression Strength of 65% Fe pellet, 1H 2013 vs. 1H 2012

%

CC

S, k

g/pe

llet

Silica content of 65% Fe pellet, 1H 2013 vs. 1H 2012

Continuous quality improvement to enhance product offering

Page 8: Business Update - Ferrexpo

Effective Business Improvement Program

7

Business Improvement Program reduced C1 cost by US$8.73/ton since 200570.5

61.8

-3.3-2.5 -0.8

-2.2

PF 2005 Electricity Gas Grinding Media

Personnel 1H 2013

6.4 5.5

2005 1H 2013

22.016.8

2005 1H 2013

205.5 169

2005 1H 2013

-18% -25% -14%

Electricity Gas Grinding MediakWh per tn of pellets m3 per tn of pellets Kg per tn of pellets

0.7

1.2

2005 1H 2013

73%

Personnel‘000 tones of pellets per employee

Page 9: Business Update - Ferrexpo

C1 cash cost: 1H 2013 vs. October 2008 (like for like basis pre-devaluation), CAGR 4%

Disciplined Cost Management

C1 ca

sh co

st US

$ per

tonn

e

8

51.0

61.8

63.9

59.7

40

45

50

55

60

65

70

C1 Oct 08 C1 1H13 C1 1Q13 C1 2Q13

25%

13%

11%7%4%

15%

13%

10% 2%

ElectricityGasFuelGrinding mediaExplosivesOther materialsSpare parts, maintenance & consumablesPersonnel costsRoyalties & levies

Benefit of past investments starting to come through

Breakdown of C1 cash cost

Page 10: Business Update - Ferrexpo

Output to Increase to12mtpa with Cost Benefits

Increase pellet output up to 12mtpa

– Average cost of processing FYM ore cheaper than FPM ore

– Reflects lower mining costs, higher Fe content on average & better processing characteristics

– Other benefits of going up to 12mtpa:

– Fixed cost dilution on c. 3mtpa (fixed costs represent approximately 30% of total costs)

– Freight savings from higher volumes, aim to do 4 capes per month

– Excludes benefit from any currency devaluation

– Devaluation will reset cost base, with higher production levels largely offsetting future inflation

– 70% of production cost (C1 cost + rail to border) in UAH

9

Page 11: Business Update - Ferrexpo

Significant Investment of Past to Yield Benefits

FPM Capital Expenditure has Peaked

US

$M

10

– Modernization and debottlenecking of FPM processing facilities to increase output by one third to 12mtpa – FPM quality upgrade programme to increase pellet Fe content to all 65% Fe– FPM mine life extension to support the sustainable availability of rich ore – Sustaining capex approximately US$90M in 2013, should reduce going forward– Remaining development capex approximately US$80 million in 2013

A well invested asset base due to:

58

104

170191

170

0

50

100

150

200

250

2009 2010 2011 2012 2013F

Page 12: Business Update - Ferrexpo

Mine Life Extension Project: US$125M Spent, US$45M Remaining

11

2012+ 13.3 Mt orecompleted

2013+ 18,5 Mt orecompleted

2012+ 48 Mt orecompleted

2027+ 29.9 Mt orein-process

2013+ 51.8 Mt orecompleted

7

6

Mine Life Extension Northern Pushback

Revision

2018+ 54 Mt oreIn-process

Page 13: Business Update - Ferrexpo

Quality Upgrade Project: US$65M Spent & Committed, US$147M Remaining

12

0%

20%

40%

60%

80%

100%

120%

2010 2011 2012 2013F 2014F Q12015F Q22015F Q32015F Q42015F

High

grad

e pell

ets fr

om ow

n raw

mate

rials

– Timely completion of floatation sections (new floatation sections # 2 & 3, and modernization of floatation # 1)– Filtration process (vacuum, press, etc)

Major milestones remaining to produce 100% 65% Fe pellets:

– Yield loss– Market environment– Timely supply of equipment and construction works performance

Also dependent on:

Page 14: Business Update - Ferrexpo

Foundations for vertical mills and auxiliary equipment. Flotation # 2,3. [09.2012].

Vertical mills VERTIMILL VTM-1500-WB have been installed Flotation # 2,3. [08.2013].

Quality Upgrade Project

Page 15: Business Update - Ferrexpo

Preparation of the construction site. Flotation #2,3. [09.2012]

7 flotation chambers have been installed. Flotation #2,3. [08.2013]

Quality Upgrade Project

Page 16: Business Update - Ferrexpo

15

Capacity Upgrade Project: US$77M Spent & Committed, US$65M Remaining

– Completion of modernisation of concentration sections (3-4 sections pa in average)– Upgrade of existing pellet lines (one line pa for 60 days off for the upgrade)– Automation of the new technological process for the upgraded sections to increase productivity and concentrate output

Major milestones remaining to produce 12mtpa of pellets:

0.0

2.0

4.0

6.0

8.0

10.0

12.0

14.0

16.0

2012 2013E 2014E 2015E

Concentrate, mtpa

240

245

250

255

260

265

270

2012 2013E 2014E 2015E

Average productivity per section, ton/hour

Page 17: Business Update - Ferrexpo

Capacity Upgrade Project

Construction of 3rd section is completed.Project: Reconstruction of sections at Concentrator #1

Ball mill and classifier have been replaced at section #1Project: Reconstruction of sections at Concentrator #1

16

Capacity Upgrade Project

Page 18: Business Update - Ferrexpo

Capacity Upgrade Project

Reconstruction of section #14 is completedReplacement of technological equipment and pipelinesProject: Reconstruction of sections at Concentrator #2

Reconstruction of section #14 is completed Replacement of electric service panels and assembly of automation system panelsProject: Reconstruction of sections at Concentrator #2

17

Capacity Upgrade Project

Page 19: Business Update - Ferrexpo

Capacity Upgrade Project

Installed Lоedige mixers at Pellet plant. Project: Kobe Steel report Capacity > 13.2 Mtpa

New building of Isotopic laboratory. Project: Construction of new tracks of Medium-fine crushing #1,2

18

Capacity Upgrade Project

Page 20: Business Update - Ferrexpo

19

Corporate Social Responsibility

Page 21: Business Update - Ferrexpo

65

77

60

52

66

5358

37

47

37

29 26

1722 24

149

1510

4

0

10

20

30

40

50

60

70

80

1984

1985

1986

1987

1988

1989

1990

1991

1992

1993

1994

1995

1996

1997

1998

1999

2000

2001

2002

2003

2004

2005

2006

2007

2008

2009

2010

2011

2012

6M 2

013

Health & Safety Fundamental to Operational Success

20

Num

ber o

f occ

upat

iona

l inj

urie

s

Note LTIFR – Number of work-related lost time injuries per million man hours.Lost days – number of days lost due to temporary disability as a result of occupational injuries

Safe

ty co

sts,

UAH

mio

Safe

ty co

sts p

er 1

empl

oyee

, UAH

/1

empl

oyee

1525 28

41

67

76

71

1,5

3,0 3,5

5,2

8,39,3

8,9

0

2

4

6

8

10

0

10

20

30

40

50

60

70

80

2007 2008 2009 2010 2011 2012 2013F

Safety costs, UAH mio Safety costs per 1 employee

2008 2009 2010 2011 2012 6M 2013

LTIFR 1,12 1,11 1,43 0,89 0,79 0,61

Fatal Accidents 3 No 1 No No No

Total Accidents 17 15 19 11 10 4

Lost days 591 530 889 469 338 186

Reduction in Injury Frequency Rates

Page 22: Business Update - Ferrexpo

Active Community Support Programme: US$44M spent since 2010

21

Poltava region

Комсомольск

Community payments: (US$M)2010: 4.42011: 11.9 2012: 19.52013F: 8.1

43.9

5% Poltava Region

75% Komsomolsk

20% Ukraine

2010 2011 2012 2013FMedical care 169 417 286 284Financial support to vulnerable people 360 1,127 1,779 1,205Education 349 1,604 3,703 1,111Sport 1,104 1,507 3,190 1,622Infrastructure 2,426 7,253 10,498 3,865TOTAL 4,409 11,907 19,456 8,088

Charitable Programmes (US$’000)

Page 23: Business Update - Ferrexpo

Contaminants Maxpermissible 2009 2010 2011 2012 6M 2013 % decline

since 2009

NO2 167.46 149.55 147.75 105.57 129.13 115.73 (23)%

SO2 39.55 38.86 38.63 36.09 31.52 37.53 (3)%

CO 126.25 120.65 117.77 110.01 89.30 91.61 (24)%

Minimising Environmental Impact, while Production set to Increase

22

Emissions snapshot in time, gram/sec

69

86100 105

148

45 46

76 77 75

0

50

100

150

2009 2010 2011 2012 2013F

Current costs Nature-protection measures

Total environmental costs (UAHM)

Page 24: Business Update - Ferrexpo

FPM a World Class Iron Ore Pellet Producer

Summary

– FPM has a track record of delivering

– Double digit production growth

– Prudent investment of past set to deliver cost benefits

– Strong focus on labour safety, community & environmental protection

– Continued management of Ukrainian country risk, well understood

23

Page 25: Business Update - Ferrexpo

24

Appendix

Page 26: Business Update - Ferrexpo

0

14

28

42

56

70

USc/dmtu

FPM

0.2 Bnt

ENRCMetalloinvest

IOC

Metinvest MetinvestLKAB

LKABVale

ValeSamarco

Vale

CLIFFS

Pelletising Cost Curve

Source: CRU, January 2013

Pelletising – Competitive Cost Position

Note: Only reflects costs incurred at pelletising stage of the production process (i.e. does not include mining, concentration and beneficiation costs) and as such should not beconsidered as a cost curve for total cost of pellets production. Site costs are defined as cash operating costs plus share of local overhead and sustaining capital

25

Page 27: Business Update - Ferrexpo

Overall Cost Position

Source Bank of America Merrill Lynch; Ferrexpo , August 2013

CIF China 62% Fe Equivalent Unit Concentrate Cash Cost1

US

$/to

nne

1 In order to determine a comparable CFR cost of concentrate for Ferrexpo, the cost of pelletising has been deducted. The calculation is as follows: C1 cash cost of production + freight to Port Yuzhny + sea freight to China – less pelletising cost - premium for higher Fe content.

26

mtpa

Page 28: Business Update - Ferrexpo

Disclaimer

This document is being supplied to you solely for your information and does notconstitute or form part of any offer or invitation or inducement to sell or issue, orany solicitation of any offer to purchase or subscribe for, any shares in theCompany or any other securities, nor shall any part of it nor the fact of itsdistribution form part of or be relied on in connection with any contract orinvestment decision relating thereto, nor does it constitute a recommendationregarding the securities of the Company. No information made available to youin connection with this document may be passed on, copied, reproduced, inwhole or in part, or otherwise disseminated, directly or indirectly, to any otherperson.

Some of the information in this document is still in draft form and is subject toverification, finalisation and change. Neither the Company nor its affiliates noradvisers are under an obligation to correct, update or keep current theinformation contained in this document or to publicly announce the result of anyrevision to the statements made herein except where they would be required todo so under applicable law.

No reliance may be placed for any purpose whatsoever on the informationcontained in this document. No representation or warranty, expressed orimplied, is given by or on behalf of the Company or any of the Company’sdirectors, officers or employees or any other person as to the accuracy orcompleteness of the information or opinions contained in this document and noliability whatsoever is accepted by the Company or any of the Company’smembers, directors, officers or employees nor any other person for any losshowsoever arising, directly or indirectly, from any use of such information oropinions otherwise arising in connection therewith.

This presentation and its contents are confidential. By reviewing and / orattending this presentation you are deemed to accept that you are under a dutyof confidentiality in relation to the contents of this presentation. You agree thatyou will not at any time have any discussion, correspondence or contactconcerning the information in this document with any of the directors oremployees of the Company or its subsidiaries nor with any of their customers orsuppliers, or any governmental or regulatory body without the prior writtenconsent of the Company.

Certain statements, beliefs and opinions in this document and any materialsdistributed in connection with this document are forward-looking. Thestatements typically contain words such as “anticipate”, “assume”, “believe”,“estimate”, “expect”, “plan”, “intend” and words of similar substance. By theirnature, forward-looking statements involve a number of risks, uncertainties andassumptions that could actual results or events to differ materially from thoseexpressed or implied by the forward-looking statements. These risk,uncertainties and assumptions could adversely affect the outcome and financialeffects of the plans and events described herein. Statements contained in thedocument regarding past trends or activities should not be taken as arepresentation or warranty (express or implied) that such trends or activities willcontinue in the future. No statement in this document is intended to be a profitforecast. You should not place reliance on forward-looking statements, whichspeak only as of the date of this document.

You should not base any behaviour in relation to financial instruments related tothe Company’s securities or any other securities and investments on informationuntil after it is made publicly available by the Company or any of their respectiveadvisers. Any dealing or encouraging others to deal on the basis of suchinformation may amount to insider dealing under the Criminal Justice Act 1993and to market abuse under the Financial Services and Markets Act 2000.

27

Page 29: Business Update - Ferrexpo

Yeristovo MiningPresentation to Analysts

October 2013

Page 30: Business Update - Ferrexpo

Location of Current and Future Projects

2

Page 31: Business Update - Ferrexpo

Yeristovo Deposit

– JORC Classified Reserve / Resource (2007 SRK Report)– Total reserves of 632 mt– Total Measured and Indicated resource, incl. reserves of 828 mt– Inferred resource of 364 mt– Grand total resource, incl. reserves of 1,192 mt

– Based on Yeristovo pit optimisation model and additional geological data, further evaluation expected to increase reserves – According to design, Phase 1 of Mine development is now complete (50 mio m3 of overburden removed giving access to 153 mt of ore)– Phase 2 assumes plans for mine extension to the North, further Phases 3 and 4 shall see continued northerly and easterly extension– Upper layers of overburden contain sand and clay material, significantly water encroached which has complicated heavy machinery operation. As

per the geological model, clay material will last from surface (+ 68 m) till – 5 m level – Yeristovo ore starts at + 22 m level in the southern part of the pit, first upper layers containing mainly weathered ore– Ore quality (Fe content and yield) fully in line with DFS projections, blended weathered ore processed at FPM– Weathered ore and main clay layers will be removed during the ramp-up period to unlock the full potential of the Yeristovo Mine

3

Page 32: Business Update - Ferrexpo

Yeristovo Stage I – Mining

– Mine status:– Project to date material removed 65 mio bcm, current

pit depth approx.100 m (– 30 m sea level)– Ore achieved in 2HY 2012

– Expected 2013 ore volume mined – up to 9 mio tn, of which:– 6,5 mio tn expected to shipped to FPM for processing– About 2,5 mio tn of weathered ore stockpiled

– 1HY 2013 mining cash cost c.US$1.9/tn of mined (in line with the DFS)– Conveyor (vs. Trucks) option for waste transportation

under consideration to further reduce operational cost– Mining Infrastructure 75% complete:

– Wash centre and tire handling facility in operation– Service and repair centers to be in operation by end 2013– Remaining cost c.US$20M

– Total capital invested in FYM to date c.US$450M, c.7% below DFS due to design improvement and CapEx savings

4

Page 33: Business Update - Ferrexpo

Prime Production Fleet

Current fleet Fleet expansionOct 2013 2014 2015

Draglines 5 – –Excavators / Shovels>28 m3 Overburden 1 – –>34 m3 Ore 2 – +1Loaders>18 m3 1 – –Trucks>180t capacity 16 – –>220t capacity 15 – –Dozers>Tracked 11 – –>Wheel 2 +1 –Drills>160mm diameter 1 – –>250mm diameter 2 +1 –Graders 3 – +1

Current Fleet capacity is sufficient for ore mining of up to 21 mtpa.Further fleet expansion is subject to decision re Conveyor vs Truck option.

On site On order Required

5

Page 34: Business Update - Ferrexpo

Yeristovo Production Schedule

000’ t2013

expect. 2014 2015 2016 2017 2018

Total stripping 37 016 59 183 57 022 56 584 59 959 74 949

Incl. – Sand 32 500 48 916 49 966 50 103 46 969 46 969

– Fresh rock 4 516 10 267 7 056 6 481 12 990 27 980

Ore mining, total 9 000 10 000 10 000 13 500 28 700 28 700

– Ore to FPM (for benefication and pelletizing) 6 500 10 000 10 000 10 000 8 700 0

– Ore to FYM concentrator 3 500 20 000 28 700

Pellets volume (FPM) from FYM ore 2 100 3 501 3 501 3 501 3 046 0

Concentrate volume Fe 67,3% (FYM) 0 0 0 1 336 7 632 10 952

* Subject to Ferrexpo Board Concentrator project approval.

6

Page 35: Business Update - Ferrexpo

Yeristovo Stage II – Processing Complex / Concentrator

– Basic design developed by ProMet Engineering (Australia) in 2008– DFS restated by Bateman (Israel) in 2010– Regulatory approval (“expertise”) in place– Detailed design currently under development by Ukrainian Design institute

(MekhanObrChermet). Schematics for early construction stage available by Q4 2013

– Total Concentrator capacity 10 mtpa dry (4 sections x 2,5 mtpa of concentrate output each)

– As per Oct 2012 Ferrexpo Board approval, concentrator detailed design is in progress and site preparation has commenced

– Concentrator project scope and schedule are subject to Ferrexpo Board approval – Costs to be finalised during detailed design phase – Expectation remains in line with DFS c.US$850M, on track to present to Board

Q4 2013 / Q1 2014

7

Page 36: Business Update - Ferrexpo

Processing Complex General Plan

8

Page 37: Business Update - Ferrexpo

Concentrator Product Handling Options

Option 1 – Slurry Pipeline

Option 2 – Railway

Incremental Slurry Pipeline CapEx is up to US$305M higher than Railway Option CapEx whereas concentrate transportation cost via Slurry Pipeline is more than USD4/tonne lower than Railway Option.

Slurry Pipeline to South + Filtration Plant nearthe Black Sea Port

Slurry Pipeline 5 mtpa to FPM Filtration Plantfor pelletizing or shipment

Full capacity Concentrator

Half capacity Concentrator

Shipment to Black Sea port by railway whichrequires construction of the railway station and Filtration Plant at the Vorskla Steel area + investments into upgrade of the state railroads

Slurry Pipeline 5 mtpa to FPM Filtration Plantfor pelletizing or shipment

Full capacity Concentrator

Half capacity Concentrator

9

Page 38: Business Update - Ferrexpo

Yeristovo Stage III – Slurry Pipeline and Pelletizer

– Slurry Pipeline:– Scoping study being conducted re option to transport FYM concentrate via slurry pipeline to the

Black Sea Coast for pelletizing (approx. 420 km)– Basic Design developed by Ausenco PSI (USA)

– New Pelletizer:– New Pelletizer is assumed to be built at the Slurry Pipeline Destination Point (close to the Marine

Facilities at the Black Sea Coast)– PFS ongoing by Kobe Steel, Ltd (Japan)

10

Page 39: Business Update - Ferrexpo

Corporate Social Responsibility

People Safety Risk management controls within the mine and construction areas in place (installation of the fatigue management system on CAT haul trucks – to prevent truck collision – is under consideration)

OccupationalHealth

Sustaining ZERO health related issues arising from the mine (introduction of the state-of-the-art mining equipment and ergonomic / user-friendly infrastructure has allowed safer working practices)

NaturalEnvironment

Management system to minimize the impact to the environment (in compliance with ISO Environmental Standard 14001) – developed

SocialEnvironment

94 FYM employees have received subsidized loans covered by Social Loyalty Programme. Local communities support duly continues as an integral part of land acquisition activity

ResourceManagement

Mobile in-pit crusher is put into operation for gravel production, aimed to effectively utilize deposit resources

FacilitiesManagement

Mining infrastructure facilities are constructed under the best international practice

11

Page 40: Business Update - Ferrexpo

The end

Page 41: Business Update - Ferrexpo

0

Jason Keys, Chief Marketing Officer

October 2013

Analyst Site Visit to Port Yuzhny

Page 42: Business Update - Ferrexpo

Ferrexpo Key Objectives

− Continue expansion to 12Mtpa & then to 20 Mtpa of pellet equivalent production

− Improve product mix – increase average quality of pellets to 65% Fe

− Retain & improve position on the global cash cost curve

− Reduce freight costs to Asia to below Brazilian competitors (C3 benchmark)

− Maintain and expand high quality customer base

− Prudent financial management to efficiently fund growth strategy

− Maintain high quality corporate governance associated with a premium listed company

1

Page 43: Business Update - Ferrexpo

3 Step Process to a World Class Marketing Organisation

2

Process, S

ystems, G

overnance, P

eople Improvem

ent

Stabilize and strengthen the sales portfolio

Optimize distribution channels

Maximize and protect value

– Modernize pricing structure to index– Increase sales on delivered/ CFR basis– Maintain diversified portfolio with growth towards crisis

resistant customers– Coordinate with operations to deliver agreed quality

– Reduce ocean freight costs– Increase control of supply chain– Have multiple distribution options

– Evaluate use of trading platforms & price risk management tools

– Steer operations to produce the “right” products– Long term contracts covering up to 90% of

production

Page 44: Business Update - Ferrexpo

Sales Volume by Market

78

4934

18

42 49

4 9 17

0

30

60

90

2008 2012 2018Traditional Growth Natural

+31 percentage points%

3

Ferrexpo sales volume Benefits of diversity to Ferrexpo2010 2011 2012 2013F

Volume (Mt) 9.7 9.9 9.7 10.5‐11.0

Diversified Customer Portfolio

– Ferrexpo is in a unique position to competitively supply Europe, Middle East and Asia

– Diversity reduces the risk of being unable to sell in a weak market environment

– Due to its location & product Ferrexpo can target the premium steel mills around the world

– Regional factors can present opportunities to shift product to better performing markets

– Global market intelligence

Sales Volume by Contract Type

40%

14%

46%

Benchmark indexed

Spot

Quarterly negotiated

1H 2013

Page 45: Business Update - Ferrexpo

Integrated & Growing Logistics Capability

– Achieving at or better than C3 in 2H 2013

– Phasing out of panamax continues

– First vessel over 200kt successfully loaded

Ferrexpo seaborne freight costUS$/tonne

4

16

21

26

31

36

41

1H 2010

2H 2010

1H 2011

2H 2011

1H 2012

2H 2012

Q1 13

Q2 13

Q3 13

Q4 13

Q1 14

Ferrexpo

C3 Tubarao‐Qingdao

Traditional MarketsNatural MarketsGrowth MarketsFerrexpo London officeMarketing offices

Page 46: Business Update - Ferrexpo

5

Growing Brand Awareness with Premium Steel Mills

Ferrexpo has been able to:– Differentiate itself from other CIS producers, emphasizing that it is a reliable, good quality supplier, with

capsize shipping capability & competitive freight rates

– Present itself as a viable alternative to Brazilian suppliers

– Debunk the myth that premium customers in Japan cannot use acid pellets

Page 47: Business Update - Ferrexpo

6

Ferrexpo Premium Pellets: Well RegardedBF Pellets (Higher Grade)

Chemistry % RemarksFe 65.1 Good

SiO2 5.6Aiming for <5% after completion of

Quality Upgrade ProjectAl2O3 0.32 ExcellentCaO 0.28 GoodMgO 0.60 Very GoodP 0.006 ExcellentS 0.005 GoodMn 0.03 GoodTiO2 0.04 GoodK2O+Na2O 0.12 Good

CaO+MgO/SiO2+Al2O3 0.15Good. Can produce higher by

increasing limestonePhysical Properties:CCS, kg/p 250 Good. Should not be lessSize, %

+16mm 2.83 Good5-16mm 93.5 Good

-5mm 3.65 Good

Page 48: Business Update - Ferrexpo

7

Ferrexpo Premium Pellets: Well Regarded

- Better control of compression strength (CCS), which results in:

Lower fines generation in handling and during reduction

- Uniform pellet firing, which leads to:

Steady operation of BF

Less oxide and product fines

- Superior Pellet Shape that yields:

Superior high temperature reduction behaviour

Higher stack permeability

Quality advantages of Grate-Kiln (GK) pelletizing system:

Page 49: Business Update - Ferrexpo

Ferrexpo’s Changing Product Suite

8

Ferrexpo Basic 62% Pellets

Ferrexpo Premium 65%

Pellets

65.5% Fe BF Pellets and < 5% silica BF

Pellets

Pellet Feed 67.5% Fe and

4.5% silica pellet feed

DRI pellets 68% Fe and 1.7%

silica DR pellet

Concentrate Purchases (3rd

party)

Existing products

Future planned products

Quality Upgrade Project will result in100% Ferrexpo Premium Pellets by end 2014.

Page 50: Business Update - Ferrexpo

9

Outlook for Pellet Premiums

5

10

15

20

25

30

4 Ja

n - 3

1 D

ec18

Jan

- 14

Jan

1 Fe

b - 2

8 Ja

n15

Feb

- 11

Feb

1 M

ar -

26 F

eb15

Mar

- 11

Mar

29 M

ar -

25 M

ar12

Apr

- 8

Apr

26 A

pr -

22 A

pr10

May

- 6

May

24 M

ay -

20 M

ay7

Jun

- 3 J

un21

Jun

- 17

Jun

5 Ju

l - 1

Jul

19 J

ul -

15 J

ul2

Aug

- 29

Jul

16 A

ug -

12 A

ug30

Aug

- 26

Aug

13 S

ep -

9 S

ep

US

$/to

nne

Metal Bulletin weekly derived China spot pellet premium (2013) – Pellet premiums have recovered in Chinese spot market in

2013

0

10

20

30

40

50

60

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017

– Represents long term contract market, Ferrexpo’s primary focus

– Pellet premiums supported around the US$30/tonne level– Reflects cost of pelletising

US

$/to

nne

(nom

inal

)

CRU annual pellet premium forecast

Source: Iron Ore market outlook 3Q 2013

Page 51: Business Update - Ferrexpo

0

14

28

42

56

70

USc/dmtu

Ferrexpo

0.2 Bnt

ENRCMetalloinvest

IOC

Metinvest MetinvestLKAB

LKABVale

ValeSamarco

Vale

CLIFFS

Pelletising Cost Curve

Source: CRU, January 2013

Pelletising – Competitive Cost Position

Note: Only reflects costs incurred at pelletising stage of the production process (i.e. does not include mining, concentration and beneficiation costs) and as such should not be considered as a cost curve for total cost of pellets production. Site costs are defined as cash operating costs plus share of local overhead and sustaining capital

10

Page 52: Business Update - Ferrexpo

11

Appendix

Page 53: Business Update - Ferrexpo

Overall Cost Position

Source Bank of America Merrill Lynch; Ferrexpo , August 2013

CIF China 62% Fe Equivalent Unit Concentrate Cash Cost1

US

$/to

nne

1 In order to determine a comparable CFR cost of concentrate for Ferrexpo, the cost of pelletising has been deducted. The calculation is as follows: C1 cash cost of production + freight to Port Yuzhny + sea freight to China – less pelletising cost - premium for higher Fe content.

12

mtpa

0

20

40

60

80

100

120

140

0 200 400 600 800 1000 1200 1400

Rio TintoValeBHPMid cost producersChina - low costChina - mid costChina - high cost Ferrexpo

Page 54: Business Update - Ferrexpo

Disclaimer

This document is being supplied to you solely for your information and does not constitute or formpart of any offer or invitation or inducement to sell or issue, or any solicitation of any offer topurchase or subscribe for, any shares in the Company or any other securities, nor shall any partof it nor the fact of its distribution form part of or be relied on in connection with any contract orinvestment decision relating thereto, nor does it constitute a recommendation regarding thesecurities of the Company. No information made available to you in connection with thisdocument may be passed on, copied, reproduced, in whole or in part, or otherwise disseminated,directly or indirectly, to any other person.

Some of the information in this document is still in draft form and is subject to verification,finalisation and change. Neither the Company nor its affiliates nor advisers are under anobligation to correct, update or keep current the information contained in this document or topublicly announce the result of any revision to the statements made herein except where theywould be required to do so under applicable law.

No reliance may be placed for any purpose whatsoever on the information contained in thisdocument. No representation or warranty, expressed or implied, is given by or on behalf of theCompany or any of the Company’s directors, officers or employees or any other person as to theaccuracy or completeness of the information or opinions contained in this document and noliability whatsoever is accepted by the Company or any of the Company’s members, directors,officers or employees nor any other person for any loss howsoever arising, directly or indirectly,from any use of such information or opinions otherwise arising in connection therewith.

This presentation and its contents are confidential. By reviewing and / or attending thispresentation you are deemed to accept that you are under a duty of confidentiality in relation tothe contents of this presentation. You agree that you will not at any time have any discussion,correspondence or contact concerning the information in this document with any of the directorsor employees of the Company or its subsidiaries nor with any of their customers or suppliers, orany governmental or regulatory body without the prior written consent of the Company.Certain statements, beliefs and opinions in this document and any materials distributed inconnection with this document are forward-looking. The statements typically contain words suchas “anticipate”, “assume”, “believe”, “estimate”, “expect”, “plan”, “intend” and words of similarsubstance. By their nature, forward-looking statements involve a number of risks, uncertaintiesand assumptions that could actual results or events to differ materially from those expressed orimplied by the forward-looking statements. These risk, uncertainties and assumptions couldadversely affect the outcome and financial effects of the plans and events described herein.Statements contained in the document regarding past trends or activities should not be taken as arepresentation or warranty (express or implied) that such trends or activities will continue in thefuture. No statement in this document is intended to be a profit forecast. You should not placereliance on forward-looking statements, which speak only as of the date of this document.You should not base any behaviour in relation to financial instruments related to the Company’ssecurities or any other securities and investments on information until after it is made publiclyavailable by the Company or any of their respective advisers. Any dealing or encouraging othersto deal on the basis of such information may amount to insider dealing under the Criminal JusticeAct 1993 and to market abuse under the Financial Services and Markets Act 2000.